CN216590622U - A control early warning device for foundation ditch construction - Google Patents

A control early warning device for foundation ditch construction Download PDF

Info

Publication number
CN216590622U
CN216590622U CN202122580416.3U CN202122580416U CN216590622U CN 216590622 U CN216590622 U CN 216590622U CN 202122580416 U CN202122580416 U CN 202122580416U CN 216590622 U CN216590622 U CN 216590622U
Authority
CN
China
Prior art keywords
base
early warning
monitoring
warning device
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122580416.3U
Other languages
Chinese (zh)
Inventor
林艳生
李首才
马立群
张超
刘小磊
牟森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mcc Beijing Traffic Technology Development Co ltd
Original Assignee
Mcc Beijing Traffic Technology Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mcc Beijing Traffic Technology Development Co ltd filed Critical Mcc Beijing Traffic Technology Development Co ltd
Priority to CN202122580416.3U priority Critical patent/CN216590622U/en
Application granted granted Critical
Publication of CN216590622U publication Critical patent/CN216590622U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Alarm Devices (AREA)

Abstract

The utility model discloses a monitoring and early warning device for foundation pit construction, in particular to the field of building equipment, which comprises an adjusting component and a base, wherein the adjusting component comprises a limiting nut, the inner part of the limiting nut is connected with a threaded rod through a bolt, the top end of the threaded rod is fixedly connected with an adjusting disc, the bottom end of the threaded rod is fixedly connected with a universal ball, the outer surface of the universal ball is movably connected with a fixed foot, the outer surface of the base is provided with a chute, the upper surface of the base is provided with a limiting groove above the chute, the inner part of the chute is connected with a limiting plate in a sliding way, the relative distance between each fixed foot and the base is adjusted through respectively adjusting four threaded rods on the base, so that the integral level of the base is ensured, a camera on the base can work normally, and the monitoring and early warning of the monitoring and early warning equipment can comprehensively monitor the foundation pit condition, and timely early warning is carried out when problems occur.

Description

A control early warning device for foundation ditch construction
Technical Field
The utility model relates to the technical field of building equipment, in particular to a monitoring and early warning device for foundation pit construction.
Background
The foundation pit is a soil pit excavated at the design position of the foundation according to the elevation of the foundation and the plane size of the foundation. Before excavation, an excavation scheme is determined according to geological and hydrological data and by combining the conditions of buildings nearby the site, waterproof drainage work is well done, and a monitoring and early warning device is needed to be used for monitoring and early warning the foundation pit under construction in the process of foundation pit construction.
However, in the using process of the existing monitoring and early warning device, because the ground around the foundation pit is uneven in the process of foundation pit construction, the monitoring and early warning device is very inconvenient to install, and the monitoring and early warning device cannot work better due to the fact that no proper installation position exists. Therefore, the monitoring and early warning device for foundation pit construction is improved, and the monitoring and early warning device for foundation pit construction is provided to solve the problems.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problems, the utility model provides the following technical scheme:
the utility model relates to a monitoring and early warning device for foundation pit construction, which comprises an adjusting component and a base, wherein the adjusting component comprises a limiting nut, the inner bolt of the limiting nut is connected with a threaded rod, the top end of the threaded rod is fixedly connected with an adjusting disc, the bottom end of the threaded rod is fixedly connected with a universal ball, the outer surface of the universal ball is movably connected with a fixing foot, the outer surface of the base is provided with a sliding groove, the upper surface of the base is positioned above the sliding groove and provided with a limiting groove, the inner part of the sliding groove is slidably connected with a limiting plate, the inner part of the limiting groove is slidably connected with a limiting pin, and the bottom end of the limiting pin is fixedly connected with the upper surface of the limiting plate.
As a preferred technical scheme of the present invention, a connecting assembly is disposed on one side of the adjusting assembly, the connecting assembly includes a supporting plate, an adjusting seat is fixedly connected to a middle position of a lower surface of the supporting plate, a mounting plate is fixedly connected to a driving end of the adjusting seat and above the supporting plate, a camera is fixedly connected to an upper surface of the mounting plate, and a base is fixedly connected to a bottom end of the supporting plate.
As a preferred technical scheme of the utility model, the upper surface of the base is fixedly connected with a limit nut, and the upper surface of the base is provided with a through hole matched with the limit nut.
As a preferable technical solution of the present invention, the upper surface of the supporting plate is provided with a hole, and the top end of the adjusting seat penetrates through the hole on the upper surface of the supporting plate.
According to a preferable technical scheme of the utility model, the limiting plates are arranged in multiple groups, and the multiple groups of limiting plates are arranged in the chute in a mirror symmetry mode by using a vertical center line of the chute.
As a preferred technical scheme of the utility model, the limiting nuts are arranged in multiple groups, and the multiple groups of limiting nuts are respectively distributed at four corners of the upper surface of the base.
As a preferable technical scheme of the utility model, the lower surface of the fixing foot is provided with anti-skid grooves, and the anti-skid grooves on the lower surface of the fixing foot are uniformly distributed on the lower surface of the fixing foot.
The utility model has the beneficial effects that:
1. this a control early warning device for foundation ditch construction, rotate the threaded rod in stop nut's inside through the adjusting disk, adjust the relative distance between fixed foot and the base, with this level of adjusting the base, meet the different positions of placing, adjust the relative distance between each fixed foot and the base through adjusting four threaded rods on the base respectively, with this holistic level of guaranteeing the base, work that the camera on the assurance base can be normal, guarantee the control early warning that control early warning equipment can be comprehensive control foundation ditch condition, and timely early warning that carries on when the problem appears.
2. This a control early warning device for foundation ditch construction, after the control early warning equipment installation finishes take the limiting plate out suitable distance from the inside of spout, then die the spacer pin lock on the limiting plate, make and keep relatively fixed between limiting plate and the spout, then use the gag lever post to pass the spacing hole on the limiting plate, fix on the installation ground to keep the stability of control early warning equipment at the in-process of work.
Drawings
The accompanying drawings, which are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate embodiments of the utility model and together with the description serve to explain the principles of the utility model and not to limit the utility model.
In the drawings:
FIG. 1 is an external view of a monitoring and early warning device for foundation pit construction according to the present invention;
FIG. 2 is a schematic view of a monitoring and early warning device adjusting assembly for foundation pit construction according to the present invention;
FIG. 3 is a front view of a monitoring and pre-warning device for foundation pit construction according to the present invention;
fig. 4 is an enlarged view of a portion a of fig. 1 of a monitoring and early warning apparatus for foundation pit construction according to the present invention.
In the figure: 1. a connecting assembly; 11. a support plate; 12. mounting a disc; 13. a camera; 14. a base; 15. an adjusting seat; 2. an adjustment assembly; 201. a limiting plate; 202. a chute; 203. a limiting groove; 204. a spacing pin; 205. an adjusting disk; 206. a threaded rod; 207. a limit nut; 208. a universal ball; 209. and fixing the feet.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it will be understood that they are described herein for the purpose of illustration and explanation and not limitation.
Example (b): as shown in fig. 2 and 4, the monitoring and early warning device for foundation pit construction of the present invention comprises an adjusting component 2 and a base 14, wherein the adjusting component 2 comprises a plurality of sets of limiting nuts 207, the plurality of sets of limiting nuts 207 are respectively distributed at four corners of the upper surface of the base 14, a threaded rod 206 is bolted inside the limiting nut 207, an adjusting disc 205 is fixedly connected to the top end of the threaded rod 206, a universal ball 208 is fixedly connected to the bottom end of the threaded rod 206, a fixing foot 209 is movably connected to the outer surface of the universal ball 208, an anti-slip groove is formed on the lower surface of the fixing foot 209, the anti-slip groove on the lower surface of the fixing foot 209 is uniformly distributed on the lower surface of the fixing foot 209, a sliding groove 202 is formed on the outer surface of the base 14, a limiting groove 203 is formed on the upper surface of the base 14 and above the sliding groove 202, a limiting plate 201 is slidably connected inside the sliding groove 202, and the limiting plates 201 are arranged in a plurality of sets, and the limiting plates 201 that the multiunit set up are mirror symmetry with the vertical central line of spout 202 and set up in the inside of spout 202, and the inside sliding connection of spacing groove 203 has spacing pin 204, and the bottom of spacing pin 204 is connected with the upper surface fixed of limiting plate 201.
The threaded rod 206 is rotated in the limiting nut 207 through the adjusting disc 205, the relative distance between the fixed foot 209 and the base 14 is adjusted, the level of the base 14 is adjusted, different placing positions are met, the relative distance between each fixed foot 209 and the base 14 is adjusted through adjusting the four threaded rods 206 on the base 14 respectively, the overall level of the base 14 is ensured, the camera 13 on the base 14 can work normally, the monitoring foundation pit condition that monitoring early warning equipment can be comprehensive is ensured, and early warning is timely performed when problems occur.
As shown in fig. 1 and 3, one side of adjusting part 2 is provided with coupling assembling 1, coupling assembling 1 includes backup pad 11, the upper surface of backup pad 11 is seted up porosely, adjust the hole that the top of seat 15 runs through in the backup pad 11 upper surface, lower surface intermediate position department fixedly connected with of backup pad 11 adjusts seat 15, adjust the drive end of seat 15 and be located the top fixedly connected with mounting disc 12 of backup pad 11, the last fixed surface of mounting disc 12 is connected with camera 13, the bottom fixedly connected with base 14 of backup pad 11, the last fixed surface of base 14 is connected with stop nut 207, the through-hole with stop nut 207 looks adaptation is seted up to the upper surface of base 14.
After the monitoring and early warning device is installed, the limiting plate 201 is pulled out from the inside of the sliding groove 202 for a proper distance, then the limiting pin 204 on the limiting plate 201 is locked, so that the limiting plate 201 and the sliding groove 202 are kept relatively fixed, and then the limiting rod penetrates through the limiting hole in the limiting plate 201 and is fixed on the installation ground so as to keep the monitoring and early warning device stable in the working process.
The working principle is as follows: when the monitoring early warning device is used, when the monitoring early warning device needs to be installed around a foundation pit under construction, the installation position is selected firstly, then the monitoring early warning device is placed at the installation position, after the monitoring early warning device is placed, the threaded rod 206 is rotated inside the limit nut 207 through the adjusting disc 205, the relative distance between the fixed foot 209 and the base 14 is adjusted, the level of the base 14 is adjusted accordingly, different placement positions are met, the relative distance between each fixed foot 209 and the base 14 is adjusted through adjusting the four threaded rods 206 on the base 14 respectively, the overall level of the base 14 is ensured, the camera 13 on the base 14 can work normally, the monitoring early warning of the monitoring early warning device can be ensured to monitor the foundation pit condition comprehensively, and early warning is timely performed when problems occur.
Meanwhile, after the monitoring and early warning device is installed, the limiting plate 201 is drawn out from the inside of the sliding groove 202 by a proper distance, then the limiting pin 204 on the limiting plate 201 is locked, so that the limiting plate 201 and the sliding groove 202 are relatively fixed, and then the limiting rod penetrates through the limiting hole in the limiting plate 201 and is fixed on the installation ground so as to keep the monitoring and early warning device stable in the working process.
Finally, it should be noted that: in the description of the present invention, it should be noted that the terms "vertical", "upper", "lower", "horizontal", and the like indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the utility model. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. A monitoring and early warning device for foundation pit construction comprises an adjusting component (2) and a base (14), characterized in that the adjusting component (2) comprises a limit nut (207), a threaded rod (206) is connected with the internal bolt of the limit nut (207), the top end of the threaded rod (206) is fixedly connected with an adjusting disc (205), the bottom end of the threaded rod (206) is fixedly connected with a universal ball (208), the outer surface of the universal ball (208) is movably connected with a fixed foot (209), the outer surface of the base (14) is provided with a sliding groove (202), a limit groove (203) is arranged on the upper surface of the base (14) and above the sliding groove (202), a limit plate (201) is connected inside the sliding groove (202) in a sliding manner, a limit pin (204) is connected inside the limit groove (203) in a sliding manner, the bottom end of the limiting pin (204) is fixedly connected with the upper surface of the limiting plate (201).
2. The monitoring and early warning device for foundation pit construction according to claim 1, wherein one side of the adjusting component (2) is provided with a connecting component (1), the connecting component (1) comprises a supporting plate (11), an adjusting seat (15) is fixedly connected to the middle position of the lower surface of the supporting plate (11), a mounting plate (12) is fixedly connected to the driving end of the adjusting seat (15) and located above the supporting plate (11), a camera (13) is fixedly connected to the upper surface of the mounting plate (12), and a base (14) is fixedly connected to the bottom end of the supporting plate (11).
3. The monitoring and early warning device for foundation pit construction according to claim 2, wherein a limit nut (207) is fixedly connected to the upper surface of the base (14), and a through hole matched with the limit nut (207) is formed in the upper surface of the base (14).
4. The monitoring and early warning device for foundation pit construction according to claim 2, wherein the upper surface of the supporting plate (11) is provided with a hole, and the top end of the adjusting seat (15) penetrates through the hole on the upper surface of the supporting plate (11).
5. The monitoring and early warning device for foundation pit construction according to claim 1, wherein the limiting plates (201) are arranged in multiple groups, and the limiting plates (201) arranged in multiple groups are arranged inside the sliding chute (202) in a mirror symmetry mode with the vertical center line of the sliding chute (202).
6. The monitoring and early warning device for foundation pit construction according to claim 3, wherein the limiting nuts (207) are arranged in multiple groups, and the limiting nuts (207) arranged in multiple groups are respectively distributed at four corners of the upper surface of the base (14).
7. The monitoring and early warning device for foundation pit construction according to claim 1, wherein the lower surface of the fixing foot (209) is provided with anti-skid lines, and the anti-skid lines on the lower surface of the fixing foot (209) are uniformly distributed on the lower surface of the fixing foot (209).
CN202122580416.3U 2021-10-26 2021-10-26 A control early warning device for foundation ditch construction Active CN216590622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122580416.3U CN216590622U (en) 2021-10-26 2021-10-26 A control early warning device for foundation ditch construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122580416.3U CN216590622U (en) 2021-10-26 2021-10-26 A control early warning device for foundation ditch construction

Publications (1)

Publication Number Publication Date
CN216590622U true CN216590622U (en) 2022-05-24

Family

ID=81641128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122580416.3U Active CN216590622U (en) 2021-10-26 2021-10-26 A control early warning device for foundation ditch construction

Country Status (1)

Country Link
CN (1) CN216590622U (en)

Similar Documents

Publication Publication Date Title
CN216590622U (en) A control early warning device for foundation ditch construction
CN210395435U (en) Collapse-proof supporting device for open excavation method construction of urban underground comprehensive pipe gallery
CN215929105U (en) Mapping and positioning device for engineering mapping
CN212053822U (en) Assembled adjustable jacking protects a device
CN214066142U (en) Measuring instrument support for architectural design
CN221481505U (en) Stable structure of installation engineering support
CN220649577U (en) Deep foundation pit monitoring device convenient to fix
CN216109924U (en) Template support frame of usefulness is pour in civil engineering
CN213475243U (en) Crane safety limiting equipment in civil engineering construction
CN221256316U (en) Iron tower supporting component
CN220927605U (en) Foundation pit construction safety prompting device
CN211432960U (en) A move quick-witted device for medical large aperture CT
CN216586044U (en) Highway engineering is template strutting arrangement for concrete placement
CN219082720U (en) Site survey device for building design
CN218582825U (en) Water conservancy dam safety monitoring equipment
CN221171396U (en) Water level monitoring device based on hydraulic engineering survey and drawing
CN220930690U (en) Auxiliary device for highway design survey and drawing
CN214696890U (en) Be used for adjustable bracing device of basement unilateral wall form
CN214889394U (en) Municipal administration plumbing construction pipeline fixing device
CN221222024U (en) Flood disaster early warning device
CN215952560U (en) Civil engineering is with measuring equipment of automatic calibration basic point
CN220132962U (en) Municipal road inspection shaft prevents subsiding construction equipment
CN214885482U (en) Template supporting beam device for building engineering
CN218772282U (en) Wireless network bridge device of surface mine monitoring device
CN219673793U (en) Monitoring equipment mounting frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant