CN216429086U - Connection structure of overhanging type discharging platform and steel column - Google Patents

Connection structure of overhanging type discharging platform and steel column Download PDF

Info

Publication number
CN216429086U
CN216429086U CN202122878259.4U CN202122878259U CN216429086U CN 216429086 U CN216429086 U CN 216429086U CN 202122878259 U CN202122878259 U CN 202122878259U CN 216429086 U CN216429086 U CN 216429086U
Authority
CN
China
Prior art keywords
steel column
platform
shaped steel
column
unloading
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122878259.4U
Other languages
Chinese (zh)
Inventor
管聪聪
郭奇
陶宇
姚彪
袁江涛
李超
侯双明
赵飞扬
沈晨旸
郁宁智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd, Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202122878259.4U priority Critical patent/CN216429086U/en
Application granted granted Critical
Publication of CN216429086U publication Critical patent/CN216429086U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a connection structure of formula of encorbelmenting platform of unloading and shaped steel column, including the shaped steel column, coupling nut and stiffening plate weld in shaped steel column surface, and the screw rod passes through coupling nut to be fixed on the shaped steel column, and the connecting plate passes screw rod cooperation nut and fixes it on the shaped steel column, and above-mentioned part has constituted a complete tie point, and U type pull ring is connected behind the rope and is unloaded the platform with the formula of encorbelmenting and link to each other. The utility model discloses for the current platform steel wire drawknot stress point of unloading of encorbelmenting state on acting on the structure roof beam, improved the security of the platform of unloading of encorbelmenting. And through adjusting the position of connecting plate at the screw rod, avoid shaped steel column concreting around, the secondary of above-mentioned tie point is pre-buried and the secondary conversion, improves work efficiency, reduces construction cost.

Description

Connection structure of overhanging type discharging platform and steel column
Technical Field
The utility model relates to a super high-rise building construction correlation technique field specifically is platform wire rope and shaped steel column connection structure of unloading encorbelmenting.
Background
The unloading platform is an operation platform and an operation frame which are temporarily built, is hoisted to an upper floor by means of vertical transportation equipment such as a tower crane and the like, and is mainly applied to material turnover. With the rapid development of the building engineering industry, the number of super high-rise buildings is continuously increased, the corresponding problem of the turnover of building materials becomes more important, and in the super high-rise buildings, a section steel cantilever unloading platform is a transportation platform which is relatively common in application and is applied to material transfer between floors or between floors and the ground. The traditional connection mode of the profile steel overhanging type discharging platform and the upper structure (a structural beam or a structural wall) mostly adopts pre-embedded U-shaped round steel pull rings, and the safety and the stability of the platform are ensured by the connection mode of a steel wire rope and the embedded part of the upper structure. The dead weight and the final stress of the stacked load are concentrated on the steel wire rope, and whether the connection between the steel wire rope and the structure is reliable and firm or not is concerned about the use safety of the discharging platform. If the hoisting ring is in a pre-treatment form and can only be arranged on the surface of the upper floor, the inclination angle of the unloading steel wire rope is possibly too large, and the unloading effect is influenced; if the hanging ring is fixed at the bottom of the steel beam in a welding mode, welding needs to be performed on the steel beam, and the stress effect of the steel beam is influenced to a certain extent; in addition, superstructure's boundary beam is mostly H shaped steel, and the formula of encorbelmenting platform of unloading is connected with the girder steel mostly, because the super high-rise building material of present stage is heavy objects such as reinforcing bar, steel pipe mostly, and transportation weight is big, and is also big to the atress of girder steel, probably leads to the girder steel to be bent the increase, produces adverse effect to super high-rise structure. The patent number is CN 201921013091.7's utility model discloses an anchor that is used for shaped steel formula of encorbelmenting platform wire rope of unloading, including upper structure floor and lower structure floor, the fixed platform of unloading that is equipped with in lower structure floor top, the upper and lower both sides of upper structure floor lateral wall are equipped with the through-hole respectively, be equipped with in the through-hole with through-hole matched with PVC casing coupling, two PVC casing coupling fit-in pegs graft and is equipped with the U-shaped round steel, the inboard of upper structure floor lateral wall is stretched out to U-shaped round steel straight flange, the U-shaped round steel straight flange stretches out the end and is helicitic texture, and the cooperation is equipped with the nut, the dog-ear of U-shaped round steel and the platform of unloading are connected and are equipped with wire rope. However, the PVC sleeve is embedded in the surface of the upper floor, and when the device is used, a split screw which is processed, manufactured and formed and can be pulled needs to be inserted into the PVC reserved pipe, so that the problem that the inclination angle of the unloading steel wire rope is overlarge exists. The utility model with the patent number of CN201420198177.2 discloses a novel overhanging discharging platform drawknot device, which comprises a hanging ring, a steel wire rope and a cross beam, wherein the length of the cross beam is longer than the width of a reserved door and window opening of a building, the cross beam is transversely arranged at the inner side of the reserved door and window opening, and two ends of the cross beam are close to a vertical structural column or a shear wall of the building; the lifting ring is welded on the cross beam, one end of the steel wire rope is connected with the discharging platform, and the other end of the steel wire rope is connected with the lifting ring through a detachable steel wire rope clamping head to form counter-pulling. The beam is installed before use and removed after use, can be used for multiple times and can be recycled, but brings inconvenience to operators.
Based on the above description, a need exists for a new connection mode of an overhanging type discharging platform and a connecting piece, so as to solve the problem that the stress of a steel beam is large and the steel beam is easy to bend to cause unstable structure and generate adverse effect on the structure due to the fact that the overhanging type discharging platform is connected to the steel beam in a super high-rise building.
SUMMERY OF THE UTILITY MODEL
In order to overcome the not enough of prior art, the utility model aims at providing a connection structure of formula of encorbelmenting platform of unloading and shaped steel post has avoided the platform of unloading that leads to with the girder steel connection to bear the great deformation influence that produces the girder steel, has guaranteed the holistic security of structure.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a formula of encorbelmenting platform of unloading and connection structure of shaped steel post, includes the shaped steel post, and coupling nut and stiffening plate welding back together are together welded on the shaped steel post, and the screw rod is connected in coupling nut, and the connecting plate is used for connecting U type pull ring, and the connecting plate is fixed on the screw rod, and above-mentioned part has constituted a complete tie point, and U type pull ring is connected behind the rope and is continuous with the formula of encorbelmenting platform of unloading.
According to the connection structure of the overhanging type discharging platform and the section steel column, the stiffening plates are welded around the connecting nut in a cross manner.
According to the connection structure of the overhanging type discharging platform and the section steel column, the stiffening plate is in a right-angled triangle shape, and the two right-angled edges are respectively welded on the connecting nut and the section steel column.
According to the connection structure of the overhanging type discharging platform and the section steel column, each section steel column is provided with at least two connection points which are arranged from top to bottom.
According to the connection structure of the cantilever type discharging platform and the section steel column, before concrete is poured, the connection plate is fixed to the outer side of the section steel column; when the column is used for formwork support, the connecting plate is fixed on the outer side of the wood formwork, and after concrete is poured, the connecting plate is fixed on the outer surface of the concrete.
Has the advantages that: compared with the prior art, the utility model, have following advantage:
(1) the utility model discloses the connection structure of formula of encorbelmenting platform of unloading and shaped steel post, screw rod 4 are connected to the shaped steel post through coupling nut 3, fix the connecting plate on screw rod 4 with the help of two nuts, and paste tightly with the concrete surface, and after the rope was connected to U type pull ring 7, it linked to each other with the platform of unloading to pass the connecting plate. Double nuts, connecting plates and U-shaped pull rings can be disassembled and then recycled, and the cost is reduced.
(2) This shaped steel column structure, before concrete placement, when formwork, can all be used to the anchor formula of encorbelmenting platform of unloading, increased application scenario, do not receive the restriction of construction progress.
(3) Different from the mode that traditional shaped steel overhanging type platform of unloading connected in the roof beam, cause the damage to the roof beam even whole structure, the utility model discloses furthest's increase overall structure's safety and stability.
(4) The position of the connecting plate (5) on the screw (4) can be adjusted by adjusting the double nuts (6) to adapt to the influences of the support of the section steel column template and the pouring of concrete.
Drawings
FIG. 1 is an assembly view of the connection structure of the overhanging type discharging platform and the section steel column of the utility model before concrete pouring;
FIG. 2 is a top view of FIG. 1;
fig. 3 is an assembly view of the cantilever type unloading platform superstructure provided by the utility model after concrete pouring;
FIG. 4 is a top view of FIG. 3;
fig. 5 is a right side view of fig. 3.
Description of the reference numerals in the figures: the steel-reinforced concrete steel column comprises section steel columns-1, stiffening plates-2, connecting nuts-3, screws-4, connecting plates-5, double nuts-6, U-shaped pull rings-7 and concrete-9.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings in the embodiments of the present invention. The information of the size, the model specification, the section, the material and the like of the component related to the following embodiment is determined by calculation according to the load condition, and different items are determined according to the actual conditions of the different items.
Example 1
Fig. 1 is the utility model discloses the connection structure of overhanging type platform of unloading and shaped steel post assembly drawing, fig. 2 are the top view of fig. 1, fig. 3 is before concrete placement the utility model provides an assembly drawing, fig. 4 are the top view of fig. 3, fig. 5 is the right side view of fig. 3 after overhanging type platform superstructure's concrete placement.
As shown in fig. 1-5, the connection structure of the overhanging type discharging platform and the section steel column comprises a section steel column 1, a connecting nut 3 and a stiffening plate 2 are welded together and then welded on the section steel column 1, a screw 4 is connected on the connecting nut 3, a connecting plate 5 is used for connecting a U-shaped pull ring 7, and a double nut 6 fixes the connecting plate 5 on the screw 4, so as to form a complete connection point.
Before concrete pouring, four stiffening plates 2 are welded around a connecting nut 3 in a cross shape, as shown in fig. 5, the four stiffening plates are respectively welded on two section steel columns through measurement, a screw rod 4 is connected with the connecting nut 3, a connecting plate 5 is fixed on the outer sides of the section steel columns 1 through double nuts 6, and a U-shaped pull ring 7 is connected with a discharging platform after being connected with a rope. When the column formwork is erected, the connecting plate 5 is fixed on the outer side of the wood formwork through the double nuts 6, the formwork is reinforced, and the outer side can be connected with the U-shaped pull ring 7 and the rope. After the concrete is poured, the connecting plate is fixed on the outer surface of the concrete and is tightly attached.
In this embodiment, each section steel column needs to have at least two connecting points distributed on the upper side and the lower side. The distance can be obtained according to actual conditions and calculation, and the specific conditions can be slightly adjusted according to engineering practice.
In this embodiment, the stiffening plate 2 reinforces the connection of the connecting nut 3 and the section steel column 1. The stiffening plate needs to be in the shape of a right triangle, and right-angle sides are welded on the connecting nut and the section steel column respectively, so that the stress area is increased, and the stability is improved.
The above description is only a preferred example of the present invention and is not intended to limit the present invention, and for those skilled in the art, many variations may be made in the present invention according to the actual situation, and any modifications, equivalent substitutions, improvements and variations within the principle and spirit of the present invention are all within the protection scope of the present invention.

Claims (5)

1. The utility model provides a connection structure of formula of encorbelmenting platform of unloading and shaped steel column, including shaped steel column (1), a serial communication port, coupling nut (3) and stiffening plate (2) welding back together, together weld on shaped steel column (1), screw rod (4) are connected in coupling nut (3), connecting plate (5) are used for connecting U type pull ring (7), connecting plate (5) are fixed on screw rod (4), a complete tie point has been constituted, U type pull ring (7) are connected behind the rope and are encorbelmented the platform of unloading and link to each other.
2. The structure for connecting an overhanging type discharging platform and a steel-section column as claimed in claim 1, wherein the stiffening plates (2) are welded around the connecting nut (3) in a cross shape.
3. The connecting structure of the overhanging type discharging platform and the section steel column as claimed in claim 2, wherein the stiffening plate is in a right triangle shape, and two right-angle sides are respectively welded on the connecting nut and the section steel column.
4. The connecting structure of the overhanging type discharging platform and the steel section column as claimed in claim 1, wherein each steel section column is provided with at least two connecting points which are arranged up and down.
5. The connecting structure of the overhanging type discharging platform and the section steel column as claimed in claim 1, wherein the connecting plate (5) is fixed on the outer side of the section steel column (1) before concrete pouring; when the column is used for formwork support, the connecting plate (5) is fixed on the outer side of the wood formwork, and after concrete is poured, the connecting plate (5) is fixed on the outer surface of the concrete.
CN202122878259.4U 2021-11-23 2021-11-23 Connection structure of overhanging type discharging platform and steel column Active CN216429086U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122878259.4U CN216429086U (en) 2021-11-23 2021-11-23 Connection structure of overhanging type discharging platform and steel column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122878259.4U CN216429086U (en) 2021-11-23 2021-11-23 Connection structure of overhanging type discharging platform and steel column

Publications (1)

Publication Number Publication Date
CN216429086U true CN216429086U (en) 2022-05-03

Family

ID=81338153

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122878259.4U Active CN216429086U (en) 2021-11-23 2021-11-23 Connection structure of overhanging type discharging platform and steel column

Country Status (1)

Country Link
CN (1) CN216429086U (en)

Similar Documents

Publication Publication Date Title
CN111472530A (en) Flower basket pull rod I-shaped steel cantilever bearing frame for constructional engineering and mounting method thereof
CN207268073U (en) Novel flexible formwork bearing frame
CN113279582A (en) Hanging construction method for overhanging and hanging type cast-in-place plate
CN111648585A (en) Construction method and device of suspended support type steel truss platform
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN212336672U (en) I-steel overhanging bearing frame of basket pull rod for constructional engineering
CN216429086U (en) Connection structure of overhanging type discharging platform and steel column
CN210976552U (en) Foldable operation platform device in elevator shaft
CN215564318U (en) Rigid pull rod large-cantilever scaffold platform structure
CN215055324U (en) High-rise structure construction device
CN105370027A (en) Construction method for integrally lifted and supported steel platform structure in high-rise suspended structure
CN214996139U (en) Safe operation platform for overhead large-span steel reinforced concrete beam suspension formwork construction
CN210340110U (en) Two T board hoisting structure of large-span assembled
CN213774763U (en) Reinforced structure of air film building
CN212101770U (en) Double-rail device convenient to install and detach quickly and used for hoisting curtain wall unit plate
CN211646957U (en) Assembled house ground reinforcing plate structure
CN209228053U (en) Large cantilever combined type anchor curable type steel operation platform
CN111622347A (en) Cross-shaped node connecting structure of assembled frame structure and construction method thereof
CN219794710U (en) Cantilever type unloading platform
CN220319075U (en) Guy rope hanging basket assembling platform
CN205369874U (en) Elevartor shaft outer wall cantilever frame
CN216305342U (en) Suspension cage for installing external climbing tower crane oblique beam
CN216475048U (en) Novel steel reinforcement cage hanging system
CN219587239U (en) Attached scaffold unloading platform
CN213569101U (en) Auxiliary lifting appliance for reinforcement cage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant