CN217204030U - C80 early strength concrete pipe pile - Google Patents

C80 early strength concrete pipe pile Download PDF

Info

Publication number
CN217204030U
CN217204030U CN202220404586.8U CN202220404586U CN217204030U CN 217204030 U CN217204030 U CN 217204030U CN 202220404586 U CN202220404586 U CN 202220404586U CN 217204030 U CN217204030 U CN 217204030U
Authority
CN
China
Prior art keywords
tubular pile
pile body
concrete tubular
strength concrete
early
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220404586.8U
Other languages
Chinese (zh)
Inventor
丁爱华
张全良
于春晓
邬金林
周平伟
姚福强
凌元忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiashan Ningxin Concrete Component Co ltd
Original Assignee
Jiashan Ningxin Concrete Component Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiashan Ningxin Concrete Component Co ltd filed Critical Jiashan Ningxin Concrete Component Co ltd
Priority to CN202220404586.8U priority Critical patent/CN217204030U/en
Application granted granted Critical
Publication of CN217204030U publication Critical patent/CN217204030U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a C80 early strength concrete tubular pile, including first early strength concrete tubular pile body, the early strength concrete tubular pile body of second and coupling assembling, first early strength concrete tubular pile body passes through coupling assembling and this body coupling of the early strength concrete tubular pile of second, coupling assembling includes installed part, connecting piece, connecting pipe, installed part, connecting piece, connecting pipe are ring-shaped structure, the fixed installed part of locating between two parties in the connecting pipe outside, first early strength concrete tubular pile body, the early strength concrete tubular pile body both ends of second all are equipped with first mounting and second mounting, first mounting and second mounting are ring-shaped structure. Through coupling assembling's design, the first early strong concrete tubular pile body of being convenient for, the early strong concrete tubular pile body of second are connected, and the first early strong concrete tubular pile body of also being convenient for simultaneously, the early strong concrete tubular pile body of second are connected with other concrete tubular pile.

Description

C80 early strength concrete pipe pile
Technical Field
The utility model relates to a concrete pipe pile technical field, in particular to C80 early strength concrete pipe pile.
Background
Along with the change of building environment, different building construction technologies are required to be adopted under different geological conditions, the production technology and the application field of the concrete pipe pile are greatly developed, the high-strength concrete pipe pile adopts a pre-tensioning method prestress and centrifugal forming process, a hollow round and simple equal-section member is manufactured through autoclaved curing, the hollow round and simple equal-section member is sunk underground through a hammering or static pressure method to serve as the foundation of a building, and the high-strength concrete pipe pile has the advantages of high single-pile bearing capacity, low unit bearing capacity price, wide application range, short construction speed block, short construction period and the like. The concrete early strength agent is an additive capable of improving the early strength of concrete, and is mostly adopted in winter or emergency repair. The existing concrete pipe piles are inconvenient to connect, so that the use requirements of enterprises cannot be met.
Therefore, a C80 early strength concrete pipe pile is provided.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a C80 early strength concrete tubular pile, can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a C80 early strength concrete tubular pile comprises a first early strength concrete tubular pile body, a second early strength concrete tubular pile body and a connecting assembly, wherein the first early strength concrete tubular pile body is connected with the second early strength concrete tubular pile body through the connecting assembly, the connecting assembly comprises a mounting part, a connecting part and a connecting pipe, the mounting part, the connecting part and the connecting pipe are all of circular ring structures, the mounting part is fixedly sleeved at the middle part of the outer side of the connecting pipe, the first early strength concrete tubular pile body and the second early strength concrete tubular pile body can be conveniently connected through the design of the connecting assembly, and meanwhile, the first early strength concrete tubular pile body and the second early strength concrete tubular pile body can be conveniently connected with other concrete tubular piles;
first early strong concrete tubular pile body, the early strong concrete tubular pile body both ends of second all are equipped with first mounting and second mounting, first mounting and second mounting are ring shape structure, through the design of first mounting and second mounting, make first early strong concrete tubular pile body, the early strong concrete tubular pile body of second and coupling assembling can zonulae occludens.
Further, first mounting and second mounting pass through reinforcement fixed connection, the reinforcement is fixed to be inlayed at first early strong concrete tubular pile body, the early strong concrete tubular pile body both ends of second to make first mounting and second mounting can zonulae occludens.
Further, equal fixed mounting in installed part both sides periphery has the connecting piece, be equipped with the spacing groove between connecting piece and the connecting pipe.
Further, first early strong concrete tubular pile body, second early strong concrete tubular pile body both ends all are located the spacing inslot.
Further, the connecting piece passes through the bolt and respectively with first early strong concrete tubular pile body, second early strong concrete tubular pile body fixed connection.
Furthermore, a first thread groove is formed in the outer side of the connecting pipe, and a second thread groove is formed in the inner side of the second fixing piece.
Compared with the prior art, the utility model discloses following beneficial effect has: through coupling assembling's design, be convenient for first early strong concrete tubular pile body, the second early strong concrete tubular pile body is connected, the first early strong concrete tubular pile body of also being convenient for simultaneously, the second early strong concrete tubular pile body is connected with other concrete tubular pile, design through first mounting and second mounting, make first early strong concrete tubular pile body, the second early strong concrete tubular pile body can zonulae occludens with coupling assembling, the fixed inlaying of reinforcement is at first early strong concrete tubular pile body, second early strong concrete tubular pile body both ends, thereby make first mounting and second mounting can zonulae occludens, connecting pipe and second mounting threaded connection, further improve first early strong concrete tubular pile body, stability between the second early strong concrete tubular pile body.
Drawings
Fig. 1 is the utility model relates to a structure schematic diagram of C80 early strength concrete tubular pile.
Fig. 2 is the utility model relates to a C80 early strength concrete tubular pile's first early strength concrete tubular pile body stereogram.
Fig. 3 is the utility model relates to a installed part inner structure schematic diagram of C80 early strength concrete tubular pile.
In the figure: 1. a first early strength concrete pipe pile body; 2. a second early strength concrete pipe pile body; 3. a connecting assembly; 4. a bolt; 5. a mounting member; 6. a connecting member; 7. a connecting pipe; 8. a first thread groove; 9. a limiting groove; 10. a first fixing member; 11. a reinforcement; 12. a second fixing member; 13. a second thread groove.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
As shown in fig. 1-3, a C80 early strength concrete tubular pile comprises a first early strength concrete tubular pile body 1, a second early strength concrete tubular pile body 2 and a connecting assembly 3, wherein the first early strength concrete tubular pile body 1 is connected with the second early strength concrete tubular pile body 2 through the connecting assembly 3, the connecting assembly 3 comprises a mounting piece 5, a connecting piece 6 and a connecting pipe 7, the mounting piece 5, the connecting piece 6 and the connecting pipe 7 are all of a circular ring structure, the mounting piece 5 is fixedly sleeved at the middle position outside the connecting pipe 7, and through the design of the connecting assembly 3, the first early strength concrete tubular pile body 1 and the second early strength concrete tubular pile body 2 can be conveniently connected, and meanwhile, the first early strength concrete tubular pile body 1 and the second early strength concrete tubular pile body 2 can be conveniently connected with other concrete tubular piles;
first early strong concrete tubular pile body 1, the 2 both ends of the early strong concrete tubular pile body of second all are equipped with first mounting 10 and second mounting 12, first mounting 10 and second mounting 12 are the ring annular structure, through the design of first mounting 10 and second mounting 12, make first early strong concrete tubular pile body 1, the early strong concrete tubular pile body of second 2 and coupling assembling 3 can zonulae occludens.
Wherein, first mounting 10 and second mounting 12 pass through 11 fixed connection of reinforcement, 11 fixed inlays at first early strong concrete tubular pile body 1, 2 both ends of second early strong concrete tubular pile body of reinforcement 11 to make first mounting 10 and second mounting 12 can zonulae occludens.
Wherein, equal fixed mounting in installed part 5 both sides periphery has connecting piece 6, be equipped with spacing groove 9 between connecting piece 6 and the connecting pipe 7.
Wherein, first early strong concrete tubular pile body 1, 2 both ends of second early strong concrete tubular pile body all are located spacing groove 9.
Wherein, the connecting piece 6 is respectively fixedly connected with the first early strength concrete tubular pile body 1 and the second early strength concrete tubular pile body 2 through bolts 4.
Wherein, first thread groove 8 has been seted up in the connecting pipe 7 outside, second thread groove 13 has been seted up to second mounting 12 inboards, and connecting pipe 7 and 12 threaded connection of second mounting further improve the stability between first early strong concrete tubular pile body 1, the early strong concrete tubular pile body 2 of second.
It should be noted that the utility model is a C80 early strength concrete pipe pile, wherein a reinforcement 11 is fixedly embedded at two ends of a first early strength concrete pipe pile body 1 and a second early strength concrete pipe pile body 2, the first fixing member 10 and the second fixing member 12 are fixedly connected by the reinforcement 11, so that the first fixing member 10 and the second fixing member 12 can be tightly connected, the first early strength concrete pipe pile body 1 is connected with the second early strength concrete pipe pile body 2 by a connecting component 3, the outer edges of two sides of the mounting member 5 are fixedly provided with connecting members 6, a spacing groove 9 is arranged between the connecting members 6 and a connecting pipe 7, two ends of the first early strength concrete pipe pile body 1 and the second early strength concrete pipe pile body 2 are positioned in the spacing groove 9, the connecting members 6 are respectively fixedly connected with the first early strength concrete pipe pile body 1 and the second early strength concrete pipe pile body 2 by bolts 4, the stability between the first early strength concrete tubular pile body 1 and the second early strength concrete tubular pile body 2 can be further improved.
The foregoing shows and describes the basic principles and principal features of the invention, together with the advantages thereof. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The C80 early strength concrete tubular pile comprises a first early strength concrete tubular pile body (1), a second early strength concrete tubular pile body (2) and a connecting assembly (3), and is characterized in that the first early strength concrete tubular pile body (1) is connected with the second early strength concrete tubular pile body (2) through the connecting assembly (3), the connecting assembly (3) comprises a mounting part (5), a connecting part (6) and a connecting pipe (7), the mounting part (5), the connecting part (6) and the connecting pipe (7) are all of a circular ring structure, and the mounting part (5) is fixedly sleeved at the center of the outer side of the connecting pipe (7);
first early strong concrete tubular pile body (1), second early strong concrete tubular pile body (2) both ends all are equipped with first mounting (10) and second mounting (12), first mounting (10) and second mounting (12) are the ring structure.
2. The C80 early strength concrete pipe pile of claim 1, wherein: first mounting (10) and second mounting (12) pass through reinforcement (11) fixed connection, reinforcement (11) are fixed to be inlayed at first early strong concrete tubular pile body (1), second early strong concrete tubular pile body (2) both ends.
3. The C80 early strength concrete pipe pile of claim 1, wherein: the mounting piece (5) is characterized in that connecting pieces (6) are fixedly mounted at the outer edges of two sides of the mounting piece (5), and a limiting groove (9) is arranged between each connecting piece (6) and each connecting pipe (7).
4. The C80 early strength concrete pipe pile of claim 1, wherein: the first early-strength concrete tubular pile body (1) and the second early-strength concrete tubular pile body (2) are both located in the limiting groove (9).
5. The C80 early strength concrete pipe pile of claim 1, wherein: the connecting piece (6) is fixedly connected with the first early strength concrete tubular pile body (1) and the second early strength concrete tubular pile body (2) through bolts (4) respectively.
6. The C80 early strength concrete pipe pile of claim 1, wherein: a first thread groove (8) is formed in the outer side of the connecting pipe (7), and a second thread groove (13) is formed in the inner side of the second fixing piece (12).
CN202220404586.8U 2022-02-28 2022-02-28 C80 early strength concrete pipe pile Active CN217204030U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220404586.8U CN217204030U (en) 2022-02-28 2022-02-28 C80 early strength concrete pipe pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220404586.8U CN217204030U (en) 2022-02-28 2022-02-28 C80 early strength concrete pipe pile

Publications (1)

Publication Number Publication Date
CN217204030U true CN217204030U (en) 2022-08-16

Family

ID=82754396

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220404586.8U Active CN217204030U (en) 2022-02-28 2022-02-28 C80 early strength concrete pipe pile

Country Status (1)

Country Link
CN (1) CN217204030U (en)

Similar Documents

Publication Publication Date Title
CN107798166B (en) Method for calculating combined action of load structure under water pressure in composite lining of shield tunnel
CN217204030U (en) C80 early strength concrete pipe pile
CN204645074U (en) A kind of single pile-gravity associating offshore wind power foundation
CN203362176U (en) Tunnel segment
CN201347556Y (en) Concrete pipe pile cut-off device
CN210216312U (en) Supporting structure of steel sheet pile for bank protection
CN110616802A (en) Prefabricated steel sleeve connecting node of assembled concrete frame
CN202945601U (en) Thin-wall steel tube centrifugal concrete (TSC) and prestress high concrete (PHC) combined pile
CN214574448U (en) Large-diameter assembly type non-pressure rainwater sewage pipe ring
CN210767512U (en) Special-shaped grouting sleeve for steel bar connection
CN203346880U (en) Novel prestressed concrete pipe pile
CN204371413U (en) A kind of highstrenghtpiston's pipe for escaping
CN209586399U (en) A kind of underground pipe gallery shield-tunneling construction waterproof construction
CN201487456U (en) Steel-plastic composite tee joint
CN110805028A (en) FRP elastic composite pile and manufacturing method thereof
CN2890553Y (en) Big-flow centripetal stress sewage-treatment pipe
CN212361100U (en) Hydraulic joint convenient to install
CN221256788U (en) Corrugated steel pipe opening reinforcing device
CN221034487U (en) Concrete push pipe
CN213626016U (en) Prefabricated steel pipe concrete column and crossbeam quick connecting device
CN218935488U (en) Foam concrete jacking pipe suitable for obstacle avoidance and direction change
CN210827437U (en) Non-autoclaved high-strength prefabricated pipe pile
CN219470916U (en) Water-stopping anti-seepage pipe pile
CN209875154U (en) Combined reinforced concrete prefabricated round vertical shaft
CN215522253U (en) Supporting device for laying gas engineering pipeline

Legal Events

Date Code Title Description
GR01 Patent grant