CN216665060U - Membrane structure cable wire stretch-draw auxiliary device - Google Patents

Membrane structure cable wire stretch-draw auxiliary device Download PDF

Info

Publication number
CN216665060U
CN216665060U CN202123302426.7U CN202123302426U CN216665060U CN 216665060 U CN216665060 U CN 216665060U CN 202123302426 U CN202123302426 U CN 202123302426U CN 216665060 U CN216665060 U CN 216665060U
Authority
CN
China
Prior art keywords
membrane material
installation pole
membrane
pole
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123302426.7U
Other languages
Chinese (zh)
Inventor
李鹏飞
许自林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hefei Membrane Force Membrane Structure Co ltd
Original Assignee
Hefei Membrane Force Membrane Structure Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hefei Membrane Force Membrane Structure Co ltd filed Critical Hefei Membrane Force Membrane Structure Co ltd
Priority to CN202123302426.7U priority Critical patent/CN216665060U/en
Application granted granted Critical
Publication of CN216665060U publication Critical patent/CN216665060U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model relates to a membrane structure technical field discloses a membrane structure cable wire stretch-draw auxiliary device, including the membrane material, the upper surface middle part position department of membrane material wears to be equipped with the installation pole, the one end of installation pole and the top position department fixed connection of membrane material, and the one end setting that the membrane material was kept away from to the installation pole is in the ground, one side lateral wall department of installation pole is provided with spacing subassembly, the equal distance of side department all around that the installation pole was kept away from to the membrane material is provided with a plurality of supporting mechanism, and is a plurality of supporting mechanism is the annular distribution around the perpendicular center line of membrane material, the installation pole is close to many steel cable ropes of one end department fixed connection of membrane material, and is many the steel cable rope is the annular distribution around the perpendicular center line of membrane material, and this application is convenient for improving the stretch-draw auxiliary effect to membrane material and cable wire, is favorable to improving membrane material integral erection structure's fastness.

Description

Membrane structure cable wire stretch-draw auxiliary device
Technical Field
The application relates to the technical field of membrane structures, in particular to a steel cable stretching auxiliary device for a membrane structure.
Background
The membrane structure is also called a tension membrane structure, and is a novel building structure form developed in the middle of the 20 th century, mainly comprising a membrane material, a steel cable and a support, wherein the steel cable and the support are utilized to introduce tension in the membrane material to achieve a stress structure balance form, so that a certain pre-tension stress is generated inside the membrane material to form a certain space shape to serve as a covering structure, and the space structure form can bear a certain external load effect.
The existing membrane structure is only installed by matching a single support with a steel cable rope, so that the stability of the support structure is general, the stretching auxiliary effect of membrane materials and the steel cable rope is not high, and the firmness of the whole membrane material installation structure is not enough.
SUMMERY OF THE UTILITY MODEL
In order to improve the stretch-draw auxiliary effect to membrane material and cable wire to improve the fastness of membrane material integral erection structure, this application provides a membrane structure cable wire stretch-draw auxiliary device.
The application provides a membrane structure cable wire stretch-draw auxiliary device adopts following technical scheme:
the utility model provides a membrane structure cable wire stretch-draw auxiliary device, includes the membrane material, the upper surface middle part position department of membrane material wears to be equipped with the installation pole, the one end of installation pole and the top position department fixed connection of membrane material, and the one end setting that the membrane material was kept away from to the installation pole is in the ground, one side lateral wall department of installation pole is provided with spacing subassembly, the equal distance of side department all around that the installation pole was kept away from to the membrane material is provided with a plurality of supporting mechanism, and is a plurality of supporting mechanism is the annular distribution around the perpendicular center line of membrane material, the installation pole is close to many steel cable ropes of one end department fixedly connected with of membrane material, many the steel cable rope is the annular distribution around the perpendicular center line of membrane material.
Through adopting the above technical scheme, through installation pole and membrane material cooperation, be convenient for support jack-up membrane material, and then through installation pole and stand cooperation pulling steel cable rope, be convenient for assist stretch-draw installation membrane material structure, and then through two butt pole cooperation butt support pillars, and constitute the bearing structure of the triangular cone shape of slope with the pillar cooperation, moreover, the steam generator is simple in structure, be convenient for realize the lightweight, adopt triangular stability, be convenient for improve pillar bearing structure's steadiness, and then improve the supplementary effect of stretch-draw to membrane material and cable wire, be favorable to improving membrane material integral erection structure's fastness.
Preferably, spacing subassembly includes bracing piece and anchor strut, the bracing piece is provided with two, two the one end welding of bracing piece is in one side lateral wall department of installation pole, and the bracing piece is kept away from the one end setting of installation pole and is opened the form, two the one end setting of installation pole is kept away from to the bracing piece is in the ground.
Through adopting above-mentioned technical scheme, through the spacing installation pole of two spinal branch vaulting poles cooperation, be convenient for stabilize and support the installation pole, strengthen the structural stability of installation pole, make it be difficult for receiving environmental factor to influence and empty.
Preferably, the reinforcing rods are arranged in a plurality of numbers, the reinforcing rods are welded between the opposite side walls of the two support rods at intervals in the transverse direction, and the mounting rods and the support rods are arranged in an inclined mode.
By adopting the technical scheme, the reinforcing rods are welded between the opposite surfaces of the two support rods, so that the firmness of the connecting structure of the support rods is improved conveniently.
Preferably, the supporting mechanism includes pillar and butt pole, the one end fixed connection of pillar is in the side department that the installation pole was kept away from to the membrane material, and the one end setting that the membrane material was kept away from to the pillar is in the ground, the butt joint pole is provided with two, two the one end of butt joint pole is welded respectively in the lateral wall both sides department that the pillar is close to the membrane material, and the butt joint pole keeps away from the one end setting of pillar in the ground, pillar and two butt joint pole combinations set up the triangular pyramid structure that is the slope.
Through adopting above-mentioned technical scheme, support the pillar through two butt pole cooperations butt to constitute the bearing structure of the triangular pyramid of slope with the pillar cooperation, simple structure is convenient for realize the lightweight, adopts triangular stability, is convenient for improve pillar bearing structure's steadiness, and then improves the stretch-draw auxiliary effect to membrane material and cable wire, is favorable to improving the fastness of membrane material overall installation structure.
Preferably, one end of each steel cable rope far away from the installation rod is connected with one end of the support close to the membrane material in a one-to-one correspondence mode.
Through adopting above-mentioned technical scheme, through installation pole and stand cooperation pulling wire rope, be convenient for supplementary stretch-draw installation membrane material structure.
In summary, the present application includes at least one of the following beneficial technical effects:
1. through being equipped with the membrane material, the installation pole, supporting mechanism and wire rope cooperate, through installation pole and membrane material cooperation, be convenient for support jack-up membrane material, and then through installation pole and stand cooperation pulling wire rope, be convenient for assist stretch-draw installation membrane material structure, and then support the pillar through two butt pole cooperations butt cones, and constitute the bearing structure of the triangular pyramid of slope with the pillar cooperation, moreover, the steam generator is simple in structure, be convenient for realize the lightweight, adopt triangle-shaped's stability, be convenient for improve pillar bearing structure's steadiness, and then improve the stretch-draw auxiliary effect to membrane material and cable wire, be favorable to improving membrane material integral erection structure's fastness.
2. Cooperate through being equipped with membrane material, installation pole and spacing subassembly, cooperate through two spinal branch vaulting poles, again through the anchor strut welding between the opposite face of two spinal branch vaulting poles, be convenient for improve the connection structure fastness of bracing piece, and then be convenient for stabilize and support the installation pole, strengthen the structural stability of installation pole, make it be difficult for receiving the environmental factor influence and empty, be favorable to ensureing the job stabilization nature of membrane material structure.
Drawings
Fig. 1 is a schematic front view of a film according to an embodiment of the present invention.
Description of the reference numerals: 1. film material; 2. mounting a rod; 3. a limiting component; 31. a support bar; 32. a reinforcing rod; 4. a support mechanism; 41. a pillar; 42. a butting rod; 5. a steel cable.
Detailed Description
The present application is described in further detail below with reference to fig. 1.
The embodiment of the application discloses membrane structure cable wire stretch-draw auxiliary device. Referring to fig. 1, a film structure steel cable stretching auxiliary device comprises a film material 1, wherein an installation rod 2 penetrates through the middle position of the upper surface of the film material 1, one end of the installation rod 2 is fixedly connected with the top position of the film material 1 so as to support and jack up the film material 1, one end of the installation rod 2, which is far away from the film material 1, is arranged in a foundation, a limit component 3 is arranged on the side wall of one side of the installation rod 2 so as to stably support the installation rod 2, so that the structural stability of the installation rod 2 is enhanced, the installation rod is not easy to topple due to the influence of environmental factors, the operation stability of the structure of the film material 1 is favorably ensured, a plurality of supporting mechanisms 4 are arranged at equal distances around the side edge of the film material 1, which is far away from the installation rod 2, the plurality of supporting mechanisms 4 are annularly distributed around the vertical center line of the film material 1, so as to improve the stretching auxiliary effect on the film material 1 and the steel cable, and improve the firmness of the whole installation structure of the film material 1, the installation pole 2 is close to the one end department fixedly connected with many wire ropes 5 of membrane material 1, and many wire ropes 5 are the annular distribution around the perpendicular center line of membrane material 1, are convenient for supplementary stretch-draw installation membrane material 1 structure.
Referring to fig. 1, spacing subassembly 3 includes bracing piece 31 and anchor strut 32, and bracing piece 31 is provided with two, and the one end welding of two bracing pieces 31 is in one side lateral wall department of installation pole 2, and the one end setting that the installation pole 2 was kept away from to bracing piece 31 is the form of opening, and the one end setting that the installation pole 2 was kept away from to two bracing pieces 31 is in the ground, is convenient for stabilize and supports installation pole 2, strengthens the structural stability of installation pole 2, makes it be difficult for receiving environmental factor to influence and topple over.
Referring to fig. 1, the reinforcing rods 32 are provided with a plurality of reinforcing rods 32, the plurality of reinforcing rods 32 are welded between the opposite side walls of the two support rods 31 at equal intervals in the transverse direction, and the installation rods 2 and the support rods 31 are both arranged to be inclined, so that the firmness of the connection structure of the support rods 31 is improved.
Referring to fig. 1, supporting mechanism 4 includes pillar 41 and butt rod 42, the one end fixed connection of pillar 41 is in the side department that installation pole 2 was kept away from to membrane material 1, and the one end setting that membrane material 1 was kept away from to pillar 41, butt rod 42 is provided with two, the one end of two butt rods 42 is welded respectively in the lateral wall both sides department that pillar 41 is close to membrane material 1, and the one end that pillar 41 was kept away from to butt rod 42 sets up in the ground, pillar 41 and two butt rod 42 combinations set up the triangular pyramid structure that is the slope, moreover, the steam generator is simple in structure, be convenient for realize the lightweight, adopt triangular stability, be convenient for improve pillar 41 bearing structure's steadiness, and then improve the stretch-draw auxiliary effect to membrane material 1 and cable wire, be favorable to improving the fastness of membrane material 1 integral erection structure.
Referring to fig. 1, one end of each steel cable rope 5 far away from the installation rod 2 is connected with one end of the support 41 close to the membrane material 1 in a one-to-one correspondence mode, and the steel cable ropes 5 are pulled through the installation rod 2 and the stand column in a matching mode, so that the membrane material 1 structure can be conveniently and auxiliarily tensioned and installed.
The implementation principle of a membrane structure cable wire stretch-draw auxiliary device of the embodiment of the application is as follows: the installation rod 2 is matched with the membrane material 1, so that the membrane material 1 can be supported and jacked conveniently, the steel cable rope 5 is pulled through the matching of the installation rod 2 and the stand column, the structure of the membrane material 1 can be conveniently and auxiliarily tensioned and installed, the two butting rods 42 are matched with the butting supporting pillars 41 and matched with the supporting pillars 41 to form an inclined triangular pyramid-shaped supporting structure, the structure is simple, the light weight is convenient to realize, the stability of a triangle is adopted, the stability of the supporting structure of the supporting pillars 41 is convenient to improve, the tensioning auxiliary effect on the membrane material 1 and the steel cable is further improved, and the firmness of the integral installation structure of the membrane material 1 is favorably improved;
through two bracing pieces 31 cooperation spacing installation pole 2 again, through the anchor strut 32 welding again between two bracing pieces 31's the opposite face, be convenient for improve bracing piece 31's connection structure fastness, and then be convenient for firm support installation pole 2, strengthen the structural stability of installation pole 2, make it be difficult for receiving the environmental factor influence and empty, be favorable to ensureing the job stabilization nature of membrane material 1 structure.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (5)

1. The utility model provides a membrane structure cable wire stretch-draw auxiliary device which characterized in that: including membrane material (1), installation pole (2) are worn to be equipped with by the upper surface middle part position department of membrane material (1), the one end of installation pole (2) and the top position department fixed connection of membrane material (1), and the one end setting of keeping away from membrane material (1) in the ground of installation pole (2), one side lateral wall department of installation pole (2) is provided with spacing subassembly (3), the side that installation pole (2) were kept away from in membrane material (1) locates impartial distance all around and is provided with a plurality of supporting mechanism (4), and is a plurality of supporting mechanism (4) are the annular distribution around the perpendicular center line of membrane material (1), one end department fixed connection that installation pole (2) are close to membrane material (1) has many steel cable rope (5), many steel cable rope (5) are the annular distribution around the perpendicular center line of membrane material (1).
2. A membrane structure cable tensioning assistance device according to claim 1, wherein: spacing subassembly (3) are including bracing piece (31) and anchor strut (32), bracing piece (31) are provided with two, two the one end welding of bracing piece (31) is in the lateral wall department on one side of installation pole (2), and bracing piece (31) keep away from the one end setting of installation pole (2) and be the form of opening, two the one end setting of keeping away from installation pole (2) of bracing piece (31) is in the ground.
3. A membrane structure cable tensioning assistance device according to claim 2, wherein: the reinforcing rods (32) are arranged in a plurality of positions, the reinforcing rods (32) are welded between the opposite side walls of the two supporting rods (31) at equal intervals in the transverse direction, and the mounting rods (2) and the supporting rods (31) are all arranged in an inclined mode.
4. A membrane structure cable tensioning assistance device according to claim 1, wherein: supporting mechanism (4) are including pillar (41) and butt pole (42), the one end fixed connection of pillar (41) is in the side department of keeping away from installation pole (2) in membrane material (1), and the one end setting of keeping away from membrane material (1) in pillar (41) is in the ground, butt joint pole (42) are provided with two, two butt joint pole (42) one end welds respectively in the lateral wall both sides department that pillar (41) are close to membrane material (1), and butt joint pole (42) keep away from the one end setting of pillar (41) in the ground, pillar (41) and two butt joint pole (42) combination set up the three-edged cone structure that is the slope.
5. A membrane structure cable tensioning assistance device according to claim 4, wherein: and one ends of the steel cable ropes (5) far away from the mounting rod (2) are respectively connected with one end of the support column (41) close to the membrane material (1) in a one-to-one correspondence manner.
CN202123302426.7U 2021-12-22 2021-12-22 Membrane structure cable wire stretch-draw auxiliary device Active CN216665060U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123302426.7U CN216665060U (en) 2021-12-22 2021-12-22 Membrane structure cable wire stretch-draw auxiliary device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123302426.7U CN216665060U (en) 2021-12-22 2021-12-22 Membrane structure cable wire stretch-draw auxiliary device

Publications (1)

Publication Number Publication Date
CN216665060U true CN216665060U (en) 2022-06-03

Family

ID=81798637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123302426.7U Active CN216665060U (en) 2021-12-22 2021-12-22 Membrane structure cable wire stretch-draw auxiliary device

Country Status (1)

Country Link
CN (1) CN216665060U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115142551A (en) * 2022-08-25 2022-10-04 中国二十二冶集团有限公司 Large-span venue building cable membrane structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115142551A (en) * 2022-08-25 2022-10-04 中国二十二冶集团有限公司 Large-span venue building cable membrane structure
CN115142551B (en) * 2022-08-25 2024-01-23 中国二十二冶集团有限公司 Large-span stadium building cable membrane structure

Similar Documents

Publication Publication Date Title
CN216665060U (en) Membrane structure cable wire stretch-draw auxiliary device
CN113241998B (en) Prestressed flexible photovoltaic fixing support
CN206617282U (en) Half truss formula pylon
CN112709155A (en) Fish belly type suspension cable combined support and construction method thereof
CN216713950U (en) Steel construction assembled supports bed-jig
CN111764306A (en) Cantilever pouring arching control method for arranging buckling cable steering device on large-span main arch stand column
CN113431052B (en) Foundation pit prestress steel supporting system
CN210374121U (en) Self-balancing flexible photovoltaic panel support
CN212000638U (en) Overhead cover beam type steel supporting structure
CN210186407U (en) Support frame structure for ski platforms
CN218204333U (en) Stable in structure's stand stake is used in subway construction
CN212835930U (en) Outrigger supporting structure of small-size formula steel construction ceiling of choosing
CN219587247U (en) Temporary device for tensioning ground of beam string structure
CN214272978U (en) Large-span pipe truss segmentation construction auxiliary structure
CN212388802U (en) Keel component and hoisting structure of double-fish belly guy cable curtain wall
CN220830404U (en) Flexible photovoltaic support and photovoltaic system
CN220359070U (en) High stability photovoltaic support
CN215109284U (en) Fan pylon structure
CN220789459U (en) Bracket system for steel structure arch frame installation and sectional construction
CN220924864U (en) Cage assembly platform supporting device
CN214377571U (en) Single-column three-side billboard
CN215367169U (en) A leading truck platform for construction of offshore wind power steel-pipe pile
CN220100394U (en) High stability lattice column
CN217811598U (en) Wood structure beam column tenon fourth of twelve earthly branches node reinforcing apparatus
CN210561669U (en) Cable-stayed through-arch cooperation system bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant