CN216685264U - Hoop type transportation tool for large-span wind power jacket - Google Patents

Hoop type transportation tool for large-span wind power jacket Download PDF

Info

Publication number
CN216685264U
CN216685264U CN202122728652.5U CN202122728652U CN216685264U CN 216685264 U CN216685264 U CN 216685264U CN 202122728652 U CN202122728652 U CN 202122728652U CN 216685264 U CN216685264 U CN 216685264U
Authority
CN
China
Prior art keywords
half hoop
hoop
right half
staple bolt
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122728652.5U
Other languages
Chinese (zh)
Inventor
孙权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yongjie Special Equipment Co ltd
Original Assignee
Jiangsu Yongjie Engineering Logistics Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yongjie Engineering Logistics Co ltd filed Critical Jiangsu Yongjie Engineering Logistics Co ltd
Priority to CN202122728652.5U priority Critical patent/CN216685264U/en
Application granted granted Critical
Publication of CN216685264U publication Critical patent/CN216685264U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Wind Motors (AREA)

Abstract

The utility model discloses a hoop type transportation tool for a large-span wind power jacket, which comprises: go up staple bolt and lower staple bolt of aligning from top to bottom, it includes to go up the staple bolt: half hoop on the last left that links to each other through the bolt reaches half hoop on the last right, lower staple bolt includes: the lower left half hoop and the lower right half hoop are connected through bolts, the lower right half hoop extends rightwards to form a connecting seat, a supporting seat which inclines towards the upper left side is welded on the connecting seat, the supporting seat and the upper right half hoop are welded, and a plurality of pile tip anti-slip plates are uniformly distributed on the inner walls of the lower left half hoop and the lower right half hoop of the lower hoop along the circumference. The utility model has simple structure, convenient disassembly and assembly and can be repeatedly used.

Description

Hoop type transportation tool for large-span wind power jacket
Technical Field
The utility model relates to a hoop type transportation tool for a large-span wind power jacket.
Background
The large-span wind power jacket is composed of hollow leg columns and longitudinal cross rods connected with the leg columns, a fixed platform is lapped on the upper surface of the large-span wind power jacket and used for supporting offshore wind power generation equipment, first circular ring reinforcing plates protruding out of the leg columns are arranged between the leg columns and the longitudinal cross rods connected with the leg columns, pile tips are connected to the bottoms of the leg columns, and second circular ring reinforcing plates protruding out of the pile tips and the leg columns are arranged between the leg columns and the pile tips. The large-span wind power jacket is mainly composed of large-diameter steel pipes and is manufactured by adopting proper processing equipment and procedures suitable for the characteristics of the large-span wind power jacket. Because the volume of jacket basis is great, generally set up the portal on the jacket and carry, but use portal transport to have following defect: 1. when the portal frame is connected with the jacket, the installation process is complicated and the efficiency is low; 2. the jacket is large in size, and the size of the jacket is further increased by arranging the portal on the jacket, so that a larger site and a transport ship need to be selected, and the freight cost is increased; 3. the gantry arranged on the jacket is inconvenient to disassemble, so that the gantry is generally transported away along with the jacket and cannot be reused, and the manufacturing cost is increased.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a hoop type transportation tool for a large-span wind power jacket, which can reduce freight cost and manufacturing cost and improve disassembly and assembly efficiency.
In order to achieve the purpose, the utility model adopts the technical scheme that: large-span wind-powered electricity generation jacket staple bolt formula transportation frock includes: can support last staple bolt of the first ring reinforcing plate on the leg and can support the lower staple bolt of the second ring reinforcing plate between leg and the stake point, it includes to go up the staple bolt: half hoop on the last left that links to each other through the bolt reaches half hoop on the last right, lower staple bolt includes: the lower left half hoop and the lower right half hoop are connected through bolts, the lower right half hoop extends rightwards to form a connecting seat, a supporting seat which inclines towards the upper left side is welded on the connecting seat, the supporting seat and the upper right half hoop are welded, and a plurality of pile tip anti-slip plates are uniformly distributed on the inner walls of the lower left half hoop and the lower right half hoop of the lower hoop along the circumference.
Further, aforementioned large-span wind-powered electricity generation jacket staple bolt formula transportation frock, wherein, all be provided with first reinforcing plate on half hoop on last left and half hoop on last right, all be provided with the second reinforcing plate on half hoop on the left side down and half hoop on the right side down.
Further, aforementioned wind-powered electricity generation jacket staple bolt formula transportation frock of striding across, wherein, weld a bracing piece on lieing in the left connecting seat of supporting seat, the bracing piece welds with the left side wall of supporting seat mutually, welds an diagonal brace respectively on lieing in the connecting seat of both sides around the supporting seat, and two diagonal braces weld with the both sides wall around the supporting seat mutually respectively.
Further, according to the hoop type transportation tool for the large-span wind power jacket, the pile tip anti-slip plate is triangular, and the pile tip anti-slip plate is perpendicularly welded to the inner walls of the lower left half hoop and the lower right half hoop.
The utility model has the advantages that: the wind power jacket is simple in structure and convenient to disassemble and assemble with the wind power jacket, the disassembling and assembling efficiency is improved, and after the wind power jacket and the hoop type transportation tool are transported to a cargo ship together, the hoop type transportation tool can be disassembled from the leg column and the pile tip for repeated utilization, so that the production cost is greatly reduced; the four hoop type transportation tools are respectively connected with the four leg columns, and then the size of the wind power jacket cannot be additionally increased, so that a larger place and a freight ship do not need to be selected, and the freight cost is reduced.
Drawings
Fig. 1 is a schematic perspective view of a hoop type transportation tool for a large-span wind power jacket according to the present invention.
Fig. 2 is a schematic diagram of the left-side view in fig. 1.
Detailed Description
The technical solution of the present invention is further explained with reference to the drawings and the preferred embodiments.
As shown in fig. 1 and 2, the hoop type transportation tool for the large-span wind power jacket of the utility model comprises: go up staple bolt 1 and staple bolt 2 down of aligning from top to bottom, it includes to go up staple bolt 1: through the last half hoop 11 and the last half hoop 12 on the left that the bolt links to each other, all be provided with first reinforcing plate 13 on last half hoop 11 on the left and last half hoop 12 on the right, first reinforcing plate 13 can improve the intensity of last half hoop 11 on the left and last half hoop 12 on the right, staple bolt 2 includes down: the lower left half hoop 21 and the lower right half hoop 22 are connected through bolts, the second reinforcing plate 23 is arranged on the lower left half hoop 21 and the lower right half hoop 22, the strength of the lower left half hoop 21 and the lower right half hoop 22 can be improved through the second reinforcing plate 23, the lower right half hoop 22 extends rightwards to form a connecting seat 24, the supporting seat 3 inclined towards the left upper side is welded on the connecting seat 24, the supporting seat 3 is welded with the upper right half hoop 12, the supporting rod 31 is welded on the connecting seat 24 on the left side of the supporting seat 3, the supporting rod 31 is welded with the left side wall of the supporting seat 3, the connecting seat 24 on the front side and the rear side of the supporting seat 3 is respectively welded with an inclined strut 32, the two inclined struts 32 are respectively welded with the front side wall and the rear side wall of the supporting seat 3, and the supporting rod 31 and the two inclined struts 32 form three-point support for the supporting seat 3, so that the supporting strength of the supporting seat 3 is improved. A plurality of triangular pile tip anti-slip plates 4 are uniformly distributed on the inner walls of the lower left half hoop 21 and the lower right half hoop 22 of the lower anchor ear 2 along the circumference, and the pile tip anti-slip plates 4 are vertically welded with the inner walls of the lower left half hoop 21 and the lower right half hoop 22.
The working principle of the utility model is as follows: when transporting the wind-powered electricity generation jacket, need install four leg posts of wind-powered electricity generation jacket respectively with four staple bolt formula transportation frocks: firstly, placing the wind power jacket on the field, at the moment, abutting the pile toe on the wind power jacket against the field, then detaching the upper left half hoop 11 and the lower left half hoop 21 of the hoop type transportation tool, then respectively embracing the upper right half hoop 12 and the lower right half hoop 22 of the hoop type transportation tool against the leg post and the pile toe, abutting the first circular ring reinforcing plate on the leg post against the upper right half hoop 12, abutting the second circular ring reinforcing plate between the leg post and the pile toe against the lower right half hoop 22, clamping the pile toe slip-limiting plate 4 in the lower right half hoop 22 with the pile toe, then connecting the upper left half hoop 11 with the upper right half hoop 12 through bolts, connecting the lower left half hoop 21 with the lower right half hoop 22 through bolts, after the four hoop type transportation tools are respectively connected with the four leg posts on the wind power jacket, hoisting the four hoop type transportation tools by using a hoisting vehicle, hoisting the hoop type transportation tools after being hoisted, last staple bolt 1 on staple bolt formula transportation frock plays the effect that upwards pushes away to first ring reinforcing plate and second ring reinforcing plate respectively with staple bolt 2 down to make whole wind-powered electricity generation jacket can be hung up and transported, simultaneously, stake point limited slip board 4 in the staple bolt 2 down plays the card and keeps off limiting displacement to the stake point, prevents that the stake point from rotating in staple bolt 2 down.
The utility model has the advantages that: the wind power jacket is simple in structure and convenient to disassemble and assemble with the wind power jacket, the disassembling and assembling efficiency is improved, and after the wind power jacket and the hoop type transportation tool are transported to a cargo ship together, the hoop type transportation tool can be disassembled from the leg column and the pile tip for repeated utilization, so that the production cost is greatly reduced; the four hoop type transportation tools are respectively connected with the four leg columns, and then the size of the wind power jacket cannot be additionally increased, so that a larger place and a freight ship do not need to be selected, and the freight cost is reduced.

Claims (4)

1. Big span wind-powered electricity generation jacket staple bolt formula transportation frock, its characterized in that: the method comprises the following steps: can support last staple bolt of the first ring reinforcing plate on the leg and can support the lower staple bolt of the second ring reinforcing plate between leg and the stake point, it includes to go up the staple bolt: half hoop on the last left that links to each other through the bolt reaches half hoop on the last right, lower staple bolt includes: the lower left half hoop and the lower right half hoop are connected through bolts, the lower right half hoop extends rightwards to form a connecting seat, a supporting seat which inclines towards the upper left side is welded on the connecting seat, the supporting seat and the upper right half hoop are welded, and a plurality of pile tip anti-slip plates are uniformly distributed on the inner walls of the lower left half hoop and the lower right half hoop of the lower hoop along the circumference.
2. The large-span wind power jacket hoop type transportation tool according to claim 1, characterized in that: all be provided with first reinforcing plate on last left half hoop and last right half hoop, all be provided with the second reinforcing plate on lower left half hoop and lower right half hoop.
3. The large-span wind power jacket hoop type transportation tool according to claim 1, characterized in that: a supporting rod is welded on the connecting seat on the left side of the supporting seat, the supporting rod is welded with the left side wall of the supporting seat, inclined supporting rods are respectively welded on the connecting seats on the front side and the rear side of the supporting seat, and the two inclined supporting rods are respectively welded with the front side wall and the rear side wall of the supporting seat.
4. The large-span wind power jacket hoop type transportation tool according to claim 1, characterized in that: the pile toe anti-slip plate is triangular, and the pile toe anti-slip plate is vertically welded with the inner walls of the lower left half hoop and the lower right half hoop.
CN202122728652.5U 2021-11-09 2021-11-09 Hoop type transportation tool for large-span wind power jacket Active CN216685264U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122728652.5U CN216685264U (en) 2021-11-09 2021-11-09 Hoop type transportation tool for large-span wind power jacket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122728652.5U CN216685264U (en) 2021-11-09 2021-11-09 Hoop type transportation tool for large-span wind power jacket

Publications (1)

Publication Number Publication Date
CN216685264U true CN216685264U (en) 2022-06-07

Family

ID=81831675

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122728652.5U Active CN216685264U (en) 2021-11-09 2021-11-09 Hoop type transportation tool for large-span wind power jacket

Country Status (1)

Country Link
CN (1) CN216685264U (en)

Similar Documents

Publication Publication Date Title
CN214493276U (en) Offshore floating type wind power combined semi-submersible platform foundation
CN110761557A (en) Reverse construction method major diameter ring beam makes up movable template system of consolidating
CN210914947U (en) Hoisting and turning-over system suitable for large prefabricated stand board
CN110925146B (en) Offshore wind power jacket supporting seat
CN105730305A (en) Nuclear power structure module overturning device and installation method
CN216685264U (en) Hoop type transportation tool for large-span wind power jacket
CN102777050B (en) Assembly type jig frame for longspan pipe truss roof girder
CN102995560B (en) Thin-wall hollow pier lifting frame and use method thereof
CN102864746A (en) Bearing frame for bridge construction
CN110029671A (en) A kind of steep slope pile foundation steel bar cage transfers construction technology using aperture bracket section by section
CN207361652U (en) Moving device for large steel pipe
CN214994605U (en) Modularization steel structure spare
CN212000638U (en) Overhead cover beam type steel supporting structure
CN201785764U (en) Steel pipe concrete structured tower mast foundation
CN210213096U (en) Auxiliary stand steel construction
CN203546619U (en) Horizontal type simple cable unreeling disc for bridge construction
CN217576496U (en) Single pile lantern transferring tool based on flat car
CN211006694U (en) Connecting structure of supporting beam and upright post pile in building engineering
CN218477618U (en) Combined supporting jig frame
CN221297594U (en) Crossbeam support bearing truss sheet device with active cross braces
CN211286708U (en) Auxiliary supporting jig frame for mounting steel stairs
CN211286625U (en) Reverse construction method major diameter ring beam makes up movable template system of consolidating
CN212796955U (en) Adjustable oxygen tank supporting and moving device
CN218431275U (en) A transport vechicle for vibratory hammer transports
CN218712789U (en) Height-adjustable steady pile platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 215600 Jiangsu Yongjie Engineering Logistics Co., Ltd., room 1405, Aikang building, No. 5, Binhe Road, yangshe Town, Zhangjiagang City, Suzhou City, Jiangsu Province

Patentee after: Jiangsu Yongjie Special Equipment Co.,Ltd.

Address before: 215600 Jiangsu Yongjie Engineering Logistics Co., Ltd., room 1405, Aikang building, No. 5, Binhe Road, yangshe Town, Zhangjiagang City, Suzhou City, Jiangsu Province