CN216789437U - Electromechanical mounting engineering is with adjustable two support of piecing together - Google Patents
Electromechanical mounting engineering is with adjustable two support of piecing together Download PDFInfo
- Publication number
- CN216789437U CN216789437U CN202220386572.8U CN202220386572U CN216789437U CN 216789437 U CN216789437 U CN 216789437U CN 202220386572 U CN202220386572 U CN 202220386572U CN 216789437 U CN216789437 U CN 216789437U
- Authority
- CN
- China
- Prior art keywords
- channel steel
- cross arms
- steel cross
- channel
- bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 91
- 239000010959 steel Substances 0.000 claims abstract description 91
- 238000009434 installation Methods 0.000 claims abstract description 16
- 238000010276 construction Methods 0.000 abstract description 7
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000003466 welding Methods 0.000 abstract description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model discloses an adjustable double-spliced bracket for electromechanical installation engineering, which comprises: channel steel upright posts, channel steel cross arms, U-shaped clamps and round steel; two channel steel upright columns are arranged; two channel steel cross arms are arranged, the two channel steel cross arms are connected between the lower ends of the two channel steel stand columns in a welding mode, and a gap is reserved between the two channel steel cross arms; the U-shaped clamps are arranged in a plurality of gaps formed between the two channel steel cross arms, and the bottoms of the U-shaped clamps are connected with the channel steel cross arms through bolts; a plurality of round steel are arranged and correspondingly fixed in each U-shaped card; the channel steel upright posts mainly play roles in fixing channel steel cross arms and bearing pipeline tension; the channel steel cross arm plays a role of bearing a pipeline; the utility model solves the problem that too much working hours are consumed by mechanically perforating the bracket when manufacturing the comprehensive bracket in the traditional construction.
Description
Technical Field
The utility model belongs to the technical field of constructional engineering equipment, and particularly relates to an adjustable double-spliced bracket for electromechanical installation engineering.
Background
The pipeline support is a structural member for supporting an overhead laying pipeline, and is also called a pipeline support, a pipe part and the like, and the pipeline support is used in any place where the pipeline is laid.
The preparation is synthesized the support and need be opened a lot of mouths on the support during electromechanical installation engineering tradition construction, and this often can consume too much man-hour, but also can cause the unsafe problem of support machinery trompil because of setting up the inaccurate problem of pipeline position location.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide an adjustable double-spliced bracket for electromechanical installation engineering, which solves the problem that too much working hours are consumed for mechanically drilling holes on the bracket when a comprehensive bracket is manufactured in the traditional construction.
The technical scheme adopted by the utility model is that the adjustable double-spliced bracket for the electromechanical installation engineering comprises:
two channel steel upright columns are arranged;
two channel steel cross arms are arranged, the two channel steel cross arms are arranged between the lower ends of the two channel steel stand columns, and a gap is formed between the two channel steel cross arms;
the U-shaped clamps are arranged in a plurality of gaps formed between the two channel steel cross arms, and the bottoms of the U-shaped clamps are connected with the channel steel cross arms through bolts;
the round steel is provided with a plurality of, and the round steel corresponds to be fixed between every U type card and channel-section steel cross arm.
The gap distance between the two channel steel cross arms is 13-25 mm.
The top of each channel steel stand column is also provided with a steel plate.
Four sides of the steel plate exceed the channel steel upright posts by 4-5 cm.
The steel plate, the channel steel cross arm and the channel steel stand column are all in welded connection.
And a gasket is arranged between the bolt and the bottom surface of the channel steel cross arm.
The utility model has the beneficial effects that:
according to the adjustable double-spliced bracket for the electromechanical installation engineering, disclosed by the utility model, when a fixed pipeline is installed and erected, the position of the U-shaped clamp can be freely adjusted through the gap between the two brackets, so that the pipeline to be erected can be placed in the space between the two round steels, the problem that mechanical hole opening is needed to install the round steels in the brackets during traditional construction manufacturing is reduced, the problem that excessive working hours are consumed during traditional construction methods is reduced, in addition, the position of the pipeline can be adjusted directly through adjusting the position of the U-shaped clamp, and the accuracy of the position of the pipeline is also obviously improved.
Drawings
FIG. 1 is a schematic structural view of an adjustable double-split bracket for electromechanical installation engineering according to the present invention;
fig. 2 is a cross-sectional view of a channel steel cross arm of the adjustable double-spliced bracket for the electromechanical installation engineering.
In the figure, 1 is a channel steel upright post, 2 is a channel steel cross arm, 3 is a U-shaped clamp, 4 is round steel, 5 is a steel plate, and 6 is a gasket.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments. The following examples are only for illustrating the technical solutions of the present invention more clearly, and the protection solutions of the present invention are not limited thereto.
Example 1
The utility model discloses an adjustable double-spliced bracket for electromechanical installation engineering, which is shown in figures 1-2 and comprises: the device comprises a channel steel upright post 1, a channel steel cross arm 2, a U-shaped clamp 3 and round steel 4; two channel steel upright columns 1 are arranged; two channel steel cross arms 2 are arranged, the two channel steel cross arms 2 are arranged between the lower ends of the two channel steel upright posts 1, and a gap is formed between the two channel steel cross arms 2; a plurality of U-shaped cards 3 are arranged and are arranged between gaps formed by the two channel steel cross arms 2, and the bottoms of the U-shaped cards 3 are connected with the channel steel cross arms 2 through bolts; a plurality of round steel 4 are arranged, and the round steel 4 is correspondingly fixed between each U-shaped clamp 3 and the channel steel cross arm 2; the channel steel upright posts 1 mainly play roles in fixing the channel steel cross arms 2 and bearing pipeline tension; the channel steel cross arm plays a role of bearing a pipeline.
When in specific implementation, the size of the bracket is determined according to the arrangement, the size and the number of the pipelines, and the size of the channel steel is determined; channel-section steel 8 is adopted to this embodiment channel-section steel stand 1, and channel-section steel cross arm 2 adopts channel-section steel 8.
In order to move the U-shaped card 3 conveniently, the gap distance between the two channel steel cross arms 2 is 13-25 mm.
The top of each channel steel upright post 1 is also welded and connected with a steel plate 5, and the steel plate 5 is used for increasing the bearing capacity of the whole bracket and the contact surface of the wall surface, the beam and the plate; the steel plate 5, the channel steel cross arm 2 and the channel steel upright post 1 are all connected in a welding way.
For reliable connection, a gasket 6 is connected between the U-shaped clamp 3 and the bottom surface of the channel steel cross arm 2.
When the adjustable double-spliced bracket for the electromechanical installation engineering is used, the distance between the two round steel is adjusted by moving the U-shaped clamp 3, then the pipeline is installed in the space between the two round steel, and the erection of the pipeline can be directly completed, so that the problem that mechanical hole opening is needed to be carried out on the bracket to install the round steel in the traditional construction manufacturing process is reduced, the problem that too much working time is needed in the traditional construction method is reduced, in addition, the position of the pipeline can be adjusted by directly adjusting the position of the U-shaped clamp, and the accuracy of the position of the pipeline is obviously improved.
The above-mentioned embodiments are only preferred embodiments of the present invention, and the scope of the present invention is not limited thereto, and any simple modifications or equivalent substitutions of the technical solutions that can be made obvious by those skilled in the art within the technical scope of the present invention are included in the scope of the present invention.
Claims (6)
1. The utility model provides an electromechanical installation engineering is with adjustable double pin support which characterized in that includes:
two channel steel upright columns (1) are arranged;
two channel steel cross arms (2) are arranged, the two channel steel cross arms (2) are arranged between the lower ends of the two channel steel stand columns (1), and a gap is formed between the two channel steel cross arms (2);
a plurality of U-shaped clamps (3) are arranged and are arranged between gaps formed by the two channel steel cross arms (2), and the bottoms of the U-shaped clamps (3) are connected with the channel steel cross arms (2) through bolts;
the U-shaped clamp is characterized in that a plurality of round steel (4) are arranged, and the round steel (4) are correspondingly fixed between each U-shaped clamp (3) and the channel steel cross arm (2).
2. An adjustable double-split bracket for electromechanical installation engineering according to claim 1, wherein the gap distance between the two channel steel cross arms (2) is 13-25 mm.
3. The adjustable double-split bracket for the electromechanical installation engineering according to claim 1, wherein a steel plate (5) is further arranged at the top of each channel steel upright (1).
4. The adjustable double-split support for electromechanical installation engineering according to claim 3, wherein four sides of the steel plate (5) exceed the channel steel upright posts (1) by 4-5 cm.
5. The adjustable double-split bracket for the electromechanical installation engineering according to claim 3, wherein the steel plate (5), the channel steel cross arm (2) and the channel steel upright (1) are all in welded connection.
6. The adjustable double-split bracket for the electromechanical installation engineering as claimed in claim 1, wherein a gasket (6) is further arranged between the bolt and the bottom surface of the channel steel cross arm (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220386572.8U CN216789437U (en) | 2022-02-24 | 2022-02-24 | Electromechanical mounting engineering is with adjustable two support of piecing together |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202220386572.8U CN216789437U (en) | 2022-02-24 | 2022-02-24 | Electromechanical mounting engineering is with adjustable two support of piecing together |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216789437U true CN216789437U (en) | 2022-06-21 |
Family
ID=82017969
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202220386572.8U Expired - Fee Related CN216789437U (en) | 2022-02-24 | 2022-02-24 | Electromechanical mounting engineering is with adjustable two support of piecing together |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216789437U (en) |
-
2022
- 2022-02-24 CN CN202220386572.8U patent/CN216789437U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112081391A (en) | Single-pipe splicing device for steel structure truss | |
CN216789437U (en) | Electromechanical mounting engineering is with adjustable two support of piecing together | |
CN202839658U (en) | Photovoltaic support with adjustable inclination angle | |
CN113931360A (en) | Method for fixing curtain wall keel on I-shaped steel web | |
CN113241693A (en) | Cable bridge tubular pile mounting structure for photovoltaic power station on water | |
CN214785314U (en) | Steel construction factory building roofing truss lower carriage mounting structure | |
CN219825295U (en) | Horizontal steel supporting structure for reverse construction method | |
CN113872514B (en) | Photovoltaic support upright post fixing device of T-shaped groove preassembling platform and mounting method | |
CN218966731U (en) | Contact net device in tunnel | |
CN210792170U (en) | Supporting platform for film production equipment | |
CN219430570U (en) | Inserting plate type roadbed sound barrier H-shaped steel stand column embedded part positioning device | |
CN220577092U (en) | Station lateral wall contact net hangs installation device | |
CN219697014U (en) | Fixing device of distribution box on light steel keel wall | |
CN220412644U (en) | Pipeline laying equipment | |
CN221167760U (en) | Glass fiber I-shaped joint structure of underground diaphragm wall of water-rich deep soft soil layer | |
CN220848643U (en) | Back-pull type anchoring wall-riding hanging basket support frame | |
CN220377305U (en) | Foundation pit collapse prevention fixing frame for subway building | |
CN220284782U (en) | Land-based prefabricated photovoltaic pile system | |
CN216551945U (en) | Cast-in-situ bored pile steel protects a section of thick bamboo center positioning device | |
CN220978368U (en) | Independent reinforcing base for steel pipe vertical rod | |
CN217946448U (en) | Movable bracket device | |
CN218845299U (en) | Support structure of push bench | |
CN220849675U (en) | Auxiliary guiding device for pipe jacking construction | |
CN219080278U (en) | Larson steel sheet pile supporting device | |
CN218425295U (en) | Steel bar bending device in narrow environment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220621 |