CN216475107U - Box frame device for quickly constructing gabion - Google Patents

Box frame device for quickly constructing gabion Download PDF

Info

Publication number
CN216475107U
CN216475107U CN202123119587.2U CN202123119587U CN216475107U CN 216475107 U CN216475107 U CN 216475107U CN 202123119587 U CN202123119587 U CN 202123119587U CN 216475107 U CN216475107 U CN 216475107U
Authority
CN
China
Prior art keywords
steel
templates
gabion
frame device
box frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202123119587.2U
Other languages
Chinese (zh)
Inventor
刘建文
孙永胜
刘帅方
张燕柯
李纪龙
王铁成
王军鹏
王文博
孙俊峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical Zhengzhou Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority to CN202123119587.2U priority Critical patent/CN216475107U/en
Application granted granted Critical
Publication of CN216475107U publication Critical patent/CN216475107U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a case frame device of quick construction gabion, include: the forming part is composed of three steel templates which are connected into a U-shaped structure, the steel templates are placed on the construction ground, and the U-shaped opening end and the hard end face are opposite to form a filling cavity with an upper opening structure; the hoisting fixing part is positioned on the top surface of the forming part and is a steel pipe arranged between two parallel steel templates, and a limiting block positioned on the outer side of each steel template is arranged on each steel pipe; a connection fixing portion having: the first connecting pieces are provided with a plurality of groups, each group of first connecting pieces comprises horizontal rings which are respectively arranged at the end parts of the side surfaces of two adjacent steel templates, and L-shaped inserting rods which are arranged in the horizontal rings in a penetrating manner and are used for connecting the two steel templates; the second connecting piece is a vertical ring arranged at the tops of the two parallel steel templates and used for connecting the steel pipes, and a puller bolt is arranged at the top of the vertical ring. The utility model discloses simple structure can improve the stone greatly and load speed, accelerates the construction of gabion.

Description

Box frame device for quickly constructing gabion
Technical Field
The utility model belongs to the technical field of engineering construction gabion construction technique and specifically relates to a box holder device of quick construction gabion.
Background
The gabion is a hexahedral steel wire mesh cage with stones inside, is mainly used for slope protection, roadbed reinforcement and the like, and has the advantages of good durability, low price and the like. During construction, the steel wire mesh is made into a hexahedral structure, the top cover is lifted and filled with stones, and then the top cover is sealed. Because the wire net adopts galvanized (alloy) steel wire to weave and forms, the texture is softer, when placing the stone, takes place to warp easily even damaged, leads to the efficiency of gabion construction low, influences whole construction progress.
Disclosure of Invention
In order to solve the problem, the utility model provides a quick construction gabion's tank tower device specifically can take following technical scheme:
case frame device of quick construction gabion, include
The forming part is composed of three steel templates which are connected into a U-shaped structure, the steel templates are placed on the construction ground, and the U-shaped opening end and the hard end face are opposite to form a filling cavity with an upper opening structure;
the hoisting fixing part is positioned on the top surface of the forming part and is a steel pipe arranged between two parallel steel templates, and a limiting block positioned on the outer side of each steel template is arranged on each steel pipe;
a connection fixing part is provided with
The first connecting pieces are provided with a plurality of groups, each group of first connecting pieces comprises horizontal rings which are respectively arranged at the end parts of the side surfaces of two adjacent steel templates, and L-shaped inserting rods which are arranged in the horizontal rings in a penetrating manner and are used for connecting the two steel templates;
the second connecting piece is a vertical ring arranged at the tops of the two parallel steel templates and used for connecting the steel pipes, and a puller bolt is arranged at the top of the vertical ring.
And a hook used for connecting a steel wire mesh is arranged at the top of the inner side surface of the steel template.
And reinforcing ribs are arranged on the outer side surface of the steel template.
The two steel pipes are arranged in parallel.
The spacing of the limiting blocks is matched with the spacing of the parallel steel templates.
The vertical ring is a U-shaped ring.
The utility model provides a case frame device of gabion of quick construction, simple structure, convenient to use adopts steel form etc. to carry out the plastic reinforcement to the wire net as the supporting surface, and box with a net warp when can avoiding placing the stone, owing to need not to consider above-mentioned factor, therefore no matter manual loading or mechanical loading, can improve the stone loading speed greatly, accelerate the construction of gabion; secondly, the steel formwork is connected with a steel frame body, and the steel frame body can not only enhance the stability of the steel formwork, but also be used as a hoisting support body, so that the transfer is convenient, and the construction efficiency of the whole batch of gabion gabions is improved; and thirdly, the utility model discloses easy dismounting, the storage transportation of being convenient for reaches used repeatedly, reduce cost's purpose.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a top view of fig. 1.
Fig. 3 is a left side view of fig. 1.
Detailed Description
The following describes embodiments of the present invention in detail with reference to the accompanying drawings, and the embodiments of the present invention are implemented on the premise of the technical solution of the present invention, and detailed embodiments and specific working procedures are given, but the scope of the present invention is not limited to the following embodiments.
Quick construction gabion's tank tower device, by shaping portion, hoist and mount fixed part and connect the fixed part and constitute.
As shown in fig. 1-3, the forming part is a U-shaped structure formed by connecting three steel formworks 1, the steel formworks 1 are placed on the construction ground, and the U-shaped open end and the hard end face are opposite to form a filling cavity with an upper opening structure, which is used for installing a steel wire mesh and filling stones inwards. The hard end face refers to the mounting vertical face where the gabion is located or the side face of the gabion which is manufactured. In order to fix the steel wire mesh, a plurality of hooks 101 used for connecting the steel wire mesh are welded at the top of the inner side surface of the steel template 1. In order to prevent the steel form 1 from being deformed when the stone is loaded, reinforcing ribs 102 are welded to the outer side surface of the steel form 1.
The connection fixing part comprises a first connecting piece and a second connecting piece. The first connecting pieces are provided with a plurality of groups, each group of first connecting pieces comprises horizontal rings 201 which are respectively welded at the end parts of the side surfaces of two adjacent steel templates 1, and L-shaped inserting rods 202 which are arranged in the two horizontal rings 201 in a penetrating manner and are used for connecting the two steel templates 1; the second connector is a vertical ring 301 (usually a U-shaped ring) welded on top of two parallel steel form 1, and its top is provided with a puller bolt 302.
The hoisting fixing part is positioned on the top surface of the forming part and is two steel pipes 401 arranged in parallel, two ends of each steel pipe 401 are respectively welded with a limiting block 402, and the distance between the limiting blocks 402 is matched with the distance between the parallel steel templates 1.
When the gabion is manufactured on site, three steel templates 1 are placed on the construction ground and are sequentially connected through a first connecting piece to form a U-shaped opening structure, and the opening end of the U-shaped opening structure is in contact with the installation vertical surface where the gabion is located or the side surface of the gabion which is manufactured to form a filling cavity; then, placing the steel wire mesh in the steel formwork, and hanging the steel wire mesh on a hook 101 on the inner side surface of the steel formwork 1 for fixing; then, the steel pipe 401 is arranged in the vertical ring 301 at the top of the parallel steel templates 1 in a penetrating manner, after the steel pipe reaches a proper position, the tightening bolt 302 is screwed to fix the steel pipe 401, at the moment, the two limiting blocks 402 at the bottom of the steel pipe 401 are respectively positioned at two sides of the parallel steel templates 1, and the inner surfaces of the limiting blocks 402 are in contact with the outer surfaces of the parallel steel templates 1 to limit the two parallel steel templates 1 and prevent the parallel steel templates 1 from displacing; and then, filling stones into the steel wire mesh through manpower or a lifting appliance, and covering a top cover of the steel wire mesh after filling to form a complete gabion. And then, connecting the steel pipe 401 with a crane, transferring to the next manufacturing position, and repeating the steps to complete the manufacturing of the next gabion.
It should be noted that in the description of the present invention, terms of orientation or positional relationship such as "front", "rear", "left", "right", "vertical", "horizontal", "inner", "outer", etc., are based on the orientation or positional relationship shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.

Claims (6)

1. The utility model provides a box frame device of quick construction gabion, its characterized in that: comprises that
The forming part is composed of three steel templates which are connected into a U-shaped structure, the steel templates are placed on the construction ground, and the U-shaped opening end and the hard end face are opposite to form a filling cavity with an upper opening structure;
the hoisting fixing part is positioned on the top surface of the forming part and is a steel pipe arranged between two parallel steel templates, and a limiting block positioned on the outer side of each steel template is arranged on each steel pipe;
a connection fixing part is provided with
The first connecting pieces are provided with a plurality of groups, each group of first connecting pieces comprises horizontal rings which are respectively arranged at the end parts of the side surfaces of two adjacent steel templates, and L-shaped inserting rods which are arranged in the horizontal rings in a penetrating manner and are used for connecting the two steel templates;
the second connecting piece is a vertical ring arranged at the tops of the two parallel steel templates and used for connecting the steel pipes, and a jacking bolt is arranged at the top of the vertical ring.
2. The box frame device for rapidly constructing the gabion according to claim 1, wherein: and a hook used for connecting a steel wire mesh is arranged at the top of the inner side surface of the steel template.
3. The box frame device for rapidly constructing the gabion according to claim 1, wherein: and reinforcing ribs are arranged on the outer side surface of the steel template.
4. The box frame device for rapidly constructing the gabion according to claim 1, wherein: the two steel pipes are arranged in parallel.
5. The box frame device for rapidly constructing the gabion according to claim 1, wherein: the spacing of the limiting blocks is matched with the spacing of the parallel steel templates.
6. The box frame device for rapidly constructing the gabion according to claim 1, wherein: the vertical ring is a U-shaped ring.
CN202123119587.2U 2021-12-13 2021-12-13 Box frame device for quickly constructing gabion Active CN216475107U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202123119587.2U CN216475107U (en) 2021-12-13 2021-12-13 Box frame device for quickly constructing gabion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202123119587.2U CN216475107U (en) 2021-12-13 2021-12-13 Box frame device for quickly constructing gabion

Publications (1)

Publication Number Publication Date
CN216475107U true CN216475107U (en) 2022-05-10

Family

ID=81421511

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202123119587.2U Active CN216475107U (en) 2021-12-13 2021-12-13 Box frame device for quickly constructing gabion

Country Status (1)

Country Link
CN (1) CN216475107U (en)

Similar Documents

Publication Publication Date Title
CN207160585U (en) Superelevation outer wall of basement Bailey bracket single side formwork architecture
CN103510469B (en) Construction method for manufacturing thin-walled hollow pier
CN216475107U (en) Box frame device for quickly constructing gabion
CN114575589A (en) Construction method for lifting template of electric hoist of steel reinforced concrete structural column
CN106884664B (en) Tunnel inverted arch template and tunnel inverted arch filling rapid construction method
CN112227399A (en) Template mounting and dismounting device of large cup-shaped foundation and template supporting and dismounting method
CN201914835U (en) Vertical transportation cradle
CN218757635U (en) High antidetonation type building foundation
CN214219654U (en) Pipe pole reverse-pulling device
CN214143777U (en) Template mounting and dismounting device for large cup-shaped foundation
CN214692858U (en) Floor transportation frock
CN202416347U (en) Foundation structure for tower crane
CN212245889U (en) Integral aerated brick stack hoisting device
CN109778806B (en) Construction method for integrally sliding and lifting pier wall with connecting beam
CN211948447U (en) Foundation pit supporting device
CN109231003B (en) Method for shifting and mounting dust remover
CN102020197A (en) Vertical transportation hanger
CN204282920U (en) A kind of communication tower being furnished with spliced pedestal
CN204456164U (en) A kind of spliced pedestal of communication tower
CN115182391B (en) Construction method of anti-scour interlocking block mollusk for large-diameter single pile
TWI835533B (en) The root-type column structure of the basement structure and its assembly method
CN214698303U (en) Simple support of suction pump
CN204112827U (en) A kind of communications tower
CN210797580U (en) Large-scale round foundation ditch interior lining wall construction system
CN221500319U (en) Combined material lifting basket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant