CN217106105U - Climbing frame platform plate - Google Patents
Climbing frame platform plate Download PDFInfo
- Publication number
- CN217106105U CN217106105U CN202220800114.4U CN202220800114U CN217106105U CN 217106105 U CN217106105 U CN 217106105U CN 202220800114 U CN202220800114 U CN 202220800114U CN 217106105 U CN217106105 U CN 217106105U
- Authority
- CN
- China
- Prior art keywords
- plate
- reinforcing plate
- receiver
- platform board
- stay tubes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Ladders (AREA)
Abstract
The utility model belongs to the technical field of the technique of climbing the frame and specifically relates to a climb a landing slab is related to, and it includes that two are the stay tubes that the interval set up, and two stay tubes pass through the backup pad to be connected, and the both ends of backup pad all are equipped with the connecting plate, and the connecting plate is connected in the tip of two stay tubes, and two connecting plates are connected through same reinforcing plate, and the reinforcing plate is located between two stay tubes. The two supporting tubes and the two connecting plates jointly enclose a frame body, so that the supporting plates are stably supported; the reinforcing plate is used for connecting the two connecting plates, and the reinforcing plate and the two connecting plates jointly form an I-shaped plate, so that the overall strength of the platform plate is improved. The reinforcing plate and the supporting pipe are arranged in a hollow mode, and the overall weight of the platform plate is reduced. This application has made things convenient for the installation and the transport of landing slab.
Description
Technical Field
The utility model belongs to the technical field of the technique of climbing the frame and specifically relates to a climb a landing slab.
Background
The climbing frame is a short name of an attached lifting scaffold. The climbing frame can reduce the number of hoisting machines and accelerate the construction speed, so the economic benefit is better.
The current climbing frame comprises a frame body and a plurality of platform plates, wherein the frame body is supported on the ground, and the platform plates are erected on the frame body so as to be used for workers to walk.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: the current flat deck is generally a solid plate, heavy, and inconvenient to install and carry, and therefore needs to be improved.
Disclosure of Invention
In order to facilitate installation and transport, the application provides a climb a landing deck.
The application provides a climb a landing slab, adopts following technical scheme: the utility model provides a climb a landing slab, includes that two are the stay tubes that the interval set up, and two stay tubes pass through the backup pad to be connected, and the both ends of backup pad all are equipped with the connecting plate, and the connecting plate is connected in the tip of two stay tubes, and two connecting plates are connected through same reinforcing plate, and the reinforcing plate is located between two stay tubes.
By adopting the technical scheme, the two supporting tubes and the two connecting plates form a frame body together in an enclosing manner, so that the supporting plates are stably supported; the reinforcing plate is used for connecting the two connecting plates, and the reinforcing plate and the two connecting plates jointly form an I-shaped plate, so that the overall strength of the platform plate is improved. The reinforcing plate and the supporting pipe are arranged in a hollow mode, so that the whole weight of the platform plate is reduced, and the platform plate is convenient to mount and carry.
Optionally, a plurality of first through holes are arranged on the supporting tube in sequence along the length direction of the supporting tube.
Through adopting above-mentioned technical scheme, the bolt can pass first through-hole to made things convenient for to fix stay tube locking on the support body, made things convenient for the installation of landing slab.
Optionally, the lower surface of backup pad is equipped with the receiver, is equipped with the opening on the receiver, and the opening part is equipped with the shut.
Through adopting above-mentioned technical scheme, in the transportation of landing slab, need be used for the bolt and the nut on this landing slab to store in the containing box.
Optionally, the closing plate rotates to be connected in the receiver, and the closing plate is kept away from to be equipped with the elastic plate that is used for supporting tight receiver inner wall in one of self rotation department.
Through adopting above-mentioned technical scheme, rotate when the closing plate and seal in the opening after, the elastic plate will support tightly in the inner wall of receiver for the closing plate is by spacing fixed, has guaranteed that the closing plate seals the open-ended stability.
Optionally, the elastic plate is provided with elastic protrusions, and the inner wall of the storage box is provided with clamping grooves for clamping the elastic protrusions.
Through adopting above-mentioned technical scheme, when the closing plate seals in the opening, the elastic plate will support tightly in the inner wall of receiver, and the elastic bulge will joint in the joint inslot to the stability of closing plate when sealing in the opening has been improved.
Optionally, the receiver is worn to locate by the reinforcing plate, and the reinforcing plate divides into two cavitys with the receiver inside, and two cavitys all communicate in the opening.
Through adopting above-mentioned technical scheme for bolt and nut can be put respectively in the cavity that corresponds, have realized the categorised placing of bolt and nut.
Optionally, the storage box is connected to the two support tubes through a plurality of fixing plates.
Through adopting above-mentioned technical scheme, receiver and fixed plate are connected two spinal branch vaulting poles as a whole to the bulk strength of landing slab has been improved.
Optionally, a plurality of second through holes are arranged on the connecting plate in sequence along the length direction of the connecting plate.
Through adopting above-mentioned technical scheme, the bolt can pass the second through-hole, has made things convenient for the connection of adjacent connecting plate, and the connecting plate of being convenient for is fixed on the support body.
To sum up, the application comprises the following beneficial technical effects:
1. the supporting tubes, the supporting plates, the connecting plates and the reinforcing plates are arranged, the two supporting tubes and the two connecting plates form a frame body together, and the reinforcing plates and the two connecting plates form an I-shaped plate together, so that the overall strength of the platform plate is improved; the reinforcing plate and the supporting pipe are arranged in a hollow manner, so that the overall weight of the platform plate is reduced, and the platform plate is convenient to mount and carry;
2. the storage box is arranged, and in the transportation process of the platform plate, bolts and nuts required to be used on the platform plate can be stored in the storage box;
3. the setting of fixed plate, receiver and fixed plate are connected two spinal branch vaulting poles as a whole to the bulk strength of landing slab has been improved.
Drawings
FIG. 1 is a schematic view of the overall structure in embodiment 1 of the present application;
FIG. 2 is a schematic view of the overall structure in embodiment 2 of the present application;
FIG. 3 is a schematic sectional view showing the whole structure in embodiment 2 of the present application;
fig. 4 is a partially enlarged schematic view at a in fig. 3.
Reference numerals are as follows: 1. supporting a tube; 11. a first through hole; 2. a support plate; 3. a connecting plate; 31. a second through hole; 4. a reinforcing plate; 5. a storage box; 51. an opening; 52. a closing plate; 53. a cavity; 54. a fixing plate; 55. an elastic plate; 56. an elastic bulge; 57. a clamping groove.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
Example 1:
the embodiment of the application discloses a platform board for a climbing frame. As shown in fig. 1, a platform board for a climbing frame comprises two support pipes 1 arranged at intervals, wherein the two support pipes 1 extend in the same direction; the same supporting plate 2 is welded on one side opposite to the two supporting tubes 1, and the upper surface of the supporting plate 2 is flush with the upper ends of the two supporting tubes 1; both ends of the supporting plate 2 are bent downwards to form connecting plates 3, and both ends of the connecting plates 3 are respectively welded at the end parts of the two supporting tubes 1. Two stay tubes 1 and two connecting plates 3 have enclosed into a framework jointly, have realized the stable support to backup pad 2.
The same reinforcing plate 4 is welded on one side opposite to the two connecting plates 3, and the reinforcing plate 4 is positioned between the two supporting tubes 1. The reinforcing plate 4 and the two connecting plates 3 form an I-shaped plate together, so that the overall strength of the platform plate is improved. The reinforcing plate 4 and the supporting tube 1 are arranged in a hollow mode, so that the whole weight of the platform plate is reduced, and the platform plate is convenient to mount and carry.
Be equipped with a plurality of first through-holes 11 of arranging in proper order along self length direction on the stay tube 1, the bolt can pass first through-hole 11 to made things convenient for to fix stay tube 1 locking on the support body, made things convenient for the installation of landing slab.
Be equipped with a plurality of second through-holes 31 of arranging in proper order along self length direction on connecting plate 3, the bolt can pass second through-hole 31, has made things convenient for adjacent connecting plate 3's connection, and the connecting plate 3 of being convenient for is fixed on the support body.
The implementation principle of the platform plate of the climbing frame in the embodiment of the application is as follows: two stay tubes 1 and two connecting plates 3 have enclosed into a framework jointly, and reinforcing plate 4 has formed worker's shape board jointly with two connecting plates 3 to the bulk strength of landing slab has been improved. Reinforcing plate 4, two stay tubes 1 and two connecting plates 3 have enclosed the bottom frame that has enclosed backup pad 2 jointly, have reduced the whole weight of landing slab to the installation and the transport of landing slab have been made things convenient for.
Example 2:
this example differs from example 1 in that: as shown in fig. 2 and 3, a storage box 5 is fixed on the lower surface of the support plate 2, an opening 51 is arranged at the lower side of the storage box 5, and a closing plate 52 rotatably connected to the storage box 5 is arranged at the opening 51; storage box 5 is worn to locate by reinforcing plate 4, and reinforcing plate 4 becomes two cavitys 53 with storage box 5 internal partitioning, and two cavitys 53 all communicate in opening 51. During transportation of the deck plate, bolts and nuts required for the deck plate can be stored in the two cavities 53, respectively.
The both ends of receiver 5 all connect in two spinal branch stay tubes 1 through two fixed plates 54, and fixed plate 54 is fixed in the lower surface of backup pad 2. The fixing plate 54 connects the storage box 5, the support tube 1 and the support plate 2 as a whole, and the stability of the platform plate is improved.
As shown in fig. 3 and 4, an elastic plate 55 is fixed on the end of the closing plate 52 away from the rotation position, an elastic protrusion 56 is fixed on the elastic plate 55, and a clamping groove 57 for clamping the elastic protrusion 56 is formed on the inner wall of the storage box 5. When closing plate 52 seals in opening 51, elastic plate 55 will support tightly in receiver 5's inner wall, and elastic bulge 56 will the joint in joint groove 57 to the stability of closing plate 52 when sealing in opening 51 has been improved.
The implementation principle of the platform plate of the climbing frame in the embodiment of the application is as follows: during transportation of the deck plate, the bolts and nuts required for the deck plate can be stored in the two cavities 53, respectively; the closing plate 52 will be closed in opening 51, and elastic plate 55 will support tightly in receiver 5's inner wall, and elastic bulge 56 will be the joint in joint groove 57, has improved the stability of closing plate 52 when closing in opening 51.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.
Claims (8)
1. The utility model provides a climb a platform board which characterized in that: including two stay tubes (1) that are the interval and set up, two stay tubes (1) are connected through backup pad (2), and the both ends of backup pad (2) all are equipped with connecting plate (3), and connecting plate (3) are connected in the tip of two stay tubes (1), and two connecting plates (3) are connected through same reinforcing plate (4), and reinforcing plate (4) are located between two stay tubes (1).
2. A creeper platform board as claimed in claim 1, wherein: the supporting tube (1) is provided with a plurality of first through holes (11) which are sequentially arranged along the length direction of the supporting tube.
3. A creeper platform board as claimed in claim 2, wherein: the lower surface of backup pad (2) is equipped with receiver (5), is equipped with opening (51) on receiver (5), and opening (51) department is equipped with closing plate (52).
4. A creeper platform board as claimed in claim 3, wherein: the closing plate (52) is rotatably connected to the storage box (5), and one end, far away from the rotating position of the closing plate (52), of the closing plate is provided with an elastic plate (55) used for tightly abutting against the inner wall of the storage box (5).
5. A creeper platform board as claimed in claim 4, wherein: be equipped with elastic bulge (56) on elastic plate (55), be equipped with joint groove (57) that supply elastic bulge (56) joint on the inner wall of receiver (5).
6. A creeper platform board as claimed in claim 3, wherein: receiver (5) are worn to locate in reinforcing plate (4), and two cavitys (53) are separated into with receiver (5) internal partitioning in reinforcing plate (4), and two cavitys (53) all communicate in opening (51).
7. A creeper platform board as claimed in claim 3, wherein: the storage box (5) is connected to the two support pipes (1) through a plurality of fixing plates (54).
8. A creeper platform board as claimed in claim 1, wherein: and a plurality of second through holes (31) which are sequentially arranged along the length direction of the connecting plate (3) are formed in the connecting plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220800114.4U CN217106105U (en) | 2022-04-06 | 2022-04-06 | Climbing frame platform plate |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220800114.4U CN217106105U (en) | 2022-04-06 | 2022-04-06 | Climbing frame platform plate |
Publications (1)
Publication Number | Publication Date |
---|---|
CN217106105U true CN217106105U (en) | 2022-08-02 |
Family
ID=82579823
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220800114.4U Active CN217106105U (en) | 2022-04-06 | 2022-04-06 | Climbing frame platform plate |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN217106105U (en) |
-
2022
- 2022-04-06 CN CN202220800114.4U patent/CN217106105U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
BRPI0509291B1 (en) | wind power installation | |
CN101117792A (en) | Erection method of large-span continuous steel truss arch | |
CN217106105U (en) | Climbing frame platform plate | |
FI77913B (en) | STATIVROER MED ETT ANTAL KONSOLARMAR, VARI BETONG INJICERAS, SAERSKILT FOER UPPBAERANDE AV BALKONGDAECK. | |
CN110005449A (en) | Open type TBM circle steel frame construction and its installation method | |
KR101628223B1 (en) | Perpendicular hall module and construction method for perpendicular hall using the same | |
CN213473470U (en) | Intelligent navigation mark lamp pile | |
CN212176685U (en) | Instrument formula foundation ditch hangs step ladder | |
CN115199476A (en) | Tower drum full-coating type reinforcing system and tower drum reinforcing method | |
JP3115544B2 (en) | Loading method of abutment bearing device | |
CN113062756A (en) | Semi-assembly type independent arch sheathing structure for tunnel zero-excavation hole entering and construction method thereof | |
CN212453885U (en) | Communication holding pole fixing structure | |
CN215329304U (en) | Connection structure of assembled bridge | |
CN112575788A (en) | Inner support structure for reinforcing foundation pit support and construction method | |
CN217760338U (en) | Anti-corrosion concrete pole | |
CN211174127U (en) | Tunnel skeleton location stable installation base | |
CN111734111A (en) | Assembled hoisting construction platform and installation method thereof | |
CN219412672U (en) | Prefabricated flue box culvert, integral assembly type flue structure and shield tunnel | |
CN217001431U (en) | Integrated connecting device arranged between passive door and concrete | |
CN218622285U (en) | Support system in cofferdam | |
CN217203667U (en) | Glue injection device for bridge maintenance | |
CN216277206U (en) | Reinforced structure suitable for single-pipe tower column foot bolt | |
CN216809602U (en) | Thin-wall hollow pier built-in derrick | |
CN217651601U (en) | Adjustable steel pipe column joint | |
CN217104691U (en) | Novel supporting template for highway bridge pier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |