Prior art keywords
grout
grout outlet
outlet
sleeve
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220560718.6U
Other languages
Chinese (zh)
Inventor
陈冬冬
杨辉
何军利
付斌
柯伟席
孔金鸣
白琪
雷生
杨铁龙
徐鹏
田晓航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Laiyuan Machinery Processing Co.,Ltd.
Original Assignee
Wuhan Ujoin Building Material Technology Co ltd
Wuhan Sanyuan Speical Building Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Ujoin Building Material Technology Co ltd, Wuhan Sanyuan Speical Building Materials Co Ltd filed Critical Wuhan Ujoin Building Material Technology Co ltd
Priority to CN202220560718.6U priority Critical patent/CN217150926U/en
Application granted granted Critical
Publication of CN217150926U publication Critical patent/CN217150926U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a V type grout outlet is grout sleeve and mends thick liquid device for steel bar connection, including setting up grout outlet and grout outlet on grout sleeve, grout outlet slope sets up, grout outlet department still is equipped with the viewing aperture, the viewing aperture with grout outlet is "V" font and arranges, grout outlet with contained angle between the viewing aperture is not less than 20 degrees and the contained angle sets up for radius angle transition, the viewing aperture is arranged in grout in-process and/or grout and accomplishes the full condition of back observation grout. This grout sleeve for V type grout outlet steel bar connection passes through the full condition of the real-time observation grout of viewing aperture can convenient and fast, and the cooperation design of mending thick liquid device and grout outlet simultaneously can guarantee the full of grout, also can see through the viewing aperture is audio-visual even the not full condition appears to mend thick liquid through mending thick liquid device convenient and fast, thereby guarantee the quality of grout connected node, guarantee the safety of engineering structure.

Description

Grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection
Technical Field
The utility model relates to a connecting piece in assembly type structure field, concretely relates to grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection.
Background
At present, the extensive application of grout sleeve grout connection technique is in the fabricated construction, the fabricated construction prevalence is also higher and higher, but in the actual engineering because the construction is not normative inadequately, and the fabricated construction material quality is uneven, the phenomenon ubiquitous that the grout is not full, very big potential safety hazard has been brought for the engineering, the grout technique of present universal adoption is UNICOM's chamber grout, in time plug up after grout outlet, arrange the thick liquid mouth and go out the thick liquid, unable real time monitoring grout condition in the grout process, the condition of inspection grout plumpness after the grout construction is accomplished generally adopts drilling observation, the condition that the grout is not full generally adopts the syringe to mend the technology of thick liquid, the operation is very loaded down with trivial details and consuming time, and the theory of green with the fabricated construction is contradicted.
For example, in 2019, a steel bar grouting sleeve with a grout outlet inclined upward and a connection structure thereof are disclosed in the chinese utility model patent (publication No. CN208763307U), wherein a grouting opening and a grout outlet are formed in the sleeve wall of the sleeve, the grouting opening is perpendicular to the wall of the bottom end portion, the grout outlet is inclined upward relative to the wall of the top end portion, and the inner surface of the sleeve wall protrudes inward to form annular inward protrusions arranged at intervals. This grout sleeve can improve the not full condition of grout through the setting of the grout outlet of slope, but still need use the depth measurement chi at the inspection of the grout plumpness at the actual grout in-process, can not the full condition of visual observation grout.
Disclosure of Invention
The utility model aims at providing a V type grout outlet grout sleeve and benefit thick liquid device for steel bar connection to the problem that prior art exists.
In order to achieve the above object, the utility model adopts the following technical scheme:
a grouting sleeve for connecting reinforcing steel bars at a V-shaped grout outlet comprises a grouting opening and a grout outlet which are arranged on the grouting sleeve, wherein the grout outlet is obliquely arranged, an observation opening is also arranged at the grout outlet, the observation opening and the grout outlet are arranged in a V shape, and the observation opening and the grouting opening are arranged in parallel and are respectively perpendicular to the grouting sleeve; the grout outlet inclines towards the direction far away from the grout inlet, an included angle between the grout outlet and the observation port is not less than 20 degrees and is in transition arrangement through a fillet, and the observation port is used for observing the full condition of grout in the grouting process and/or after the grout is completely grouted.
This grout sleeve for V type grout outlet steel bar connection passes through the full condition of the real-time observation grout of viewing aperture can convenient and fast, and the cooperation design of mending thick liquid device and grout outlet simultaneously can guarantee the full of grout, also can see through the viewing aperture is audio-visual even the not full condition appears to mend thick liquid through mending thick liquid device convenient and fast, thereby guarantee the quality of grout connected node, guarantee the safety of engineering structure.
The slurry outlet is obliquely arranged, so that the filling of slurry at the end part of the grouting sleeve is facilitated, and the connection with a slurry supplementing device is also facilitated; the observation port is arranged on one side of the pulp outlet, a V-shaped pulp outlet is formed, and the purpose of observation can be realized while pulp is discharged. Compared with the traditional vertically arranged slurry outlet, the slurry outlet has better slurry outlet effect; compared with a single oblique grout outlet, the grout outlet has the observation function. The observation port is arranged perpendicular to the grouting sleeve, so that the sight can be better seen into the sleeve directly, the observation port can be observed in real time in the grouting process, when slurry reaches the grouting port, the observation port can be temporarily sealed by using a rubber plug, and the slurry overflows from the slurry outlet; although grout is discharged from the grout outlet in the grouting process, the inside of the grout outlet cannot be completely ensured to be completely full, the grout may not be filled fully due to the existence of gaps and gas, when the grout outlet needs to be judged again, the grout can be visually observed through the observation hole by naked eyes to fill the grout, and the grout can be replenished by utilizing the grout replenishing device when the grout is not filled.
The observation port with the transition of radius angle sets up between the grout outlet, can reduce stress concentration on the one hand, keeps holistic intensity and stability, and on the other hand, comparatively circular arc in transition department is favorable to thick liquids to flow, reduces thick liquids flow resistance.
Further, the fillet includes the fillet of inboard fillet and outside, inboard fillet with there is the interval between the body periphery place arc surface of grout sleeve. The arrangement is such that the viewing port is not arranged independently of the slurry outlet, but in close relation thereto.
Further, the size of the fillet is R0.5-R2 mm.
Furthermore, the included angle between the slurry outlet and the axis of the observation port is 20-80 degrees.
Furthermore, the inner diameter of the observation port is 14-18 mm, and the inner diameter of the grout outlet is 20-40 mm. The size of the slurry outlet is larger than that of the observation port, so that slurry can flow to the slurry outlet with larger size.
Furthermore, the observation port and the grouting port are respectively arranged at two ends of the grouting sleeve.
Furthermore, the end part of the observation port is also detachably provided with a rubber plug, and the outer side of the rubber plug is provided with a handle. The rubber plug can be the rubber plug, the rubber plug can use repeatedly, the setting of handle is convenient for pull out and insert the rubber plug.
Furthermore, a plurality of shear grooves are circumferentially arranged on the grouting sleeve at intervals, and the observation port and the grout outlet are arranged at a straight section between the adjacent shear grooves.
The arrangement of the shear groove is beneficial to improving the mechanical property of the grouting sleeve, and the grout outlet and the observation port are arranged in a manner of avoiding the shear groove so as to avoid influencing the integrity of the shear groove.
Further, a thick liquid device is mended to grout sleeve for V type grout outlet steel bar connection, mend thick liquid device including hourglass hopper-shaped grout outlet, mend the below of thick liquid mouth and set up the pipe chute, the pipe chute with grout outlet can dismantle the connection and use, the inclination of pipe chute is 20 ~ 80, that is to say with grout outlet's inclination keeps the unanimity.
For example, grouting material is injected from a grouting opening in the grouting construction process, when the slurry overflows from the observation opening, the slurry is blocked by a rubber plug, and when the grouting material fills the slurry supplementing device, the grouting is stopped; and then the full grouting condition can be visually observed through the observation port, the grout is supplemented through the grout supplementing device, and after the full grouting condition is achieved, the grout supplementing device can be taken down and can be used repeatedly.
The inclined conduit arranged below the grout supplementing port is convenient to butt with the grout outlet and is easy to keep coaxial arrangement of the inclined conduit and the grout outlet; the inclined conduit can be inserted into the grout outlet and also can be sleeved on the grout outlet.
Compared with the prior art, the beneficial effects of the utility model are that: 1. the grouting sleeve for connecting the steel bars at the V-shaped grout outlet can conveniently and quickly observe the full condition of grouting in real time through the observation port, meanwhile, the matching design of the grout supplementing device and the grout outlet can ensure the full condition of grouting, the grouting can be visually observed through the observation port even if the full condition occurs, and the grout can be conveniently and quickly supplemented through the grout supplementing device, so that the quality of a grouting connection node is ensured, and the safety of an engineering structure is ensured; 2. the observation port and the slurry outlet are in transition arrangement by rounding off, so that stress concentration can be reduced, the integral strength and stability are kept, slurry flow is facilitated, and the slurry flow resistance is reduced; 3. mend thick liquid device simple structure, easy to use can dismantle and use repeatedly.
Drawings
Fig. 1 is a schematic view of the overall structure of a grouting sleeve for connecting reinforcing steel bars at a V-shaped grout outlet of the present invention;
FIG. 2 is a schematic view of the overall structure of the slurry replenishing device of the present invention;
fig. 3 is the utility model discloses grout sleeve and the schematic diagram of mending thick liquid device use for the connection of V type grout outlet reinforcing bar.
In the figure: 1. grouting a sleeve; 2. grouting ports; 3. a pulp outlet; 4. a viewing port; 5. rounding off; 6. a pulp replenishing device; 601. a pulp supplementing port; 602. a deflection conduit; 7. prefabricating a component; 8. reinforcing steel bars; 9. a laminated plate.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are only some embodiments, not all embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "middle", "upper", "lower", "left", "right", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
The first embodiment is as follows:
as shown in fig. 1, a grouting sleeve for connecting reinforcing steel bars at a V-shaped grout outlet comprises a grouting opening 2 and a grout outlet 3 which are arranged on the grouting sleeve 1, wherein the grout outlet 3 is obliquely arranged, an observation opening 4 is further arranged at the grout outlet 3, the observation opening 4 and the grout outlet 3 are arranged in a V shape, and the observation opening 4 and the grouting opening 2 are arranged in parallel and are respectively perpendicular to the grouting sleeve 1; grout outlet 3 is to keeping away from grout mouth 2's direction slope, grout outlet 3 with contained angle between observation port 4 is not less than 20 degrees and the contained angle sets up for the radius transition, observation port 4 is used for the full condition of grout in-process and/or grout completion back observation.
This grout sleeve for V type grout outlet steel bar connection passes through the full condition of the real-time observation grout of viewing aperture 4 that can convenient and fast, the full of grout can be guaranteed in the cooperation design of simultaneously benefit thick liquid device and grout outlet 3, even the condition that is not full also can pass through the audio-visual viewing of viewing aperture to through the benefit thick liquid of benefit thick liquid device convenient and fast, thereby guarantee the quality of grout connected node, guarantee the safety of engineering structure.
The slurry outlet 3 is obliquely arranged, so that the filling of slurry at the end part of the grouting sleeve is facilitated, and the connection with a slurry supplementing device is also facilitated; the observation port 4 is arranged on one side of the device to form a V-shaped slurry outlet, so that the purpose of observation can be realized while slurry is discharged.
The observation port 4 with the transition of radius angle sets up between the grout outlet 3, can reduce stress concentration on the one hand, keeps holistic intensity and stability, and on the other hand, comparatively circular arc in transition department is favorable to thick liquids to flow, reduces thick liquids flow resistance.
Further, the fillet 5 includes the fillet of inboard and the fillet of outside, inboard fillet with there is the interval between the body periphery place arc surface of grout sleeve 1. The arrangement is such that the viewing port 4 is not arranged independently of the outlet 3.
Further, the size of the rounded corner 5 is R1 mm.
Further, the included angle between the slurry outlet 3 and the axis of the observation port 4 is 25 degrees.
Further, the inner diameter of the observation port 4 is 15mm, and the inner diameter of the grout outlet 3 is 30 mm. The size of the slurry outlet 3 is larger than that of the observation port 4, so that the slurry can flow to the slurry outlet 3 with larger size.
Further, the observation port 4 and the grouting port 2 are respectively arranged at two ends of the grouting sleeve 1.
Further, the tip of viewing aperture 4 is detachable still and is provided with the plug, the length of plug does not exceed viewing aperture 4 exposes the length of grout sleeve periphery, the outside of plug is equipped with the handle. The rubber plug can be the rubber plug, the rubber plug can use repeatedly, the setting of handle is convenient for pull out and insert the rubber plug.
Furthermore, a plurality of shear grooves are circumferentially arranged on the grouting sleeve 1 at intervals, and the observation port 4 and the grout outlet 3 are arranged at a straight section between the adjacent shear grooves at the upper end.
The arrangement of the shear grooves is beneficial to improving the connection performance of the internal slurry, and the slurry outlet and the observation port are arranged in a manner of avoiding the shear grooves so as to avoid influencing the integrity of the shear grooves.
Example two:
the embodiment provides a grout filling device matched with the grouting sleeve in the first embodiment.
As shown in fig. 2, the slurry supplementing device 6 includes a funnel-shaped slurry supplementing opening 601, a straight pipe is arranged below the slurry supplementing opening 601 and then an inclined conduit 602 is connected to the straight pipe, the inclined conduit 602 is detachably connected to the slurry outlet 3 for use, and the inclination angle of the inclined conduit 602 is consistent with that of the slurry outlet 3.
For example, the filling state is visually observed through the observation opening 4, the grout is supplemented through the grout supplementing device 6, after the grouting is full and full, the grout supplementing device 6 can be taken down, and the grout supplementing device 6 can be used repeatedly.
The inclined conduit 602 arranged below the grout filling port 601 is convenient to be butted with the grout outlet 3 and is easy to keep coaxial arrangement of the two; the slant conduit 602 may be inserted in the grout outlet 3.
Example three:
this embodiment provides a mode that this grout sleeve and benefit thick liquid device used.
As shown in fig. 3, when two adjacent prefabricated components 7 are assembled, the grouting sleeve 1 is arranged above the middle laminated slab 9, an upper reinforcing steel bar 8 and a lower reinforcing steel bar 8 are respectively inserted into the grouting sleeve 1, after the prefabricated components are installed, slurry is poured into the grouting opening 2, the slurry gradually fills the inner space and moves upwards along with the progress of the grouting, the ascending condition of the slurry can be observed through the observation opening 4, when the slurry is about to ascend to the grout outlet 3, the observation opening 4 is blocked by a rubber plug, the grouting is continued, the slurry continuously ascends, after the slurry enters the grout outlet 3, the grouting from the grouting opening 2 is stopped, the grouting opening 2 is blocked, the slurry is kept still, the slurry flows and disperses by the self gravity inside, and the slurry descends and is not filled known, at this time, the observation opening 4 can be opened to further observe the full condition of the slurry, if not full, the pulp supplementing device 6 is used for continuously supplementing pulp from the pulp outlet 3 until the pulp is filled fully.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. A grouting sleeve for connecting reinforcing steel bars at a V-shaped grout outlet comprises a grouting opening and a grout outlet which are arranged on the grouting sleeve, wherein the grout outlet is obliquely arranged; the grout outlet inclines towards the direction far away from the grout inlet, the included angle between the grout outlet and the observation port is not less than 20 degrees and is transition setting for the fillet, and the observation port is used for observing the full condition of grout in the grout process and/or after the grout is finished.
2. The V-shaped grout outlet steel bar connection grouting sleeve as claimed in claim 1, wherein the fillet comprises an inner fillet and an outer fillet, and a space exists between the inner fillet and the arc surface of the periphery of the grouting sleeve body.
3. The V-type grout outlet sleeve for connecting steel bars according to claim 1, wherein the size of the fillet is R0.5 to R2 mm.
4. The grouting sleeve for connecting the V-shaped grout outlet and the steel bar according to claim 1, wherein an included angle between the grout outlet and the axis of the observation port is 20-80 degrees.
5. The grouting sleeve for connecting the V-shaped grout outlet and the steel bar according to claim 1, wherein the inner diameter of the observation port is 14-18 mm, and the inner diameter of the grout outlet is 20-40 mm.
6. The grouting sleeve for connecting the V-shaped grout outlet and the steel bar according to claim 1, wherein the observation port and the grouting port are respectively arranged at two ends of the grouting sleeve.
7. The V-shaped grout outlet steel bar connection grouting sleeve as claimed in claim 1, wherein a rubber plug is detachably arranged at the end part of the observation port, and a handle is arranged at the outer side of the rubber plug.
8. The grouting sleeve for connecting the V-shaped grout outlet and the steel bar according to claim 1, wherein a plurality of shear grooves are arranged at intervals in the circumferential direction of the grouting sleeve, and the observation port and the grout outlet are arranged at a straight section between the adjacent shear grooves.
9. A grout supplementing device for a grouting sleeve for connecting V-shaped grout outlet reinforcing steel bars according to claim 1, wherein the grout supplementing device comprises a funnel-shaped grout supplementing opening, an inclined conduit is arranged below the grout supplementing opening and is detachably connected with the grout outlet for use, and the inclined conduit has an inclination angle of 20-80 degrees.
CN202220560718.6U 2022-03-15 2022-03-15 Grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection Active CN217150926U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220560718.6U CN217150926U (en) 2022-03-15 2022-03-15 Grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220560718.6U CN217150926U (en) 2022-03-15 2022-03-15 Grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection

Publications (1)

Publication Number Publication Date
CN217150926U true CN217150926U (en) 2022-08-09

Family

ID=82695515

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220560718.6U Active CN217150926U (en) 2022-03-15 2022-03-15 Grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection

Country Status (1)

Country Link
CN (1) CN217150926U (en)

Similar Documents

Publication Publication Date Title
CN112962868A (en) Grouting sleeve assembly and method for improving grouting quality
CN217150926U (en) Grout sleeve and benefit thick liquid device for V type grout outlet steel bar connection
CN109701409A (en) Venturi mixer
CN109098468A (en) Supplementary irrigation method is injected in drilling for sleeve grouting defect
CN210459180U (en) Grouting sleeve valve pipe device for reinforcing interval ground
CN204575366U (en) A kind of concrete real time sample device
CN110374265B (en) Assembled concrete half grouting sleeve connection and construction control method
CN211080786U (en) Full grout sleeve convenient to control construction quality of being in milk
CN217711767U (en) Grouting assembly for grouting sleeve
CN214668089U (en) Novel sleeve for visually detecting grouting fullness and detecting position of reinforcing steel bar
CN216787853U (en) Sleeve grout filling device
CN210530146U (en) Assembled concrete half-grouting sleeve
CN210622828U (en) Hollow anchor rod grouting joint
CN208953317U (en) It is a kind of for mending the deflecting wedge for taking coal core
CN208330407U (en) A kind of double-liquid grouting system for constructing tunnel
CN217976267U (en) Grouting anchor rod
CN205627687U (en) Vacuum is penetrated and is inhaled blender
CN207287437U (en) Aqueous insulation insulating moulding coating stress reaction device
CN203584346U (en) Automatic locking and unlocking delivery cap of packer
CN210713537U (en) Novel grouting self-compacting sleeve
CN209975532U (en) Novel pile foundation construction slip casting pipe
CN210766786U (en) Perfusion catheter quick joint
CN208390048U (en) A kind of pipette tips structure that anti-suction pipe falls off
CN211286293U (en) Grouting sleeve joint for connecting reinforcing steel bars
CN220725093U (en) Drilling slurry guiding device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230821

Address after: 271100 east of Nangong village, Niuquan Town, Laiwu District, Jinan City, Shandong Province

Patentee after: Shandong Laiyuan Machinery Processing Co.,Ltd.

Address before: 430083 Industrial Park, Worker Village, Qingshan District, Hubei, Wuhan

Patentee before: WUHAN UJOIN BUILDING MATERIAL TECHNOLOGY Co.,Ltd.