CN216520025U - Assembled antidetonation gallows - Google Patents

Assembled antidetonation gallows Download PDF

Info

Publication number
CN216520025U
CN216520025U CN202121086209.6U CN202121086209U CN216520025U CN 216520025 U CN216520025 U CN 216520025U CN 202121086209 U CN202121086209 U CN 202121086209U CN 216520025 U CN216520025 U CN 216520025U
Authority
CN
China
Prior art keywords
hoop
fixing
hanger
fixed
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121086209.6U
Other languages
Chinese (zh)
Inventor
高辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hengshui Hengyin Enterprise Management Co.,Ltd.
Original Assignee
Jiangsu Huipeng Complete Equipment Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Huipeng Complete Equipment Technology Co ltd filed Critical Jiangsu Huipeng Complete Equipment Technology Co ltd
Priority to CN202121086209.6U priority Critical patent/CN216520025U/en
Application granted granted Critical
Publication of CN216520025U publication Critical patent/CN216520025U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

本实用新型公开一种装配式抗震支吊架,具体涉及支吊架技术领域,包括安装板,所述安装板的顶端两侧设置有连接座,所述连接座的顶端设置有固定螺杆,所述安装板的顶端设置有抱箍,所述抱箍的内部设置有弧形杆,所述抱箍的顶端设置有固定螺栓,所述弧形杆的外侧设置有限定弹簧所述固定螺杆的顶端设置有固定座,所述固定座的顶端设置有固定顶板。本实用新型通过向外扩展抱箍,进而使得弧形杆可以通过滑块从抱箍内部延伸出来,进而使得限定弹簧向外侧拉伸,当水管安装好后,在限定弹簧的弹力作用下,使得抱箍紧密贴合水管的表面,然后通过固定螺栓可以将水管固定在抱箍内部,使得抱箍可以适应不同尺寸的水管的安装工作。

Figure 202121086209

The utility model discloses an assembled anti-seismic support and hanger, which specifically relates to the technical field of support and hangers. The top of the mounting plate is provided with a hoop, the inside of the hoop is provided with an arc-shaped rod, the top of the hoop is provided with a fixing bolt, and the outer side of the arc-shaped rod is provided with a top end of the fixing screw that defines the spring A fixed seat is provided, and the top of the fixed seat is provided with a fixed top plate. The utility model expands the hoop outwards, so that the arc-shaped rod can be extended from the inside of the hoop through the sliding block, so that the limiting spring is stretched to the outside. After the water pipe is installed, under the elastic force of the limiting spring, the The hoop closely fits the surface of the water pipe, and then the water pipe can be fixed inside the hoop by fixing bolts, so that the hoop can adapt to the installation of water pipes of different sizes.

Figure 202121086209

Description

一种装配式抗震支吊架An assembled anti-seismic support hanger

技术领域technical field

本实用新型涉及支吊架技术领域,更具体地说,本实用涉及一种装配式抗震支吊架。The utility model relates to the technical field of a support and hanger, more particularly, the utility model relates to an assembled anti-seismic support and hanger.

背景技术Background technique

支吊架主要用于电厂汽水管道或锅炉设备,在运行中产生热位移及其设备装置上,支吊架主要可分为弹簧支吊架、管部支吊架、根部支吊架和附件支吊架四种。Supports and hangers are mainly used for steam-water pipelines or boiler equipment in power plants, which generate thermal displacement during operation and their equipment devices. Supports and hangers can be mainly divided into spring supports and hangers, pipe supports and hangers, root supports and hangers There are four types of hangers.

现有技术中存在的不足:受到不同管道尺寸的影响,现有的支吊架在安装管道时需要更换不同的固定装置,使得管道的安装过程中会需要大量的时间,因此会增加管道安装的成本。Shortcomings in the prior art: Affected by different pipe sizes, the existing support and hanger need to replace different fixing devices when installing pipes, so that a lot of time is required in the installation process of the pipes, so the installation time of the pipes will be increased. cost.

实用新型内容Utility model content

为了克服现有技术的上述缺陷,本实用新型的实施例提供一种装配式抗震支吊架,通过向外扩展抱箍,进而使得弧形杆可以通过滑块从抱箍内部延伸出来,进而使得限定弹簧向外侧拉伸,当水管安装好后,在限定弹簧的弹力作用下,弧形杆向抱箍内部收纳,进而使得抱箍紧密贴合水管的表面,然后通过固定螺栓可以将水管固定在抱箍内部,进而使得抱箍可以适应不同尺寸的水管的安装工作,以解决上述背景技术中提出的问题。In order to overcome the above-mentioned defects of the prior art, the embodiment of the present invention provides a prefabricated anti-seismic support and hanger. By expanding the hoop outwards, the arc-shaped rod can be extended from the inside of the hoop through the slider, thereby making The limiting spring is stretched to the outside. When the water pipe is installed, under the elastic force of the limiting spring, the arc-shaped rod is accommodated inside the hoop, so that the hoop is tightly attached to the surface of the water pipe, and then the water pipe can be fixed by the fixing bolts. The inside of the hoop makes the hoop adapt to the installation work of water pipes of different sizes, so as to solve the problems raised in the above background art.

为实现上述目的,本实用新型提供如下技术方案:一种装配式抗震支吊架,包括安装板,所述安装板的顶端两侧设置有连接座,所述连接座的顶端设置有固定螺杆,所述安装板的顶端设置有固定板,所述固定板的顶端设置有抱箍,所述抱箍的内部活动插接有弧形杆,所述抱箍的顶端螺纹插接有固定螺栓,所述弧形杆的外侧活动套接有限定弹簧,所述固定螺杆的顶端设置有固定座,所述固定座的顶端活动连接有固定顶板。In order to achieve the above purpose, the present utility model provides the following technical solutions: an assembled anti-seismic support and hanger, comprising a mounting plate, the top of the mounting plate is provided with connecting seats on both sides, and the top of the connecting seat is provided with a fixing screw, The top of the mounting plate is provided with a fixing plate, the top of the fixing plate is provided with a hoop, an arc-shaped rod is movably inserted inside the hoop, and the top of the hoop is screwed with a fixing bolt, so The outer side of the arc-shaped rod is movably sleeved with a limiting spring, the top end of the fixed screw rod is provided with a fixed seat, and the top end of the fixed seat is movably connected with a fixed top plate.

在一个优选的实施方式中,所述弧形杆的两端固定安装有滑块,所述滑块与抱箍的内壁相匹配。In a preferred embodiment, sliding blocks are fixedly installed at both ends of the arc-shaped rod, and the sliding blocks are matched with the inner wall of the hoop.

在一个优选的实施方式中,所述固定顶板的内部活动插接有活动杆,所述活动杆的两端固定安装有限定板。In a preferred embodiment, a movable rod is movably inserted into the interior of the fixed top plate, and a limiting plate is fixedly installed at both ends of the movable rod.

在一个优选的实施方式中,所述所述固定顶板与固定座之间固定连接有牵引弹簧,所述牵引弹簧套接在活动杆的外侧。In a preferred embodiment, a traction spring is fixedly connected between the fixed top plate and the fixed seat, and the traction spring is sleeved on the outer side of the movable rod.

在一个优选的实施方式中,所述固定螺杆的顶端固定安装有阻隔板,所述阻隔板与固定座相匹配。In a preferred embodiment, a blocking plate is fixedly installed on the top end of the fixing screw, and the blocking plate is matched with the fixing seat.

在一个优选的实施方式中,所述安装板与连接座固定连接,所述连接座与固定螺杆螺纹连接。In a preferred embodiment, the mounting plate is fixedly connected to a connecting seat, and the connecting seat is threadedly connected to a fixing screw.

在一个优选的实施方式中,所述固定螺杆与固定座螺纹连接,所述固定座与牵引弹簧固定连接。In a preferred embodiment, the fixing screw is threadedly connected to a fixing seat, and the fixing seat is fixedly connected to the traction spring.

在一个优选的实施方式中,所述安装板与固定板固定连接,所述固定板与抱箍活动连接。In a preferred embodiment, the mounting plate is fixedly connected to the fixing plate, and the fixing plate is movably connected to the hoop.

本实用新型的技术效果和优点:Technical effects and advantages of the present utility model:

1、通过向外扩展抱箍,进而使得弧形杆可以通过滑块从抱箍内部延伸出来,进而使得限定弹簧向外侧拉伸,当水管安装好后,在限定弹簧的弹力作用下,弧形杆向抱箍内部收纳,进而使得抱箍紧密贴合水管的表面,然后通过固定螺栓可以将水管固定在抱箍内部,进而使得抱箍可以适应不同尺寸的水管的安装工作,与现有技术相比,有适应不同尺寸水管安装的进步;1. By expanding the hoop outwards, the arc-shaped rod can be extended from the inside of the hoop through the slider, so that the limiting spring is stretched to the outside. When the water pipe is installed, under the elastic force of the limiting spring, the arc-shaped The rod is stored inside the hoop, so that the hoop closely fits the surface of the water pipe, and then the water pipe can be fixed inside the hoop by fixing bolts, so that the hoop can adapt to the installation of water pipes of different sizes, which is consistent with the existing technology. ratio, there are improvements to adapt to the installation of water pipes of different sizes;

2、通过固定顶板内部的活动杆的设置,在发生振动的时候,活动杆可以在固定顶板内部向下滑动,进而使得牵引弹簧向下延伸,进而使得固定座向下移动,在活动杆的移动过程中,限定板可以限定活动杆的移动,可以防止活动杆从固定顶板内部脱离,牵引弹簧和活动杆的设置使得支吊架在感受到振动时,可以通过牵引弹簧起到缓冲避震的作用,可以防止支吊架在受到振动后出现脱落的情况,与现有技术相比,有抗震避震的进步。2. Through the setting of the movable rod inside the fixed top plate, when the vibration occurs, the movable rod can slide down inside the fixed top plate, so as to make the traction spring extend downward, so that the fixed seat moves down, and when the movable rod moves During the process, the limiting plate can limit the movement of the movable rod, which can prevent the movable rod from detaching from the inside of the fixed top plate. The setting of the traction spring and the movable rod enables the support and hanger to use the traction spring to buffer the shock when it feels vibration. , it can prevent the support and hanger from falling off after being vibrated, and compared with the prior art, there is an improvement in shock resistance and shock absorption.

附图说明Description of drawings

图1为本实用新型的整体结构示意图。FIG. 1 is a schematic diagram of the overall structure of the present invention.

图2为本实用新型图1的A部结构放大图。FIG. 2 is an enlarged view of the structure of part A of FIG. 1 of the present utility model.

图3为本实用新型图1的B部结构放大图。FIG. 3 is an enlarged view of the structure of part B of FIG. 1 of the present invention.

图4为本实用新型图1的C部结构放大图。FIG. 4 is an enlarged view of the structure of part C of FIG. 1 of the present invention.

图5为本实用新型的固定底座俯视图。FIG. 5 is a top view of the fixed base of the present invention.

附图标记为:1安装板、2连接座、3固定螺杆、4固定板、5抱箍、6弧形杆、7滑块、8限定弹簧、9固定螺栓、10固定座、11固定顶板、12活动杆、13限定板、14牵引弹簧、15阻隔板。Reference numerals are: 1 mounting plate, 2 connecting seat, 3 fixing screw, 4 fixing plate, 5 hoop, 6 arc rod, 7 sliding block, 8 limiting spring, 9 fixing bolt, 10 fixing seat, 11 fixing top plate, 12 Active rod, 13 limiting plate, 14 traction spring, 15 blocking plate.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model. Obviously, the described embodiments are only a part of the embodiments of the present utility model, rather than all the implementations. example. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work fall within the protection scope of the present invention.

如图1-3所示,本实用新型提供了一种装配式抗震支吊架,包括安装板1,所述安装板1的顶端两侧设置有连接座2,所述连接座2的顶端设置有固定螺杆3,所述安装板1的顶端设置有固定板4,所述固定板4的顶端设置有抱箍5,所述抱箍5的内部活动插接有弧形杆6,所述抱箍5的顶端螺纹插接有固定螺栓9,所述弧形杆6的外侧活动套接有限定弹簧8,所述固定螺杆3的顶端设置有固定座10,所述固定座10的顶端活动连接有固定顶板11;As shown in Figures 1-3, the present utility model provides a prefabricated anti-seismic support and hanger, comprising a mounting plate 1, the top of the mounting plate 1 is provided with connecting seats 2 on both sides, and the top of the connecting seat 2 is provided with There is a fixed screw 3, the top of the mounting plate 1 is provided with a fixed plate 4, the top of the fixed plate 4 is provided with a hoop 5, and an arc-shaped rod 6 is movably inserted inside the hoop 5. The top of the hoop 5 is screwed with a fixing bolt 9, the outer side of the arc-shaped rod 6 is movably sleeved with a limiting spring 8, the top of the fixing screw 3 is provided with a fixing seat 10, and the top of the fixing seat 10 is movably connected There is a fixed top plate 11;

所述弧形杆6的两端固定安装有滑块7,所述滑块7与抱箍5的内壁相匹配,弧形杆6可以通过滑块7在抱箍5内进行移动,使得抱箍5可以向外扩展,同时可以限定抱箍5的扩展程度;The two ends of the arc-shaped rod 6 are fixedly installed with a slider 7, and the slider 7 is matched with the inner wall of the hoop 5. The arc-shaped rod 6 can be moved in the hoop 5 through the slider 7, so that the hoop can be moved. 5 can be expanded outward, and at the same time can limit the expansion degree of the hoop 5;

所述安装板1与连接座2固定连接,所述连接座2与固定螺杆3螺纹连接,固定螺杆3可以对安装板1进行吊装,可以将水管固定在高处;The mounting plate 1 is fixedly connected with the connecting seat 2, the connecting seat 2 is threadedly connected with the fixing screw 3, and the fixing screw 3 can hoist the mounting plate 1, and can fix the water pipe at a high place;

所述安装板1与固定板4固定连接,所述固定板4与抱箍5活动连接,使得抱箍5可以很好地进行向外的扩展,使得抱箍5可以适应不同的水管安装;The mounting plate 1 is fixedly connected with the fixing plate 4, and the fixing plate 4 is movably connected with the hoop 5, so that the hoop 5 can be well expanded outward, so that the hoop 5 can be adapted to different water pipe installations;

实施方式具体为:通过向外扩展抱箍5,进而使得弧形杆6可以通过滑块7从抱箍5内部延伸出来,进而使得限定弹簧8向外侧拉伸,当水管安装好后,在限定弹簧8的弹力作用下,弧形杆6向抱箍5内部收纳,进而使得抱箍5紧密贴合水管的表面,然后通过固定螺栓9可以将水管固定在抱箍5内部,进而使得抱箍5可以适应不同尺寸的水管的安装工作,该实施方式具体解决了现有技术中存在的无法适应不同尺寸水管安装工作的问题。The specific embodiment is as follows: by expanding the hoop 5 outward, the arc-shaped rod 6 can be extended from the inside of the hoop 5 through the slider 7, so that the limiting spring 8 is stretched to the outside. Under the elastic force of the spring 8, the arc-shaped rod 6 is accommodated inside the hoop 5, so that the hoop 5 closely fits the surface of the water pipe, and then the water pipe can be fixed inside the hoop 5 by the fixing bolts 9, thereby making the hoop 5 It can adapt to the installation work of water pipes of different sizes, and this embodiment specifically solves the problem existing in the prior art that it cannot adapt to the installation work of water pipes of different sizes.

如图1和图4-5所示,所述固定顶板11的内部活动插接有活动杆12,所述活动杆12的两端固定安装有限定板13,限定板13可以限定活动杆12的活动,可以防止活动杆12从固定顶板11中脱落;As shown in FIG. 1 and FIGS. 4-5 , a movable rod 12 is movably inserted into the interior of the fixed top plate 11 , and a limiting plate 13 is fixedly installed at both ends of the movable rod 12 , and the limiting plate 13 can limit the position of the movable rod 12 . It can prevent the movable rod 12 from falling off from the fixed top plate 11;

所述固定顶板11与固定座10之间固定连接有牵引弹簧14,所述牵引弹簧14套接在活动杆12的外侧,活动杆12的活动可以对牵引弹簧14起到限定作用,可以防止牵引弹簧14在震动过程中会向下脱落的情况;A traction spring 14 is fixedly connected between the fixed top plate 11 and the fixed seat 10. The traction spring 14 is sleeved on the outer side of the movable rod 12. The movement of the movable rod 12 can limit the traction spring 14 and prevent traction. The situation that the spring 14 will fall down during the vibration process;

所述固定螺杆3的顶端固定安装有阻隔板15,所述阻隔板15与固定座10相匹配,阻隔板15可以限定固定螺杆3的移动,可以防止固定螺杆3与固定座10脱落,出现水管安装不牢固的情况;The top of the fixing screw 3 is fixedly installed with a blocking plate 15, the blocking plate 15 is matched with the fixing seat 10, the blocking plate 15 can limit the movement of the fixing screw 3, and can prevent the fixing screw 3 and the fixing seat 10 from falling off and water pipes appearing The installation is not firm;

所述固定螺杆3与固定座10螺纹连接,所述固定座10与牵引弹簧14固定连接,牵引弹簧14可以对固定座10起到牵引作用,可以防止固定座10在震动过程中出现脱落的情况。The fixing screw 3 is threadedly connected with the fixing seat 10, and the fixing seat 10 is fixedly connected with the traction spring 14. The traction spring 14 can pull the fixing seat 10, which can prevent the fixing seat 10 from falling off during the vibration process. .

实施方式具体为:通过固定顶板11内部的活动杆12的设置,在发生振动的时候,活动杆12可以在固定顶板11内部向下滑动,进而使得牵引弹簧14向下延伸,进而使得固定座10向下移动,在活动杆12的移动过程中,限定板13可以限定活动杆12的移动,可以防止活动杆12从固定顶板11内部脱离,牵引弹簧14和活动杆12的设置使得支吊架在感受到振动时,可以通过牵引弹簧14起到缓冲避震的作用,可以防止支吊架在受到振动后出现脱落的情况,该实施方式具体解决了现有技术中存在的受到振动容易脱落的问题。The specific embodiment is as follows: through the setting of the movable rod 12 inside the fixed top plate 11, when vibration occurs, the movable rod 12 can slide down inside the fixed top plate 11, thereby causing the traction spring 14 to extend downward, thereby making the fixed seat 10. Moving down, during the movement of the movable rod 12, the limiting plate 13 can limit the movement of the movable rod 12, which can prevent the movable rod 12 from detaching from the fixed top plate 11. The setting of the traction spring 14 and the movable rod 12 makes the support and hanger in When the vibration is felt, the traction spring 14 can play a role of buffering and shock absorption, which can prevent the support and hanger from falling off after being subjected to vibration. This embodiment specifically solves the problem that the existing technology is easy to fall off after vibration .

本实用新型工作原理:The working principle of the utility model:

参照说明书附图1-3,通过向外扩展抱箍5,进而使得弧形杆6可以通过滑块7从抱箍5内部延伸出来,进而使得限定弹簧8向外侧拉伸,当水管安装好后,在限定弹簧8的弹力作用下,弧形杆6向抱箍5内部收纳,进而使得抱箍5紧密贴合水管的表面,然后通过固定螺栓9可以将水管固定在抱箍5内部;Referring to the accompanying drawings 1-3 of the description, by expanding the hoop 5 outward, the arc-shaped rod 6 can be extended from the inside of the hoop 5 through the slider 7, so that the limiting spring 8 is stretched to the outside. When the water pipe is installed , under the elastic force of the limiting spring 8, the arc-shaped rod 6 is accommodated inside the hoop 5, so that the hoop 5 closely fits the surface of the water pipe, and then the water pipe can be fixed inside the hoop 5 through the fixing bolt 9;

进一步的,参照说明书附图1和图4-5,通过固定顶板11内部的活动杆12的设置,在发生振动的时候,活动杆12可以在固定顶板11内部向下滑动,进而使得牵引弹簧14向下延伸,进而使得固定座10向下移动,在活动杆12的移动过程中,限定板13可以限定活动杆12的移动,牵引弹簧14可以对固定座10和支吊架进行牵引和限定。Further, referring to FIG. 1 and FIGS. 4-5 of the specification, through the setting of the movable rod 12 inside the fixed top plate 11, when vibration occurs, the movable rod 12 can slide down inside the fixed top plate 11, thereby making the traction spring 14 Extending downward, the fixed seat 10 moves downward. During the movement of the movable rod 12, the limiting plate 13 can limit the movement of the movable rod 12, and the traction spring 14 can pull and limit the fixed seat 10 and the support and hanger.

最后应说明的几点是:首先,在本申请的描述中,需要说明的是,除非另有规定和限定,术语“安装”、“相连”、“连接”应做广义理解,可以是机械连接或电连接,也可以是两个元件内部的连通,可以是直接相连,“上”、“下”、“左”、“右”等仅用于表示相对位置关系,当被描述对象的绝对位置改变,则相对位置关系可能发生改变;The last points to be noted are: First of all, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, and may be mechanical connection. or electrical connection, or internal communication between two components, or direct connection, "up", "down", "left", "right", etc. are only used to indicate relative positional relationship, when the absolute position of the object being described changes, the relative positional relationship may change;

其次:本实用新型公开实施例附图中,只涉及到与本公开实施例涉及到的结构,其他结构可参考通常设计,在不冲突情况下,本实用新型同一实施例及不同实施例可以相互组合;Secondly: in the drawings of the disclosed embodiments of the present invention, only the structures involved in the embodiments of the present invention are involved, and other structures may refer to the general design. In the case of no conflict, the same embodiment and different embodiments of the present invention can be mutually combination;

最后:以上所述仅为本实用新型的优选实施例而已,并不用于限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。Finally: the above is only the preferred embodiment of the present utility model, and is not intended to limit the present utility model, all within the spirit and principle of the present utility model, any modification, equivalent replacement, improvement, etc. made, should include within the scope of protection of the present invention.

Claims (8)

1. The utility model provides an assembled antidetonation gallows, includes mounting panel (1), its characterized in that: the top both sides of mounting panel (1) are provided with connecting seat (2), the top of connecting seat (2) is provided with clamping screw (3), the top of mounting panel (1) is provided with fixed plate (4), the top of fixed plate (4) is provided with staple bolt (5), the inside activity of staple bolt (5) is pegged graft and is had arc pole (6), the top screw thread of staple bolt (5) is pegged graft and is had fixing bolt (9), limited spring (8) have been cup jointed in the outside activity of arc pole (6), the top of clamping screw (3) is provided with fixing base (10), the top swing joint of fixing base (10) has fixed roof (11).
2. An assembled earthquake-resistant support and hanger as defined in claim 1, wherein: the two ends of the arc-shaped rod (6) are fixedly provided with sliding blocks (7), and the sliding blocks (7) are matched with the inner wall of the hoop (5).
3. An assembled earthquake-resistant support and hanger as defined in claim 1, wherein: the inner part of the fixed top plate (11) is movably inserted with a movable rod (12), and two ends of the movable rod (12) are fixedly provided with limiting plates (13).
4. An assembled earthquake-resistant support and hanger as defined in claim 1, wherein: and a traction spring (14) is fixedly connected between the fixed top plate (11) and the fixed seat (10), and the traction spring (14) is sleeved on the outer side of the movable rod (12).
5. An assembled earthquake-resistant support and hanger as defined in claim 1, wherein: the top end fixed mounting of clamping screw (3) has baffler (15), baffler (15) and fixing base (10) phase-match.
6. An assembled earthquake-resistant support and hanger as defined in claim 1, wherein: the mounting plate (1) is fixedly connected with the connecting seat (2), and the connecting seat (2) is in threaded connection with the fixing screw (3).
7. An assembled earthquake-resistant support and hanger as defined in claim 4, wherein: the fixing screw rod (3) is in threaded connection with the fixing seat (10), and the fixing seat (10) is fixedly connected with the traction spring (14).
8. An assembled earthquake-resistant support and hanger as defined in claim 1, wherein: the mounting plate (1) is fixedly connected with the fixing plate (4), and the fixing plate (4) is movably connected with the hoop (5).
CN202121086209.6U 2021-05-20 2021-05-20 Assembled antidetonation gallows Active CN216520025U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121086209.6U CN216520025U (en) 2021-05-20 2021-05-20 Assembled antidetonation gallows

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121086209.6U CN216520025U (en) 2021-05-20 2021-05-20 Assembled antidetonation gallows

Publications (1)

Publication Number Publication Date
CN216520025U true CN216520025U (en) 2022-05-13

Family

ID=81460867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121086209.6U Active CN216520025U (en) 2021-05-20 2021-05-20 Assembled antidetonation gallows

Country Status (1)

Country Link
CN (1) CN216520025U (en)

Similar Documents

Publication Publication Date Title
CN217815394U (en) Building air pipe bearing damping device
CN211083103U (en) Anti-seismic fixed support hanger
CN207935554U (en) One kind being used for subway transportation antidetonation suspension and support
CN108533834A (en) A kind of adjustable damping type antidetonation suspension and support of support stiffness
CN209398930U (en) An anti-seismic support and hanger with adjustable size for pipeline installation
CN213745268U (en) An anti-vibration support hanger with high acid and alkali resistance based on PTFE anti-corrosion coating
CN215635419U (en) an anti-vibration bracket
CN210687272U (en) Box type four-way pipeline spring shock absorber
CN208058143U (en) A kind of buffer gear for para-seismic support
CN214405006U (en) Thermal engineering pipeline spring supporting and hanging frame
CN214063999U (en) Warm antidetonation stable form gallows that leads to and purify tuber pipe
CN212659943U (en) Stockbridge damper device for power transmission line
CN209398938U (en) A multifunctional anti-seismic support and hanger
CN204164607U (en) A kind of para-seismic support of building interior electromechanical equipment
CN116717656A (en) A kind of comprehensive support and hanger that resists strong earthquakes
CN211821049U (en) A kind of pipeline support for pipeline engineering
CN210830989U (en) Synthesize pipeline antidetonation gallows
CN211667382U (en) A antidetonation support for engineering pipeline is fixed
CN219263542U (en) A gallows for building electromechanical installation
CN208185608U (en) A kind of antidetonation suspension and support
CN219510290U (en) An anti-seismic support connection device
CN220016341U (en) Anti-seismic support and hanger
CN222416396U (en) A kind of underground pipe gallery pipeline support and hanger
CN219196830U (en) Anti-seismic reinforcing structure for building support
CN220396765U (en) A height-adjustable anti-seismic bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240826

Address after: Building 4, Courtyard 2, Sihezhuang Road, Fengtai District, Beijing 100071, Floors 1-17, Unit 101, 11th Floor 1112

Patentee after: TUNGHSU TECHNOLOGY GROUP Co.,Ltd.

Country or region after: China

Address before: 225000 Zhenxing East Road, dinggou Town, Jiangdu District, Yangzhou City, Jiangsu Province

Patentee before: Jiangsu Huipeng complete equipment Technology Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A prefabricated seismic support hanger

Granted publication date: 20220513

Pledgee: Hengshui Bank Co.,Ltd.

Pledgor: TUNGHSU TECHNOLOGY GROUP Co.,Ltd.

Registration number: Y2024980036681

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20220513

Pledgee: Hengshui Bank Co.,Ltd.

Pledgor: TUNGHSU TECHNOLOGY GROUP Co.,Ltd.

Registration number: Y2024980036681

PC01 Cancellation of the registration of the contract for pledge of patent right
TR01 Transfer of patent right

Effective date of registration: 20250519

Address after: Room 606, 6th Floor, Building D and E, Commercial Center, Renmin Road Central Street, Taocheng District, Hengshui City, Hebei Province 053099

Patentee after: Hengshui Hengyin Enterprise Management Co.,Ltd.

Country or region after: China

Address before: Building 4, Courtyard 2, Sihezhuang Road, Fengtai District, Beijing 100071, Floors 1-17, Unit 101, 11th Floor 1112

Patentee before: TUNGHSU TECHNOLOGY GROUP Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right