CN216476043U CN202123005835.0U CN202123005835U CN216476043U CN 216476043 U CN216476043 U CN 216476043U CN 202123005835 U CN202123005835 U CN 202123005835U CN 216476043 U CN216476043 U CN 216476043U
Authority
CN
China
Prior art keywords
layer
hollow brick
veneer
saltpetering
gardens
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123005835.0U
Other languages
Chinese (zh)
Inventor
王奇勇
王佩
李�浩
刘茂林
王�华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wanjian Ecological Environment Construction Co ltd
Original Assignee
Wanjian Ecological Environment Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wanjian Ecological Environment Construction Co ltd filed Critical Wanjian Ecological Environment Construction Co ltd
Priority to CN202123005835.0U priority Critical patent/CN216476043U/en
Application granted granted Critical
Publication of CN216476043U publication Critical patent/CN216476043U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model provides a saltpetering structure is prevented to gardens veneer tiling, saltpetering structure is prevented to gardens veneer tiling includes basal layer and hollow brick layer, the basal layer top is provided with the hollow brick layer, the hollow brick layer includes hollow brick main part, hollow groove, spread groove and connecting block, the hollow groove has been seted up to hollow brick main part surface symmetry, the spread groove has been seted up to hollow brick main part top symmetry, the connecting block is installed to hollow brick main part bottom symmetry, and spread groove and connecting block structure cooperation, the utility model provides a saltpetering structure is prevented to gardens veneer tiling can prevent that the saltpetering phenomenon from appearing in gardens building surface through installation basal layer, geotechnological cloth layer, screed-coat, hollow brick layer, cement layer, waterproof layer, adhesive linkage and finish coat, improves the intensity that saltpetering structure is prevented to gardens veneer tiling simultaneously.

Description

Saltpetering structure is prevented to gardens veneer tiling
Technical Field
The utility model relates to a gardens architectural decoration technical field especially relates to a saltpetering structure is prevented to gardens veneer tiling.
Background
Ornamental in gardens, be exactly to the surface of gardens building decorate the work of maintaining, in landscape, the powdered material of white can often be seen on the building surface, is only a building whiskering phenomenon, need use novel gardens veneer tiling for this reason and prevent whiskering structure.
Therefore, there is a need to provide a new anti-efflorescence structure for a garden veneer tile to solve the above technical problems.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides a saltpetering structure is prevented to gardens veneer tiling.
The utility model provides a saltpetering structure is prevented to gardens veneer tiling includes: basal layer and hollow brick layer, the basal layer top is provided with the hollow brick layer, the hollow brick layer includes hollow brick main part, hollow groove, spread groove and connecting block, hollow groove has been seted up to hollow brick main part surface symmetry, the spread groove has been seted up to hollow brick main part top symmetry, the connecting block is installed to hollow brick main part bottom symmetry, and spread groove and connecting block structure cooperation, conveniently assembles the hollow brick layer.
Preferably, the geotechnical cloth layer is installed on the top of the foundation layer, so that the bearing strength of the building is improved.
Preferably, the top of the geotextile layer is provided with a leveling layer, so that the surface of the building is smooth.
Preferably, a cement layer is arranged on the top of the hollow brick layer to bear loads transmitted from the outside.
Preferably, the waterproof layer is installed on the top of the cement layer, so that the waterproof performance of the building is improved.
Preferably, an adhesive layer is arranged on the top of the waterproof layer, and the waterproof layer and the finishing coat are stably connected.
Preferably, a decorative layer is arranged on the top of the bonding layer to ensure that the surface of the building is smooth.
Preferably, the hollow groove edge has been seted up the fillet, conveniently snatchs the hollow brick main part.
Compared with the prior art, the utility model provides a saltpetering structure is prevented to gardens veneer tiling has following beneficial effect:
the utility model provides a saltpetering structure is prevented to gardens veneer tiling:
1. through installation basic unit, geotechnological cloth layer, screed-coat, hollow brick layer, cement layer, waterproof layer, adhesive linkage and finish coat, can prevent that the saltpetering phenomenon from appearing in gardens building surface, improve the intensity that saltpetering structure was prevented to gardens veneer tiling simultaneously.
2. Install the cement layer through hollow brick layer top, the cement layer is the bearing layer, and the load that the outside was transmitted to with its diffusion to other structural layers, because be cement stable material, the stability can be better.
Drawings
Fig. 1 is a schematic view of an overall top-view structure provided by the present invention;
FIG. 2 is a schematic view of the overall side view structure provided by the present invention;
fig. 3 is a schematic view of the hollow brick layer structure provided by the present invention.
Reference numbers in the figures: 1. a base layer; 2. a geotextile layer; 3. leveling layer; 4. a hollow brick layer; 41. a hollow brick body; 42. a hollow groove; 43. connecting grooves; 44. connecting blocks; 5. a cement layer; 6. a waterproof layer; 7. an adhesive layer; 8. and (6) a finishing layer.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and embodiments.
Please refer to fig. 1, fig. 2 and fig. 3 in combination, wherein fig. 1 is a schematic diagram of an overall top view structure provided by the present invention; FIG. 2 is a schematic view of the overall side view structure provided by the present invention; fig. 3 is a schematic view of the hollow brick layer structure provided by the present invention. The saltpetering structure is prevented to gardens veneer tiling includes: a base layer 1 and a hollow brick layer 4.
In the concrete implementation in-process, as shown in fig. 1 and 3, 1 top on basic layer is provided with hollow brick layer 4, hollow brick layer 4 includes hollow brick main part 41, hollow groove 42, spread groove 43 and connecting block 44, hollow groove 42 has been seted up to hollow brick main part 41 surface symmetry, spread groove 43 has been seted up to hollow brick main part 41 top symmetry, connecting block 44 is installed to hollow brick main part 41 bottom symmetry, and spread groove 43 and the cooperation of connecting block 44 structure, places basic layer 1 top with hollow brick layer 4, and two hollow brick main parts 41 are close to each other, and inside connecting block 44 got into spread groove 43, conveniently assembled hollow brick layer 4 had improved the installation rate on hollow brick layer 4, formed gardens veneer tiling fast and prevented the saltpetering structure.
Referring to fig. 1 and 2, a geotextile layer 2 is installed on the top of the foundation layer 1, and the geotextile layer 2 is a water-permeable geosynthetic material formed by needling or weaving synthetic fibers, so that building materials with different properties are isolated, the building materials are not lost or mixed, the integrity of the material is maintained, and the bearing capacity of the garden building is improved.
Referring to fig. 1 and 2, the leveling layer 3 is installed at the top of the geotechnical cloth layer 2, so that the leveling effect of the wall surface of the garden building is achieved, and the laying of other structural layers is facilitated.
Referring to fig. 1 and 2, a cement layer 5 is installed on the top of the hollow brick layer 4, the cement layer 5 is a bearing layer, and the load transmitted from the outside is diffused to other structural layers, and the stability is better due to the cement stabilizing material.
Referring to fig. 1 and 2, a waterproof layer 6 is installed on the top of the cement layer 5 to play a waterproof role, so that the cement layer 5 cannot crack under the washing of rainwater, and the building is prevented from suffering from saltpetering.
Referring to fig. 1 and 2, the bonding layer 7 is installed on the top of the waterproof layer 6, so that the waterproof layer 6 and the finish coat 8 can be connected firmly, and the stability of the anti-efflorescence structure of the garden veneer patch is improved.
Referring to fig. 1 and 2, the top of the adhesive layer 7 is provided with a veneer layer 8, which has high strength and ensures the strength and flatness of the surface of the anti-efflorescence structure of the garden veneer patch.
Referring to fig. 1 and 2, the edges of the hollow groove 42 are rounded, so that when the hollow brick body 41 is carried and the edges of the hollow groove 42 are grabbed, the abrasion is reduced, and the practicability of the hollow brick body 41 is improved.
The working principle is as follows: the hollow brick layer 4 is placed above the foundation layer 1, the two hollow brick main bodies 41 are close to each other, the connecting block 44 enters the connecting groove 43, the hollow brick layer 4 is convenient to assemble, the installation speed of the hollow brick layer 4 is improved, the garden veneer sticking block anti-efflorescence structure is quickly formed, the geotechnical cloth layer 2 is installed at the top of the foundation layer 1, the geotechnical cloth layer 2 is a water-permeable geotechnical synthetic material formed by needling or weaving synthetic fibers, building materials with different properties are isolated, the building materials are not lost and mixed, the integrity of the materials is maintained, the bearing capacity of the garden building is improved, the leveling layer 3 is installed at the top of the geotechnical cloth layer 2, the effect of leveling the wall surface of the garden building is achieved, the laying of other structural layers is convenient, the cement layer 5 is installed at the top of the hollow brick layer 4, the cement layer 5 is a bearing layer, the load is transmitted from the outside, and with its diffusion to other structural layers, because cement stable material, stability can be better, install waterproof layer 6 through 5 tops of cement layer, play waterproof effect, guarantee under the washing away of rainwater, cement layer 5 can not ftracture, lead to building whiskering, install adhesive linkage 7 through 6 tops of waterproof layer, conveniently with waterproof layer 6 and finish coat 8 firm in connection, increase the stability of gardens veneer tiling anti-whiskering structure, install finish coat 8 through 7 tops of adhesive linkage, have very high intensity, guarantee gardens veneer tiling anti-whiskering structure surface's intensity and roughness, round angle has been seted up through hollow groove 42 edge, when carrying hollow brick main part 41, when snatching hollow groove 42 edge, wearing and tearing have been reduced, the practicality of hollow brick main part 41 has been improved.
The above only is the embodiment of the present invention, not limiting the scope of the present invention, all the equivalent structures or equivalent processes of the present invention are used in the specification and the attached drawings, or directly or indirectly applied to other related technical fields, and the same principle is included in the protection scope of the present invention.

Claims (8)

1. A gardens veneer tiling prevents whiskering structure, includes: basic layer (1) and hollow brick layer (4), basic layer (1) top is provided with hollow brick layer (4), its characterized in that, hollow brick layer (4) are including hollow brick main part (41), hollow groove (42), spread groove (43) and connecting block (44), hollow groove (42) have been seted up to hollow brick main part (41) surface symmetry, spread groove (43) have been seted up to hollow brick main part (41) top symmetry, connecting block (44) are installed to hollow brick main part (41) bottom symmetry, and spread groove (43) and connecting block (44) structure cooperation.
2. The landscape veneer tile saltpetering prevention structure according to claim 1, wherein a geotextile layer (2) is installed on top of the base layer (1).
3. The landscape veneer tile saltpetering prevention structure according to claim 2, wherein a leveling layer (3) is installed on top of the geotextile layer (2).
4. The landscape veneer tile saltpetering prevention structure according to claim 1, wherein a cement layer (5) is installed on top of the hollow brick layer (4).
5. The garden veneer block saltpetering prevention structure as claimed in claim 4, wherein a waterproof layer (6) is installed on top of the cement layer (5).
6. The garden veneer block saltpetering prevention structure as claimed in claim 5, wherein an adhesive layer (7) is installed on top of the waterproof layer (6).
7. The garden veneer block saltpetering prevention structure as claimed in claim 6, wherein a veneer layer (8) is installed on top of the adhesive layer (7).
8. The landscape veneer tile saltpetering prevention structure according to claim 1, wherein the edges of the hollow groove (42) are rounded.
CN202123005835.0U 2021-12-02 2021-12-02 Saltpetering structure is prevented to gardens veneer tiling Active CN216476043U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123005835.0U CN216476043U (en) 2021-12-02 2021-12-02 Saltpetering structure is prevented to gardens veneer tiling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123005835.0U CN216476043U (en) 2021-12-02 2021-12-02 Saltpetering structure is prevented to gardens veneer tiling

Publications (1)

Publication Number Publication Date
CN216476043U true CN216476043U (en) 2022-05-10

Family

ID=81402361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123005835.0U Active CN216476043U (en) 2021-12-02 2021-12-02 Saltpetering structure is prevented to gardens veneer tiling

Country Status (1)

Country Link
CN (1) CN216476043U (en)

Similar Documents

Publication Publication Date Title
CN216476043U (en) Saltpetering structure is prevented to gardens veneer tiling
CN211114595U (en) Ancient building restores and uses ground brick
CN209456827U (en) Floating floor decorating structure
CN215254259U (en) Wear-resisting little cement coating ground structure
CN201722582U (en) Cobblestone brick
CN213418205U (en) Non-bearing concrete hollow brick
CN105239751B (en) A kind of combined type floor tile of easily draining
CN212317379U (en) Terrace connection structure
CN108327364B (en) Needled non-woven fabric water-blocking felt and preparation method thereof
CN209040482U (en) Floor ground pavement structure
CN208995856U (en) A kind of water-permeable brick produced using waste ceramic
CN210117625U (en) Permeable ground structure
CN208604446U (en) Novel porous lightweight water-permeable brick
CN208235861U (en) Frangible lithotome enhances plate construction
CN202047516U (en) Dry-laying building block provided with pointing grooves
CN206267164U (en) A kind of basic blocks of ecological revetment barricade concrete segment
CN206843888U (en) A kind of structure permeable pavement brick
CN206737344U (en) A kind of wooden inorganic compounding stone plate of water-proof fire-retardant
CN206928156U (en) A kind of drainage system based on permeable pavement structure
CN111155738A (en) Composite ceramic tile installation structure with ABS substrate and installation method
CN206273891U (en) A kind of broken stone pile and CFG combined composite foundation structure
CN211548569U (en) Composite ceramic tile mounting structure with ABS basement
CN108560357A (en) A kind of spliced water-permeable brick
CN210827326U (en) Hierarchical ecological garden slope protection
CN215331195U (en) Energy-saving and heat-preserving environment-friendly concrete floor tile structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant