CN216786894U - Upward ramp dismantling system structure - Google Patents

Upward ramp dismantling system structure Download PDF

Info

Publication number
CN216786894U
CN216786894U CN202123432627.9U CN202123432627U CN216786894U CN 216786894 U CN216786894 U CN 216786894U CN 202123432627 U CN202123432627 U CN 202123432627U CN 216786894 U CN216786894 U CN 216786894U
Authority
CN
China
Prior art keywords
enclosure
construction
foundation
steel pipe
door frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202123432627.9U
Other languages
Chinese (zh)
Inventor
虞国灿
徐全民
黄文明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Xiaoshan Traffic Construction Management Co ltd
Original Assignee
Hangzhou Xiaoshan Traffic Construction Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Xiaoshan Traffic Construction Management Co ltd filed Critical Hangzhou Xiaoshan Traffic Construction Management Co ltd
Priority to CN202123432627.9U priority Critical patent/CN216786894U/en
Application granted granted Critical
Publication of CN216786894U publication Critical patent/CN216786894U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to an ascending ramp dismantling system structure, which comprises a temporary buttress system and a construction enclosure spraying system; the temporary buttress system comprises a steel pipe bracket and a bracket foundation; the steel pipe support comprises a main beam, a distribution beam, a steel pipe upright post and a high-strength split bolt; the support foundation comprises a foundation longitudinal beam the top of which is connected with the steel pipe upright post and a longitudinal beam pillow which is fixed at the bottom of the foundation longitudinal beam through a connecting part, and the foundation longitudinal beam is fixed on the bearing platform through an anchor bolt; the construction enclosure spraying system is formed by splicing an enclosure stand column and an enclosure, and surrounds outside the construction area, and a water mist nozzle is arranged on the side of the construction enclosure spraying system. The method and the device have the advantages of reducing the dismantling difficulty, the dismantling cost and reducing the construction period.

Description

Ascending ramp dismantling system structure
Technical Field
The utility model relates to the technical field of building engineering, in particular to an ascending ramp dismantling system structure.
Background
The ramp is an indispensable component of the intercommunicated type flyover crossing and is a road for up-and-down crossing. Whether the ramp is designed reasonably or not is directly related to the exertion of the flyover crossing function, the safe and smooth driving, the economy of operation, the investment of engineering and the like. However, with the progress of urbanization, the road traffic network becomes more and more complex, and the dismantling construction of the existing ascending ramp is inevitably involved in the original engineering for reconstructing and extending the expressway.
At present, the removal construction of the ascending ramp is usually carried out by adopting full-line closed enclosure construction, namely, firstly chiseling a bridge deck pavement layer, removing guardrails and flange plates on two sides, and then removing a box body and a pier stud in sequence. And the continuous box girder needed to be used adopts the construction method of erecting a steel pipe bracket, cutting a large block section and removing the continuous box girder by putting down and gradually by hoisting. However, in the construction process, the traditional enclosure construction is time-consuming and labor-consuming, and the adopted spray dust removal system can cause the problem of water accumulation in the construction site, so that potential safety hazards are easy to occur; in addition, when the continuous box girder is dismantled, temporary buttresses are needed, the foundation needs to be replaced and filled, and a large amount of bar-shaped concrete foundations need to be poured, so that time and labor are consumed, the environmental influence is large, and the dismantling efficiency of the ascending ramp is influenced.
Therefore, at present, it is important to find a safe and environment-friendly up ramp dismantling system structure with reasonable structure and high construction efficiency.
SUMMERY OF THE UTILITY MODEL
The present invention has been made keeping in mind the above problems occurring in the prior art, and an object of the present invention is to provide an up-ramp demolition architecture.
In order to realize the purpose of the utility model, the utility model adopts the following technical scheme: the ascending ramp dismantling system structure comprises a temporary buttress system erected at the bottom of a box girder of an ascending ramp and a construction fence spraying system arranged on the periphery of a construction area;
the temporary buttress system comprises a steel pipe bracket and a bracket foundation; the steel pipe support comprises a main beam, a distribution beam arranged at the top of the main beam, steel pipe upright columns arranged at the bottom of the main beam and a high-strength split bolt arranged between the two steel pipe upright columns; the support foundation comprises a foundation longitudinal beam and a longitudinal beam pillow, wherein the top of the foundation longitudinal beam is connected with the steel pipe upright column, the longitudinal beam pillow is fixed at the bottom of the foundation longitudinal beam through a connecting part, the foundation longitudinal beam is fixed on a bearing platform through an anchor bolt, and the bearing platform is fixed on a foundation through a pile foundation;
the high-strength split bolt comprises a screw rod, a limiting ring and a nut, the screw rod penetrates through two adjacent steel pipe stand columns, and the screw rod is locked and fixed on the left side and the right side of each steel pipe stand column through the matching of the limiting ring and the nut;
the construction enclosure spraying system is formed by splicing an enclosure stand column and an enclosure, and surrounds the construction area, and a water mist nozzle is arranged on the edge of the construction enclosure spraying system.
The working principle and the beneficial effects are as follows: 1. compared with the prior art, the two steel pipe upright posts are oppositely fixed through the high-strength opposite-pulling bolts to finally form the steel pipe support, which is equivalent to a prestressed opposite-pulling steel pipe combined support, and the prestressed opposite-pulling steel pipe combined support and the support foundation form a temporary buttress system, wherein the support foundation effectively utilizes a bearing platform, a foundation longitudinal beam and a longitudinal beam sleeper to solve the problem of insufficient bearing capacity of the temporary buttress foundation, so that the environmental pollution caused by replacement of the original ground and pouring of a concrete foundation is avoided, and the construction cost and the construction period are also reduced;
2. in addition, the whole steel pipe support is reasonable in structural design and simple to assemble and disassemble, so that the construction period can be greatly shortened, and the construction difficulty can be reduced;
3. compared with the prior art, the structure that the fender sprayed the system is enclosed in the construction sets up rationally, through enclosing the fender stand with enclose the fender and can make up the assembly fast, also can demolish fast, area occupied is little, compares traditional interim opening water horse and encloses the fender, and interim opening is easily opened and close more, practices thrift manpower and time.
Furthermore, the construction enclosure spraying system comprises enclosure stand columns fixed on the ground, an enclosure arranged between two adjacent enclosure stand columns and pipelines arranged at the top of the enclosure stand columns and the top of the enclosure; the enclosure upright posts and the enclosure form a circle of construction enclosure, and any one side of the construction enclosure is provided with a temporary opening; the pipeline is provided with a plurality of water mist nozzles facing the inside of the construction enclosure. Compared with the prior art, the mode that this application adopted the water smoke nozzle to carry out the spraying encloses towards the construction and keeps off inside, consequently can realize the building site dust fall, reduces the raise dust pollution by a wide margin, owing to not the mode that directly sprays, can show the ponding problem that reduces the construction site and take place.
Further, interim opening including link firmly in enclose the door frame on the fender stand with locate the door frame with enclose the activity that keeps off between the stand and enclose the fender, door frame top surface down is equipped with the slide rail, the activity is enclosed the fender top and is equipped with the double-layered rail ware with this slide rail complex, and this activity encloses the fender bottom and is equipped with the gyro wheel with the ground butt, so that the activity is enclosed the fender and can be followed door frame length direction round trip movement realizes opening the door or closes the door operation. This setting provides a simple structure's interim opening, and the activity is enclosed and is kept off the effect that has played the door, can smoothly slide convenient operation.
Furthermore, a limiting rod is arranged between the door frame and the movable enclosing barrier, and the relative distance between the door frame and the movable enclosing barrier is limited through the limiting rod. This sets up, can inject the activity well through the gag lever post and enclose the distance between fender and the door frame, prevents that the activity from enclosing fender and door frame production and interfering or rub, leads to the activity to enclose the fender and can't slide smoothly.
Furthermore, the top of the door frame is welded and fixed with the side face of the top of the enclosing and blocking upright post, and the bottom of the door frame is fixed on the ground through an anchor bolt. This setting can be conveniently installed the door frame on enclosing the fender stand, and during the dismantlement, only need pull down the crab-bolt, then cut the door frame and enclose the welding limit between the fender stand, perhaps directly let the door frame along with enclosing the fender stand and dismantle together.
Furthermore, enclose fender with the activity encloses the fender and is made by the panel that the lower part is the steel sheet, and upper portion is the wire net. This setting, not only can play the reduction and enclose the fender and the activity encloses the effect that keeps off the weight, can also guarantee to enclose to keep off and the activity encloses the fender and can play certain effect that blocks that the building piece dashes out to enclose and keep off outside.
Drawings
FIG. 1 is a partial view of a construction layout of an up-ramp removal system according to the present invention;
fig. 2 is a schematic cross-sectional view of an up ramp;
FIG. 3 is a schematic cross-sectional view of a temporary pier system;
FIG. 4 is a partial view of the placement of the stent foundation;
FIG. 5 is a schematic cross-sectional view of a stent base;
FIG. 6 is a schematic view of a high tensile split bolt;
FIG. 7 is a plan view of a construction enclosure spray system;
FIG. 8 is a schematic view of a temporary opening;
fig. 9 is a left side view of fig. 8.
In the figure, 1, a crash barrier; 2. a flange plate; 3. a continuous box girder; 4. a support; 5. pier studs; 6. a bearing platform; 7. a pile foundation; 8. hoisting holes; 9. cutting a line; 10. a distribution beam; 11. a main beam; 12. a flange plate; 13. high-strength split bolts; 14. a steel pipe upright post; 15. a base stringer; 16. an anchor bolt; 17. a longitudinal beam pillow; 18. a connecting part; 19. a groove; 20. a steel pipe bracket; 21. a support foundation; 22. a screw; 23. a limiting ring; 24. a nut; 25. a fence post; 26. fencing; 27. a pipeline; 28. a water mist nozzle; 29. a temporary opening; 30. a door frame; 31. a movable enclosure; 32. a limiting rod; 33. a roller; 34. a rail clamp; 35. a slide rail; 36. a base.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments that can be derived by one of ordinary skill in the art from the embodiments given herein are intended to be within the scope of the present invention.
It will be understood by those skilled in the art that in the present disclosure, the terms "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like are used in an orientation or positional relationship indicated in the drawings for ease of description and simplicity of description, and do not indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and thus, the above terms should not be construed as limiting the present invention.
Example 1
As shown in fig. 1-9, the upward ramp dismantling system structure includes a temporary buttress system erected at the bottom of a box girder 3 of an upward ramp, and a construction fence 26 spraying system arranged at the periphery of a construction area, wherein during the dismantling process of the upward ramp, a bridge deck pavement layer, guardrails at two sides and flange plates 2 need to be dismantled, then a box body and pier studs 5 of a continuous box girder 3, supports 4 between the pier studs 5 and the continuous box girder 3, and the like are dismantled.
The temporary buttress system comprises a steel pipe support 20 and a support foundation 21, wherein the steel pipe support 20 comprises a main beam 11, a distribution beam 10 arranged at the top of the main beam 11, steel pipe columns 14 arranged at the bottom of the main beam 11 and high-strength split bolts 13 arranged between the two steel pipe columns 14, the two adjacent steel pipe columns 14 are fixed through the high-strength split bolts 13, each high-strength split bolt 13 comprises a screw rod 22, a limiting ring 23 and a nut 24, each screw rod 22 transversely penetrates through the two adjacent steel pipe columns 14, and the screw rods 22 are locked and fixed at the left side and the right side of each steel pipe column 14 through the matching of the limiting rings 23 and the nuts 24. Therefore, the positions of the nut 24 and the limiting ring 23 can be determined according to the distance between the two steel pipe columns 14, and after the nut 24 and the limiting ring 23 are installed in place, the opposite pulling effect of the two adjacent steel pipe columns 14 can be realized.
Compared with the prior art, the two steel pipe columns 14 are fixed in a split manner through the high-strength split bolts 13 to finally form the steel pipe support 20, which is equivalent to a prestressed split steel pipe combined support, the prestressed split steel pipe combined support and the support foundation 21 form a temporary buttress system, wherein the support foundation 21 effectively utilizes the bearing platform 6, the foundation longitudinal beam 15 and the longitudinal beam pillow 17 to solve the problem of insufficient bearing capacity of the temporary buttress foundation, the environmental pollution caused by replacement of the original ground and pouring of a concrete foundation is avoided, and the construction cost and the construction period are also reduced.
And the support foundation 21 comprises a foundation longitudinal beam 15 with the top connected with the steel pipe upright post 14 and a longitudinal beam pillow 17 fixed at the bottom of the foundation longitudinal beam 15 through a connecting part, the foundation longitudinal beam 15 is fixed on the bearing platform 6 through an anchor bolt 16, the bearing platform 6 is fixed on the foundation through a pile foundation 7, and the bearing platform 6 and the foundation are the prior art in the field, so that the details are not repeated.
Preferably, the construction is enclosed fender 26 and is sprayed the system including being fixed in subaerial fender stand 25 that encloses, locate adjacent two and enclose fender 26 between the fender stand 25 and locate and enclose fender stand 25 and enclose the pipeline 27 at fender 26 top, the quantity that encloses fender stand 25 is decided according to the size of actual construction scope, and the length that encloses fender 26 also is decided according to actual design demand, pipeline 27 also docks the installation according to actual demand, pipeline 27 is formed for the concatenation of the short pipeline 27 of multistage, so can conveniently transport, also can conveniently adjust according to the site conditions.
In this embodiment, enclose and keep off stand 25 and enclose fender 26 and constitute a round of construction and enclose fender 26, enclose and keep off 26 at this construction and be equipped with interim opening 29 on any one side wherein, interim opening 29 is including welding door frame 30 on enclosing fender stand 25 and locating door frame 30 and enclose fender 31 with enclosing the activity between fender stand 25, the surface down at door frame 30 top is equipped with slide rail 35, activity is enclosed and is equipped with rail clamp 34 with this slide rail 35 complex at the top of fender 31, and this activity is enclosed and is equipped with gyro wheel 33 with ground butt at 31 bottom, so that activity is enclosed fender 31 and can realize opening the door or close the door operation along door frame 30 length direction round trip movement, wherein this door frame 30 bottom is fixed in subaerial through crab-bolt 16.
In order to conveniently adjust the distance between the door frame 30 and the movable enclosure 31, a limiting rod 32 is arranged between the door frame 30 and the movable enclosure 31, the limiting rod 32 limits the relative distance between the door frame 30 and the movable enclosure 31, and the limiting rod 32 can be installed on the movable enclosure 31 and is not connected with the door frame 30, or installed on the door frame 30 and is not connected with the movable enclosure 31. Smooth sliding of the movable fence 31 can be ensured.
Example 2
The construction method of the ascending ramp dismantling system structure is used for dismantling the ascending ramp, and specifically comprises the following steps:
s000, installing a construction enclosure 26 spraying system:
s001, transporting the enclosure upright post 25 and the enclosure 26 which are manufactured in advance in a factory to a construction area to be assembled to form a construction enclosure 26, wherein the enclosure 26 and the movable enclosure 31 are both manufactured by adopting plates with steel plates at the lower parts and steel wire meshes at the upper parts;
s002, arranging temporary openings 29 on the construction enclosure 26 according to construction requirements, after the positions of the temporary openings 29 are selected, welding door frames 30 on the inner sides of the tops of the enclosure upright posts 25 on two sides of the positions, fixing the bottoms of the door frames 30 on the ground by using anchor bolts 16, welding rail clamping devices 34 on the downward surfaces of the tops of the door frames 30, welding and installing limiting rods 32, rollers 33 and sliding rails 35 on the movable enclosure 31, installing the movable enclosure 31 into the door frames 30, forming the symmetrical sliding door type temporary openings 29, and using lock catches as door locks. The temporary opening 29 can be quickly machined by adopting the steps; and arranging wall cloth on the construction enclosure 26 according to construction needs, and performing shielding, sealing and beautifying operations.
S003, installing a pipeline 27 at the top of the construction enclosure 26, installing water mist nozzles 28 on the pipeline 27 at intervals, supplying water to the pipeline 27 through a water tank and a water pump, and controlling the range and frequency of spraying water mist during the construction period to be removed by a controller, wherein the controller is a product available on the market, so the structure and the principle of the controller are not described again;
s100, removing the auxiliary bridge deck pavement facilities of the ascending ramps and other facilities; this step is prior art and therefore is not described in further detail.
S200, cutting and dismantling the concrete anti-collision guardrail 1 and the flange plate 2 of the ascending ramp as an integral structure; this step is prior art and therefore is not described in further detail.
S300, dismantling the prestressed concrete continuous box girder 3:
s301, leveling and tamping the ground between adjacent bearing platforms 6, arranging longitudinal beam sleepers 17 at intervals, hoisting the foundation longitudinal beam 15 to the bearing platforms 6 on two sides respectively by using a crane or a tower crane, simultaneously clamping a beam body of the foundation longitudinal beam 15 in a groove 19 of the longitudinal beam sleeper 17, connecting and fixing the foundation longitudinal beam 15 and the longitudinal beam sleeper 17 by using a connecting part 18, and connecting and fixing the foundation longitudinal beam 15 and the bearing platforms 6 by using an anchor bolt 16 to complete construction of a support foundation 21;
s302, bolting the bottoms of steel pipe upright columns 14 to foundation longitudinal beams 15 through flange plates 12, forming through holes in corresponding positions of the steel pipe upright columns 14, horizontally installing high-strength split bolts 13 between every two adjacent steel pipe upright columns 14, installing a plurality of high-strength split bolts 13 according to the heights of the steel pipe upright columns 14, bolting and installing main beams 11 at the tops of the steel pipe upright columns 14 through the flange plates 12, plugging the beam bottoms and the distribution beams 10 at the bottom plates of the box beams 3 of the continuous box beams 3 by adopting wood wedges, jacking the continuous box beams 3 by adopting synchronous jacking jacks, plugging gaps between the beam bottoms and the tops of the distribution beams 10 by using wedges, and excavating steel pipe supports 20 for construction;
s303, scribing a cutting line 9 before the box body of the continuous box girder 3 is dismantled, so that the cutting section of the continuous box girder 3 is completely fallen on the temporary abutment system, hoisting the cutting section to the ground for further cutting, and finally transporting to a crushing and cleaning field for crushing to finish scribing and cutting of the box girder 3;
s400, cutting the pier body of the ascending ramp in sections, hoisting and dismantling the pier body in sections, dismantling the abutment and the bearing platform 6 after the dismantling is finished, and finally finishing the construction of the ascending ramp dismantling system structure. Wherein the pier body comprises a pier stud 5 and a support 4.
The details of the present invention are not described in detail since they are prior art.
It is understood that the terms "a" and "an" should be interpreted as meaning that a number of one element or element is one in one embodiment, while a number of other elements is one in another embodiment, and the terms "a" and "an" should not be interpreted as limiting the number.
Although terms such as the crash barrier 1, the flange plate 2, the box girder 3, the support 4, the pier stud 5, the bearing platform 6, the pile foundation 7, the hoisting hole 8, the cutting line 9, the distribution beam 10, the main girder 11, the flange 12, the high-strength split bolt 13, the steel pipe column 14, the foundation stringer 15, the anchor bolt 16, the stringer sleeper 17, the connecting part 18, the groove 19, the steel pipe support 20, the support foundation 21, the screw rod 22, the limiting ring 23, the nut 24, the enclosure column 25, the enclosure 26, the pipeline 27, the water mist nozzle 28, the temporary opening 29, the door frame 30, the movable enclosure 31, the limiting rod 32, the roller 33, the rail clamp 34, the slide rail 35, and the base 36 are used more frequently, the possibility of using other terms is not excluded. These terms are used merely to more conveniently describe and explain the nature of the present invention; they are to be construed as being without limitation to any additional limitations that may be imposed by the spirit of the present invention.
The present invention is not limited to the above-mentioned preferred embodiments, and any other products in various forms can be obtained by anyone in the light of the present invention, but any changes in the shape or structure thereof, which have the same or similar technical solutions as the present application, fall within the protection scope of the present invention.

Claims (6)

1. The ascending ramp dismantling system structure is used for dismantling an ascending ramp and is characterized by comprising a temporary buttress system erected at the bottom of a box girder of the ascending ramp and a construction fence spraying system arranged on the periphery of a construction area;
the temporary buttress system comprises a steel pipe bracket and a bracket foundation; the steel pipe support comprises a main beam, a distribution beam arranged at the top of the main beam, steel pipe stand columns arranged at the bottom of the main beam and a high-strength split bolt arranged between the two steel pipe stand columns; the support foundation comprises a foundation longitudinal beam and a longitudinal beam pillow, wherein the top of the foundation longitudinal beam is connected with the steel pipe upright column, the longitudinal beam pillow is fixed at the bottom of the foundation longitudinal beam through a connecting part, the foundation longitudinal beam is fixed on a bearing platform through an anchor bolt, and the bearing platform is fixed on a foundation through a pile foundation;
the high-strength split bolt comprises a screw rod, a limiting ring and a nut, the screw rod penetrates through two adjacent steel pipe stand columns, and the screw rod is locked and fixed on the left side and the right side of each steel pipe stand column through the matching of the limiting ring and the nut;
the construction enclosure spraying system is formed by splicing an enclosure stand column and an enclosure, and surrounds the construction area, and a water mist nozzle is arranged on the edge of the construction enclosure spraying system.
2. The upward ramp demolition system according to claim 1, wherein the construction enclosure spraying system comprises enclosure columns fixed on the ground, an enclosure arranged between two adjacent enclosure columns, and a pipeline arranged at the top of the enclosure columns and the enclosure; the enclosure upright posts and the enclosure form a circle of construction enclosure, and any one side of the construction enclosure is provided with a temporary opening; the pipeline is provided with a plurality of water mist nozzles facing the inside of the construction enclosure.
3. The upward ramp demolition system according to claim 2, wherein the temporary opening comprises a door frame fixedly connected to the enclosure pillar and a movable enclosure arranged between the door frame and the enclosure pillar, a downward surface of the top of the door frame is provided with a slide rail, a top of the movable enclosure is provided with a rail clamp cooperating with the slide rail, and a bottom of the movable enclosure is provided with a roller abutting against the ground, so that the movable enclosure can move back and forth along the length direction of the door frame to open or close the door.
4. An up-ramp demolition architecture according to claim 3, wherein a limiting rod is provided between the door frame and the movable enclosure, and the relative distance between the door frame and the movable enclosure is limited by the limiting rod.
5. The up-ramp demolition system according to claim 4, wherein the top of the door frame is welded to the top side of the fence post, and the bottom of the door frame is fixed to the ground by an anchor bolt.
6. An up-ramp demolition system according to claim 5, wherein the enclosure and the movable enclosure are both made of sheet material with a lower portion of steel sheet and an upper portion of steel mesh.
CN202123432627.9U 2021-12-29 2021-12-29 Upward ramp dismantling system structure Expired - Fee Related CN216786894U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123432627.9U CN216786894U (en) 2021-12-29 2021-12-29 Upward ramp dismantling system structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123432627.9U CN216786894U (en) 2021-12-29 2021-12-29 Upward ramp dismantling system structure

Publications (1)

Publication Number Publication Date
CN216786894U true CN216786894U (en) 2022-06-21

Family

ID=82011209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123432627.9U Expired - Fee Related CN216786894U (en) 2021-12-29 2021-12-29 Upward ramp dismantling system structure

Country Status (1)

Country Link
CN (1) CN216786894U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319159A (en) * 2021-12-29 2022-04-12 杭州萧山交通建设管理有限公司 Ascending ramp dismantling system and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114319159A (en) * 2021-12-29 2022-04-12 杭州萧山交通建设管理有限公司 Ascending ramp dismantling system and construction method
CN114319159B (en) * 2021-12-29 2023-08-08 杭州萧山交通建设管理有限公司 Ascending ramp dismantling system and construction method

Similar Documents

Publication Publication Date Title
CN111794254A (en) Railway slope prefabricated assembled post-cast framework slope protection structure and construction method thereof
CN216786894U (en) Upward ramp dismantling system structure
CN110685459B (en) Breaking hammer dismantling construction method for dismantling hoist bent from lower part
CN114319159B (en) Ascending ramp dismantling system and construction method
CN108589565B (en) Bridge dismantling structure system and construction method
CN111119904A (en) Construction method of soft surrounding rock karst section tunnel
CN112160247B (en) Construction method of asynchronous hydraulic creeping formwork for hollow high pier of limited space pier group
CN111648229A (en) Assembled hoop platform for bent cap construction and mounting method thereof
CN111424948A (en) Construction method and construction platform for cantilever structure layer of high-rise building
CN217078829U (en) Position structure of bridge pile foundation and subway tunnel
CN114108642B (en) Parallel construction method for ramp bridge and underground complex structure
CN111593681B (en) Pier stud retaining cast-in-place box girder ecological dismantling system and construction method
CN111749717A (en) Road slope tunnel opening reinforcing device and construction method
CN113652953A (en) Novel assembled overline bridge ramp
CN208251112U (en) A kind of detachable structural steel combination crown beam
CN212479266U (en) Road side slope cave mouth reinforcing apparatus
CN114000540B (en) Ramp bridge combined support system built in parallel with underground complex and building method
CN218643330U (en) Steel-pipe pile is inserted and is beaten construction platform
CN114134829B (en) Prestressed hollow slab girder bridge dismantling system and construction method
CN217231475U (en) Assembly type bent cap support structure under condition of opening protection
CN221119977U (en) Steel structure removing operation platform for oversized-section portal chisel
CN211498542U (en) Static crushing and dismantling construction structure of upper-span existing line arch bridge
CN212533700U (en) Pin-connected panel staple bolt platform of bent cap construction usefulness
CN216428010U (en) Cast-in-place beam support of ramp bridge
CN219732023U (en) Fender pile and steel diagonal bracing fender structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220621