CN216551946U - A fixed auxiliary device for building pile among engineering building - Google Patents

A fixed auxiliary device for building pile among engineering building Download PDF

Info

Publication number
CN216551946U
CN216551946U CN202220066393.6U CN202220066393U CN216551946U CN 216551946 U CN216551946 U CN 216551946U CN 202220066393 U CN202220066393 U CN 202220066393U CN 216551946 U CN216551946 U CN 216551946U
Authority
CN
China
Prior art keywords
equipment box
wall
bevel gear
fixing
groups
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220066393.6U
Other languages
Chinese (zh)
Inventor
孙良振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202220066393.6U priority Critical patent/CN216551946U/en
Application granted granted Critical
Publication of CN216551946U publication Critical patent/CN216551946U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a fixing auxiliary device for a building pile in an engineering building, which relates to the technical field of engineering building auxiliary equipment and comprises a first equipment box and a first supporting plate, wherein a second equipment box is arranged on one side of the first equipment box, a motor is arranged in the second equipment box, a rotating mechanism is arranged in the first equipment box, a fixing mechanism for clamping and fixing a building pile body is arranged between the first equipment box and the first supporting plate, and the stability of the building pile during installation is ensured through the rotating mechanism and the fixing mechanism.

Description

A fixed auxiliary device for building pile among engineering building
Technical Field
The utility model relates to the technical field of engineering construction auxiliary equipment, in particular to a fixing auxiliary device for a building pile in an engineering construction.
Background
The construction engineering is various technical works such as planning, investigation, design and construction, completion and the like for newly building, reconstructing or expanding a house building and an auxiliary structure facility, and installation engineering of completed engineering entities and matched lines, pipelines and equipment, wherein in the engineering construction, the building pile is usually driven into a foundation by using the friction force between a stratum and the building pile, and then the construction pile is matched with a pile cap to form a pile foundation, so that the subsequent construction is facilitated; prior pile foundation uses, at first need through with the vertical ground that inserts of building pile, then place pile cap again, but insert the building pile ground after, it is usually only fixed with the help of the frictional force of ground and building pile, its fixed effect is relatively poor, the problem of disconnected stake can appear in the building pile in the work progress, and the normal operating condition of foundation pile can be changed in the existence of pile body defect, thereby produce potential danger to the basis, certain potential safety hazard has.
SUMMERY OF THE UTILITY MODEL
In view of the problems in the background art, the present invention aims to provide a fixing auxiliary device for a building pile in an engineering building, which ensures the stability of the building pile during installation through a rotating mechanism and a fixing mechanism, thereby solving the problems in the background art.
In order to achieve the purpose, the utility model adopts the following technical scheme:
the utility model provides a fixed auxiliary device for building pile in engineering building, includes first equipment box and first backup pad, and one side of first equipment box is provided with the second equipment box, and the inside of second equipment box is provided with the motor, and the inside of first equipment box is provided with slewing mechanism, is provided with the fixed establishment of the fixed building pile body of centre gripping between first equipment box and the first backup pad.
Furthermore, the bottom of first equipment box and first backup pad is all fixed mounting has flexible post, and the bottom fixed mounting of flexible post has the second backup pad.
Further, the cavity has been seted up to the inside of first equipment box, and slewing mechanism sets up in the inside of cavity, and slewing mechanism includes the pivot, the one end of pivot run through the second equipment box and with the output fixed connection of motor, fixed mounting has first bevel gear and second bevel gear on the outer wall of pivot.
Furthermore, a support frame is arranged between the first bevel gear and the second bevel gear, the inner wall of the support frame is rotatably connected with the outer wall of the rotating shaft, the bottom end of the support frame is fixedly connected with the inner wall of the first equipment box, and the outer walls of the first bevel gear and the second bevel gear are respectively connected with a third bevel gear in a meshed mode.
Further, the fixing mechanism comprises two-way threaded screws, limiting rods, threaded holes and limiting holes, the two-way threaded screws and the limiting rods are provided with two groups, the threaded holes and the limiting holes are provided with four groups, one ends of the two groups of two-way threaded screws penetrate through the inner wall of the first equipment box and are fixedly connected with the inner walls of the two groups of third bevel gears respectively, and the other ends of the two groups of two-way threaded screws are fixedly connected with the outer wall of the first supporting plate.
Furthermore, two groups of fixing plates are arranged on the outer walls of the two groups of bidirectional threaded screw rods, two groups of limiting rods are fixedly installed on the outer wall of one side, opposite to the first supporting plate, of the first equipment box, and two groups of threaded holes and two groups of limiting holes which are located on the same side are respectively arranged on two sides of one fixing plate.
Furthermore, the threaded hole is in threaded connection with the outer wall of the bidirectional threaded screw rod, the limiting hole is in sliding connection with the outer wall of the limiting rod, and one side, opposite to the two groups of fixing plates, of each fixing plate is connected with a fixing wheel in a rotating mode through a bolt.
The beneficial effects of the utility model are as follows:
1. through slewing mechanism, the motor can drive the pivot and rotate when the pivoted, and the pivot is in the pivoted, and its upper face fixed mounting's first bevel gear and second bevel gear all can rotate along with the pivot together, and when first bevel gear and second bevel gear rotated, the drive third bevel gear that can be simultaneous rotated, and the support frame mainly plays the purpose of supporting the pivot simultaneously, and slewing mechanism mainly plays linkage fixed establishment's purpose.
2. Through fixed establishment, when third bevel gear rotated, can drive the two-way screw lead screw and rotate, fixed plate above the two-way screw lead screw can be because the spacing of gag lever post, and mutual drawing close, when two fixed plates draw close each other, can grasp building pile, so just the skew can not take place for the position when building the installation of pile.
Drawings
FIG. 1 is a schematic perspective view of the present invention;
FIG. 2 is a top view of the present invention shown in FIG. 1;
FIG. 3 is an enlarged view of the structure of area A in FIG. 2 according to the present invention;
FIG. 4 is a schematic perspective view of a fixing plate according to the present invention;
fig. 5 is a front view of the present invention in fig. 1.
In the figure: 1-a first equipment cabinet; 2, a motor; 3-a cavity; 4-a rotation mechanism; 5-a second equipment box; 6-a first support plate; 7-a fixing mechanism; 8-telescopic column; 9-a second support plate; 401-a first bevel gear; 402-a rotating shaft; 403-a support frame; 404-a second bevel gear; 405-a third bevel gear; 701-a limiting rod; 702-a two-way threaded lead screw; 703-a fixing plate; 704-a fixed wheel; 706-a threaded hole; 707-limiting hole.
Detailed Description
For the convenience of understanding, the technical solution of the present invention will be clearly and completely described by the embodiments with reference to the accompanying drawings.
Please refer to fig. 1, fig. 2 and fig. 5, a fixing auxiliary device for a building pile in an engineering building includes a first equipment box 1 and a first supporting plate 6, a second equipment box 5 is disposed on one side of the first equipment box 1, a motor 2 is disposed inside the second equipment box 5, a rotating mechanism 4 is disposed inside the first equipment box 1, and a fixing mechanism 7 for clamping and fixing a building pile body is disposed between the first equipment box 1 and the first supporting plate 6.
Referring to fig. 1, 2 and 5, the bottom ends of the first equipment box 1 and the first support plate 6 are both fixedly provided with a telescopic column 8, and the bottom end of the telescopic column 8 is fixedly provided with a second support plate 9.
Referring to fig. 2, a cavity 3 is formed in the first equipment box 1, the rotating mechanism 4 is disposed in the cavity 3, the rotating mechanism 4 includes a rotating shaft 402, one end of the rotating shaft 402 penetrates through the second equipment box 5 and is fixedly connected to the output end of the motor 2, and a first bevel gear 401 and a second bevel gear 404 are fixedly mounted on the outer wall of the rotating shaft 402. Specifically, the second bevel gear 404 is mounted on the outer wall of the other end of the rotating shaft 402.
Referring to fig. 2, a support frame 403 is disposed between the first bevel gear 401 and the second bevel gear 404, an inner wall of the support frame 403 is rotatably connected to an outer wall of the rotating shaft 402, a bottom end of the support frame 403 is fixedly connected to an inner wall of the first equipment box 1, and outer walls of the first bevel gear 401 and the second bevel gear 404 are both connected to a third bevel gear 405 in a meshing manner. Specifically, the motor 2 can drive the rotating shaft 402 to rotate when rotating, when the rotating shaft 402 rotates, the first bevel gear 401 and the second bevel gear 404 which are fixedly mounted on the rotating shaft 402 can rotate along with the rotating shaft 402, when the first bevel gear 401 and the second bevel gear 404 rotate, the third bevel gear 405 can be driven to rotate simultaneously, and meanwhile, the supporting frame 403 mainly plays a role in supporting the rotating shaft 402.
Referring to fig. 1, 2, 3, and 4, the fixing mechanism 7 includes two sets of two-way threaded screws 702, two sets of limiting rods 701, four sets of threaded holes 706 and four sets of limiting holes 707, two sets of two-way threaded screws 702 and two sets of limiting rods 701 are provided, one end of each of the two sets of two-way threaded screws 702 penetrates through the inner wall of the first equipment box 1 and is fixedly connected to the inner walls of the two sets of third bevel gears 405, and the other end of each of the two sets of two-way threaded screws 702 is fixedly connected to the outer wall of the first support plate 6.
Referring to fig. 1, 2, 3, and 4, two sets of fixing plates 703 are disposed on outer walls of two sets of two-way threaded screws 702, two sets of limiting rods 701 are fixedly mounted on an outer wall of a side of the first equipment box 1 opposite to the first support plate 6, and two sets of threaded holes 706 and two sets of limiting holes 707 located on the same side are respectively disposed on two sides of one fixing plate 703. Specifically, two sets of fixing plates 703 are oppositely mounted on the outer wall of the two-way threaded screw 702.
Referring to fig. 1, 2, 3 and 4, the threaded hole 706 is in threaded connection with the outer wall of the two-way threaded screw rod 702, the limiting hole 707 is in sliding connection with the outer wall of the limiting rod 701, and the opposite sides of the two sets of fixing plates 703 are rotatably connected with the fixing wheels 704 through bolts. Specifically, when third bevel gear 405 rotates, can drive two-way screw lead screw 702 and rotate, fixed plate 703 above two-way screw lead screw 702 can be because gag lever post 701's is spacing, and mutual drawing close, when two fixed plates 703 draw close each other, can grasp building pile, so just the skew can not take place for the position when building the installation of building pile.
In summary, the following steps: motor 2 can drive pivot 402 in the pivoted and rotate, pivot 402 is in the pivoted, first bevel gear 401 and second bevel gear 404 of its upper fixed mounting all can rotate along with pivot 402 together, when first bevel gear 401 and second bevel gear 404 rotate, drive third bevel gear 405 that can be simultaneous rotates, support frame 403 mainly plays the purpose of supporting pivot 402 simultaneously, when third bevel gear 405 rotates, can drive two-way screw lead screw 702 and rotate, fixed plate 703 above two-way screw lead screw 702 can be because gag lever post 701's spacing, mutual drawing close, when two fixed plates 703 draw close each other, can grasp building pile, so the position just can not take place the skew when building the installation.
In this document, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.

Claims (7)

1. The utility model provides a fixed auxiliary device for building pile among engineering building, includes first equipment box (1) and first backup pad (6), one side of first equipment box (1) is provided with second equipment box (5), the inside of second equipment box (5) is provided with motor (2), its characterized in that: the inside of first equipment box (1) is provided with slewing mechanism (4), be provided with fixed establishment (7) of the fixed building pile body of centre gripping between first equipment box (1) and first backup pad (6).
2. A fixing aid for a construction pile in an engineering construction according to claim 1, characterized in that: the bottom of first equipment box (1) and first backup pad (6) is equal fixed mounting has flexible post (8), the bottom fixed mounting of flexible post (8) has second backup pad (9).
3. A fixing aid for a construction pile in an engineering construction according to claim 1, characterized in that: the cavity (3) has been seted up to the inside of first equipment case (1), slewing mechanism (4) set up in the inside of cavity (3), slewing mechanism (4) include pivot (402), the one end of pivot (402) run through second equipment case (5) and with the output fixed connection of motor (2), fixed mounting has first bevel gear (401) and second bevel gear (404) on the outer wall of pivot (402).
4. A fixing aid for a construction pile in an engineering construction according to claim 3, characterized in that: a supporting frame (403) is arranged between the first bevel gear (401) and the second bevel gear (404), the inner wall of the supporting frame (403) is rotatably connected with the outer wall of the rotating shaft (402), the bottom end of the supporting frame (403) is fixedly connected with the inner wall of the first equipment box (1), and the outer walls of the first bevel gear (401) and the second bevel gear (404) are respectively connected with a third bevel gear (405) in a meshed mode.
5. A fixing aid for a construction pile in an engineering construction according to claim 1, characterized in that: the fixing mechanism (7) comprises a two-way threaded screw rod (702), a limiting rod (701), threaded holes (706) and limiting holes (707), the two-way threaded screw rod (702) and the limiting rod (701) are both provided with two groups, the threaded holes (706) and the limiting holes (707) are both provided with four groups, one end of the two-way threaded screw rod (702) penetrates through the inner wall of the first equipment box (1) and is fixedly connected with the inner walls of the two groups of third bevel gears (405) respectively, and the other end of the two-way threaded screw rod (702) is fixedly connected with the outer wall of the first supporting plate (6).
6. A fixing auxiliary device for a construction pile in an engineering construction according to claim 5, characterized in that: two groups of fixing plates (703) are arranged on the outer wall of the two-way threaded screw rod (702), two groups of limiting rods (701) are fixedly installed on the outer wall of one side, opposite to the first supporting plate (6), of the first equipment box (1), and the two groups of threaded holes (706) and the two groups of limiting holes (707) which are located on the same side are respectively formed in two sides of one fixing plate (703).
7. A fixing aid for a construction pile in an engineering construction according to claim 6, characterized in that: the threaded hole (706) is in threaded connection with the outer wall of the two-way threaded screw rod (702), the limiting hole (707) is in sliding connection with the outer wall of the limiting rod (701), and one opposite sides of the two groups of fixing plates (703) are rotatably connected with fixing wheels (704) through bolts.
CN202220066393.6U 2022-01-12 2022-01-12 A fixed auxiliary device for building pile among engineering building Active CN216551946U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220066393.6U CN216551946U (en) 2022-01-12 2022-01-12 A fixed auxiliary device for building pile among engineering building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220066393.6U CN216551946U (en) 2022-01-12 2022-01-12 A fixed auxiliary device for building pile among engineering building

Publications (1)

Publication Number Publication Date
CN216551946U true CN216551946U (en) 2022-05-17

Family

ID=81562520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220066393.6U Active CN216551946U (en) 2022-01-12 2022-01-12 A fixed auxiliary device for building pile among engineering building

Country Status (1)

Country Link
CN (1) CN216551946U (en)

Similar Documents

Publication Publication Date Title
CN216551946U (en) A fixed auxiliary device for building pile among engineering building
CN220927874U (en) Support frame
CN218116477U (en) Foundation pit supporting device with high practicability
CN214883946U (en) Foundation pit displacement monitoring device
CN212689557U (en) Telescopic building template
CN214248879U (en) Site survey device that building engineering cost was used
CN212664760U (en) Steel bar bending device for building engineering
CN212175779U (en) Building pile body fixing device
CN114060696A (en) Environmental monitoring system for construction engineering
CN112563934A (en) Power transmission and transformation framework column
CN212484943U (en) Instrument cabinet convenient to adjust instrument and meter position
CN217044681U (en) Drilling device for producing display screen
CN216196870U (en) Be used for civil engineering construction strutting arrangement convenient to remove
CN221236049U (en) Supporting structure of foundation pit
CN220433679U (en) Foundation pit supporting structure for building engineering
CN217712574U (en) Tunnel excavation construction rack
CN220246879U (en) Cell sheet connecting device for geotechnical cells
CN217950457U (en) Auxiliary positioning mechanism is used in installation of subway people's air defense door
CN210827127U (en) Bridge floor hollow slab centre form is demolishd and is used reaction frame
CN218428185U (en) Building engineering pipe strutting arrangement
CN220338093U (en) Electromechanical installing support
CN218758638U (en) Civil engineering is with adjustable bearing stores pylon
CN218236724U (en) Equipment mounting support
CN218324085U (en) Firm steel structure support
CN217456780U (en) Waterproofing membrane deposits support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant