CN216405147U - Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam - Google Patents

Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam Download PDF

Info

Publication number
CN216405147U
CN216405147U CN202121791509.4U CN202121791509U CN216405147U CN 216405147 U CN216405147 U CN 216405147U CN 202121791509 U CN202121791509 U CN 202121791509U CN 216405147 U CN216405147 U CN 216405147U
Authority
CN
China
Prior art keywords
temporary
construction
anchor
adjusting
adjusting device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121791509.4U
Other languages
Chinese (zh)
Inventor
单继安
姜平
杨晓海
许奇峰
游晓祥
何费
薛美萍
费汉兵
金平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Faersheng Road And Bridge Technology Co ltd
Jiangsu Fasten Steel Cable Co ltd
Jiangyin Fasten Sumiden New Material Co ltd
Fasten Group Co Ltd
Original Assignee
Jiangsu Faersheng Road And Bridge Technology Co ltd
Jiangsu Fasten Steel Cable Co ltd
Jiangyin Fasten Sumiden New Material Co ltd
Fasten Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Faersheng Road And Bridge Technology Co ltd, Jiangsu Fasten Steel Cable Co ltd, Jiangyin Fasten Sumiden New Material Co ltd, Fasten Group Co Ltd filed Critical Jiangsu Faersheng Road And Bridge Technology Co ltd
Priority to CN202121791509.4U priority Critical patent/CN216405147U/en
Application granted granted Critical
Publication of CN216405147U publication Critical patent/CN216405147U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a temporary buckling cable force adjusting device for construction of a bilateral cantilever type girder, and belongs to the technical field of bridge construction. The temporary buckle cable force adjusting device comprises an adjusting sleeve, two ends of the adjusting sleeve are respectively provided with an adjusting rod and a connecting nut, the adjusting rod penetrates through the connecting nut, and the exposed ends of the adjusting rods are respectively in threaded connection with the adjusting sleeve, so that the two adjusting rods are symmetrically arranged in the adjusting sleeve; the temporary buckle cable comprises a steel strand bundle, an anchor plate is penetrated through by one end of the steel strand bundle, a P anchor is arranged at the end part of the steel strand bundle, a pressing plate is arranged at the end part of the P anchor, the pressing plate is fixedly connected with the anchor plate, the anchor plate is arranged in the connecting nut, and the anchor plate and the connecting nut are fixedly connected through threads. According to the hanging basket construction method and the hanging basket construction device, the hanging basket construction load in the cantilever state of the two sides of the main beam in the construction process is met, and the cable force of the temporary buckling cable can be adjusted according to actual construction requirements in the construction process.

Description

Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam
Technical Field
The utility model relates to a temporary buckling cable force adjusting device for construction of a bilateral cantilever type girder, and belongs to the technical field of bridge construction.
Background
The cantilever construction refers to a construction method that working platforms are arranged on two sides of a pier, and beam sections are poured or assembled to a midspan cantilever section by section in a balanced manner until a bridge span structure is closed. The cantilever construction has the characteristics that no or few supports are used, navigation or under-bridge traffic is not influenced during construction, and the cantilever construction is also suitable for occasions with complex mountainous terrain and occasions with difficult support erection of mountainous high-pier large-span bridges. However, for the main beam of the long cantilever pouring construction, the main beam structure generally cannot independently bear the construction load of the hanging basket in the long cantilever state in the construction process, and the hanging basket pouring construction needs to be carried out by adopting auxiliary means such as temporary support or buckling cables.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem of providing a temporary buckling cable force adjusting device for construction of a bilateral cantilever type main beam in the prior art, which can not only provide hanging basket construction load in a bilateral cantilever state of the main beam in the construction process, but also adjust the temporary buckling cable force according to actual construction requirements in the construction process.
The technical scheme adopted by the utility model for solving the problems is as follows: a temporary buckling cable force adjusting device for double-side cantilever type girder construction is arranged between two limb piers, two ends of the temporary buckling cable force adjusting device are respectively connected with one end of a temporary buckling cable on the corresponding side in an anchoring mode, and the other end of the temporary buckling cable penetrates through buckling cable holes of the two limb piers on the corresponding side and buckling cable holes of a girder and is anchored at the lower end of the girder; the temporary buckle cable force adjusting device comprises an adjusting sleeve, two ends of the adjusting sleeve are respectively provided with an adjusting rod and a connecting nut, the adjusting rod penetrates through the connecting nut, and the exposed ends of the adjusting rods are respectively in threaded connection with the adjusting sleeve, so that the two adjusting rods are symmetrically arranged in the adjusting sleeve; the temporary buckle cable comprises a steel strand bundle, one end of the steel strand bundle penetrates through the anchor plate, a P anchor is arranged at the end part of the steel strand bundle, a pressing plate is arranged at the end part of the P anchor, and the pressing plate is fixedly connected with the anchor plate, so that two ends of the P anchor are tightly attached to the pressing plate and the anchor plate; the anchor plate is arranged in the connecting nut and fixedly connected with the connecting nut through threads.
One end of the adjusting rod is provided with an external thread, and the other end of the adjusting rod is provided with an outward convex step.
The inner cavity of the connecting nut is provided with an inner convex step which is matched with the outer convex step.
The inner walls of two ends of the adjusting sleeve are respectively provided with a thread section, a round hole section is arranged between the two thread sections, and the diameter of the round hole section is larger than the major diameter of the thread section.
Still include the tensioning assembly, the tensioning assembly includes the bearing plate, two the coupling nut outside is equipped with the bearing plate respectively, two stretch-draw pole is worn to establish by the level between the bearing plate, just stretch-draw pole one end is through fixation nut and a bearing plate fixed connection, the stretch-draw pole other end sets up the tensioning jack, through tensioning nut makes stretch-draw pole, tensioning jack and another bearing plate fixed connection for the tensioning assembly card is in two coupling nut's terminal surface.
Compared with the prior art, the utility model has the advantages that: the temporary buckling cable force adjusting device is arranged between a double-limb pier and a main beam, so that the hanging basket construction load in the cantilever state of the two sides of the main beam in the construction process is met, the cable force of the temporary buckling cable can be adjusted according to actual construction requirements in the construction process, and the temporary buckling cable force adjusting device is simple in structure and convenient to disassemble and assemble.
Drawings
Fig. 1 is an installation schematic diagram of a temporary buckle cable force adjusting device for construction of a double-side cantilever type main beam according to an embodiment of the utility model;
fig. 2 is a schematic view of a temporary buckle cable force adjusting device for construction of a double-side cantilever type main beam according to an embodiment of the present invention;
FIG. 3 is a cross-sectional view of FIG. 2;
FIG. 4 is a schematic view of the adjustment sleeve of FIG. 2;
FIG. 5 is a schematic view of the adjustment lever of FIG. 2;
FIG. 6 is a schematic view of the coupling nut of FIG. 2;
FIG. 7 is a schematic view of the anchor plate of FIG. 2;
FIG. 8 is a schematic view of the platen of FIG. 2;
FIG. 9 is a schematic view of the use of FIG. 2;
in the figure, 1, a temporary buckle cable force adjusting device, 11 adjusting sleeves, 12 adjusting rods, 121 outer convex steps, 13 connecting nuts, 131 inner convex steps, 14 anchor plates, 15 steel strand bundles, 16P anchors, 17 screws, 18 pressing plates, 2 double-limb piers, 3 main beams, 4 tensioning assemblies, 41 tension rods, 42 supporting plates, 43 tensioning jacks, 44 tensioning nuts and 45 fixing nuts.
Detailed Description
The utility model is described in further detail below with reference to the accompanying examples.
As shown in fig. 1, in the temporary buckle cable force adjusting device for construction of a double-side cantilever-type main beam in this embodiment, a temporary buckle cable force adjusting device 1 is disposed between two pier legs 2, two ends of the temporary buckle cable force adjusting device 1 are respectively connected to one end of a temporary buckle cable on a corresponding side in an anchoring manner, and the other end of the temporary buckle cable is inserted into a temporary buckle cable hole of the two pier legs 2 and a temporary buckle cable hole of a main beam 3 on the corresponding side and anchored at the lower end of the main beam 3.
As shown in fig. 2, 3, 4, 5, 6, 7 and 8, the cable force adjusting device 1 includes a hollow adjusting sleeve 11, and the inner walls of both ends of the adjusting sleeve 11 are symmetrically provided with threaded sections. The two ends of the adjusting sleeve 11 are respectively provided with a connecting nut 13 and an adjusting rod 12, one end of the adjusting rod 12 is provided with an external thread, the other end of the adjusting rod 12 is provided with an outer convex step 121, the adjusting rod 12 penetrates through the connecting nut 13, and the end of the adjusting rod 12 with the external thread is exposed out of the connecting nut 13 and is in threaded connection with the adjusting sleeve 11. The inner cavity of the connecting nut 13 is provided with an inner convex step 131, the outer convex step 121 is matched with the inner convex step 131, and the inner convex step 131 of the connecting nut 13 limits and bears the outer convex step 131 of the adjusting rod 12. The temporary buckle cable comprises a steel strand bundle 15, one end of the steel strand bundle 15 penetrates through the anchor plate 14, a P anchor 16 is arranged at the end part of the steel strand bundle 15 penetrating through the anchor plate 14, a pressing plate 18 is arranged on the outer side of the P anchor 16, and the pressing plate 18 is fixedly connected with the anchor plate 14 through a screw 17, so that one end of the P anchor 16 is attached to the end part of the pressing plate 18, and the other end of the P anchor is attached to the end part of the anchor plate 14. The anchor plate 14 is arranged in the connecting nut 13, the outer surface of the anchor plate 14 is provided with an external thread, the end part of the connecting nut 13 is provided with an internal thread, and the anchor plate and the connecting nut are fixedly connected through the threads.
A round hole section is arranged between the two thread sections of the adjusting sleeve 11, the diameter of the round hole section is larger than the major diameter of the thread sections, and the round hole section is used for screwing in and screwing out the two adjusting rods 12.
As shown in fig. 9, a method for using a temporary buckling cable force adjusting device for construction of a double-side cantilever type main beam includes the following steps:
step 1: and respectively enabling one ends of the N steel strands in the steel strand bundle to penetrate through corresponding through holes of the anchor plate, and carrying out extrusion manufacturing of a single P anchor on the N steel strands, or firstly carrying out single P anchor manufacturing on the N steel strands, and then enabling the steel strands subjected to P anchor to penetrate through the through holes of the anchor plate.
Step 2: and after the P anchor is manufactured by all the steel strands, arranging the pressing plate at the end part of the P anchor, fixing the pressing plate with the anchor plate through a screw, and screwing the screw to enable the other end of the P anchor to be tightly attached to the end surface of the anchor plate.
And step 3: the adjusting rods penetrate through the connecting nuts and are screwed in the adjusting sleeves, the screwing lengths of the adjusting rods at the two ends of the adjusting sleeves are consistent, the adjusting rods are symmetrically arranged at the two ends of the adjusting sleeves, the initial distance between the end parts of the two adjusting rods is T1, and the value of T1 is a value obtained by calculating the extension amount according to the cable force required to be increased by cable adjustment at the later stage; the length of the adjusting rod screwed into the round hole section of the adjusting sleeve is T2, and the T2 value is obtained by calculating the extension of the inhaul cable according to the maximum tensile force of the inhaul cable.
And 4, step 4: the anchor plate is arranged at the end part of the corresponding connecting nut, and the connecting nut is rotated to enable the anchor plate to be fixedly connected with the connecting nut through threads.
And 5: and the adjusting rod, the connecting nut and the anchor plate are symmetrically assembled, so that the temporary buckle cable force adjusting device is formed.
Step 6: and when the cable is adjusted in the later period, the tensioning assembly is adopted for adjustment. The tensioning assembly 4 comprises a supporting plate 42, the outer sides of the two connecting nuts 13 are respectively provided with the supporting plate 42, a tensioning rod 41 horizontally penetrates between the two supporting plates 42, one end of the tensioning rod 41 is fixed through a fixing nut 45, the other end of the tensioning rod 41 is provided with a tensioning jack 43, the tensioning rod 41, the tensioning jack 43 and the supporting plates 42 are fixedly connected through a tensioning nut 44, and the tensioning assembly is clamped on the end faces of the connecting nuts at the two ends. When the cable force needs to be increased, the tensioning jack enables the adjusting rods and the connecting nut to be in a stress-free state, the adjusting sleeve is fixed indefinitely, the two adjusting rods rotate synchronously, the two adjusting rods are screwed into the center of the adjusting sleeve simultaneously until the end faces of the outer convex steps of the adjusting rods cling to the end faces of the inner convex steps of the connecting nut, and the step is repeated to complete the increase of the cable force.
When cable force needs to be reduced or completely released in later cable adjustment, the tensioning jack enables the adjusting rods and the connecting nuts to be in a stress-free state, the adjusting sleeve is fixed, the two adjusting rods rotate synchronously, the two adjusting rods are screwed out towards the center of the adjusting sleeve simultaneously until the side faces of the convex steps of the adjusting rods cling to the end face of the pressing plate, the tensioning jack is released slowly, the distance between the pressing plate and the end face of the adjusting rod is slowly recovered to the initial distance, the adjusting rods are screwed out continuously, the step is repeated, and cable force reduction or cable force release is completed.
Steel strand wires pencil one end adopts single P anchor structure in this application, detains the cable temporarily and can realize the preparation in the building site, uses the small-size extruder of standard can carry out system cable, simple economy. This application not only can provide the basket construction load of hanging under the two side cantilever states of girder in the work progress, can also adjust the cable force of detaining the cable temporarily according to actual construction needs simultaneously in the work progress to be convenient for demolish after the construction.
In addition to the above embodiments, the present invention also includes other embodiments, and any technical solutions formed by equivalent transformation or equivalent replacement should fall within the scope of the claims of the present invention.

Claims (5)

1. The utility model provides a two side cantilever type girder construction is with interim knot cable power adjusting device which characterized in that: the temporary buckle cable force adjusting device (1) is arranged between the double-limb piers (2), two ends of the temporary buckle cable force adjusting device (1) are respectively connected with one end of a temporary buckle cable on the corresponding side in an anchoring manner, and the other end of the temporary buckle cable penetrates through a buckle cable hole of the double-limb pier (2) on the corresponding side and a buckle cable hole of the main beam (3) and is anchored at the lower end of the main beam (3); the temporary buckle cable force adjusting device (1) comprises an adjusting sleeve (11), two ends of the adjusting sleeve (11) are respectively provided with an adjusting rod (12) and a connecting nut (13), the connecting nut (13) is internally provided with the adjusting rod (12) in a penetrating manner, and the exposed ends of the adjusting rod (12) are respectively in threaded connection with the adjusting sleeve (11), so that the two adjusting rods (12) are symmetrically arranged in the adjusting sleeve (11); the temporary buckle cable comprises a steel strand (15), one end of the steel strand (15) penetrates through the anchor plate (14), a P anchor (16) is arranged at the end part of the steel strand (15), a pressing plate (18) is arranged at the end part of the P anchor (16), and the pressing plate (18) is fixedly connected with the anchor plate (14), so that two ends of the P anchor (16) are tightly attached to the pressing plate (18) and the anchor plate (14); the anchor plate (14) is arranged in the connecting nut (13) and fixedly connected with the connecting nut through threads.
2. The temporary buckling cable force adjusting device for construction of the double-side cantilever type main beam of claim 1, wherein: one end of the adjusting rod (12) is provided with an external thread, and the other end is provided with an outward convex step (121).
3. The temporary buckling cable force adjusting device for construction of the double-side cantilever type main beam of claim 2, wherein: the inner cavity of the connecting nut (13) is provided with an inner convex step (131), and the inner convex step (131) is matched with the outer convex step (121).
4. The temporary buckling cable force adjusting device for construction of the double-side cantilever type main beam of claim 2, wherein: the inner walls of two ends of the adjusting sleeve (11) are respectively provided with a thread section, a round hole section is arranged between the two thread sections, and the diameter of the round hole section is larger than the major diameter of the thread section.
5. The temporary buckling cable force adjusting device for construction of the double-side cantilever type main beam of claim 1, wherein: still include stretch-draw subassembly (4), stretch-draw subassembly (4) include bearing plate (42), two the coupling nut (13) outside is equipped with bearing plate (42) respectively, two stretch-draw pole (41) are worn to establish by the level between bearing plate (42), just stretch-draw pole (41) one end is through fixation nut (45) and a bearing plate fixed connection, stretch-draw pole (41) other end sets up stretch-draw jack (43), makes through stretch-draw nut (44) stretch-draw pole (41), stretch-draw jack (43) and another bearing plate (42) fixed connection for stretch-draw subassembly (4) card is in the terminal surface of two coupling nut (13).
CN202121791509.4U 2021-08-03 2021-08-03 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam Active CN216405147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121791509.4U CN216405147U (en) 2021-08-03 2021-08-03 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121791509.4U CN216405147U (en) 2021-08-03 2021-08-03 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam

Publications (1)

Publication Number Publication Date
CN216405147U true CN216405147U (en) 2022-04-29

Family

ID=81287902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121791509.4U Active CN216405147U (en) 2021-08-03 2021-08-03 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam

Country Status (1)

Country Link
CN (1) CN216405147U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113684769A (en) * 2021-08-03 2021-11-23 江阴法尔胜住电新材料有限公司 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam and using method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113684769A (en) * 2021-08-03 2021-11-23 江阴法尔胜住电新材料有限公司 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam and using method thereof
CN113684769B (en) * 2021-08-03 2023-01-13 江阴法尔胜住电新材料有限公司 Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam and using method thereof

Similar Documents

Publication Publication Date Title
KR100969005B1 (en) Constructing method of suspension bridge and temporary cable therefor
CN107190627B (en) Partial ground anchor type suspension bridge and construction method thereof
CN216405147U (en) Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam
CN110042767B (en) Cable buckling and anchoring method of cable hoisting system
CN109653531B (en) External prestress steel strand connector and matched tensioning device
CN108412207A (en) A kind of tooling and application method suitable for the double rope synchronous tensions of beam-string structure
CN201679149U (en) Device for middle connection and tension of steel stands
CN111924720A (en) Wind cable anchoring system of cable crane tower and construction method
CN111519530A (en) Pier head type tunnel anchor and construction method
CN113684769B (en) Temporary buckling cable force adjusting device for construction of bilateral cantilever type main beam and using method thereof
CN206346120U (en) A kind of pin-connected panel tower with suspended cable system
CN212452304U (en) A tension structure that is used for taking hoist cable of bulb pull rod to be connected with base
CN115787921B (en) Wind-resistant beam string structure with high durability and construction method thereof
CN111456449A (en) Construction device and method for guaranteeing uniform stress of each bundle of steel strands through beam body post-tensioning method
CN108322157B (en) Flexible support structure based on prestressed double-layer cable system
CN114104989B (en) Cable buckle integrated tower wind cable system of large-span cable crane and construction method
CN100396868C (en) Prestressed anchoring system by high tensile steel wire pretension and construction method thereof
CN102776841A (en) Long-span steel truss suspension bridge jointing method and device
CN112962455B (en) Cable-first-beam-second segment hoisting self-anchored suspension bridge construction method
CN210439165U (en) Prestressed carbon fiber tensioning device
CN210458909U (en) Temperature self-adaptive tower beam forward-bridge constant-temperature steel pull rod restraint system
CN108221685B (en) Tensioning method for cable-stayed bridge equidirectional rotary stay cable
CN209741864U (en) Assembled post-tensioned full-prestressed concrete X-shaped beam counter-force structure
CN108951434B (en) Control device and control method for curved light I-shaped steel beam bridge dragging construction cantilever end
CN220133582U (en) External prestressing force reinforcing apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant