CN217053458U - Retaining wall rapid construction template for water conservancy construction - Google Patents

Retaining wall rapid construction template for water conservancy construction Download PDF

Info

Publication number
CN217053458U
CN217053458U CN202220883784.7U CN202220883784U CN217053458U CN 217053458 U CN217053458 U CN 217053458U CN 202220883784 U CN202220883784 U CN 202220883784U CN 217053458 U CN217053458 U CN 217053458U
Authority
CN
China
Prior art keywords
water conservancy
plate
fixing
retaining wall
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220883784.7U
Other languages
Chinese (zh)
Inventor
罗军
李帅
潘雨馨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202220883784.7U priority Critical patent/CN217053458U/en
Application granted granted Critical
Publication of CN217053458U publication Critical patent/CN217053458U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The application discloses retaining wall fast construction template for water conservancy construction belongs to water conservancy construction equipment technical field, which comprises a fixing plate and i, the upper surface of fixed plate has been seted up and has been placed the chamber, two are seted up in the inside of fixed plate and have been deposited the chamber, every inside of depositing the chamber all activity hinge has the removal cover, the hydraulic stem is all installed to every inner wall that removes the cover, the removal post is all installed to the flexible end of every hydraulic stem, the back activity hinge of fixed plate has the fender soil board, two joint blocks are installed in the front of fender soil board, the inside all activity hinge of every joint block has the connecting rod, the bottom all activity hinge of every connecting rod has the connecting block. This retaining wall rapid construction template for water conservancy construction through the power that sets up the hydraulic stem and provide for the workman can withdraw the inside of removing the cover with removing the post, thereby makes things convenient for the workman to the recovery of removing the post, deposits the chamber through being provided with, makes the workman can rotate the inside of depositing the chamber with removing the cover after retrieving, thereby reduces the shared space of the device.

Description

Retaining wall rapid construction template for water conservancy construction
Technical Field
This application belongs to water conservancy construction equipment technical field, especially relates to a retaining wall rapid construction template for water conservancy construction.
Background
The water conservancy project is a project built for controlling and allocating surface water and underground water in the nature to achieve the purpose of removing harm and benefiting, water does not completely meet the requirements of human beings in a naturally existing state, the requirements of people's life and production on water resources can be met only by building the water conservancy project, and a retaining wall is required to be built when the water conservancy project is built, wherein the retaining wall is a structure for supporting roadbed filling or hillside soil bodies and preventing the filling or the soil bodies from deforming and destabilizing.
Most retaining wall template structure that has now is comparatively simple, and the workman can't be according to the angle of wall angle modulation template to lead to different walls to need use specific template, and then reduced the practicality of retaining wall template, and because most retaining wall template structure fixed, lead to the workman occupation space when retrieving great, be not convenient for the transportation of workman to the retaining wall template.
Therefore, the retaining wall rapid construction template for water conservancy construction is provided to solve the problems.
SUMMERY OF THE UTILITY MODEL
The purpose of this application is in order to solve prior art, the great problem of occupation space when unable adjustment template angle and recovery, and the retaining wall rapid construction template for water conservancy construction who provides.
In order to realize the purpose, the utility model adopts the following technical scheme:
a retaining wall rapid construction template for water conservancy construction comprises a fixed plate, wherein a placing cavity is formed in the upper surface of the fixed plate, two storing cavities are formed in the fixed plate, a moving sleeve is movably hinged in each storing cavity, a hydraulic rod is mounted on the inner wall of each moving sleeve, a moving column is mounted at the telescopic end of each hydraulic rod, and a retaining plate is movably hinged to the back surface of the fixed plate;
two joint blocks, every are installed in the front of fender apron the equal activity in inside of joint block articulates there is the connecting rod, every the equal activity in bottom of connecting rod articulates there is the connecting block, every the bottom surface of connecting block is all installed and is removed the seat, two remove the side that the cover is close to each other and two remove the side that the post is close to each other and all set up the screw hole that the equidistance was arranged, wherein two the equal threaded connection in inside of screw hole has fixing bolt, two the one end that fixing bolt kept away from each other all runs through in proper order and removes the seat and remove the cover and extend to the inside of removing the cover.
Preferably, the mounting panel is all installed to the both sides face of fixed plate, every the equal threaded connection in inside of mounting panel has connecting bolt, every connecting bolt's bottom all runs through the mounting panel and extends to the below of mounting panel.
Preferably, the back face of the retaining plate is provided with a connecting plate, the connecting plate is in threaded connection with a mounting bolt, and one end, far away from the fixing plate, of the mounting bolt penetrates through the connecting plate and extends to the back face of the connecting plate.
Preferably, the upper surface of the fixing plate is movably hinged with two fixing rods, and the back of the retaining plate is provided with two connecting holes.
Preferably, two fixing columns are mounted on the inner wall of the placing cavity, and a baffle is movably hinged to the outer surface of each fixing column.
Preferably, two supporting blocks are installed on the inner bottom wall of the placing cavity, and the upper surface of each supporting block is in contact with the bottom surface of the moving column.
Preferably, every the pulley is all installed to the upper surface and the bottom surface of removing the post, every two spouts, every have all been seted up to the inner wall of removal cover the equal sliding connection of pulley is in the inside of spout.
Preferably, the front surface of each group of pulleys is provided with a fixed seat, the inner wall of each fixed seat is fixedly connected with the outer surface of the hydraulic rod, and the outer surface of each fixed seat is fixedly connected with the inner wall of the movable sleeve.
To sum up, the technical effect and the advantage of this application:
1. the hydraulic rod is arranged on the movable sleeve, so that a worker can retract the movable column into the movable sleeve, the movable sleeve can be conveniently retracted by the worker, the movable sleeve can be rotated into the storage cavity by the worker due to the arrangement of the storage cavity, the occupied space of the device is reduced, the soil retaining plate can be retracted into the fixed plate due to the arrangement of the storage cavity, the occupied space of the device is further reduced, and the device is convenient to transport by the worker;
2. through being provided with joint piece, connecting rod and connecting block for the workman can keep off the angle of native board according to the angle modulation of wall, thereby makes the device be applicable to the wall of different angles, and then has increased the device's practicality, through being provided with fixing bolt, screw hole and removing the seat, has realized carrying out the purpose fixed to the connecting rod.
Drawings
Fig. 1 is a three-dimensional structure diagram of the fixing plate of the present invention;
FIG. 2 is a three-dimensional structure diagram of the back view of the earth-retaining plate of the present invention;
fig. 3 is a schematic structural view of a cross-sectional view of the movable sleeve of the present invention;
fig. 4 is a schematic view of the three-dimensional structure of the cross-sectional view of the fixing plate of the present invention.
In the figure: 1. a fixing plate; 2. a placement chamber; 3. a storage chamber; 4. moving the sleeve; 5. a hydraulic rod; 6. moving the column; 7. a soil guard plate; 8. a clamping block; 9. a connecting rod; 10. connecting blocks; 11. a movable seat; 12. a threaded hole; 13. fixing the bolt; 14. mounting a plate; 15. a connecting bolt; 16. a connecting plate; 17. installing a bolt; 18. fixing the rod; 19. connecting holes; 20. fixing a column; 21. a baffle plate; 22. a supporting block; 23. a pulley; 24. a chute; 25. a fixed seat.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-4, a quick construction template of retaining wall for water conservancy construction, including fixed plate 1, the upper surface of fixed plate 1 has been seted up and has been placed chamber 2, two are seted up in the inside of fixed plate 1 and have been deposited chamber 3, mounting panel 14 is all installed to the both sides face of fixed plate 1, the equal threaded connection in inside of every mounting panel 14 has connecting bolt 15, the bottom of every connecting bolt 15 all runs through mounting panel 14 and extends to the below of mounting panel 14, utilize connecting bolt 15 with mounting panel 14 and ground looks fixed connection, avoid the device to take place automatic movement's phenomenon as far as possible, the device's stability has been guaranteed.
Every inside of depositing chamber 3 is all articulated to have and is had removal cover 4, hydraulic stem 5 is all installed to every inner wall that removes cover 4, the flexible end of every hydraulic stem 5 is all installed and is removed post 6, the back activity of fixed plate 1 articulates there is fender apron 7, the back mounted of fender apron 7 has connecting plate 16, the internal thread connection of connecting plate 16 has construction bolt 17, construction bolt 17 keeps away from the one end through connection board 16 of fixed plate 1 and extends to the back of connecting plate 16, utilize construction bolt 17 with connecting plate 16 and wall looks fixed connection, keep away as far as possible and keep off the phenomenon that fender apron 7 takes place the slope, the stability of fender apron 7 has been guaranteed.
The activity of the upper surface of fixed plate 1 articulates there are two dead levers 18, and two connecting holes 19 have been seted up at the back of retaining plate 7, with the inside of dead lever 18 joint at connecting hole 19 for when the workman transported the device, the phenomenon of avoiding retaining plate 7 to open automatically as far as possible takes place, has further guaranteed the stability of retaining plate 7.
The inner wall of the placing cavity 2 is provided with two fixing columns 20, the outer surface of each fixing column 20 is movably hinged with a baffle 21, and the fixing columns 20 and the baffles 21 are arranged to prevent the device from sliding away from the storing cavity 3 when the device is transported, so that the stability of the moving sleeve 4 is ensured.
Two clamping blocks 8 are arranged on the front surface of the retaining plate 7, a connecting rod 9 is movably hinged inside each clamping block 8, a connecting block 10 is movably hinged at the bottom end of each connecting rod 9, a moving seat 11 is arranged on the bottom surface of each connecting block 10, threaded holes 12 which are arranged equidistantly are formed in one side surface of each moving sleeve 4 and one side surface of each moving column 6, wherein the two threaded holes 12 are connected with fixing bolts 13 in a threaded manner, one ends of the two fixing bolts 13, which are far away from each other, sequentially penetrate through the moving seat 11 and the moving sleeve 4 and extend into the moving sleeve 4, the retaining plate 7 is driven to rotate by the connecting rod 9, so that a worker can adjust the angle of the retaining plate 7 according to needs, the moving seat 11 is connected with the threaded holes 12 by using the fixing bolts 13, thereby fixing the connecting rod 9, two supporting blocks 22 are arranged on the inner bottom wall of the placing cavity 2, the upper surface of every supporting shoe 22 all contacts with the bottom surface that removes post 6, and supporting shoe 22's installation has played the effect that supports removal post 6, avoids removing post 6 as far as possible and takes place the phenomenon of rocking, has guaranteed the stability that removes post 6.
Every upper surface and the bottom surface that removes post 6 all install pulley 23, and two spouts 24 have all been seted up to the inner wall of every removal cover 4, and every pulley 23 equal sliding connection is in the inside of spout 24, and the phenomenon of skew orbit takes place for removal post 6 when removing is avoided as far as possible in the installation of pulley 23 and spout 24 to the stability that removes post 6 and remove has been guaranteed.
The front of every group pulley 23 all is provided with fixing base 25, the inner wall of every fixing base 25 all with the outer fixed surface connection of hydraulic stem 5, the surface of every fixing base 25 all with the inner wall fixed connection who removes cover 4, the effect of fixing and supporting hydraulic stem 5 has been played in the installation of fixing base 25, avoids hydraulic stem 5 as far as possible to take place the phenomenon of rocking at the during operation, has guaranteed hydraulic stem 5's stability.
The working principle of the utility model is that; when the device is used, the hydraulic rod 5 is firstly communicated with a power supply, when a worker installs the device, the mounting plate 14 is firstly connected with the ground by using the connecting bolt 15, then the worker pulls the retaining plate 7, then the baffle plate 21 is rotated, the movable sleeve 4 is taken out from the inner part of the storage cavity 3, then the worker clamps the movable seat 11 on the outer surface of the movable sleeve 4, then the worker opens the hydraulic rod 5, the movable column 6 is driven by the power provided by the hydraulic rod 5 to move backwards, so that the movable column 6 is contacted with the supporting block 22, then the worker adjusts the position of the movable seat 11 according to the angle of the wall surface, then the worker fixedly connects the movable seat 11 with the threaded hole 12 by using the fixing bolt 13, thereby completing the process of adjusting the angle of the retaining plate 7, and further increasing the practicability of the device, when the worker recovers the device, the worker takes down the fixing bolt 13 firstly, then the worker opens the hydraulic rod 5, make the power that hydraulic stem 5 provided drive and move post 6 forward movement to with removing the inside of post 6 recovery removal cover 4, then the workman will remove seat 11 and take out from the surface of removal cover 4, later the workman takes off construction bolt 17, and rotate baffle 21, then will remove the cover 4 and rotate to the inside of depositing chamber 3, and make baffle 21 block and remove cover 4, later the workman will keep off the inside of board 7 recovery placing chamber 2, and rotate dead lever 18, make dead lever 18 joint in the inside of connecting hole 19, thereby accomplish the recovery of the device, and then reduced the space that the device took up.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and for simplicity of description, but do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically limited otherwise.
The above, only be the embodiment of the preferred of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, which are designed to be replaced or changed equally, all should be covered within the protection scope of the present invention.

Claims (8)

1. The utility model provides a water conservancy construction is with quick construction formwork of retaining wall, includes fixed plate (1), its characterized in that: a placing cavity (2) is formed in the upper surface of the fixing plate (1), two storing cavities (3) are formed in the fixing plate (1), a moving sleeve (4) is movably hinged in each storing cavity (3), a hydraulic rod (5) is mounted on the inner wall of each moving sleeve (4), a moving column (6) is mounted at the telescopic end of each hydraulic rod (5), and a soil retaining plate (7) is movably hinged to the back surface of the fixing plate (1);
two joint blocks (8), every are installed in the front of retaining plate (7) the inside equal activity of joint block (8) articulates there is connecting rod (9), every the bottom equal activity of connecting rod (9) articulates there is connecting block (10), every removal seat (11), two are all installed to the bottom surface of connecting block (10) remove the side that cover (4) are close to each other and two remove a side that post (6) are close to each other and all set up screw hole (12) that the equidistance was arranged, wherein two the inside equal threaded connection of screw hole (12) has fixing bolt (13), two the one end that fixing bolt (13) kept away from each other all runs through in proper order and removes seat (11) and remove cover (4) and extend to the inside of removing cover (4).
2. The retaining wall rapid construction template for water conservancy construction according to claim 1, characterized in that: mounting panel (14), every are all installed to the both sides face of fixed plate (1) the equal threaded connection in inside of mounting panel (14) has connecting bolt (15), every the bottom of connecting bolt (15) all runs through mounting panel (14) and extends to the below of mounting panel (14).
3. The retaining wall rapid construction template for water conservancy construction according to claim 1, characterized in that: the back mounted who keeps off native board (7) has connecting plate (16), the inside threaded connection of connecting plate (16) has construction bolt (17), the one end that fixed plate (1) was kept away from in construction bolt (17) runs through connecting plate (16) and extends to the back of connecting plate (16).
4. The retaining wall rapid construction template for water conservancy construction according to claim 1, characterized in that: the upper surface of the fixing plate (1) is movably hinged with two fixing rods (18), and the back of the soil retaining plate (7) is provided with two connecting holes (19).
5. The retaining wall rapid construction template for water conservancy construction according to claim 1, characterized in that: two fixing columns (20) are installed on the inner wall of the placing cavity (2), and a baffle (21) is movably hinged to the outer surface of each fixing column (20).
6. The retaining wall rapid construction template for water conservancy construction according to claim 1, characterized in that: two supporting blocks (22) are installed on the inner bottom wall of the placing cavity (2), and the upper surface of each supporting block (22) is in contact with the bottom surface of the moving column (6).
7. The retaining wall rapid construction template for water conservancy construction according to claim 1, characterized in that: every pulley (23) are all installed to the upper surface and the bottom surface of removal post (6), every two spout (24), every have all been seted up to the inner wall of removal cover (4) the equal sliding connection of pulley (23) is in the inside of spout (24).
8. The retaining wall rapid construction template for water conservancy construction according to claim 7, characterized in that: every group the front of pulley (23) all is provided with fixing base (25), every the inner wall of fixing base (25) all is connected with the surface fixed of hydraulic stem (5), every the surface of fixing base (25) all with the inner wall fixed connection who removes cover (4).
CN202220883784.7U 2022-04-15 2022-04-15 Retaining wall rapid construction template for water conservancy construction Active CN217053458U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220883784.7U CN217053458U (en) 2022-04-15 2022-04-15 Retaining wall rapid construction template for water conservancy construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220883784.7U CN217053458U (en) 2022-04-15 2022-04-15 Retaining wall rapid construction template for water conservancy construction

Publications (1)

Publication Number Publication Date
CN217053458U true CN217053458U (en) 2022-07-26

Family

ID=82472280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220883784.7U Active CN217053458U (en) 2022-04-15 2022-04-15 Retaining wall rapid construction template for water conservancy construction

Country Status (1)

Country Link
CN (1) CN217053458U (en)

Similar Documents

Publication Publication Date Title
CN211371469U (en) Quick pipeline erection support frame with adjustable
CN109487701B (en) Construction method of adjustable bent cap die
CN212865963U (en) Foundation pit supporting device for civil engineering construction
CN217053458U (en) Retaining wall rapid construction template for water conservancy construction
CN209990109U (en) Cement mortar ground equipment of making level for building
CN116237553A (en) Boring device for crawler excavator chain piece
CN214119537U (en) Novel mining machinery supporting platform
CN213625647U (en) Building foundation ditch water retaining structure
CN212164460U (en) Novel nursery stock is transplanted with multi-functional keep-alive device
CN112797228A (en) Seismic-isolation laying method for water conservancy pipeline
CN216999763U (en) Municipal administration pipeline slot supporting construction
CN214839538U (en) Adjustment mechanism of support for engineering construction
CN217636714U (en) Rotary kiln cold smoke chamber mounting structure
CN219952759U (en) Mounting device for embedded part
CN217480193U (en) Foundation pit supporting pile
CN214006498U (en) Guide rail pavement board connector convenient to connect and mount for lifting scaffold
CN212249073U (en) Surrounding rock tunnel pipe shed installation device
CN218757653U (en) Movable type high-rise building raft plate concrete crack automatic filling device
CN213806173U (en) Concrete constructional column structure for construction
CN218134685U (en) Shield segment steel bar die welding explorator capable of adjusting steel bar spacing
CN217760861U (en) Water conservancy construction buries effective fluting device that digs
CN220666658U (en) Building floor structure
CN215359489U (en) Forming device for machining excavator handrail
CN215931870U (en) Geotechnical engineering landslide model test device
CN212200246U (en) Adjustable scaffold for water conservancy construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant