CN216346515U - Indoor heating ventilation installation construction structures - Google Patents

Indoor heating ventilation installation construction structures Download PDF

Info

Publication number
CN216346515U
CN216346515U CN202121334961.8U CN202121334961U CN216346515U CN 216346515 U CN216346515 U CN 216346515U CN 202121334961 U CN202121334961 U CN 202121334961U CN 216346515 U CN216346515 U CN 216346515U
Authority
CN
China
Prior art keywords
thick bamboo
installation
section
ventilation pipe
installation section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121334961.8U
Other languages
Chinese (zh)
Inventor
吴飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Shangnuo Hvac Technology Service Co ltd
Original Assignee
Shaanxi Shangnuo Hvac Technology Service Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Shangnuo Hvac Technology Service Co ltd filed Critical Shaanxi Shangnuo Hvac Technology Service Co ltd
Priority to CN202121334961.8U priority Critical patent/CN216346515U/en
Application granted granted Critical
Publication of CN216346515U publication Critical patent/CN216346515U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to the technical field of construction devices and discloses an indoor heating and ventilating installation construction structure which comprises a first ventilating pipe, wherein a second ventilating pipe is arranged on one side of the first ventilating pipe, a first installation barrel and a second installation barrel are respectively sleeved on the outer sides of the first ventilating pipe and the second ventilating pipe, a rotating barrel is arranged in the middle of the first installation barrel and the second installation barrel, and a clamping groove is formed in the outer side of the front end of the second installation barrel. This indoor heating ventilation installation construction structures, rotate the butt joint to first ventilation pipe and second ventilation pipe, and first installation section of thick bamboo, the equal fixedly connected with electric putter in the inside of second installation section of thick bamboo and rotation section of thick bamboo, and the roll board of the inside electric putter front end installation of second installation section of thick bamboo can drive the second ventilation pipe and carry out the axial roll, the front end installation backing plate of the inside electric putter of first installation section of thick bamboo and rotation section of thick bamboo, the backing plate carries out the fixed clamp to first ventilation pipe, and can guarantee horizontal migration, be convenient for the butt joint of first ventilation pipe and second ventilation pipe.

Description

Indoor heating ventilation installation construction structures
Technical Field
The utility model relates to the technical field of construction devices, in particular to an indoor heating and ventilating installation construction structure.
Background
The pipeline installation is a novel technology introduced by all electromechanical equipment, and comprises common data, pipes, pipe fittings, flanges, a basic operation technology of the pipeline installation, pipeline connection, installation of a support and a compensator, a valve, installation of a building water supply and drainage pipeline, installation of a heating system, pressure test and cleaning of the pipeline, installation of common industrial pipelines, installation of non-ferrous metal pipelines and stainless steel pipelines, installation of common non-metallic pipelines and anti-corrosion lining pipelines, installation of instrument pipelines and corrosion prevention and heat insulation of the pipelines.
Along with the development of times and science and technology, the technological progress of the pipeline installation fixed knot who has promoted refrigeration ventilation equipment's of science and technology simultaneously, but still there is the defect, present refrigeration ventilation equipment's pipeline installation fixed knot constructs does not possess absorbing function, the phenomenon that the installation drops appears easily, and current air pipe has certain problem when connecting, because air pipe need be with the fixed back in top, just can connect the pipeline, but the pipeline carries out the operation degree of difficulty at the high altitude great, not only work is loaded down with trivial details, it is complicated, need be with the help of the instrument, staff is comparatively dangerous when high altitude construction simultaneously, the potential safety hazard appears very easily, work efficiency's problem has been reduced.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects of the prior art, the utility model provides an indoor heating and ventilating installation construction structure which has the advantages of convenience for quick and automatic alignment installation and a damping and buffering function, and solves the problems in the background art.
The utility model provides the following technical scheme: an indoor heating and ventilation installation construction structure comprises a first ventilation pipe, wherein a second ventilation pipe is arranged on one side of the first ventilation pipe, a first installation barrel and a second installation barrel are respectively sleeved on the outer sides of the first ventilation pipe and the second ventilation pipe, a rotating barrel is arranged in the middle of the first installation barrel and the second installation barrel, a clamping groove is formed in the outer side of the front end of the second installation barrel, a clamping ring is sleeved on the outer side of the clamping groove, the clamping ring is fixedly installed on the inner side of the rotating barrel, rotating teeth are fixedly installed on the outer side of the rotating barrel, gears are meshed below the rotating teeth, a motor is fixedly installed on one side of each gear, the motor is fixedly installed on the outer side of the second installation barrel, electric push rods are fixedly connected to the inner sides of the first installation barrel, the second installation barrel and the rotating barrel, and a backing plate is fixedly installed on the front ends of the electric push rods on the inner sides of the first installation barrel and the rotating barrel, the front end of the electric push rod on the inner side of the second mounting cylinder is fixedly provided with a rolling plate, and rolling shafts are arranged in the base plate and the rolling plate.
Selected, the equal fixed mounting in bottom of a first installation section of thick bamboo and a second installation section of thick bamboo has the picture peg, the bottom fixed mounting of picture peg has the attachment strap, the upper end fixedly connected with spring of attachment strap, the upper end fixedly connected with splint of spring, the splint cup joint is at the middle part of picture peg, the bottom fixedly connected with telescopic link of attachment strap, the bottom fixed mounting of telescopic link has the bottom plate.
Carefully, electric putter, backing plate and roll board all are the circumference array and install inside first installation section of thick bamboo, second installation section of thick bamboo and a rotation section of thick bamboo, and the backing plate with roll the roller bearing rotation direction mutually perpendicular on the board.
Carefully, the through hole is opened at the splint middle part, and the through hole cup joints in the middle part outside of picture peg.
And carefully selecting, wherein the diameter values of the first ventilating pipe and the second ventilating pipe are consistent, and the first ventilating pipe and the second ventilating pipe are in butt joint through threads.
Compared with the prior art, the utility model has the following beneficial effects:
1. this indoor heating ventilation installation construction structures, through installing first ventilation pipe and second ventilation pipe at the middle part of a first installation section of thick bamboo and a second installation section of thick bamboo, and the front end of a second installation section of thick bamboo rotates and is connected with a rotation section of thick bamboo, a rotation section of thick bamboo rotates under the rotation of motor, be convenient for rotate the butt joint to first ventilation pipe and second ventilation pipe, and a first installation section of thick bamboo, the equal fixedly connected with electric putter in inside of a second installation section of thick bamboo and a rotation section of thick bamboo, and the roll board of the installation of the inside electric putter front end of a second installation section of thick bamboo can drive the second ventilation pipe and carry out the axial roll, the front end installation backing plate of the inside electric putter of a first installation section of thick bamboo and a rotation section of thick bamboo, the backing plate carries out fixed clamp to first ventilation pipe, and can guarantee horizontal migration, be convenient for the butt joint of first ventilation pipe and second ventilation pipe.
2. This indoor heating ventilation installation construction structures is equipped with the picture peg through the below at first installation section of thick bamboo and second installation section of thick bamboo, and the picture peg passes through spring, attachment strap and telescopic link and installs in the top of bottom plate, is convenient for cushion the shock attenuation to first installation section of thick bamboo and second installation section of thick bamboo, avoids the installation between first ventilation pipe and the second ventilation pipe to receive vibrations and influences, guarantees the stable installation between first ventilation pipe and the second ventilation pipe.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a cross-sectional view of the structure of the present invention;
FIG. 3 is an exploded view of the structure of the present invention;
FIG. 4 is a schematic view of a rotary barrel of the present invention;
FIG. 5 is a schematic view of the electric putter of the present invention.
In the figure: 1. a first vent pipe; 2. a second vent pipe; 3. a first mounting cylinder; 4. a second mounting cylinder; 5. a card slot; 6. a snap ring; 7. a rotating cylinder; 8. rotating the teeth; 9. a gear; 10. a motor; 11. an electric push rod; 12. a base plate; 13. rolling the plate; 14. inserting plates; 15. a splint; 16. a base plate; 17. a spring; 18. a butt strap; 19. a telescopic rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, an indoor heating and ventilating installation and construction structure includes a first ventilating pipe 1, a second ventilating pipe 2 is disposed on one side of the first ventilating pipe 1, the diameter values of the first ventilating pipe 1 and the second ventilating pipe 2 are the same, the first ventilating pipe 1 and the second ventilating pipe 2 are in butt joint through threads, the first ventilating pipe 1 and the second ventilating pipe 2 are in thread butt joint inside a first installation cylinder 3 and a second installation cylinder 4, so as to ensure stable connection of the first ventilating pipe 1 and the second ventilating pipe 2 and facilitate operation of the device, the first installation cylinder 3 and the second installation cylinder 4 are respectively sleeved outside the first ventilating pipe 1 and the second ventilating pipe 2, a plug board 14 is fixedly installed at the bottom of the first installation cylinder 3 and the second installation cylinder 4, a butt strap 18 is fixedly installed at the bottom of the plug board 14, and a spring 17 is fixedly connected at the upper end of the butt strap 18, the upper end of the spring 17 is fixedly connected with a clamping plate 15, the clamping plate 15 is sleeved in the middle of the plug board 14, the bottom end of the clamping plate 18 is fixedly connected with an expansion link 19, the bottom end of the expansion link 19 is fixedly provided with a bottom board 16, the plug board 14 installs the first installation cylinder 3 and the second installation cylinder 4 above the bottom board 16, and shock absorption treatment is carried out through the spring 17 and the expansion link 19, so that the shock absorption treatment is avoided when the first ventilation pipe 1 and the second ventilation pipe 2 are installed in the first installation cylinder 3 and the second installation cylinder 4 and in the using process, the shock absorption influence is avoided, the stable use and installation of the first ventilation pipe 1 and the second ventilation pipe 2 are ensured, the middle part of the clamping plate 15 is provided with a through hole, the through hole is sleeved outside the middle part of the plug board 14, the clamping plate 15 is sleeved above the bottom board 16, when the clamping plate 15 and the bottom board 16 are fixed, shock absorption buffering can be carried out on the installation of the first installation cylinder 3 and the second installation cylinder 4 through the spring 17 and the expansion link 19, the first installation cylinder 3 and the second installation cylinder 4 are prevented from being affected by vibration, stable installation and use of the first ventilation pipe 1 and the second ventilation pipe 2 are ensured, the rotating cylinder 7 is arranged in the middle of the first installation cylinder 3 and the second installation cylinder 4, the clamping groove 5 is formed in the outer side of the front end of the second installation cylinder 4, the clamping ring 6 is sleeved on the outer side of the clamping groove 5, the clamping ring 6 is fixedly installed on the inner side of the rotating cylinder 7, the rotating teeth 8 are fixedly installed on the outer side of the rotating cylinder 7, the gear 9 is installed below the rotating teeth 8 in a meshed mode, the motor 10 is fixedly installed on one side of the gear 9, the motor 10 is fixedly installed on the outer side of the second installation cylinder 4, the electric push rods 11 are fixedly connected to the inner sides of the first installation cylinder 3, the second installation cylinder 4 and the rotating cylinder 7, the backing plate 12 is fixedly installed at the front ends of the electric push rods 11 on the inner sides of the first installation cylinder 3 and the rotating cylinder 7, the front end of the electric push rod 11 on the inner side of the second installation cylinder 4 is fixedly installed with the rolling plate 13, backing plate 12 and roll board 13's inside is equipped with the roller bearing, electric putter 11, backing plate 12 and roll board 13 all are the circumference array and install at a first installation section of thick bamboo 3, inside a second installation section of thick bamboo 4 and a rotation section of thick bamboo 7, and backing plate 12 and the roller bearing direction of rotation mutually perpendicular on the roll board 13, roll board 13 of 11 front ends installations of the inside electric putter of a second installation section of thick bamboo 4 can drive second ventilation pipe 2 and carry out the axial roll, the front end installation backing plate 12 of the inside electric putter 11 of a first installation section of thick bamboo 3 and a rotation section of thick bamboo 7, backing plate 12 carries out fixed clamp to first ventilation pipe 1, and can guarantee horizontal migration, be convenient for the butt joint of first ventilation pipe 1 and second ventilation pipe 2.
The working principle is as follows: during the use, pass through picture peg 14 with first installation section of thick bamboo 3 and second installation section of thick bamboo 4, attachment strap 18, spring 17 and telescopic link 19 are installed on bottom plate 16, and wear first ventilation pipe 1 and second ventilation pipe 2 at the middle part of first installation section of thick bamboo 3 and second installation section of thick bamboo 4, later with first ventilation pipe 1 and second ventilation pipe 2 through the inside electric putter 11 of first installation section of thick bamboo 3 and second installation section of thick bamboo 4, backing plate 12 and roll board 13 are fixed, and the starting drive power, motor 10 drives gear 9 and rotates, and the rotation of gear 9 drives a rotation section of thick bamboo 7 and rotates at the front end of second installation section of thick bamboo 4, drive and mesh between second ventilation pipe 2 and the first ventilation pipe 1, make second ventilation pipe 2 and first ventilation pipe 1 accomplish the butt joint installation, can.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Meanwhile, in the drawings of the utility model, the filling pattern is only used for distinguishing the layers and is not limited at all.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides an indoor heating ventilation installation construction structures, includes first ventilation pipe (1), its characterized in that: one side of first ventilation pipe (1) is equipped with second ventilation pipe (2), first installation section of thick bamboo (3) and second installation section of thick bamboo (4) have been cup jointed respectively in the outside of first ventilation pipe (1) and second ventilation pipe (2), the middle part of first installation section of thick bamboo (3) and second installation section of thick bamboo (4) is equipped with rotates a section of thick bamboo (7), and the front end outside of second installation section of thick bamboo (4) has seted up draw-in groove (5), snap ring (6) have been cup jointed in the outside of draw-in groove (5), snap ring (6) fixed mounting is in the inboard of rotating a section of thick bamboo (7), the outside fixed mounting who rotates a section of thick bamboo (7) has rotation tooth (8), gear (9) are installed in the below meshing of rotation tooth (8), one side fixed mounting of gear (9) has motor (10), motor (10) fixed mounting is in the outside of second installation section of thick bamboo (4), just first installation section of thick bamboo (3), The equal fixedly connected with electric putter (11) in the inboard of a second installation section of thick bamboo (4) and a rotation section of thick bamboo (7), just first installation section of thick bamboo (3) and the inboard electric putter (11) front end fixed mounting of a rotation section of thick bamboo (7) have backing plate (12), the inboard electric putter (11) front end fixed mounting of a second installation section of thick bamboo (4) has roll board (13), backing plate (12) and the inside of roll board (13) are equipped with the roller bearing.
2. An indoor heating and ventilation installation and construction structure as claimed in claim 1, wherein: the equal fixed mounting in bottom of first installation section of thick bamboo (3) and second installation section of thick bamboo (4) has picture peg (14), the bottom fixed mounting of picture peg (14) has attachment strap (18), the upper end fixedly connected with spring (17) of attachment strap (18), the upper end fixedly connected with splint (15) of spring (17), splint (15) cup joint the middle part in picture peg (14), the bottom fixedly connected with telescopic link (19) of attachment strap (18), the bottom fixed mounting of telescopic link (19) has bottom plate (16).
3. An indoor heating and ventilation installation and construction structure as claimed in claim 1, wherein: electric putter (11), backing plate (12) and rolling board (13) all are the circumference array and install inside first installation section of thick bamboo (3), second installation section of thick bamboo (4) and a rotation section of thick bamboo (7), and the roller bearing direction of rotation mutually perpendicular on backing plate (12) and rolling board (13).
4. An indoor heating and ventilation installation and construction structure as claimed in claim 2, wherein: the middle part of the clamping plate (15) is provided with a through hole, and the through hole is sleeved on the outer side of the middle part of the inserting plate (14).
5. An indoor heating and ventilation installation and construction structure as claimed in claim 1, wherein: the diameter values of the first ventilation pipe (1) and the second ventilation pipe (2) are consistent, and the first ventilation pipe (1) and the second ventilation pipe (2) are in butt joint through threads.
CN202121334961.8U 2021-06-16 2021-06-16 Indoor heating ventilation installation construction structures Active CN216346515U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121334961.8U CN216346515U (en) 2021-06-16 2021-06-16 Indoor heating ventilation installation construction structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121334961.8U CN216346515U (en) 2021-06-16 2021-06-16 Indoor heating ventilation installation construction structures

Publications (1)

Publication Number Publication Date
CN216346515U true CN216346515U (en) 2022-04-19

Family

ID=81160318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121334961.8U Active CN216346515U (en) 2021-06-16 2021-06-16 Indoor heating ventilation installation construction structures

Country Status (1)

Country Link
CN (1) CN216346515U (en)

Similar Documents

Publication Publication Date Title
CN206483877U (en) A kind of coating steel pipe punching apparatus
CN216346515U (en) Indoor heating ventilation installation construction structures
CN111112251A (en) Pipeline cleaning robot
CN207279146U (en) A kind of prefabricated direct-buried heat insulation pipe
CN214093452U (en) Split flange plate
CN207334065U (en) A kind of FlexbleJoint with cardan universal joint component load-bearing
CN206625791U (en) A kind of submarine pipeline vortex-induced vibration restraining device
CN215791817U (en) Simple tool for cutting groove of polyurethane prefabricated heat-insulating pipeline
CN214393580U (en) Burr removing device for orifice of metal round pipe
CN210566944U (en) Water heating pipeline installation fixer
CN209415579U (en) A kind of liquid crystal wall furnace controller laying bracket
CN217583420U (en) Multi-pipeline combined support
CN208765097U (en) A kind of air-conditioner outdoor unit that installation is firm
CN219037059U (en) Machine room air conditioner drainage device
CN112172459B (en) Swinging radian heating ventilation air conditioner air duct
CN219734542U (en) Double-deck spiral duct connection structure
CN220379170U (en) Nonmetal compensator convenient to assemble, disassemble and maintain
CN214146824U (en) Supporting device with good fixing effect for pipeline installation
CN220396835U (en) Water supply and drainage connecting mechanism with different pipe diameters
CN207893283U (en) A kind of Novel firefighting steel pipe
CN219734641U (en) Lining for pipeline repair
CN217356084U (en) Be used for fire control antidetonation support
CN209469924U (en) A kind of universal compensator of high temperature resistant
CN219836855U (en) Steam trap with external cleaning structure
CN210737807U (en) Connection structure of overlength steel construction factory building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant