CN216840366U - FC board mounting structure for building engineering - Google Patents

FC board mounting structure for building engineering Download PDF

Info

Publication number
CN216840366U
CN216840366U CN202220571109.0U CN202220571109U CN216840366U CN 216840366 U CN216840366 U CN 216840366U CN 202220571109 U CN202220571109 U CN 202220571109U CN 216840366 U CN216840366 U CN 216840366U
Authority
CN
China
Prior art keywords
board
lead screw
mounting structure
plate
installing support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220571109.0U
Other languages
Chinese (zh)
Inventor
岳鑫
王现成
李波
王秀志
王普锋
付豪
张鑫亮
王浩天
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202220571109.0U priority Critical patent/CN216840366U/en
Application granted granted Critical
Publication of CN216840366U publication Critical patent/CN216840366U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model discloses a FC board mounting structure for building engineering, including installing support and cement board body, the installing support is the Contraband font, and the surface rotation of installing support is connected with two-way lead screw, and the surperficial threaded connection of two-way lead screw has two movable blocks, and there is a support scute on the surface of movable block through bolt fixed mounting, and the surface of support scute is provided with the extension board, and the right side fixedly connected with of extension board adjusts the lead screw. This FC board mounting structure for building engineering, through setting up the installing support, two-way lead screw, movable block and brace angle board, be convenient for adjust and fix the distance between two upper and lower brace angle boards, thereby be applicable to and install the FC cement board of equidimension not, trapezoidal draw-in groove has been seted up through the back at the FC cement board, utilize the chucking frame to insert trapezoidal draw-in groove, can install and fix the FC cement board, and convenient for operation, and need not to drill the cement board and install, the FC cement board integrality has been guaranteed.

Description

FC board mounting structure for building engineering
Technical Field
The utility model relates to a building engineering technical field specifically is a FC board mounting structure for building engineering.
Background
The FC board is a new type of building material, and is produced by using fiber and cement as main raw materials and other auxiliary materials through the processes of pulping, copying, pressurizing, maintaining, etc.
At present, when the FC cement board is mounted on a wall in a building engineering, the surface of the FC cement board is drilled, and the FC cement board is fixed on a wall bracket by using bolts and nuts, and because the hardness of the fiber cement board cannot be compared with that of other composite boards, the strength of the FC cement board is easy to reduce when the fiber cement board is mounted by using the method, and the service life is influenced, therefore, an FC board mounting structure for the building engineering is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a FC board mounting structure for building engineering to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a FC board mounting structure for building engineering, includes installing support and cement board body, the installing support is the Contraband font, and the surface rotation of installing support is connected with two-way lead screw, and the surperficial threaded connection of two-way lead screw has two movable blocks, and there is a supporting angle board on the surface of movable block through bolt fixed mounting, and the surface of supporting angle board is provided with the extension board, and the right side fixedly connected with of extension board adjusts the lead screw, and the surperficial threaded connection who adjusts the lead screw has and is trapezoidal chucking frame, the trapezoidal draw-in groove with chucking frame looks adaptation is seted up on the surface of cement board body, the chucking frame forms the joint with trapezoidal draw-in groove.
Preferably, the inner wall of the trapezoidal clamping groove is fixedly connected with a rubber non-slip pad, and the rubber non-slip pad is in lap joint with the surface of the clamping frame.
Preferably, the end part of the adjusting screw rod is fixedly connected with an anti-dropping nut.
Preferably, the surface of the supporting angle plate is provided with a strip-shaped mounting hole, the surface of the extension plate is provided with a bolt hole, the inner wall of the bolt hole is in threaded connection with a fastening bolt, and the fastening bolt is matched with the strip-shaped mounting hole.
Preferably, the bottom end of the fastening bolt penetrates through the strip-shaped mounting hole, a fastening nut is connected to the surface of the fastening bolt in a threaded mode, and the surface of the fastening nut is in lap joint with the supporting angle plate.
Preferably, the side surface of the movable block is in sliding connection with the surface of the mounting bracket.
Advantageous effects
The utility model provides a FC board mounting structure for building engineering possesses following beneficial effect:
1. this FC board mounting structure for building engineering, through setting up the installing support, two-way lead screw, movable block and brace angle board, be convenient for adjust and fix the distance between two upper and lower brace angle boards, thereby be applicable to and install the FC cement board of equidimension not, trapezoidal draw-in groove has been seted up through the back at the FC cement board, utilize the chucking frame to insert trapezoidal draw-in groove, can install and fix the FC cement board, and convenient for operation, and need not to drill the cement board and install, the FC cement board integrality has been guaranteed.
2. This FC board mounting structure for building engineering adjusts the lead screw through setting up, conveniently adjusts the position of chucking frame, is convenient for finely tune the operation in the installation, is provided with bar mounting hole and fastening bolt through the surface at the brace angle board, is convenient for adjust the mounted position of extension board to be convenient for adjust the distance between FC board and the installing support.
Drawings
FIG. 1 is a schematic view of a front cross-sectional structure of the present invention;
FIG. 2 is a schematic view of a three-dimensional structure of a cement board body according to the present invention;
FIG. 3 is an enlarged view of the structure at A in FIG. 1;
fig. 4 is an enlarged schematic view of a portion B in fig. 1.
In the figure: the concrete slab comprises an installation support 1, a cement slab body 2, a bidirectional screw rod 3, a movable block 4, a supporting angle plate 5, a fastening nut 6, an extension plate 7, an adjusting screw rod 8, a clamping frame 9, a trapezoidal clamping groove 10, a rubber non-slip mat 11, an anti-falling nut 12, a strip-shaped installation hole 13 and a fastening bolt 14.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a FC board mounting structure for building engineering, includes installing support 1 and cement board body 2, installing support 1 is the Contraband font, and the surperficial rotation of installing support 1 is connected with two-way lead screw 3, and two-way lead screw 3's surperficial threaded connection has two movable blocks 4, the side of movable block 4 and installing support 1's sliding surface connection, and there is a support scute 5 on the surface of movable block 4 through bolt fixed mounting, and the surface of support scute 5 is provided with extension board 7.
The surface of the supporting angle plate 5 is provided with a strip-shaped mounting hole 13, the surface of the extension plate 7 is provided with a bolt hole, the inner wall of the bolt hole is in threaded connection with a fastening bolt 14, and the fastening bolt 14 is matched with the strip-shaped mounting hole 13.
The bottom end of the fastening bolt 14 penetrates through the strip-shaped mounting hole 13, the surface of the fastening bolt 14 is connected with the fastening nut 6 in a threaded mode, and the surface of the fastening nut 6 is in lap joint with the supporting angle plate 5.
Lead screw 8 is adjusted to the right side fixedly connected with of extension plate 7, adjusts lead screw 8's tip fixedly connected with anticreep nut 12, and the surface threaded connection who adjusts lead screw 8 has and is trapezoidal chucking frame 9, and the trapezoidal draw-in groove 10 with chucking frame 9 looks adaptation is seted up on the surface of cement board body 2, and chucking frame 9 forms the joint with trapezoidal draw-in groove 10.
Through setting up adjusting screw 8, conveniently adjust the position of chucking frame 9, be convenient for finely tune the operation in the installation, be provided with bar mounting hole 13 and fastening bolt 14 through the surface at support angle board 5, be convenient for adjust the mounted position of extension board 7 to be convenient for adjust the distance between FC board and installing support 1.
The inner wall of the trapezoidal clamping groove 10 is fixedly connected with a rubber non-slip mat 11, and the rubber non-slip mat 11 is in lap joint with the surface of the clamping frame 9.
Through setting up installing support 1, two-way lead screw 3, movable block 4 and supporting angle board 5, be convenient for adjust and fix the distance between two upper and lower supporting angle boards 5, thereby be applicable to and install the FC cement board of equidimension not, trapezoidal draw-in groove 10 has been seted up through the back at the FC cement board, utilize chucking frame 9 to insert trapezoidal draw-in groove 10, can install and fix the FC cement board, and convenient for operation, and need not to drill the installation to the cement board, the FC cement board integrality has been guaranteed.
The working principle is as follows: when installing the FC board, at first with installing support 1 through expansion bolts fixed mounting at the wall, then drive two movable blocks 4 through rotating two-way lead screw 3 and remove, then with two support scute 5 difference fixed mounting on the surface of movable block 4 through the bolt, install extension plate 7 on the surface of support scute 5 again, then rotate the chucking frame 9 on adjusting lead screw 8 surface again, rotate chucking frame 9 to suitable mounted position, carry out the joint with trapezoidal draw-in groove 10 at the 2 backs of cement slab body and chucking frame 9 again, thereby accomplish the installation and the fixed to cement slab body 2, and convenient for operation, and high stability.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a FC board mounting structure for building engineering, includes installing support (1) and cement board body (2), its characterized in that: installing support (1) is Contraband font, and the surface rotation of installing support (1) is connected with two-way lead screw (3), and the surperficial threaded connection of two-way lead screw (3) has two movable block (4), and there is supporting angle board (5) on the surface of movable block (4) through bolt fixed mounting, and the surface of supporting angle board (5) is provided with extending plate (7), and lead screw (8) are adjusted to the right side fixedly connected with of extending plate (7), and the surperficial threaded connection who adjusts lead screw (8) has and is trapezoidal chucking frame (9), trapezoidal draw-in groove (10) with chucking frame (9) looks adaptation are seted up on the surface of cement plate body (2), chucking frame (9) and trapezoidal draw-in groove (10) form the joint.
2. The FC plate mounting structure for construction engineering according to claim 1, wherein: the inner wall of the trapezoidal clamping groove (10) is fixedly connected with a rubber anti-slip pad (11), and the rubber anti-slip pad (11) is in lap joint with the surface of the clamping frame (9).
3. The FC plate mounting structure for construction engineering according to claim 1, wherein: the end part of the adjusting screw rod (8) is fixedly connected with an anti-drop nut (12).
4. The FC panel mounting structure for construction engineering according to claim 1, wherein: the surface of the supporting angle plate (5) is provided with a strip-shaped mounting hole (13), the surface of the extension plate (7) is provided with a bolt hole, the inner wall of the bolt hole is in threaded connection with a fastening bolt (14), and the fastening bolt (14) is matched with the strip-shaped mounting hole (13).
5. The FC plate mounting structure for construction engineering according to claim 4, wherein: the bottom end of the fastening bolt (14) penetrates through the strip-shaped mounting hole (13), the surface of the fastening bolt (14) is in threaded connection with the fastening nut (6), and the surface of the fastening nut (6) is in lap joint with the supporting angle plate (5).
6. The FC plate mounting structure for construction engineering according to claim 1, wherein: the side surface of the movable block (4) is in sliding connection with the surface of the mounting bracket (1).
CN202220571109.0U 2022-03-16 2022-03-16 FC board mounting structure for building engineering Active CN216840366U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220571109.0U CN216840366U (en) 2022-03-16 2022-03-16 FC board mounting structure for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220571109.0U CN216840366U (en) 2022-03-16 2022-03-16 FC board mounting structure for building engineering

Publications (1)

Publication Number Publication Date
CN216840366U true CN216840366U (en) 2022-06-28

Family

ID=82096092

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220571109.0U Active CN216840366U (en) 2022-03-16 2022-03-16 FC board mounting structure for building engineering

Country Status (1)

Country Link
CN (1) CN216840366U (en)

Similar Documents

Publication Publication Date Title
CN216840366U (en) FC board mounting structure for building engineering
CN108943373B (en) Movable tool for producing concrete prefabricated part
CN214368885U (en) Finished product support convenient to use
CN210713928U (en) Main body reinforcing structure of old building
CN201385385Y (en) Worktable of cutting machine
CN220451320U (en) Overhead ceramic tile paving structure
CN112900695A (en) Wall frame device for building and building implementation method thereof
CN220080892U (en) Ancient building wall reinforcing structure
CN220686667U (en) Telescopic laser leveling machine
CN217975017U (en) Suspended ceiling framework mounting structure with adjustable suspender distance
CN217054303U (en) A building templates for building engineering's be convenient for aggregate erection
CN217151175U (en) Rotary adjustable base
CN217630710U (en) Balcony curtain wall mounting structure
CN2889602Y (en) Drill bracket for top plate drilling
CN220479795U (en) Simple adjusting tool for local deformation of guardrail
CN211666331U (en) Building structure design roof beam reinforced structure
CN217704077U (en) A drilling equipment for ALC panel
CN216476324U (en) A prevent device that ftractures for steel truss building carrier plate
CN214034850U (en) ECP board flatness auxiliary correction tool
CN217557018U (en) Adjustable steel plate water stop fixing device
CN220301762U (en) Adjustable scaffold frame location structure that encorbelments
CN217894970U (en) Crane upright post reinforcing device
CN220100217U (en) High bearing capacity steel structure connection group
CN218028380U (en) Outer unit curtain wall switching structure that leaks
CN215290867U (en) Can realize GRC board mounting structure of angle modulation

Legal Events

Date Code Title Description
GR01 Patent grant