CN216810759U CN202220211956.6U CN202220211956U CN216810759U CN 216810759 U CN216810759 U CN 216810759U CN 202220211956 U CN202220211956 U CN 202220211956U CN 216810759 U CN216810759 U CN 216810759U
Authority
CN
China
Prior art keywords
keel
mounting groove
dry
installation
locking plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220211956.6U
Other languages
Chinese (zh)
Inventor
王清
陈玉刚
卢宇
尤伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Jincheng Dongsheng Decoration Engineering Co ltd
Original Assignee
Wuhan Jincheng Dongsheng Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Jincheng Dongsheng Decoration Engineering Co ltd filed Critical Wuhan Jincheng Dongsheng Decoration Engineering Co ltd
Priority to CN202220211956.6U priority Critical patent/CN216810759U/en
Application granted granted Critical
Publication of CN216810759U publication Critical patent/CN216810759U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Finishing Walls (AREA)

Abstract

The application discloses a keel structure for installation of architectural decoration stone board relates to architectural decoration technical field, and it includes the main joist, installs the last false keel of main joist and with the dry pendant that the false keel is connected, the mounting groove has been seted up on the false keel, dry pendant slides and connects in the mounting groove, be provided with on the false keel be used for with the dry pendant locking is in locking subassembly in the mounting groove. This application has the effect that improves stone material installation effectiveness.

Description

Keel structure for mounting architectural decoration stone plate
Technical Field
The utility model belongs to the technical field of architectural decoration technique and specifically relates to a keel structure for installation of architectural decoration stone board is related to.
Background
At present, in order to improve the heat insulation performance of a building wall, a stone plate is often installed on an outer vertical face of the wall, and a dry hanging method is often adopted for installation of the stone plate.
Chinese patent with application number 202020134843.1 in the correlation technique, a keel structure for installation of architectural decoration stone board is proposed, including main joist and false keel, main joist and false keel are vertically and horizontally staggered and distribute, the false keel includes vertical portion and horizontal part, the false keel still is including setting up the mounting bar that keeps away from horizontal part one side in vertical portion, the length direction of vertical portion is followed to the mounting bar extends, set up the mounting groove that supplies the mounting bar installation on the main joist, be equipped with between main joist and the false keel and be used for being fixed in the coupling mechanism in the mounting groove with the mounting bar, be equipped with between mounting bar and the main joist and be used for further being fixed in the strengthening mechanism in the mounting groove with the mounting bar.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: when hanging the stone material board on the wall body through the false keel, need beat the mounting hole on the false keel earlier, then install the dry pendant in mounting hole department, be connected stone material board and dry pendant at last. For making two adjacent stone material boards closely laminate, often need confirm the distance between two adjacent mounting holes on the false keel according to the width of stone material board, when the distance between two adjacent mounting holes and the width of stone material board mismatch, need beat the mounting hole in addition on the false keel, and then lead to stone material board installation inefficiency.
SUMMERY OF THE UTILITY MODEL
In order to improve the problem that stone material board installation effectiveness is low, this application provides a keel structure for the installation of architectural decoration stone material board.
The application provides a keel structure for installation of architectural decoration stone board adopts following technical scheme:
the utility model provides a keel structure for installation of architectural decoration stone board, includes the main joist, installs false keel on the main joist and with the dry pendant that the false keel is connected, the mounting groove has been seted up on the false keel, dry pendant slides and connects in the mounting groove, be provided with on the false keel and be used for with dry pendant locking is in locking subassembly in the mounting groove.
Through adopting above-mentioned technical scheme, when the installation stone material board, fix main joist and false keel installation earlier on the wall body, then slide a plurality of dry pendants through the mounting groove and connect on the false keel, adjust the distance between two adjacent dry pendants according to the width dimension of stone material board after that, install a plurality of dry pendant lockings in the mounting groove through the locking subassembly at last, distance between two adjacent dry pendants and the width dimension looks adaptation of stone material board this moment for can laminate each other when two adjacent stone material boards are installed. The keel structure for the installation of the architectural decoration stone plate is designed by the structure, and the mounting groove and the locking assembly are arranged, so that two adjacent stone plates can be quickly mounted and attached together, and the purpose of improving the stone mounting efficiency is achieved.
Optionally, the locking subassembly includes that to slide and set up the locking plate in the mounting groove and be used for driving about the locking plate supports tightly and is in the piece that supports on the dry pendant, the locking plate is in the mounting groove towards/keep away from the dry pendant direction slides.
By adopting the technical scheme, the locking plate can slide in the mounting groove, when the dry hanging piece is mounted on the auxiliary keel, the forerunner enables the locking plate to slide in the mounting groove, and a mounting environment is provided for the dry hanging piece to be mounted in the mounting groove; then inserting the dry hanging piece into the mounting groove, and adjusting the position of the dry hanging piece in the mounting groove; at last, the locking plate is driven to move towards the direction close to the dry hanging piece through the abutting piece and abuts tightly with the dry hanging piece, so that the dry hanging piece is stably locked in the mounting groove, and then two adjacent stone plates can be rapidly mounted and attached together through the dry hanging piece, and the purpose of improving the stone mounting efficiency is achieved.
Optionally, the abutting pieces are provided in a plurality, and the abutting pieces are distributed at intervals along the length direction of the locking plate.
Through adopting above-mentioned technical scheme, a plurality of tight piece that support act on the lock plate simultaneously for the lock plate can stabilize the butt on a plurality of dry hangers, reaches the purpose that improves dry hanger installation stability.
Optionally, the abutting piece is provided with a screw rod which synchronously slides with the locking plate, and the auxiliary keel is provided with a synchronous component which is used for driving the screw rods to synchronously slide.
Through adopting above-mentioned technical scheme, move the subassembly with can order about a plurality of screw rods and slide in step for a plurality of screw rods order about the lock plate simultaneously and move towards being close to/keeping away from dry pendant direction, avoid sliding of lock plate to be obstructed as far as, improved the efficiency that dry pendant was locked the installation simultaneously, and then reach the purpose that improves stone material installation effectiveness.
Optionally, the simultaneous movement subassembly is including rotating to be connected a plurality of screw thread section of thick bamboo on the false keel, coaxial cup joint be in ring gear on the screw thread section of thick bamboo and with the rack of ring gear meshing adaptation, it is a plurality of the screw thread section of thick bamboo is with a plurality of screw rod one-to-one, the one end of screw rod with the lock plate rigid coupling, the other end screw thread is worn to establish the screw thread section of thick bamboo, the rack is along a plurality of the screw rod is laid the direction and is set up, and the rack is followed a plurality of the screw rod is laid the direction and is slided and connect on the false keel.
Through adopting above-mentioned technical scheme, order about the rack and slide, rack and ring gear meshing, the ring gear orders about a plurality of screw thread section of thick bamboo synchronous rotations, the pivoted screw thread section of thick bamboo orders about rather than the screw rod that corresponds and slides, realize the purpose that a plurality of screw rods slided in step, and then make a plurality of screw rods order about the lock plate simultaneously and move towards being close to/keeping away from dry pendant direction, avoid sliding of lock plate to be obstructed as far as possible, improved the efficiency that dry pendant was installed by the locking simultaneously, reach the purpose that improves stone material installation effectiveness.
Optionally, a guide member for limiting the deflection of the locking plate is arranged in the mounting groove.
Through adopting above-mentioned technical scheme, the deflector of guide can restrict the lock plate for the lock plate can be in the mounting groove towards being close to/keeping away from the steady slip of dry pendant direction, and then reaches the purpose of stabilizing the butt on dry pendant.
Optionally, an anti-slip structure is arranged on the locking plate, and the anti-slip structure is located on the end face, close to the dry hanging piece, of the locking plate.
Through adopting above-mentioned technical scheme, anti-skidding structure can increase the frictional force size between lock plate and the dry pendant for the lock plate is stabilized the butt on the dry pendant, reaches the purpose that improves dry pendant installation stability.
Optionally, a lubricating piece is arranged in the mounting groove, and the dry hanging piece is in sliding contact with the lubricating piece.
By adopting the technical scheme, after the stone plate is hung on the dry hanging piece, if the position of the stone plate and the dry hanging piece needs to be adjusted, the locking plate is driven to move towards the direction far away from the dry hanging piece, so that the locking plate is not abutted to the dry hanging piece any more; then promote the stone material board and slide, the stone material board drives the pendant of doing and moves in the mounting groove, because the stone material board has certain weight, so the lubricating piece can reduce the frictional force size between pendant and the mounting groove inner wall futilely for the pendant of doing can be in the mounting groove fast movement, reaches the purpose of quick adjustment stone material board position, and then reaches the effect that improves stone material installation effectiveness.
In summary, the present application includes at least one of the following beneficial technical effects:
1. when the stone plate is installed, the main keel and the auxiliary keel are installed and fixed on a wall body, then the dry hangers are connected to the auxiliary keel in a sliding mode through the installation grooves, the distance between every two adjacent dry hangers is adjusted according to the width size of the stone plate, and finally the dry hangers are installed in the installation grooves in a locking mode through the locking assembly;
2. the synchronous moving assembly can drive the plurality of screws to synchronously slide, so that the plurality of screws simultaneously drive the locking plate to move towards the direction close to or away from the dry hanging piece, the sliding resistance of the locking plate is avoided as much as possible, the efficiency of locking and installing the dry hanging piece is improved, and the aim of improving the stone installing efficiency is fulfilled;
3. the lubricating piece can reduce the friction force between the dry hanging piece and the inner wall of the mounting groove, so that the dry hanging piece can move quickly in the mounting groove, the purpose of quickly adjusting the position of the stone plate is achieved, and the effect of improving the stone mounting efficiency is further achieved.
Drawings
Fig. 1 is a schematic overall structure diagram of an embodiment of the present application.
Fig. 2 is a schematic structural diagram of a false keel, a dry hanging piece, a synchronous moving component and a lubricating piece in the embodiment of the application.
Figure 3 is an exploded view of the cross runner, dry suspension, locking assembly and co-acting assembly of the embodiment of the present application.
Reference numerals: 1. a main keel; 2. a false keel; 3. a dry hanging part; 4. mounting grooves; 5. a locking assembly; 51. a lock plate; 52. an abutting piece; 6. a simultaneous movement component; 61. a threaded barrel; 62. a ring gear; 63. a rack; 7. a guide member; 8. an anti-slip structure; 9. a lubricating member; 10. a sawtooth block; 11. a drive handle.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses a keel structure for installation of architectural decoration stone board. Referring to fig. 1, a keel structure for installation of architectural decoration stone board includes main joist 1, install false keel 2 on main joist 1 and the dry hanging piece 3 of being connected with false keel 2, and main joist 1 passes through the built-in fitting and installs on the wall body, and main joist 1 and false keel 2 set up perpendicularly, and on the terminal surface of wall body was kept away from at main joist 1 to false keel 2 rigid coupling, the rigid coupling mode between main joist 1 and the false keel 2 can be for welded fastening, also can be for the screw connection. The auxiliary keel 2 is far away from the main keel 1, the end face of the auxiliary keel is provided with a mounting groove 4, in the embodiment of the application, the cross section of the mounting groove 4 is in a T shape, the mounting groove 4 is arranged along the length direction of the auxiliary keel 2, and the two ends of the mounting groove 4 are both arranged in an opening mode.
Referring to fig. 2 and 3, a plurality of dry hangers 3 are provided, in the embodiment of the present application, two dry hangers 3 are connected to each furring channel 2, and in other embodiments, the number of dry hangers 3 may be three, four, or five. Dry pendant 3 is the I shape, and the one end of dry pendant 3 slides and pegs graft in mounting groove 4, and dry pendant 3 can slide along the length direction of false keel 2 in mounting groove 4, is provided with on the false keel 2 to be used for the locking subassembly 5 in mounting groove 4 with dry pendant 3 locking.
In order to enable the dry hanging piece 3 to rapidly move in the installation groove 4, referring to fig. 2 and 3, a lubricating piece 9 is arranged in the installation groove 4, the lubricating piece 9 can be a teflon coating, a roller or balls, in the embodiment of the application, the lubricating piece 9 is provided with a plurality of balls, the plurality of balls are all embedded on the bottom wall in the installation groove 4 in a rolling manner, and the plurality of balls are arranged at intervals along the length direction of the installation groove 4. One end of the dry hanging piece 3 is inserted in the mounting groove 4 in a sliding manner and is in sliding contact with the ball. The ball can reduce the friction between the dry hanging piece 3 and the inner wall of the mounting groove 4, so that the dry hanging piece 3 can rapidly move in the mounting groove 4.
The dry hanging pieces 3 are driven to slide in the mounting grooves 4 according to the width of the stone plate, and the purpose of adjusting the distance between every two adjacent dry hanging pieces 3 is achieved. After the adjustment of distance between two adjacent dry hangers 3 is accomplished, accessible locking subassembly 5 will dry hanger 3 quick locking in mounting groove 4. The distance between two adjacent dry pendants 3 and the width size looks adaptation of stone material board this moment for can laminate each other when two adjacent stone material boards are installed.
Referring to fig. 2 and 3, the locking assembly 5 includes a locking plate 51 slidably disposed in the mounting groove 4 and a fastening member 52 for fastening the locking plate 51 to the dry suspension member 3, the locking plate 51 is disposed along the length direction of the mounting groove 4, the locking plate 51 is disposed on a side of the dry suspension member 3 away from the balls, the locking plate 51 slidably moves in the mounting groove 4 toward a direction close to/away from the dry suspension member 3, and the fastening member 52 is disposed on a side of the locking plate 51 away from the dry suspension member 3.
Because the length of the locking plate 51 is long, the locking plate 51 needs to stably lock a plurality of dry hangers 3 in the mounting groove 4, so for making the locking plate 51 stably abut on a plurality of dry hangers 3, referring to fig. 2 and 3, the fastening piece 52 is provided with a plurality of, the fastening piece 52 can be provided with two, three, four, in this embodiment, the fastening piece 52 is provided with two, and two fastening pieces 52 are arranged at two ends of the locking plate 51 along the length direction of the locking plate 51 at intervals.
Referring to fig. 2 and 3, support tight 52 and can be electric putter, also can be the screw rod, for reducing the cost of manufacture, in this application embodiment, support tight 52 and set up to the screw rod, the screw rod slides and sets up on false keel 2, and the one end of screw rod is located mounting groove 4, the other end is located outside mounting groove 4, the screw rod sets up along locking plate 51 direction of sliding, the screw rod is located the one end and the locking plate 51 rigid coupling of mounting groove 4, when locking plate 51 slides in mounting groove 4, two screw rods follow locking plate 51 and slide in step.
Referring to fig. 2 and 3, the anti-slip structure 8 is arranged on the lock plate 51, the anti-slip structure 8 is located on the end face of the lock plate 51 close to the dry hanging part 3, the anti-slip structure 8 may be a rubber strip or a sawtooth strip 63, in this embodiment, the anti-slip structure 8 is arranged as a sawtooth strip 63, and the sawtooth strip 63 is bonded on the lock plate 51. The end face, close to the sawtooth strip 63, of the dry hanging piece 3 is provided with a sawtooth block 10 in an integrated forming mode, and the sawtooth block 10 is matched with the sawtooth strip 63 in an occlusion mode.
For making sawtooth rack 63 and sawtooth block 10 stabilize the interlock, refer to fig. 2 and 3, be provided with the guide 7 that is used for restricting locking plate 51 beat in the mounting groove 4, guide 7 sets up to the T type piece of rigid coupling on locking plate 51, T type piece and locking plate 51 integrated into one piece, offers the T type groove that slides the adaptation with T type piece on the inner wall of mounting groove 4 keeping away from its notch, and T type groove sets up along locking plate 51 direction of sliding. When the lock plate 51 slides in the mounting groove 4, the T-shaped block stably slides in the T-shaped groove, so that when the lock plate 51 abuts against the dry hanging piece 3, the sawtooth block 10 is stably meshed with the sawtooth strip 63.
Referring to fig. 2 and 3, be provided with on the false keel 2 and be used for driving about the synchronous subassembly 6 that moves that slides of a plurality of screws, move subassembly 6 including rotating a plurality of screw thread section of thick bamboos 61 of connection on false keel 2 with moving, the coaxial ring gear 62 that cup joints on screw thread section of thick bamboo 61 and with the rack 63 of ring gear 62 meshing adaptation, because the screw rod on every false keel 2 all is provided with two, so also rotate on every false keel 2 and be connected with two screw thread sections of thick bamboo 61, two screw thread sections of thick bamboo 61 and two screw rod one-to-ones, screw thread section of thick bamboo 61 is located outside mounting groove 4, and the screw rod is kept away from the one end screw thread of locking plate 51 and is worn to establish screw thread section of thick bamboo 61. Two gear rings 62 are also provided, and the two gear rings 62 correspond one-to-one to the two thread cylinders 61.
Referring to fig. 2 and 3, the rack 63 is arranged along the arrangement direction of the two screws, the rack 63 is connected to the furring channel 2 in a sliding manner along the arrangement direction of the two screws, and the two gear rings 62 are both meshed with the rack 63. One end of the rack 63 is welded with a driving handle 11 for driving the rack 63 to slide.
The implementation principle of the keel structure for installing the architectural decoration stone plate is as follows: when the installation stone material board, fix on the wall body with the installation of main joist 1 and false keel 2 earlier, then order about the rack 63 through drive handle 11 and slide, the rack 63 orders about two ring gear 62 synchronous rotations, and two ring gear 62 order about two screw rods respectively and slide, and two screw rods order about locking plate 51 and provide the installation environment in installing groove 4 towards the direction motion of keeping away from the ball in installing groove 4 for dry-hang member 3.
Then inserting the dry hanging piece 3 into the mounting groove 4, and adjusting the position of the dry hanging piece 3 in the mounting groove 4; order about rack 63 through drive handle 11 again and reverse slide, rack 63 orders about two ring gear 62 synchronous rotations, two ring gear 62 order about two screw rods respectively and slide, two screw rods order about lock plate 51 in mounting groove 4 towards the direction motion that is close to the ball, when lock plate 51 and dry pendant 3 butt, serration block 10 and the stable interlock of sawtooth strip 63, make dry pendant 3 by stable locking in mounting groove 4, and then make two adjacent stone plates can be installed the laminating by the high speed through dry pendant 3 and be in the same place, reach the purpose that improves stone material installation effectiveness.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a keel structure for installation of architectural decoration stone board, includes main joist (1), installs false keel (2) on main joist (1) and with dry pendant (3) that false keel (2) are connected, its characterized in that: the auxiliary keel (2) is provided with a mounting groove (4), the dry hanging piece (3) is connected in the mounting groove (4) in a sliding manner, and the auxiliary keel (2) is provided with a locking assembly (5) which is used for locking the dry hanging piece (3) in the mounting groove (4).
2. A keel structure for the installation of architectural decorative stone panels according to claim 1, wherein: locking subassembly (5) including slide and set up locking plate (51) in mounting groove (4) and be used for driving locking plate (51) support tightly and are in support piece (52) on dry pendant (3), locking plate (51) are in mounting groove (4) are close to/are kept away from dry pendant (3) direction is slided.
3. A keel structure for the installation of architectural decorative stone panels according to claim 2, wherein: the abutting pieces (52) are arranged in a plurality, and the abutting pieces (52) are distributed at intervals along the length direction of the locking plate (51).
4. A keel structure for the installation of architectural decorative stone panels according to claim 3, wherein: the abutting piece (52) is arranged to be a screw rod which synchronously slides with the locking plate (51), and the auxiliary keel (2) is provided with a synchronous moving assembly (6) which is used for driving the screw rods to synchronously slide.
5. A keel structure for the installation of architectural decorative stone panels according to claim 4, wherein: with moving subassembly (6) including rotate to be connected a plurality of screw thread section of thick bamboo (61) on false keel (2), coaxial cup joint be in ring gear (62) on the screw thread section of thick bamboo (61) and with rack (63) of ring gear (62) meshing adaptation, it is a plurality of screw thread section of thick bamboo (61) and a plurality of screw rod one-to-one, the one end of screw rod with locking plate (51) rigid coupling, the other end screw thread is worn to establish a screw thread section of thick bamboo (61), rack (63) are along a plurality of the direction setting is laid to the screw rod, and rack (63) are along a plurality of the screw rod is laid the direction and is slided and connect on false keel (2).
6. A keel structure for the installation of architectural decorative stone panels according to claim 2, wherein: and a guide piece (7) used for limiting the deflection of the locking plate (51) is arranged in the mounting groove (4).
7. A keel structure for the installation of architectural decorative stone panels according to claim 2, wherein: be provided with on lock plate (51) anti-skidding structure (8), anti-skidding structure (8) are located lock plate (51) are close to on the terminal surface of dry pendant (3).
8. A keel structure for the installation of architectural decorative stone panels according to claim 1, wherein: a lubricating piece (9) is arranged in the mounting groove (4), and the dry hanging piece (3) is in sliding contact with the lubricating piece (9).
CN202220211956.6U 2022-01-25 2022-01-25 Keel structure for mounting architectural decoration stone plate Active CN216810759U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220211956.6U CN216810759U (en) 2022-01-25 2022-01-25 Keel structure for mounting architectural decoration stone plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220211956.6U CN216810759U (en) 2022-01-25 2022-01-25 Keel structure for mounting architectural decoration stone plate

Publications (1)

Publication Number Publication Date
CN216810759U true CN216810759U (en) 2022-06-24

Family

ID=82065982

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220211956.6U Active CN216810759U (en) 2022-01-25 2022-01-25 Keel structure for mounting architectural decoration stone plate

Country Status (1)

Country Link
CN (1) CN216810759U (en)

Similar Documents

Publication Publication Date Title
US10822806B2 (en) Anchor-free system for fastening of cladding panels and a method of fastening thereof
CN210395967U (en) Building exterior finish decorative board mounting structure
US10508441B2 (en) Demountable wall system
CN216810759U (en) Keel structure for mounting architectural decoration stone plate
CN212926840U (en) Building energy-saving external wall heat-insulation decorative plate based on BIM
CN210288838U (en) Grid suspended ceiling
CN111997294B (en) Wallboard mounting system
CN111809821A (en) Steel frame assembly decoration integrated plate
CN217232339U (en) Energy-saving curtain wall
CN217299592U (en) Assembled heat insulation board for interior decoration
CN211923070U (en) Heat insulation plate assembly
CN215802871U (en) Wall surface system of honeycomb plate composite ceramic tile
CN212583109U (en) Steel frame assembly decoration integrated plate
CN215888727U (en) Internal corner structure of toilet
CN114737841A (en) Anti-swing balance structure of sliding door
CN219825933U (en) Facing structure of building outer wall
CN219281591U (en) Combined door and window section bar
CN213897929U (en) Wallboard mounting system and bracket mechanism thereof
CN112554385A (en) Internal corner structure of toilet
CN220377608U (en) Multidirectional adjusting pendant
CN220451291U (en) Wallboard is decorated in heating of indoor building convenient to installation is dismantled
CN114108983B (en) Wall surface dry hanging structure
CN220225835U (en) Special-shaped unit type glass curtain wall
CN218814662U (en) Dry-hanging suspended ceiling mounting mechanism
CN215054447U (en) Building ceiling structure

Legal Events

Date Code Title Description
GR01 Patent grant