CN216999687U - Lead wall construction structures - Google Patents

Lead wall construction structures Download PDF

Info

Publication number
CN216999687U
CN216999687U CN202220186556.4U CN202220186556U CN216999687U CN 216999687 U CN216999687 U CN 216999687U CN 202220186556 U CN202220186556 U CN 202220186556U CN 216999687 U CN216999687 U CN 216999687U
Authority
CN
China
Prior art keywords
picture peg
hexagonal
wall construction
guide wall
spout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220186556.4U
Other languages
Chinese (zh)
Inventor
黄傲傲
曾金中
许光麟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN202220186556.4U priority Critical patent/CN216999687U/en
Application granted granted Critical
Publication of CN216999687U publication Critical patent/CN216999687U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mirrors, Picture Frames, Photograph Stands, And Related Fastening Devices (AREA)

Abstract

The utility model discloses a guide wall construction structure, which belongs to the technical field of guide walls and comprises two installation frames, wherein two installation holes are respectively formed in the front ends of the two installation frames, two connecting rods are movably inserted between the four installation holes, a lower inserting plate and an upper inserting plate are movably inserted in the two installation frames, the lower inserting plate is positioned on the lower side of the upper inserting plate, and side inserting plates are respectively arranged on the upper sides of the two connecting rods.

Description

Lead wall construction structures
Technical Field
The utility model relates to the technical field of guide walls, in particular to a guide wall construction structure.
Background
The guide wall is a construction measure mode of a construction unit, the guide wall is constructed before grooving of the underground continuous wall, the guide wall is a key for ensuring the accurate position and grooving quality of the underground continuous wall, and during construction, the guide wall always bears the static and dynamic loads of a reinforcement cage, a guide pipe for pouring concrete, a drilling machine and the like, so that formal construction of the underground continuous wall can be carried out only by careful design and construction.
The guide wall commonly used at present is combined slowly when being installed, so that the construction efficiency of the guide wall is influenced, and the guide wall construction structure is provided for solving the problem.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
Aiming at the problems in the prior art, the utility model aims to provide a guide wall construction structure which can improve the convenience of combination in an inserting mode, uses fewer screws when combining a guide wall and optimizes the combination speed.
2. Technical scheme
In order to solve the problems, the utility model adopts the following technical scheme:
the utility model provides a lead wall construction structures, includes two installing frames, two mounting holes, four have all been seted up to the front end of two installing frames activity is pegged graft between the mounting hole has two connecting rods, two equal activity is pegged graft in the installing frame has lower picture peg and last picture peg, and the lower picture peg is located the downside of picture peg, two the upside of connecting rod all is provided with the side picture peg.
As a preferred scheme of the present invention, two first sliding grooves are formed in each of the two mounting frames, a screw is rotatably connected in each of the first sliding grooves, threaded sleeves are fixedly connected to both left and right ends of the lower insert plate, the four threaded sleeves are in threaded connection with surfaces of the four screws, the four threaded sleeves are in sliding connection with the four first sliding grooves, sliders are fixedly connected to both left and right ends of the two upper insert plates, the four sliders are in sliding connection with surfaces of the four screws, and the four sliders are in sliding connection with the four first sliding grooves.
As a preferred scheme of the utility model, the lower ends of the two upper inserting plates are fixedly connected with inserting strips, the upper ends of the two lower inserting plates are provided with inserting slots, and the two inserting strips are movably inserted into the two inserting slots respectively.
According to a preferable scheme of the utility model, the ends, close to each other, of the two mounting frames are fixedly connected with sliding plates, the front ends and the rear ends of the two side edge inserting plates are respectively provided with a second sliding groove, and the four sliding plates are in sliding fit with the four second sliding grooves.
As a preferable scheme of the utility model, the upper ends of the four screw rods are respectively provided with a hexagonal jack, the upper ends of the four hexagonal jacks are movably inserted with a hexagonal inserted rod, and the upper ends of the four hexagonal inserted rods are respectively fixedly connected with a rotating handle.
As a preferred scheme of the utility model, a fixed frame is installed at the upper end of the installation frame, the four screw rods movably penetrate through the fixed frame, and the fixed frame is detachably connected with the two upper insertion plates through fixing screws.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages that:
(1) when the device needs to be used, firstly, two mounting frames are erected, then the connecting rod is inserted into the mounting hole, then the threaded sleeve is sleeved on the surface of the screw rod, the hexagonal inserted rod is inserted into the hexagonal inserted hole when the threaded sleeve is sleeved on the surface of the screw rod, then the handle is rotated in a forward rotation mode, the forward rotation of the handle is clamped between the hexagonal inserted rod and the hexagonal inserted hole to drive the screw rod to rotate in the forward rotation mode, the forward rotation of the screw rod enables the threaded sleeve to move downwards on the surface of the screw rod, the downward movement of the threaded sleeve drives the lower inserted plate to move downwards, the handle is stopped rotating after the threaded sleeve moves downwards until the lower inserted plate is contacted with the mounting frames, the hexagonal inserted rod is taken out of the hexagonal inserted hole at the moment, then the sliding block is sleeved on the surface of the screw rod, the inserting strip is inserted into the slot after the sliding block is sleeved on the surface of the screw rod, at the moment, the front side and the rear side edges of the mounting frames are combined, then the side edge inserted plates are held by hands, the sliding plate is inserted into the second sliding groove, the side edges are combined at the moment, then the fixing frame is sleeved on the surfaces of the four screw rods, the fixing frame is fixed on the upper inserting plate through the fixing screws, so that the fixing stability of the upper inserting plate is optimized.
(2) In this scheme, the offering of hexagonal jack is for the convenience of hexagonal inserted bar grafting, and the sliding fit of hexagonal jack and hexagonal inserted bar is convenient for rotate the screw rod, needs the explanation be: the hexagonal insertion hole and the hexagonal insertion rod can be in other shapes except a circular shape, and the rotating handle is convenient to rotate the hexagonal insertion rod.
Drawings
Fig. 1 is a front perspective view of a guide wall construction structure of the present invention;
FIG. 2 is a bottom perspective view of a guide wall construction structure of the present invention;
fig. 3 is an exploded view of a guide wall construction structure according to the present invention;
fig. 4 is an enlarged view of a portion a of fig. 3 of a guide wall construction structure according to the present invention.
The reference numbers in the figures illustrate:
1. installing a frame; 2. mounting holes; 3. a connecting rod; 4. a first chute; 5. a screw; 6. a hexagonal jack; 7. a hexagonal inserted link; 8. turning a handle; 9. a lower inserting plate; 10. a threaded sleeve; 11. inserting slots; 12. an upper plug board; 13. cutting; 14. a slider; 15. a slide plate; 16. side edge inserting plates; 17. a second chute; 18. a fixing frame; 19. and fixing the screw.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention. It is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments, and all other embodiments obtained by those skilled in the art without any inventive work are within the scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "top/bottom", etc. indicate orientations or positional relationships based on orientations or positional relationships shown in the drawings, which are merely for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and the like are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "sleeved/connected," "connected," and the like are to be construed broadly, e.g., "connected," which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The embodiment is as follows:
referring to fig. 1-4, a guide wall construction structure includes two installation frames 1, two installation holes 2 are respectively formed at the front ends of the two installation frames 1, two connection rods 3 are movably inserted between the four installation holes 2, a lower insertion plate 9 and an upper insertion plate 12 are movably inserted in the two installation frames 1, the lower insertion plate 9 is located at the lower side of the upper insertion plate 12, and side insertion plates 16 are respectively disposed at the upper sides of the two connection rods 3.
In the embodiment, firstly, two mounting frames 1 are erected, then a connecting rod 3 is inserted into a mounting hole 2, then a threaded sleeve 10 is sleeved on the surface of a screw rod 5, when the threaded sleeve 10 is sleeved on the surface of the screw rod 5, a hexagonal inserted rod 7 is inserted into a hexagonal insertion hole 6, then a rotating handle 8 is rotated in a forward direction, the forward rotation of the rotating handle 8 is clamped by the hexagonal inserted rod 7 and the hexagonal insertion hole 6 to drive the screw rod 5 to rotate in the forward direction, the forward rotation of the screw rod 5 enables the threaded sleeve 10 to move downwards on the surface of the screw rod 5, the downward movement of the threaded sleeve 10 drives a lower insertion plate 9 to move downwards, when the threaded sleeve 10 moves downwards until the lower insertion plate 9 is in contact with the mounting frames 1, the rotating handle 8 stops rotating, at the moment, the hexagonal inserted rod 7 is taken out of the hexagonal insertion hole 6, then a sliding block 14 is sleeved on the surface of the screw rod 5, and then an insertion strip 13 is inserted into an insertion slot 11 after the sliding block 14 is sleeved on the surface of the screw rod 5, the front side and the rear side of the installation frame 1 are combined, then the side edge inserting plate 16 is held by hands, the sliding plate 15 is inserted into the second sliding groove 17, the side edge is combined, then the fixing frame 18 is sleeved on the surfaces of the four screw rods 5, the fixing frame 18 is fixed on the upper inserting plate 12 through the fixing screw 19, so that the fixing stability of the upper inserting plate 12 is optimized.
Specifically, two first spouts 4 have all been seted up on two installing frames 1, all rotate in every first spout 4 and be connected with screw rod 5, lower picture peg 9 about the equal fixedly connected with threaded sleeve 10 in both ends, four threaded sleeve 10 threaded connection are on the surface of four screw rods 5, four threaded sleeve 10 sliding connection are in four first spouts 4, two go up picture peg 12 about the equal fixedly connected with slider 14 in both ends, 14 sliding connection of four sliders are on the surface of four screw rods 5, and 14 sliding connection of four sliders are in four first spouts 4.
In the embodiment, the first sliding chute 4 is used for facilitating the sliding of the threaded sleeve 10 and the sliding block 14, the screw 5 is used for facilitating the threaded connection of the threaded sleeve 10, the lower insert plate 9 is fixed through the threaded matching of the screw 5 and the threaded sleeve 10, and the upper insert plate 12 is used for facilitating the sliding on the surface of the screw 5.
Specifically, the lower ends of the two upper inserting plates 12 are fixedly connected with inserting strips 13, the upper ends of the two lower inserting plates 9 are provided with inserting grooves 11, and the two inserting strips 13 are movably inserted into the two inserting grooves 11 respectively.
In this embodiment, the slot 11 is opened to facilitate the insertion of the slip 13, and the engagement between the slot 11 and the slip 13 optimizes the connection stability.
Specifically, two equal fixedly connected with slide 15 of one end that installing frame 1 is close to mutually, second spout 17 has all been seted up at both ends around two side picture pegs 16, four slide 15 and four second spout 17 sliding fit.
In this embodiment, the slide plate 15 is for facilitating sliding engagement with the second slide groove 17, and the position of the side insert plate 16 is fixed by the sliding engagement of the slide plate 15 and the second slide groove 17.
Specifically, hexagonal jacks 6 have all been seted up to four screw rods 5's upper end, and the equal activity of four hexagonal jacks 6's upper end is pegged graft and is had hexagonal inserted bar 7, and the equal fixedly connected with in four hexagonal inserted bar 7's upper end changes 8.
In this embodiment, the hexagonal socket 6 is provided for the insertion of the hexagonal inserting rod 7, the sliding fit between the hexagonal socket 6 and the hexagonal inserting rod 7 facilitates the rotation of the screw rod 5, and what needs to be described is: the hexagonal socket 6 and the hexagonal insertion rod 7 can be in other shapes than circular, and the rotating handle 8 is used for facilitating the rotation of the hexagonal insertion rod 7.
Specifically, a fixed frame 18 is installed at the upper end of the installation frame 1, the four screw rods 5 penetrate through the fixed frame 18 in a movable mode, and the fixed frame 18 is detachably connected with the two upper insertion plates 12 through fixing screws 19.
In this embodiment, the fixing frame 18 is sleeved on the surfaces of the four screws 5, and the fixing frame 18 is fixed on the upper insertion plate 12 through the fixing screws 19, so as to optimize the fixing stability of the upper insertion plate 12.
The working principle is as follows: firstly, two mounting frames 1 are erected, then a connecting rod 3 is inserted into a mounting hole 2, then a threaded sleeve 10 is sleeved on the surface of a screw rod 5, when the threaded sleeve 10 is sleeved on the surface of the screw rod 5, a hexagonal inserted bar 7 is inserted into a hexagonal insertion hole 6, then a handle 8 is rotated forward, forward rotation of the handle 8 is realized through clamping of the hexagonal inserted bar 7 and the hexagonal insertion hole 6, the screw rod 5 is driven to rotate forward, forward rotation of the screw rod 5 enables the threaded sleeve 10 to move downwards on the surface of the screw rod 5, downward movement of the threaded sleeve 10 drives a lower insertion plate 9 to move downwards, when the threaded sleeve 10 moves downwards until the lower insertion plate 9 is in contact with the mounting frames 1, rotation of the handle 8 is stopped, at the moment, the hexagonal inserted bar 7 is taken out of the hexagonal insertion hole 6, then a sliding block 14 is sleeved on the surface of the screw rod 5, the sliding block 14 is sleeved on the surface of the screw rod 5, an insertion strip 13 is inserted into an insertion slot 11, at the moment, and the front side and the back side of the mounting frames 1 are combined, then, the side inserting plate 16 is held by hand, the sliding plate 15 is inserted into the second sliding groove 17, the side edge is combined, then the fixing frame 18 is sleeved on the surfaces of the four screw rods 5, the fixing frame 18 is fixed on the upper inserting plate 12 through the fixing screw 19, so that the fixing stability of the upper inserting plate 12 is optimized.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the equivalent replacement or change according to the technical solution and the modified concept of the present invention should be covered by the scope of the present invention.

Claims (6)

1. The utility model provides a lead wall construction structures, includes two installing frame (1), its characterized in that: two mounting holes (2), four have all been seted up to the front end of two installing frame (1) the activity is pegged graft between mounting hole (2) has two connecting rods (3), two equal activity is pegged graft in installing frame (1) has lower picture peg (9) and last picture peg (12), and lower picture peg (9) are located the downside of picture peg (12), two the upside of connecting rod (3) all is provided with side picture peg (16).
2. A guide wall construction structure according to claim 1, wherein: two all seted up two first spout (4), every on installing frame (1) all rotate in first spout (4) and be connected with screw rod (5), lower picture peg (9) about the equal fixedly connected with threaded sleeve (10) in both ends, four threaded sleeve (10) threaded connection is in the surface of four screw rods (5), four threaded sleeve (10) sliding connection is in four first spout (4), two go up picture peg (12) about the equal fixedly connected with slider (14) in both ends, four slider (14) sliding connection is in the surface of four screw rods (5), and four slider (14) sliding connection are in four first spout (4).
3. A guide wall construction structure according to claim 2, wherein: two equal fixedly connected with cutting (13) of lower extreme of last picture peg (12), two slot (11) have all been seted up to the upper end of lower picture peg (9), two cutting (13) activity is pegged graft respectively in two slots (11).
4. A guide wall construction structure according to claim 3, wherein: two equal fixedly connected with slide (15), two of one end that installing frame (1) is close to mutually second spout (17), four have all been seted up at both ends around side picture peg (16) slide (15) and four second spout (17) sliding fit.
5. The guide wall construction structure according to claim 4, wherein: hexagonal jacks (6) are formed in the upper ends of the four screw rods (5), hexagonal inserting rods (7) are movably inserted into the upper ends of the hexagonal jacks (6), and the upper ends of the hexagonal inserting rods (7) are fixedly connected with rotating handles (8).
6. A guide wall construction structure according to claim 5, wherein: fixed frame (18), four are installed to the upper end of installing frame (1) the equal activity of screw rod (5) runs through fixed frame (18), fixed frame (18) can be dismantled through set screw (19) with two last picture peg (12) and be connected.
CN202220186556.4U 2022-01-24 2022-01-24 Lead wall construction structures Active CN216999687U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220186556.4U CN216999687U (en) 2022-01-24 2022-01-24 Lead wall construction structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220186556.4U CN216999687U (en) 2022-01-24 2022-01-24 Lead wall construction structures

Publications (1)

Publication Number Publication Date
CN216999687U true CN216999687U (en) 2022-07-19

Family

ID=82390640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220186556.4U Active CN216999687U (en) 2022-01-24 2022-01-24 Lead wall construction structures

Country Status (1)

Country Link
CN (1) CN216999687U (en)

Similar Documents

Publication Publication Date Title
CN216999687U (en) Lead wall construction structures
CN218498610U (en) Automatically controlled cabinet of combination convenient to dismantle maintenance
CN215551770U (en) Positioning device for printing of advertising board
CN211172865U (en) Panel mounting structure for building decoration
CN211923569U (en) Accurate positioning tool of assembled building foundation post muscle
CN210536077U (en) Block terminal is with making an uproar acoustic celotex board that falls convenient to installation
CN211114899U (en) Assembling tool for prefabricated building
CN214123289U (en) High strength structure's miniature view sand table
CN218842699U (en) A fabric cutting machine for accurately cut cloth
CN216371151U (en) Clamping and positioning device for machining automobile parts
CN219604877U (en) Template connecting piece
CN220188062U (en) Rock soil sampling shovel
CN213034095U (en) Aluminum alloy profile drilling and polishing equipment
CN219521227U (en) Machine tool base positioning structure
CN219269007U (en) Industrial gateway
CN220621057U (en) External member for construction square timber
CN219926263U (en) Plastic part processing drilling equipment
CN212376084U (en) Assembled wallboard convenient to dismantle
CN215476765U (en) Drawing save set for engineering cost
CN217942640U (en) Positioning tool for die machining
CN214490347U (en) Double-specification sleeve
CN219100479U (en) Filling steel plate convenient to disassemble
CN217353517U (en) Standard general internal corner aluminum template for building
CN220480286U (en) Novel handle positioning puncher
CN214321960U (en) Milling machine cutter fixing mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant