CN216948287U - Can dismantle concrete placement cluster bucket - Google Patents

Can dismantle concrete placement cluster bucket Download PDF

Info

Publication number
CN216948287U
CN216948287U CN202220459811.8U CN202220459811U CN216948287U CN 216948287 U CN216948287 U CN 216948287U CN 202220459811 U CN202220459811 U CN 202220459811U CN 216948287 U CN216948287 U CN 216948287U
Authority
CN
China
Prior art keywords
chain
kebab
concrete
string
feeding hopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220459811.8U
Other languages
Chinese (zh)
Inventor
王甜
杜鹏
张小波
马海龙
蒋正轲
胡晓冬
丁燚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Luoning Pumped Storage Co ltd
State Grid Xinyuan Co Ltd
Original Assignee
Henan Luoning Pumped Storage Co ltd
State Grid Xinyuan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Luoning Pumped Storage Co ltd, State Grid Xinyuan Co Ltd filed Critical Henan Luoning Pumped Storage Co ltd
Priority to CN202220459811.8U priority Critical patent/CN216948287U/en
Application granted granted Critical
Publication of CN216948287U publication Critical patent/CN216948287U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/16Mechanical energy storage, e.g. flywheels or pressurised fluids

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to the technical field of concrete pouring, in particular to a detachable concrete pouring string barrel which comprises a tripod, wherein the tripod comprises two vertical rods and two inclined rods, a fixed plate is connected between the two inclined rods, a feeding hopper is arranged on the fixed plate, two ends of the feeding hopper are cylindrical sections, the middle of the feeding hopper is a hopper section, the cylindrical section at the upper end of the feeding hopper is connected with a fixed connecting part, a chain hook is arranged on the cylindrical section at the lower end of the feeding hopper, a string barrel is arranged at the cylindrical section at the lower end of the feeding hopper, a closed lifting lug is arranged at the upper end of the string barrel, a chain is arranged on the closed lifting lug, and the chain is hooked with the chain hook. The concrete filling device is used at rugged parts of roads or parts with large height difference, concrete is introduced into the string barrels through the feeding hopper, and the concrete reaches a pouring place through a channel connected with the string barrels, so that the concrete pouring delay caused by the fact that the concrete tank truck cannot reach the pouring place is avoided.

Description

Can dismantle concrete placement cluster bucket
Technical Field
The utility model relates to the technical field of concrete pouring, in particular to a detachable concrete pouring string barrel.
Background
The pumped storage power station is a hydropower station which pumps water to an upper reservoir by using electric energy in the low ebb period of the electric load and discharges water to a lower reservoir to generate electricity in the peak period of the electric load. In the construction process of the pumped storage power station, the road conditions in the site are complex, the excavation amount is large, the road is rugged, the concrete pouring amount of a road retaining wall and the like is large, a concrete tank truck cannot reach a construction part, so that the concrete cannot be poured normally, the construction progress of the pumped storage power station is delayed, the construction period is influenced, and meanwhile, the concrete cannot be manually transported for pouring because the road and the construction site have large height difference, so that the design of the detachable concrete pouring string barrel convenient for concrete pouring is particularly important.
Disclosure of Invention
The utility model provides a detachable concrete pouring string barrel, aiming at solving the problems that concrete cannot be transported to a construction site and cannot be poured normally at rough parts of a road or parts with large vertical height difference, and the string barrel can lead the concrete in a concrete tank truck to the pouring site and accelerate the pouring speed.
In order to achieve the purpose, the technical scheme of the utility model is as follows:
a detachable concrete pouring string barrel comprises a tripod, wherein the tripod comprises two vertical rods and two inclined rods, the top ends of the vertical rods are connected with the top ends of the inclined rods, a fixed plate is connected between the two inclined rods, the fixed plate is positioned on the upper parts of the inclined rods, a through hole is formed in the fixed plate, a feeding funnel is arranged on the through hole, two ends of the feeding funnel are cylindrical sections, the middle of the feeding funnel is a funnel section, the diameter of the cylindrical section at the upper end of the feeding funnel is the same as that of the through hole of the fixed plate, the cylindrical section at the upper end of the feeding funnel is connected with a fixed connecting part, a threaded hole is formed in the fixed connecting part, and the feeding funnel is fixed on the fixed plate through the fixed connecting part;
be equipped with the chain couple on the feed hopper lower extreme cylinder section, feed hopper lower extreme cylinder section department is equipped with the cluster bucket, the cluster bucket is the toper setting, cluster bucket top diameter is greater than cluster bucket bottom diameter, cluster bucket upper end is equipped with closed lug, be equipped with the chain on the closed lug, the chain articulates with the chain couple. Concrete is introduced into the string barrel through the feeding hopper, and the concrete reaches a pouring place through a channel connected with the string barrel, so that the rapid pouring of the retaining wall at the rugged road part is realized, and the concrete pouring delay caused by the fact that the concrete tank truck cannot reach the pouring place is avoided.
Furtherly, two be connected with the horizontal pole between the montant, be equipped with the backup pad on the horizontal pole, the backup pad is the arc, the backup pad is located feed hopper funnel section below. Prevent that feed hopper atress extrusion from appearing warping, influence feed hopper's unloading effect.
Furthermore, the vertical rod and the diagonal rod are both fixed on the edge of the road, and the vertical rod is perpendicular to the edge of the road.
Further, the lower end of the string barrel is provided with a chain hook, the chain hook is U-shaped, a cross column below the chain hook is connected with the string barrel, and a gap is formed between the cross column above the chain hook and the string barrel.
Furthermore, a plurality of string barrels are arranged at the lower end of the feeding hopper, the string barrels are connected through a chain, and the chain is connected with a closed lifting lug and a chain hook on the adjacent string barrels. The chain is connected with the adjacent string barrel through the gap between the chain hook and the string barrel, so that the installation and the disassembly are convenient.
Further, a rope is tied on the tripod and connected to the tail end of the stringing barrel along the stringing direction, and a cross buckle is tied at the middle section of each stringing barrel. Use the rope to connect the cluster bucket, when preventing that the cluster bucket from transferring along the slope, the chain connection between the adjacent cluster bucket is loosened, needs the reconnection, delays the concrete placement progress.
Furthermore, the plurality of string barrels are positioned on the slope, and the lower ends of the string barrels at the tail ends are positioned on a pouring place.
Through the technical scheme, the utility model has the beneficial effects that:
1. the concrete filling device is used at rugged parts of a road or parts with large height difference, concrete is introduced into the string barrels through the feeding hopper, and the concrete reaches a pouring place through a channel connected with the string barrels, so that the retaining wall at the rugged parts of the road is quickly poured, and the concrete pouring delay caused by the fact that the concrete tanker cannot reach the pouring place is avoided.
2. The feeding funnel is fixed through the tripod, the feeding funnel is inclined upwards, concrete in a tank car is convenient to pour into the feeding funnel, the supporting plate is used for supporting the lower part of the feeding funnel, and the feeding funnel is prevented from being deformed due to forced extrusion and affecting the feeding effect of the feeding funnel.
3. The rope is used for connecting the stringing barrels, so that the phenomenon that when the stringing barrels are placed down along a slope, the chain connection between the adjacent stringing barrels is loosened, the stringing barrels need to be reconnected, and the concrete pouring progress is delayed is avoided.
Drawings
Fig. 1 is a schematic structural view of a detachable concrete pouring string bucket according to the present invention.
Fig. 2 is a schematic structural view of a detachable concrete pouring skewer according to the present invention in use.
Fig. 3 is a schematic structural view of a feed hopper.
Fig. 4 is a structural schematic diagram of the stringing barrel.
The reference numbers in the figures are: the device comprises a barrel 1, a closed lifting lug 101, a chain hook 102, a chain 2, a feeding hopper 3, a tripod 4, a vertical rod 401, an inclined rod 402, a fixing plate 5, a fixing connecting part 6, a supporting plate 7, a rope 8, a road edge 9, a slope 10 and a pouring place 11.
Detailed Description
The utility model is further described with reference to the following figures and detailed description:
as shown in fig. 1 to 4, the detachable concrete pouring string barrel comprises a tripod 4, wherein the tripod 4 comprises two vertical rods 401 and two inclined rods 402, the top ends of the vertical rods 401 are connected with the top ends of the inclined rods 402, a fixing plate 5 is connected between the two inclined rods 402, the fixing plate 5 is positioned on the upper portions of the inclined rods 402, a through hole is formed in the fixing plate 5, a feeding funnel 3 is arranged on the through hole, two ends of the feeding funnel 3 are cylindrical sections, the middle of the feeding funnel 3 is a funnel section, the diameter of the cylindrical section at the upper end of the feeding funnel 3 is the same as that of the through hole of the fixing plate 5, the cylindrical section at the upper end of the feeding funnel 3 is connected with a fixed connecting part 6, a threaded hole is formed in the fixed connecting part 6, and the feeding funnel 3 is fixed on the fixing plate 5 through the fixed connecting part 6;
be equipped with chain couple 102 on the 3 lower extreme cylinder sections of feed hopper, 3 lower extreme cylinder sections of feed hopper are equipped with cluster bucket 1, cluster bucket 1 is the toper setting, the diameter of cluster bucket 1 top is greater than the diameter of cluster bucket 1 bottom, 1 upper end of cluster bucket is equipped with closed lug 101, be equipped with chain 2 on the closed lug 101, chain 2 articulates with chain couple 102. Feed hopper 3 passes through fixed plate 5 to be fixed on tripod 4, makes feed hopper 3 tilt up through down tube 402, and after the concrete tank car reachd feed hopper 3 position, the feed hopper 3 is aimed at to the tank car discharge gate, lets in feed hopper 3 with the concrete in the tank car in, the concrete enters into cluster bucket 1 through feed hopper 3's funnel section in, reachs pour place 11 through cluster bucket 1.
Two be connected with the horizontal pole between the montant 401, be equipped with backup pad 7 on the horizontal pole, backup pad 7 is the arc, backup pad 7 is located 3 funnel sections of feed hopper below. The supporting plate 7 supports the lower part of the feeding funnel 3, and ensures that the feeding funnel 3 is stably fixed on the fixing plate 5.
The vertical rod 401 and the diagonal rod 402 are both fixed on the road edge 9, and the vertical rod 401 is perpendicular to the road edge 9.
The utility model discloses a feeding hopper, including string bucket 1, chain hook 102, feeding hopper 3, chain hook 102, a plurality of string buckets 1, a plurality of chain 2, closed lug 101 and chain hook 102 on the adjacent string bucket 1 are connected to chain hook 102 lower extreme, chain hook 102 is "U" type, chain hook 102 below spreader is connected with string bucket 1, is equipped with the clearance between top spreader and the string bucket 1, 3 lower extremes of feeding hopper are equipped with a plurality of string buckets 1, and is a plurality of connect through the chain between the string bucket 1, closed lug 101 and chain hook 102 on the adjacent string bucket 1 are connected to chain 2. A plurality of the string barrels 1 are positioned on the slope 10, and the lower ends of the string barrels 1 at the tail ends are positioned on the pouring place 11. The chain 2 is sleeved on the chain hook 102 through a gap between the chain hook 102 and the string barrel 1 to connect the adjacent string barrels 1, so that the string barrels 1 are connected in series to form a concrete channel, and the concrete is led to the pouring place 11.
The triangular support 4 is tied with a rope 8, the rope 8 is connected to the tail end of the stringing barrel 1 along the stringing barrel 1 direction, and the middle section of each stringing barrel 1 of the rope 8 is tied with a cross buckle. The cross buckle is formed by extending a rope 8 downwards from the upper end of the stringing barrel 1, and when the stringing barrel 1 is in a middle position, the rope 8 is bent by 90 degrees, winds around the stringing barrel 1 for a circle, passes through the 90-degree bent position and then extends downwards to the next stringing barrel 1.
When in use, the tripod 4 is fixed at the road edge 9, the chain 2 is hung on the chain hook 102 through the gap between the chain hook 102 and the stringing barrel 1 to connect the adjacent stringing barrels 1, one end of the rope 8 is connected with the tripod 4, the other end is connected with the tail end stringing barrel 1 along the direction of the stringing barrel 1, the middle section of each stringing barrel 1 is cross-buckled, the outlet of the tail end stringing barrel 1 faces to the pouring place 11, the feeding funnel 3 is fixed on the tripod 4 through the fixing plate 5, the feeding funnel 3 is upwards inclined through the inclined rod 402, the supporting plate 7 supports the lower part of the feeding funnel 3 to ensure that the feeding funnel 3 is stably fixed on the fixing plate 5, the deformation of the feeding funnel 3 caused by the extrusion force is prevented, the blanking effect of the feeding funnel 3 is influenced, after the concrete tank truck reaches the position of the feeding funnel 3, the discharge port of the tank truck is aligned with the feeding funnel 3, the concrete in the tank truck is introduced into the feeding funnel 3, concrete enters the string barrel 1 through the funnel section of the feeding funnel 3, the plurality of string barrels 1 form a channel, and the concrete is communicated to the pouring place 11, so that the retaining wall at the rugged part of the road can be quickly poured, and the concrete pouring delay caused by the fact that the concrete tanker cannot reach the pouring place 11 is avoided.
The above-mentioned embodiments are merely preferred embodiments of the present invention, and not intended to limit the scope of the utility model, so that all equivalent changes and modifications made according to the technical solutions described in the claims of the present invention should be included in the claims of the present invention.

Claims (7)

1. A detachable concrete pouring string barrel comprises a tripod (4) and is characterized in that, the tripod (4) comprises two vertical rods (401) and two inclined rods (402), the top end of the vertical rod (401) is connected with the top ends of the inclined rods (402), a fixing plate (5) is connected between the two inclined rods (402), the fixing plate (5) is positioned at the upper part of the inclined rod (402), a through hole is arranged on the fixing plate (5), a feeding funnel (3) is arranged on the through hole, two ends of the feeding funnel (3) are cylindrical sections, the middle is a funnel section, the diameter of the cylindrical section at the upper end of the feeding funnel (3) is the same as that of the through hole of the fixing plate (5), the upper end cylindrical section of the feeding funnel (3) is connected with a fixed connecting part (6), the fixed connecting part (6) is provided with a threaded hole, and the feeding hopper (3) is fixed on the fixed plate (5) through the fixed connecting part (6);
be equipped with chain couple (102) on feed hopper (3) lower extreme cylinder section, feed hopper (3) lower extreme cylinder section department is equipped with cluster bucket (1), cluster bucket (1) is the toper setting, cluster bucket (1) top diameter is greater than cluster bucket (1) bottom diameter, cluster bucket (1) upper end is equipped with closed lug (101), be equipped with chain (2) on closed lug (101), chain (2) articulate with chain couple (102).
2. A detachable concrete pouring kebab according to claim 1, characterized in that a cross bar is connected between two vertical bars (401), a support plate (7) is arranged on the cross bar, the support plate (7) is arc-shaped, and the support plate (7) is located below the hopper section of the feeding hopper (3).
3. A removable concrete pouring kebab according to claim 1, characterized in that the vertical bar (401) and the diagonal bar (402) are fixed to the road edge (9), the vertical bar (401) being perpendicular to the road edge (9).
4. The detachable concrete pouring kebab according to claim 1, characterized in that a chain hook (102) is arranged at the lower end of the kebab (1), the chain hook (102) is U-shaped, a lower cross column of the chain hook (102) is connected with the kebab (1), and a gap is arranged between an upper cross column and the kebab (1).
5. The detachable concrete pouring kebab according to claim 4, characterized in that a plurality of kebabs (1) are arranged at the lower end of the feeding hopper (3), the kebabs (1) are connected by a chain (2), and the chain (2) is connected with a closing lifting lug (101) and a chain hook (102) on the adjacent kebabs (1).
6. A demountable concrete casting kebab according to claim 5, wherein the tripod (4) has a rope (8) tied thereon, the rope (8) being connected to the last kebab (1) in the direction of the kebab (1), the rope (8) having a cross-buckle tied in the middle of each kebab (1).
7. A demountable concrete casting kebab according to claim 5, wherein a number of said kebabs (1) are located on a slope (10) and the lower end of the last said kebab (1) is located on a casting site (11).
CN202220459811.8U 2022-03-03 2022-03-03 Can dismantle concrete placement cluster bucket Active CN216948287U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220459811.8U CN216948287U (en) 2022-03-03 2022-03-03 Can dismantle concrete placement cluster bucket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220459811.8U CN216948287U (en) 2022-03-03 2022-03-03 Can dismantle concrete placement cluster bucket

Publications (1)

Publication Number Publication Date
CN216948287U true CN216948287U (en) 2022-07-12

Family

ID=82294061

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220459811.8U Active CN216948287U (en) 2022-03-03 2022-03-03 Can dismantle concrete placement cluster bucket

Country Status (1)

Country Link
CN (1) CN216948287U (en)

Similar Documents

Publication Publication Date Title
CN216948287U (en) Can dismantle concrete placement cluster bucket
CN216587710U (en) Modular anti-bank reinforced structure of aluminum alloy template
CN213898162U (en) Movable chute for concrete pouring of hidden culvert
CN201786031U (en) Slip-formed concrete distributing bin device
CN110777794A (en) Hopper for underground continuous wall joint pipe bin
CN214696921U (en) Concrete switching device for construction
KR20130009191A (en) Apparatus for supporting solar energy collecting modules
CN213869898U (en) Open low pressure slip casting integrated device
CN215594919U (en) Supporting device for installing profiled metal sheet on section steel in overhanging manner
CN113235465A (en) Positioning and moving device for river channel water-blocking bridge reconstruction construction
CN218815261U (en) A uncovered type hopper for following vertical member concrete is pour to side
CN220229753U (en) Material cooling device for tungsten carbide production
CN109140472B (en) Cold ash bucket overhauls platform
CN219690519U (en) String bucket suitable for underground works concrete placement is used
CN205990770U (en) A kind of removable concreting instrument
CN213626693U (en) Concrete ash storage tank for secondary structure pouring
CN220336479U (en) Concrete spreader
CN211499187U (en) Novel groove type stay bar between purlin
CN215482358U (en) Bridge high pier steel bar installation operation device
CN220100692U (en) Large-volume concrete chute combined device
CN108978711A (en) A kind of packaged type scaffold and the pipe gallery construction method using the scaffold
CN213038883U (en) Reinforced concrete column structure pouring device
CN215558558U (en) Tower crane underframe with reinforcing structure
CN219931638U (en) Steel pipe concrete column material conveying device
CN217733766U (en) Steel corbel for construction of cylindrical pier capping beam

Legal Events

Date Code Title Description
GR01 Patent grant