CN216406816U - Ultra-close underground tunnel penetrating through bottom plate of existing building - Google Patents

Ultra-close underground tunnel penetrating through bottom plate of existing building Download PDF

Info

Publication number
CN216406816U
CN216406816U CN202122636009.XU CN202122636009U CN216406816U CN 216406816 U CN216406816 U CN 216406816U CN 202122636009 U CN202122636009 U CN 202122636009U CN 216406816 U CN216406816 U CN 216406816U
Authority
CN
China
Prior art keywords
bottom plate
side wall
layer
primary support
waterproof layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122636009.XU
Other languages
Chinese (zh)
Inventor
张仙义
李名淦
刘峰
陈若曦
王文魁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd, Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical China Energy Engineering Group Zhejiang Eleteric Power Design Institute Co ltd
Priority to CN202122636009.XU priority Critical patent/CN216406816U/en
Application granted granted Critical
Publication of CN216406816U publication Critical patent/CN216406816U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The underground excavation tunnel is characterized in that an underground excavation tunnel penetrating through an existing building bottom plate in an ultra-close mode comprises the existing building bottom plate, a raft, a waterproof layer and a protective layer from top to bottom, and grouting is conducted in the areas on the two sides of the underground excavation tunnel to reinforce the stratum; constructing a closed primary support structure in an underground excavation tunnel region, wherein the closed primary support structure is composed of an upper half primary support side wall, a lower half primary support side wall and a bottom plate, a plain concrete cushion layer of the existing building bottom plate is also reserved between the top of the upper half primary support side wall and a waterproof layer as well as a protective layer, and the plain concrete cushion layer is closely attached to the lower surfaces of the waterproof layer and the protective layer; arranging a new waterproof layer below the closely-adhered waterproof layer and the protective layer in the closed primary supporting structure; and constructing a side wall waterproof layer, a bottom plate waterproof and protective layer, closely attaching the side wall waterproof layer, the bottom plate waterproof and protective layer and a new top waterproof layer, and constructing a closed two-lining structure. The utility model does not damage the structure and the water resistance of the existing bottom plate, cancels the excavation of the primary supporting top plate and increases the height of the channel.

Description

Ultra-close underground tunnel penetrating through bottom plate of existing building
Technical Field
The utility model belongs to the technical field of underground engineering underground excavation, and relates to a structure and a method for safely penetrating an existing building by a mine method. In particular to an ultra-close underground tunnel penetrating through a bottom plate of an existing building.
Background
The existing underground tunnel underpass building structure can be divided into a short distance underpass and a close contact underpass according to the vertical distance between the underground tunnel underpass building structure and is shown in figures 1 and 2. Wherein the short-distance downward-penetrating scheme means that a vertical distance (H) exists between the primary support of the underground excavated tunnel and a bottom plate of the building structure, and the distance is less than or equal to the hair span (L) of the underground excavated tunnel; the close-fitting underpass scheme H is 0, but a primary top plate (the thickness is generally 250-350 mm) still exists between the secondary lining of the underground excavation channel and the bottom plate of the existing building. When H is larger than the undercut L, it will bring a large adverse effect to the tunnel function, and it is also uneconomical and often not worth recommending. The short-distance downward-penetrating scheme needs to reinforce the soil body in advance, so that investment and construction period are increased, and force transmission paths between structures are not clear during construction and use. The scheme of closely wearing is more favorable to saving investment and controlling risks. So that the current close-fitting underpass scheme is more and more popular.
The close-fitting underpass scheme also has the defects that: the existence of the primary support top plate of the underground excavated tunnel can extrude the height of the channel, and the permanent use function of the channel is influenced. The role of the primary support roof of the underground excavation tunnel can be roughly summarized into two parts: the first part is soil retaining; the second part forms closed frame structure together with the tunnel other parts that first prop up, guarantees that the atress is stable. Under the condition of close contact and penetration, the first part of functions can be replaced by the bottom plate of the existing building structure, and the second part of functions can be solved by planting ribs or arranging expansion bolts in the existing bottom plate through the primary support side wall of the tunnel (see figure 3 in detail). However, this solution can adversely affect the existing structure and destroy its water-resistance.
Aiming at the defects of a closely-adhered underpass scheme, a underpass underground tunnel construction method is needed to be improved, a technology for canceling an underground excavation primary supporting top plate is urgently needed to be invented, the height of a channel is increased on the premise of not damaging the existing bottom plate structure or preventing water, the sudden change and the transition length of a longitudinal linear type of the channel at an underpass node are reduced, the permanent use function of the channel is better ensured, and the investment is saved.
SUMMERY OF THE UTILITY MODEL
The utility model provides an ultra-close under-penetrating underground tunnel with an existing building bottom plate, and aims to cancel an initial support top plate of the underground tunnel in a close under-penetrating scheme, increase the height of a channel on the premise of not damaging the existing bottom plate structure or preventing water, reduce sudden change and transition length of a longitudinal linear type of the channel at an under-penetrating node, better ensure the permanent use function of the channel and save investment.
The technical scheme of the utility model is as follows:
an underground tunnel with an ultra-close bottom penetrating existing building bottom plate comprises the existing building bottom plate, wherein the bottom plate comprises a raft plate 11, a waterproof layer and a protective layer 12 from top to bottom, and grouting is arranged in the two side areas of the underground tunnel to reinforce the stratum; arranging a closed primary support structure in an underground excavation tunnel region, wherein the closed primary support structure is composed of an upper half primary support side wall 3, a lower half primary support side wall and a bottom plate 5 of the underground excavation tunnel, a plain concrete cushion layer 13 of an existing building bottom plate 1 is also reserved between the top of the upper half primary support side wall 3 and the waterproof layer and the protective layer 12, and the plain concrete cushion layer 13 is closely attached to the lower surfaces of the waterproof layer and the protective layer 12; a new waterproof layer is arranged in the closed primary supporting structure and closely attached to the lower side of the waterproof layer and the protective layer 12; arranging a side wall waterproof layer and a bottom plate waterproof and protective layer 10 in the closed primary support structure, closely attaching the side wall waterproof layer and the bottom plate waterproof and protective layer 10, and arranging a closed secondary lining structure which comprises a secondary lining top plate 8, a secondary lining side wall 7 and a secondary lining bottom plate 6, wherein the secondary lining top plate 8 clamps a waterproof layer and a protective layer 12, and a new waterproof layer is closely attached to the raft; and arranging a grouting layer behind the two lining structures to form the undercut tunnel.
The ultra-close underground tunnel penetrating through the bottom plate of the existing building is characterized in that the side wall 3 is supported in the first half primary stage, and the foot part is provided with a foot locking anchor pipe 32.
The ultra-close underground tunnel penetrating through the bottom plate of the existing building is characterized in that side wall grid steel frames 31 are arranged in the upper half primary support side wall 3 and the lower half primary support side wall.
The ultra-close underground tunnel penetrating through the bottom plate of the existing building is characterized in that construction joints 9 among the two top lining plates 8, the two side lining walls 7 and the two bottom lining plates 6 are all arranged on the two side lining walls 7.
Effect of the utility model
The scheme of the utility model for penetrating the existing building bottom plate under the ultra-close underground excavation is equivalent to the scheme of penetrating the existing building bottom plate under the close underground excavation in safety, the structure and the water resistance of the existing bottom plate are not damaged, the height of a channel is increased, the use function of the channel is improved and the construction cost is reduced by canceling the primary supporting top plate of the underground excavation.
Description of the drawings:
figure 1 is a schematic structural view of a close-distance underpassing scheme in the prior art,
figure 2 is a schematic view of a prior art snuggly-fit underpassing scheme,
FIG. 3 is a schematic view of a close-fit bottom-through scheme and the connection of a primary support and an existing bottom plate through an expansion bolt in the prior art,
figure 4 is a schematic view of the step 1 grouting to consolidate the stratum according to the utility model,
FIG. 5 is a schematic view of the step 2 of excavating the upper half section II and constructing the upper half primary support sidewall 3,
FIG. 6 is a schematic view of the connection structure of the construction I-steel with the existing bottom plate and the side wall grid,
FIG. 7 is a schematic structural view of the lower half section IV excavated by step 3, the lower half primary support side wall and the bottom plate 5 are constructed,
FIG. 8 is a schematic view showing the steps of laying a waterproof layer 4 and constructing two substrate plates 6 according to the present invention,
FIG. 9 is a schematic view showing the steps of laying a waterproof layer and constructing a secondary lining side wall 7 according to the present invention,
fig. 10 is a schematic structural diagram of the present invention, and is a schematic structural diagram of the step 6 of laying a waterproof layer and constructing a secondary roof lining plate 8.
Description of the figure numbering:
the construction method comprises the steps of constructing a bottom plate 1 of a building, a raft plate 11, a waterproof layer and a protective layer 12, a plain concrete cushion layer 13, an underground excavated tunnel 2, a small advanced guide pipe 21, an upper half primary support side wall 3, a side wall grid steel frame 31, a side wall grid steel frame main rib 311, a foot locking anchor pipe 32, I-shaped steel 4, a longitudinal connecting rib 41, L-shaped steel 42, an additional steel plate 43, an anchor rib 44, a welding steel bar 45, a lower half primary support side wall and bottom plate 5, two bottom plate 6, two lining side walls 7, two lining top plates 8, a construction joint 9, a waterproof protective layer 10 (the waterproof protective layer material of the tunnel is C20 fine stone concrete), and connecting an expansion bolt and an arch frame 101 in the prior art.
Detailed Description
The following detailed description of embodiments of the utility model refers to the accompanying drawings.
Referring to fig. 4-10, a construction method of an ultra-close underground tunnel penetrating through an existing building bottom plate comprises the existing building bottom plate, the existing building bottom plate 1 sequentially comprises a raft 11, a waterproof layer and a protective layer 12, and a plain concrete cushion layer 13 from top to bottom, and construction is performed under the plain concrete cushion layer according to the following steps:
(1) referring to fig. 4, constructing small advanced ducts 21 in the areas on two sides of the underground tunnel 2, and grouting to reinforce the strata in the areas on two sides;
(2) referring to fig. 5, reserving core soil, excavating an upper half section II of the tunnel, constructing an upper half primary support side wall 3, arranging foot locking anchor pipes 32 at feet, reserving a plain concrete cushion layer 13 below the raft at an arch part, and erecting a plurality of transverse I-shaped steels 4 at intervals in time along the longitudinal direction of the tunnel below the plain concrete cushion layer 13; the I-steel with plain concrete bed course is close-fitting, for in time forming the support to plain concrete bed course, reduces existing bottom plate and warp, needs to do as follows to I-steel and the side wall grid steelframe 31 connected node in the preliminary bracing: as shown in reference to figure 6 of the drawings,
firstly, sealing the side wall grid steel frame 31 by adopting L-shaped angle steel 42; a side wall grid steel frame is arranged at the lower part of the plain concrete cushion layer 13; the I-shaped steel is transversely arranged between the side wall grid steel frames on the two sides; the L-shaped angle steel 42 is welded with the main rib 311T of the side wall grid steel frame;
two ends of the I-shaped steel 4 are connected with the L-shaped steel 42 through an additional steel plate 43 which is vertically arranged;
aligning and closely attaching the top surfaces of the I-shaped steel and the additional steel plate, the additional steel plate and the top surface of the L-shaped steel to the plain concrete cushion layer, wherein the bottom of the additional steel plate exceeds the bottom of the I-shaped steel, the additional steel plate is connected with the L-shaped steel in a surrounding welding mode on three sides, and the I-shaped steel and the additional steel plate are connected together in a surrounding welding mode on three sides;
welding a plurality of longitudinal connecting ribs 41 with the horizontal spacing not more than 500mm on one side of the lower part of the I-steel, and integrally connecting the bottoms of the I-steels;
(3) referring to fig. 7, excavating a lower half section IV of the tunnel; constructing the lower half primary support side wall and the bottom plate 5 to form an integrally closed primary support of the underground tunnel;
(4) referring to fig. 8, after a bottom plate waterproof and protective layer 10 is laid in the primary support, a tunnel secondary lining bottom plate 6 is constructed;
(5) referring to fig. 9, constructing waterproof side walls and a second lining side wall 7 on a second backing plate to a construction joint position below a second lining top plate in a primary support, after the second lining side wall reaches the design strength, tightly jacking the second lining side wall without disassembling a full scaffold, and disassembling arch crown I-shaped steel 4 and a plain concrete cushion layer 13 below a raft plate in the primary support in sections according to the monitoring condition, wherein the disassembly length of each section is not more than 7 m;
(6) referring to fig. 10, a new waterproof layer is laid under the waterproof layer and the protective layer 12 under the raft, a second liner top plate 8 is constructed to be closely attached to the new waterproof layer under the raft, the second liner top plate 8, a second liner side wall 7 and a second liner plate 6 are integrally connected to form an integral second liner structure, grouting is performed on the back of the second liner structure, and finally the underground excavation tunnel structure is constructed.
According to the construction method for the ultra-close underground excavation tunnel penetrating through the existing building bottom plate, when the L-shaped angle steel 42 is welded with the side wall grid steel frame main rib 311T type, the height of a welding seam is not smaller than 6mm, and the height of the welding seam is not larger than 0.6d (d is the diameter of the grid steel frame main rib); when the additional steel plate is connected with the L-shaped angle steel in a three-surface welding way and the I-shaped steel is connected with the additional steel plate in a three-surface welding way, the size of the fillet weld leg of the fillet weld is not less than 1.5t1/2And must not be greater than t- (1-2 mm) (t is the smaller value of the thickness of the steel plate connected by welding, "-" is minus);
referring to fig. 10, the ultra-close underground tunnel penetrating through the existing building bottom plate comprises the existing building bottom plate, the existing building bottom plate comprises a raft 11, a waterproof layer and a protective layer 12 from top to bottom, and grouting is arranged in the two side areas of the underground tunnel to reinforce the ground layer; arranging a closed primary support structure in an underground excavation tunnel region, wherein the closed primary support structure is composed of an upper half primary support side wall 3, a lower half primary support side wall and a bottom plate 5 of the underground excavation tunnel, a plain concrete cushion layer 13 of an existing building bottom plate 1 is also reserved between the top of the upper half primary support side wall 3 and the waterproof layer and the protective layer 12, and the plain concrete cushion layer 13 is closely attached to the lower surfaces of the waterproof layer and the protective layer 12; a new waterproof layer is arranged in the closed primary supporting structure and closely attached to the lower side of the waterproof layer and the protective layer 12; arranging a side wall waterproof layer and a bottom plate waterproof and protective layer 10 in the closed primary support structure, closely attaching the side wall waterproof layer, the bottom plate waterproof and protective layer 10 and the new waterproof layer at the top, and arranging a closed secondary lining structure which comprises a secondary lining top plate 8, a secondary lining side wall 7 and a secondary lining bottom plate 6, wherein the secondary lining top plate 8 clamps the waterproof layer and the protective layer 12 and the new waterproof layer and is in double-layer waterproof close attachment with the raft; and arranging a grouting layer behind the two lining structures to form the undercut tunnel.
The ultra-close underground tunnel penetrating through the bottom plate of the existing building structure is characterized in that the side wall 3 is supported in the first half primary stage, and the foot part is provided with a foot locking anchor pipe 32.
The ultra-close underground tunnel with the bottom plate of the existing building under the construction is characterized in that side wall grid steel frames 31 are arranged in the upper half primary support side wall 3 and the lower half primary support side wall.
The ultra-close underground tunnel with the bottom plate of the existing building under the construction is characterized in that construction joints 9 among the two top lining plates 8, the two side lining walls 7 and the two bottom lining plates 6 are all arranged on the two side lining walls 7.
The principle of the ultra-dense-paste underground excavation downward penetration method is as follows: the I-shaped steel is used for replacing a traditional primary support top plate when the tunnel is excavated, the existing bottom plate is supported in time, and a closed frame structure is formed with other parts of the primary support of the tunnel, so that the stable stress is ensured; when the second lining is applied, the stress conversion is carried out, the I-shaped steel of the arch part is removed, and the top plates of the second lining are directly attached to the existing bottom plate in a close fit manner, so that the height of the channel is increased.
Examples
The method is characterized in that a certain project 3# and 4# channel vertical shaft, an underground excavation structure and a waterproof project are constructed in a test mode, wherein the length of an underground excavation section of a 4# channel under a bottom plate of a stadium is about 23 meters, and a primary supporting top plate is not allowed to be arranged between a secondary lining top plate and the bottom plate of the stadium due to the limited clear height of the channel. Monitoring and displaying that each index is in a required range.
In the following, the step method construction of the underground excavation channel is taken as an example (the other underground excavation methods can be executed by reference), and the specific steps and the key node method are briefly described as follows (the other construction details are the same as those in the above specific embodiment and are not described again): as shown in fig. 4-10;
(1) constructing small advanced guide pipes in the areas on two sides of the underground excavation tunnel 2, and grouting to reinforce the stratum; with reference to figure 4 of the drawings,
(2) reserving core soil, excavating an upper half section II, constructing an upper half primary support side wall 3, arranging locking anchor pipes at feet, reserving an original raft lower cushion layer at an arch part, and erecting I-shaped steel under the arch part in time; with reference to figure 5 of the drawings,
in order to ensure that the I-shaped steel is closely attached to the cushion layer of the existing bottom plate and form support in time, the deformation of the existing bottom plate is reduced, and the following treatment needs to be carried out on the connection nodes of the I-shaped steel and the side wall grid steel frame:
firstly, sealing end of a side wall grid steel frame by adopting L-shaped angle steel, and arranging a side wall grid steel frame at the lower part of a plain concrete cushion layer 13; the L-shaped angle steel is welded with the T-shaped main rib of the side wall grid steel frame, the height of a welding seam is not less than 6mm, and is not less than 0.6d (d is the diameter of the main rib of the grid steel frame).
And two ends of the I-shaped steel are connected with the L-shaped angle steel through additional steel plates, the top surfaces of the I-shaped steel and the additional steel plates, the top surfaces of the additional steel plates and the L-shaped angle steel are aligned, and the other three side surfaces are connected in a surrounding welding mode. The size of fillet weld leg of the fillet weld is not less than 1.5t1/2And the thickness of the steel plate is not more than t-1-2 mm (t is the smaller value of the thickness of the connecting steel plate).
Thirdly, arranging longitudinal connecting ribs with horizontal spacing of 500mm on the single surface of the lower part of the I-steel, and integrally connecting the bottoms of all the I-steels.
(3) Excavating a lower half section IV, and constructing a lower half primary support side wall and a bottom plate 5 to form an integrally closed primary support of the underground tunnel;
(4) laying a waterproof layer, constructing a second substrate plate structure 6,
(5) laying a waterproof layer, constructing a second-lining side wall 7 to a construction joint below a second-lining top plate, jacking the side wall without disassembling a full scaffold after the side wall reaches the design strength, disassembling arch crown I-shaped steel and an original raft cushion layer in a primary support in sections according to the monitoring condition (the disassembly length of each section is not more than 7m),
(6) laying a waterproof layer, constructing a second liner plate 8 to form a second liner structure, grouting after two liners to finally form the undercut tunnel structure of the utility model, which is shown in figure 10, and comprises the steps that the second liner plate 8 is closely attached to the existing bottom plate and forms a closed tunnel structure with the lower side wall and the bottom plate.

Claims (4)

1. An underground excavation tunnel with an ultra-close bottom penetrating existing building bottom plate comprises the existing building bottom plate, wherein the existing building bottom plate comprises a raft plate (11), a waterproof layer and a protective layer (12) from top to bottom, and is characterized in that grouting is arranged in the two side areas of the underground excavation tunnel to reinforce the ground layer; arranging a closed primary support structure in an underground excavation tunnel region, wherein the closed primary support structure is composed of an upper half primary support side wall (3), a lower half primary support side wall and a bottom plate (5) of the underground excavation tunnel, a plain concrete cushion layer (13) of an existing building bottom plate (1) is reserved between the top of the upper half primary support side wall (3) and a waterproof layer and a protective layer (12), and the plain concrete cushion layer (13) is closely attached to the lower surfaces of the waterproof layer and the protective layer (12); a new waterproof layer is arranged in the closed primary supporting structure and closely attached to the lower side of the waterproof layer and the protective layer (12); arranging a side wall waterproof layer and a bottom plate waterproof and protective layer (10) in the closed primary support structure, closely attaching the side wall waterproof layer and the bottom plate waterproof and protective layer (10) and the new waterproof layer at the top, and arranging a closed secondary lining structure which comprises a secondary lining top plate (8), a secondary lining side wall (7) and a secondary lining plate (6), wherein the secondary lining top plate (8) clamps the waterproof layer and the protective layer (12) and the new waterproof layer and closely attaches the raft plate; and arranging a grouting layer behind the two lining structures to form the undercut tunnel.
2. An ultra-close underground tunnel penetrating through the bottom plate of the existing building structure according to claim 1, characterized in that the upper half primary support side wall (3) is provided with a foot locking anchor pipe (32) at the foot.
3. An ultra-close underground tunnel penetrating through the bottom plate of the existing building according to claim 1, characterized in that the side wall grid steel frames (31) are arranged in the upper half primary support side wall (3) and the lower half primary support side wall.
4. An ultra-close underground tunnel penetrating through the bottom plate of the existing building according to claim 1, characterized in that the construction joints (9) between the two roof-lining plates (8), the two side-lining walls (7) and the two bottom-lining plates (6) are all arranged on the two side-lining walls (7).
CN202122636009.XU 2021-10-29 2021-10-29 Ultra-close underground tunnel penetrating through bottom plate of existing building Active CN216406816U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122636009.XU CN216406816U (en) 2021-10-29 2021-10-29 Ultra-close underground tunnel penetrating through bottom plate of existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122636009.XU CN216406816U (en) 2021-10-29 2021-10-29 Ultra-close underground tunnel penetrating through bottom plate of existing building

Publications (1)

Publication Number Publication Date
CN216406816U true CN216406816U (en) 2022-04-29

Family

ID=81298570

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122636009.XU Active CN216406816U (en) 2021-10-29 2021-10-29 Ultra-close underground tunnel penetrating through bottom plate of existing building

Country Status (1)

Country Link
CN (1) CN216406816U (en)

Similar Documents

Publication Publication Date Title
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN110630283B (en) Three-layer supporting structure suitable for double-arch tunnel and construction method
CN102562075A (en) Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
CN104790974A (en) City subway overlapped shield tunnel segment structure adopting special longitudinal connecting pieces
CN102587924A (en) Construction method for shallow-buried high-water-content clayed soil tunnel
CN111365017B (en) Construction method of underground intercommunication tunnel
CN111828019B (en) Construction method for large-section special deformation joint based on earthquake fracture zone
CN214660232U (en) Corrugated plate connecting structure for tunnel toughness support
CN110939455A (en) Construction method of tunnel portal structure
CN108708736B (en) Shield cutter head manhole assembly type construction method
CN108708727B (en) Half-excavation rear-jacking shield cutter head manhole assembly type construction method
CN113931638A (en) Underground excavation tunnel structure with ultra-close bottom penetrating existing building bottom plate and construction method
CN216406816U (en) Ultra-close underground tunnel penetrating through bottom plate of existing building
CN112962694A (en) Underpinning construction method for bridge pile foundation in mine tunnel
CN112482435A (en) Underground excavation construction method for underground multi-cabin pipe gallery through building
CN112664203A (en) Reinforcing system for controlling deformation of shield tunnel by dredging river above shield tunnel and construction method
CN112065479B (en) Construction method of asymmetric multi-curve double-arch tunnel
CN216765900U (en) U-shaped combined structure for in-situ protection of high-voltage cable pipe
CN116220701B (en) Newly built tunnel and existing tunnel reconstruction and extension parallel construction method
CN215053220U (en) Structure system for zero-distance crossing stub subway station
CN217897906U (en) Local bracing type temporary supporting structure of pilot tunnel of non-center-guide multi-arch tunnel
CN111379576B (en) Method for connecting primary support and large-diameter pipe shed in shed cover construction
CN211598680U (en) Anti reinforced structure that floats of operation subway tunnel