CN216765833U - Larsen steel sheet pile film water stopping measure equipment - Google Patents

Larsen steel sheet pile film water stopping measure equipment Download PDF

Info

Publication number
CN216765833U
CN216765833U CN202123145021.7U CN202123145021U CN216765833U CN 216765833 U CN216765833 U CN 216765833U CN 202123145021 U CN202123145021 U CN 202123145021U CN 216765833 U CN216765833 U CN 216765833U
Authority
CN
China
Prior art keywords
steel sheet
sheet pile
larsen steel
fixed
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123145021.7U
Other languages
Chinese (zh)
Inventor
肖三秀
赵俊
周静
徐志超
罗明飞
张晶晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Hanyang Municipal Construction Group Co Ltd
Original Assignee
Wuhan Hanyang Municipal Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Hanyang Municipal Construction Group Co Ltd filed Critical Wuhan Hanyang Municipal Construction Group Co Ltd
Priority to CN202123145021.7U priority Critical patent/CN216765833U/en
Application granted granted Critical
Publication of CN216765833U publication Critical patent/CN216765833U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses Larsen steel sheet pile film water stop measure equipment, relates to the technical field of Larsen steel sheet pile film water stop measure equipment, and aims to solve the problems that coarse sand, sawdust powder and cement mixture are sucked into a water leakage steel sheet pile locking gap to be tightly filled to achieve a water stop effect by utilizing the difference of water heads inside and outside a cofferdam and the action of water flow adsorption, but the method is difficult to operate, still needs divers to operate underwater when water leakage is serious, and the adopted coarse sand, sawdust powder and cement mixture can cause water environment pollution in the placing process, so that the construction cost is high, and the environment is not friendly. Fixing base is installed to the front end of Larsen steel sheet pile main part, and fixing base is provided with two, hydraulic telescoping column base is installed to fixing base's upper end, and hydraulic telescoping column base is provided with two, the installation slide rail is installed to the fixing base lower extreme.

Description

Larsen steel sheet pile film water stop measure equipment
Technical Field
The utility model relates to the technical field of Larsen steel sheet pile film water stopping measures and equipment, in particular to Larsen steel sheet pile film water stopping measures and equipment.
Background
The Larsen steel sheet pile is also called a U-shaped steel sheet pile and is used as a novel building material for serving as a soil retaining wall, a water retaining wall and a sand retaining wall when a bridge cofferdam is built, a large pipeline is laid and a temporary ditch is excavated; the method plays an important role in engineering, and is used as a retaining wall, an embankment revetment and the like in wharfs and unloading yards. The Larsen steel sheet pile cofferdam is green and environment-friendly, has high construction speed and low construction cost, and has a good waterproof function.
However, the existing Larsen steel sheet pile film water stopping measure equipment steel sheet pile cofferdam water stopping method is that the water head difference inside and outside the cofferdam is utilized, the water flow adsorption force is used, the coarse sand, the sawdust powder and the cement mixture are sucked into a water leakage steel sheet pile locking gap to be densely filled to achieve the water stopping effect, but the method is difficult to operate, a diver needs to operate underwater when the water leakage is serious, the adopted coarse sand, the sawdust powder and the cement mixture can cause the pollution of the water environment in the placing process, the construction cost is high, and the method is unfavorable for environmental protection; therefore, the existing requirements are not met, and a Larsen steel sheet pile thin film water stopping measure device is provided for the requirement.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide Larsen steel sheet pile film water stop measure equipment, which solves the problems that the existing Larsen steel sheet pile film water stop measure equipment in the background art uses the difference of water heads inside and outside a cofferdam and the action of water flow adsorption to suck coarse sand, sawdust powder and cement mixture into a water leakage steel sheet pile locking gap to be tightly filled to achieve the water stop effect, but the method is difficult to operate, a diver needs to operate underwater when water leakage is serious, and the adopted coarse sand, sawdust powder and cement mixture can cause the pollution of a water environment in the placing process, so that the construction cost is high, and the environment is not friendly.
In order to achieve the purpose, the utility model provides the following technical scheme: a Larsen steel sheet pile thin film water stop measure device comprises a Larsen steel sheet pile main body, a fixed base is arranged at the front end of the Larsen steel sheet pile main body, two fixed bases are arranged, the upper end of each fixed base is provided with a hydraulic telescopic column base, two hydraulic telescopic column bases are arranged, the lower end of the fixed base is provided with two mounting slide rails, the lower end of the fixed base is provided with a hydraulic telescopic column, two hydraulic telescopic columns are arranged, one side of the Larsen steel sheet pile main body is provided with a matching connecting sliding groove, the other side of the Larsen steel sheet pile main body is provided with a matching connection insertion block, the upper end of the Larsen steel sheet pile main body is provided with a water pump installation bottom plate, the upper end of the water pump installation bottom plate is provided with a fixed hexagon nut, and the number of the fixed hexagon nuts is four, and the upper end of the water pump mounting base plate is provided with a water pump clamping groove.
Preferably, the fixed block is installed to unable adjustment base's lower extreme, fixed block and unable adjustment base welded connection, and the fixed block is provided with two.
Preferably, servo motor is installed to the lower extreme of fixed block, servo motor and fixed block welded connection, and servo motor is provided with two.
Preferably, the lower extreme of servo motor is installed and is connected the rotation axis, and connects the rotation axis and be provided with two.
Preferably, one side of the hydraulic telescopic column is provided with two fixed clamping blocks, and the fixed clamping blocks are welded with the hydraulic telescopic column.
Preferably, one side of the connecting rotating shaft is provided with two movable clamping blocks, the movable clamping blocks are connected with the connecting rotating shaft in a welding mode, and the number of the movable clamping blocks is two.
Compared with the prior art, the utility model has the beneficial effects that:
1. the movable clamping blocks are arranged on one side of the connecting rotating shaft, the movable clamping blocks are connected with the connecting rotating shaft in a welding mode, the number of the movable clamping blocks is two, when workers perform hole blocking and water stopping work, a plastic film can be placed on the fixed clamping blocks, the servo motor drives the connecting rotating shaft to rotate, the movable clamping blocks are folded to clamp the plastic film, the hydraulic telescopic column extends out, the plastic film is driven to sink to the position of a water outlet hole, the servo motor rotates reversely to open the movable clamping blocks, the plastic film is sucked into the water outlet hole by the suction force of water flow to cause blocking, the purpose of stopping water is achieved, the problem that the water stopping method of the steel sheet pile cofferdam of the existing Larsen steel sheet pile film water stopping measure equipment is effectively solved, coarse sand, sawdust powder and cement mixture are sucked into a locking gap of the steel sheet pile of water leakage to be filled compactly to achieve the water stopping effect by means of water flow adsorption force inside and outside the cofferdam, however, the method is difficult to operate, still needs a diver to operate underwater when water leakage is serious, and the adopted mixture of coarse sand, sawdust powder and cement can cause water environment pollution in the placing process, so that the construction cost is high, and the method is unfavorable for environmental protection.
2. Through set up the cooperation in one side of Larsen steel sheet pile main part and connect the spout, the opposite side has installed the cooperation moreover and has connected the inserted block, when carrying out built-up connection with two Larsen steel sheet pile main parts, only need connect the inserted block with the cooperation and insert the cooperation and connect the spout to this realization is connected can.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the upper end structure of the present invention;
FIG. 3 is a schematic front view of the present invention;
in the figure: 1. a Larsen steel sheet pile main body; 2. a fixed base; 3. a hydraulic telescopic column base; 4. installing a slide rail; 5. a hydraulic telescopic column; 6. the sliding chutes are connected in a matching way; 7. the inserting blocks are connected in a matching way; 8. a water pump mounting bottom plate; 9. fixing a hexagonal nut; 10. a water pump clamping groove; 11. a fixed block; 12. a servo motor; 13. connecting the rotating shaft; 14. fixing the clamping block; 15. and a movable clamping block.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-3, an embodiment of the present invention is shown: a Larsen steel sheet pile thin film water stop measure device comprises a Larsen steel sheet pile main body 1, a fixed base 2 is arranged at the front end of the Larsen steel sheet pile main body 1, two fixed bases 2 are arranged, the upper end of the fixed base 2 is provided with a hydraulic telescopic column base 3, two hydraulic telescopic column bases 3 are arranged, the lower end of the fixed base 2 is provided with an installation slide rail 4, two installation slide rails 4 are arranged, the lower end of the fixed base 2 is provided with two hydraulic telescopic columns 5, the hydraulic telescopic columns 5 are arranged, one side of the Larsen steel sheet pile main body 1 is provided with a matching and connecting chute 6, the other side of the Larsen steel sheet pile main body 1 is provided with a matching and connecting insertion block 7, the upper end of the Larsen steel sheet pile main body 1 is provided with a water pump installation bottom plate 8, the upper end of the water pump installation bottom plate 8 is provided with a fixed hexagon nut 9, and four fixed hexagon nuts 9 are arranged, and the upper end of the water pump mounting bottom plate 8 is provided with a water pump clamping groove 10.
Further, fixed block 11 is installed to unable adjustment base 2's lower extreme, and fixed block 11 and unable adjustment base 2 welded connection, and fixed block 11 is provided with two, and welded connection's connected mode can make fixed block 11 and unable adjustment base 2's be connected more firmly and stable.
Further, servo motor 12 is installed to the lower extreme of fixed block 11, and servo motor 12 and fixed block 11 welded connection, and servo motor 12 is provided with two, and servo motor 12's setting can drive and connect rotation axis 13 rotatory to this comes the open and shut of control activity clamp splice 15.
Further, the lower extreme of servo motor 12 is installed and is connected rotation axis 13, and connects rotation axis 13 and be provided with two, connects the setting of rotation axis 13 and can drive movable clamp splice 15 and open and shut.
Further, fixed clamp splice 14 is installed to one side of hydraulic telescoping post 5, fixed clamp splice 14 and hydraulic telescoping post 5 welded connection, and fixed clamp splice 14 is provided with two, and welded connection's setting can make fixed clamp splice 14 more firm with the connection of hydraulic telescoping post 5.
Further, movable clamp splice 15 is installed to one side of connecting rotation axis 13, movable clamp splice 15 with be connected rotation axis 13 welded connection, and movable clamp splice 15 is provided with two, when the setting of movable clamp splice 15 can carry out the shutoff hole stagnant water work at the staff, place the plastic film on fixed clamp splice 14, servo motor 12 drives and connects rotation axis 13 rotatory, make movable clamp splice 15 fold and press from both sides the plastic film tightly, hydraulic telescoping post 5 stretches out, drive the plastic film and sink to the position of apopore, servo motor 12 reverses again and makes movable clamp splice 15 open, utilize the suction of rivers, inhale the plastic film in the apopore, cause the jam, reach the purpose of stagnant water with this.
The working principle is as follows: during the use, movable clamp splice 15 has been installed to one side of connecting rotation axis 13, movable clamp splice 15 with be connected rotation axis 13 welded connection, and movable clamp splice 15 is provided with two, the setting of movable clamp splice 15 can carry out the during operation of shutoff hole stagnant water at the staff, place plastic film on fixed clamp splice 14, servo motor 12 drives and connects rotation axis 13 rotatory, make movable clamp splice 15 fold and press from both sides the plastic film tightly, hydraulic telescoping post 5 stretches out, drive the plastic film and sink to the position of apopore, servo motor 12 reverses again and makes movable clamp splice 15 open, utilize the suction of rivers, inhale the plastic film in the apopore, cause the jam, reach the purpose of stagnant water with this.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a Larsen steel sheet pile film stagnant water measure equipment, includes Larsen steel sheet pile main part (1), its characterized in that: the front end of the Larsen steel sheet pile main body (1) is provided with a fixed base (2), the fixed base (2) is provided with two, the upper end of the fixed base (2) is provided with a hydraulic telescopic column base (3), the hydraulic telescopic column base (3) is provided with two, the lower end of the fixed base (2) is provided with an installation slide rail (4), the installation slide rail (4) is provided with two, the lower end of the fixed base (2) is provided with a hydraulic telescopic column (5), the hydraulic telescopic column (5) is provided with two, one side of the Larsen steel sheet pile main body (1) is provided with a matching connection slide groove (6), the other side of the Larsen steel sheet pile main body (1) is provided with a matching connection insertion block (7), the upper end of the Larsen steel sheet pile main body (1) is provided with a water pump installation bottom plate (8), the upper end of the water pump installation bottom plate (8) is provided with a fixed hexagon nut (9), and four fixed hexagonal nuts (9) are arranged, and the upper end of the water pump mounting base plate (8) is provided with a water pump clamping groove (10).
2. The larsen steel sheet pile thin film water stopping measure equipment as claimed in claim 1, wherein: fixed block (11) are installed to the lower extreme of unable adjustment base (2), fixed block (11) and unable adjustment base (2) welded connection, and fixed block (11) are provided with two.
3. The larsen steel sheet pile thin film water stopping measure equipment as claimed in claim 2, wherein: servo motor (12) are installed to the lower extreme of fixed block (11), servo motor (12) and fixed block (11) welded connection, and servo motor (12) are provided with two.
4. The larsen steel sheet pile thin film water stopping measure equipment as claimed in claim 3, wherein: the lower end of the servo motor (12) is provided with two connecting rotating shafts (13) which are connected with each other.
5. The larsen steel sheet pile thin film water stopping measure equipment as claimed in claim 1, wherein: fixed clamp splice (14) are installed to one side of hydraulic telescoping post (5), fixed clamp splice (14) and hydraulic telescoping post (5) welded connection, and fixed clamp splice (14) are provided with two.
6. The Larsen steel sheet pile thin film water stopping measure equipment as claimed in claim 4, wherein: connect one side of rotation axis (13) and install movable clamp splice (15), movable clamp splice (15) with be connected rotation axis (13) welded connection, and movable clamp splice (15) are provided with two.
CN202123145021.7U 2021-12-14 2021-12-14 Larsen steel sheet pile film water stopping measure equipment Active CN216765833U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123145021.7U CN216765833U (en) 2021-12-14 2021-12-14 Larsen steel sheet pile film water stopping measure equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123145021.7U CN216765833U (en) 2021-12-14 2021-12-14 Larsen steel sheet pile film water stopping measure equipment

Publications (1)

Publication Number Publication Date
CN216765833U true CN216765833U (en) 2022-06-17

Family

ID=81967703

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123145021.7U Active CN216765833U (en) 2021-12-14 2021-12-14 Larsen steel sheet pile film water stopping measure equipment

Country Status (1)

Country Link
CN (1) CN216765833U (en)

Similar Documents

Publication Publication Date Title
CN101718099B (en) Automatic wall-forming device and method of static pressure continuous concrete wall
CN109403363B (en) Self-balancing combined water retaining cofferdam and construction method thereof
CN216765833U (en) Larsen steel sheet pile film water stopping measure equipment
CN212772241U (en) Hydraulic dam bottom water stop device
CN111593733A (en) Pile-first interpolation type jacket grouting plugging system
CN2709522Y (en) Hydraulic spile pile device of water-resisting, concrete placing and seam sealing
CN216615695U (en) High water level water retaining device for flood prevention of building entrance and exit
CN211200313U (en) Integral self-rotating dam
CN212612487U (en) Pile-first interpolation type jacket grouting plugging system
CN113373930A (en) Pre-buried type biliquid slip casting plugging device of foundation ditch
CN220813892U (en) Larson steel sheet pile stake hole backfill device
CN201526047U (en) Static pressure automatic constructing device for underground continuous wall
CN218437151U (en) Open caisson excavation positioner
CN110777742A (en) Integral horizontal rotary dam
CN218818568U (en) Auxiliary device is filled to sleeve pipe clearance concrete
CN214695448U (en) Seepage-proofing water-stopping device for hydraulic engineering
CN116971369A (en) Eleven-shaft stirring pile forming machine
CN206000497U (en) A kind of device of comprehensive cleaning embedded rock pile pile bottom sediment
CN220057900U (en) Penetration structure is cut to plastic steel sheet pile
CN220451458U (en) Waterproof coiled material laying tool
CN218759953U (en) Water stop structure applied to outlet of top pipe in open caisson
CN210395315U (en) Underground continuous wall structure for water-rich sand layer deep foundation pit support
CN220888621U (en) Eleven-shaft cement soil impervious wall pile machine
CN218346177U (en) Pile pulling device for civil engineering
CN209271982U (en) A kind of Larsen stake steel plate sweeper

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant