CN216290009U - Temporary electricity utilization arrangement device based on site operation - Google Patents
Temporary electricity utilization arrangement device based on site operation Download PDFInfo
- Publication number
- CN216290009U CN216290009U CN202122930193.9U CN202122930193U CN216290009U CN 216290009 U CN216290009 U CN 216290009U CN 202122930193 U CN202122930193 U CN 202122930193U CN 216290009 U CN216290009 U CN 216290009U
- Authority
- CN
- China
- Prior art keywords
- support
- fixed
- side wall
- plate
- device based
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Patch Boards (AREA)
Abstract
The utility model belongs to the technical field of construction electricity utilization, in particular to a temporary electricity utilization arrangement device based on field construction, which aims at the problems that the installation of electricity utilization for the field construction on cables is complicated, and the cables are easy to droop and wear; according to the utility model, the cable is pushed to the position of the positioning plate a through the positioning plate b, so that the cable is quickly and efficiently limited, the working efficiency of cable installation in site construction is greatly improved, the cable installation in site construction is more convenient, and the complex mode and potential safety hazards caused by climbing and installation of constructors are reduced.
Description
Technical Field
The utility model relates to the technical field of construction power utilization, in particular to a temporary power utilization arrangement device based on field construction.
Background
In the whole process of building construction, the work load is arranged to interim power consumption, and how to guarantee the power consumption safety and the electric wire trend is arranged always to be a difficult problem, and in general construction, the phenomenon that the electric wire was settled along ground at will is general, and the built on stilts arrangement of electric wire receives various condition restrictions in addition, difficult realization.
Because the interim distribution device of site operation has more inconvenience to the cable installation, and it is particularly troublesome that the installation to the cable is loaded down with trivial details, makes the installation work efficiency of cable reduce thereupon then, because the weight of cable self when the installation, the condition that the cable droops has easily appeared, the influence of directness has arrived the quality of cable self moreover.
Therefore, a temporary electricity arrangement device based on site construction is needed to solve the problems that installation of the electric cable is complicated, the electric cable is prone to droop and abrasion, and electricity is used for site construction.
SUMMERY OF THE UTILITY MODEL
The temporary electricity distribution device based on field construction solves the problems that the installation of field construction electricity on cables is complicated, and the cables are prone to sagging and abrasion.
In order to achieve the purpose, the utility model adopts the following technical scheme: the temporary electricity utilization arrangement device based on site operation comprises an installation plate, wherein a support is fixed on one side wall of the installation plate, and the support further comprises
The rotary seats are arranged in plurality and are all fixed on the side wall of the outer side of the support, a bearing plate is rotatably connected inside the rotary seats, the side wall of the bottom end of the bearing plate is slidably connected with a hinge seat a, two hinge seats b which are symmetrically distributed are fixed on the side wall of the outer side of the support, and a connecting rod is hinged between each hinge seat b and the hinge seat a;
the positioning plate a is fixed with the side wall of the top end of the support, an installation cavity is formed in the support, and an adjusting assembly matched with the support is arranged in the installation cavity.
Preferably, the adjusting assembly comprises
The mounting block is fixed on the side wall of one side of the mounting cavity, the side wall of one side of the mounting block is rotatably connected with a threaded rod, one end of the threaded rod is rotatably connected with the inside of the mounting cavity, the external thread of the threaded rod is in threaded connection with a threaded sleeve,
the through groove is formed in the side wall of the top end of the support and communicated with the mounting cavity, a guide plate is connected inside the through groove in a sliding mode and fixed to the side wall of one side of the threaded sleeve, and a positioning plate b is fixed to the side wall of one side, away from the threaded sleeve, of the guide plate;
support the cover, support the cover and be fixed in support one side lateral wall, support the inside rotation of cover and be connected with the pivot, the pivot with all be provided with bevel gear between the threaded rod, two bevel gear intermeshing connects, the inside handle that sets up of pivot.
Preferably, two the carrier plate top surface all is the setting of concave cambered surface, two recesses that are the symmetric distribution are seted up to carrier plate bottom lateral wall, articulated seat an with the inside sliding connection of recess, the recess is inside to be fixed with the spring, the spring other end with articulated seat a is fixed.
Preferably, one side wall of the positioning plate a adjacent to one side wall of the positioning plate b is provided with an arc surface, and the positioning plate b is connected with the top surface of the bracket in a sliding manner.
Preferably, the inside passageway of having seted up of pivot, the pivot surface is seted up two draw-in grooves that are the symmetric distribution, the draw-in groove with the passageway is linked together the setting, the handle with the inside sliding connection of passageway, the handle surface is fixed with two restriction levers that are the symmetric distribution, the restriction lever with draw-in groove looks block.
Preferably, a plurality of hole grooves that are the symmetric distribution are seted up to mounting panel one side lateral wall, the mounting panel size value is greater than the size value of support.
Compared with the prior art, the utility model has the beneficial effects that:
1. according to the utility model, the cable is pushed to the position of the positioning plate a through the positioning plate b, so that the cable is quickly and efficiently limited, the working efficiency of cable installation in site construction is greatly improved, the cable installation in site construction is more convenient, and the complex mode and potential safety hazards caused by climbing and installation of constructors are reduced.
2. According to the utility model, the hinge seat a can be moved to achieve a buffering effect under the elastic action of the spring, so that the buffering effect on the bearing plate is achieved, the bearing plate is always attached to the cable, the sag of the cable is reduced, the abrasion degree of the cable is reduced, and the service life of the cable is prolonged.
Drawings
Fig. 1 is a schematic overall structure diagram of a temporary electricity distribution device based on site operation according to the present invention;
FIG. 2 is a schematic bottom view of a temporary electricity distribution device based on site operation according to the present invention;
FIG. 3 is an enlarged view of area A of FIG. 2;
FIG. 4 is a schematic structural diagram of an adjusting assembly of a temporary electricity distribution device based on field construction;
fig. 5 is a schematic structural diagram of a state at a handle of a temporary electricity distribution device based on field construction.
In the figure: 1. mounting a plate; 2. a support; 3. a rotating seat; 4. a carrier plate; 5. a hinge seat a; 6. a hinge base b; 7. a connecting rod; 8. a positioning plate a; 9. a mounting cavity; 10. an adjustment assembly; 101. mounting blocks; 102. a threaded rod; 103. a threaded sleeve; 104. a through groove; 105. a guide plate; 106. a positioning plate b; 107. a support sleeve; 108. a rotating shaft; 109. a bevel gear; 1010. a handle; 11. a groove; 12. a spring; 13. a channel; 14. a restraining bar; 15. a hole groove; 16. a clamping groove.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-5, a temporary electricity utilization arrangement device based on field construction comprises a mounting plate 1, wherein a support 2 is fixed on the side wall of one side of the mounting plate 1, the support 2 further comprises a plurality of rotating seats 3, the rotating seats 3 are all fixed on the side wall of the outer side of the support 2, a bearing plate 4 is rotatably connected inside the rotating seats 3, the side wall of the bottom end of the bearing plate 4 is slidably connected with a hinge seat a5, two hinge seats b6 which are symmetrically distributed are fixed on the side wall of the outer side of the support 2, and a connecting rod 7 is hinged between the hinge seat b6 and the hinge seat a 5; locating plate a8, locating plate a8 fixed with 2 top lateral walls of support, support 2 is inside to have seted up installation cavity 9, installation cavity 9 is inside to be provided with the adjusting part 10 with support 2 looks adaptation.
The adjusting assembly 10 comprises an installation block 101, the installation block 101 is fixed on the side wall of one side of the installation cavity 9, the side wall of one side of the installation block 101 is rotatably connected with a threaded rod 102, one end of the threaded rod 102 is rotatably connected with the inside of the installation cavity 9, a threaded sleeve 103 is connected to the external thread of the threaded rod 102 in a threaded manner, a through groove 104 is formed in the side wall of the top end of the support 2, the through groove 104 is communicated with the installation cavity 9, a guide plate 105 is slidably connected inside the through groove 104, the guide plate 105 is fixed with the side wall of one side of the threaded sleeve 103, and a positioning plate b106 is fixed on the side wall, away from the threaded sleeve 103, of the guide plate 105; support cover 107, support cover 107 and be fixed in 2 one side lateral walls of support, support cover 107 internal rotation and be connected with pivot 108, all be provided with bevel gear 109 between pivot 108 and the threaded rod 102, two bevel gear 109 intermeshing are connected, the inside handle 1010 that sets up of pivot 108, through locating plate b106 with the cable migration to with locating plate a8 department, then it is spacing to accomplish the cable quick and efficient, promote site operation cable installation work efficiency by a wide margin, it is more convenient to make installation cable to site operation, the loaded down with trivial details mode of exempting from because of constructor climbing installation, and the potential safety hazard.
Two 4 top surfaces of loading board all are the concave arc face setting, two recess 11 that are the symmetric distribution are seted up to 4 bottom lateral walls of loading board, articulated seat an 5 and the inside sliding connection of recess 11, recess 11 inside is fixed with spring 12, the spring 12 other end is fixed with articulated seat a5, through spring 12's elastic force, make loading board 4 remain the laminating with the cable all the time, reduce the sag of cable, reduce the cable degree of wear, then promote the life of cable, a lateral wall that locating plate a8 and locating plate b106 are adjacent all is the arc surface setting, locating plate b106 and 2 top surface sliding connection of support, all be the arc surface setting through a lateral wall that locating plate a8 and locating plate b106 are adjacent, can be better be applicable to cable positioning effect.
The working principle is as follows: when the cable for field construction needs to be installed, firstly, the cable is laid on the top surface of the support 2, the handle 1010 is inserted into the channel 13, the limiting rod 14 and the clamping groove 16 are clamped to achieve a more convenient rotating shaft 108, the handle 1010 is rotated to match the transmission effect of the limiting rod 14, the rotating shaft 108 is synchronously rotated and matches the meshing transmission effect of the bevel gear 109, the threaded rod 102 is synchronously rotated, the guide plate 105 and the through groove 104 are in sliding connection arrangement by utilizing the thread transmission effect between the threaded rod 102 and the threaded sleeve 103, the guide limiting effect on the threaded sleeve 103 is achieved, the stability of the threaded sleeve 103 in the moving process is improved, the positioning plate b106 is synchronously moved along the opening direction of the through groove 104, until the positioning plate b106 is attached to the cable, the cable is pushed to the positioning plate a8, then, the quick and efficient limiting of the cable is completed, the working efficiency of cable installation in site construction is greatly improved, the cable installation in site construction is more convenient, and the complex mode and potential safety hazards caused by climbing and installation of constructors are reduced; when the cable bears on bearing, when flagging because of cable gravity, transmission effect through connecting rod 7, make articulated seat a5 remove along recess 11, and extrude spring 12, utilize spring 12's elastic force effect, can remove to articulated seat a5 and make cushioning effect, then play the cushioning effect to loading board 4, make loading board 4 remain the laminating with the cable all the time, reduce the sag of cable, reduce the cable degree of wear, then promote the life of cable.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and equivalent alternatives or modifications according to the technical solution of the present invention and the inventive concept thereof should be covered by the scope of the present invention.
Claims (6)
1. The utility model provides a temporary electricity arrangement device based on site operation, includes mounting panel (1), mounting panel (1) one side lateral wall is fixed with support (2), its characterized in that, support (2) still include
The device comprises a plurality of rotating seats (3), wherein the rotating seats (3) are all fixed on the side wall of the outer side of the support (2), a bearing plate (4) is rotatably connected inside the rotating seats (3), the side wall of the bottom end of the bearing plate (4) is slidably connected with a hinge seat a (5), two hinge seats b (6) which are symmetrically distributed are fixed on the side wall of the outer side of the support (2), and a connecting rod (7) is hinged between each hinge seat b (6) and each hinge seat a (5);
locating plate a (8), locating plate a (8) fixed with support (2) top lateral wall, installation cavity (9) have been seted up to support (2) inside, installation cavity (9) inside be provided with adjusting part (10) of support (2) looks adaptation.
2. A temporary electricity utilization arrangement device based on field construction according to claim 1, characterized in that the adjusting assembly (10) comprises
The mounting block (101), the mounting block (101) is fixed on the side wall of one side of the mounting cavity (9), the side wall of one side of the mounting block (101) is rotatably connected with a threaded rod (102), one end of the threaded rod (102) is rotatably connected with the inside of the mounting cavity (9), a threaded sleeve (103) is connected with the external thread of the threaded rod (102) in a threaded manner,
the through groove (104), the through groove (104) is arranged on the side wall of the top end of the support (2), the through groove (104) is communicated with the mounting cavity (9), a guide plate (105) is connected inside the through groove (104) in a sliding manner, the guide plate (105) is fixed with the side wall of one side of the threaded sleeve (103), and a positioning plate b (106) is fixed on the side wall of one side, far away from the threaded sleeve (103), of the guide plate (105);
support cover (107), support cover (107) and be fixed in support (2) one side lateral wall, support cover (107) internal rotation and be connected with pivot (108), pivot (108) with all be provided with bevel gear (109) between threaded rod (102), two bevel gear (109) intermeshing connects, pivot (108) inside setting handle (1010).
3. The temporary electricity utilization arrangement device based on field construction is characterized in that the top surfaces of the two bearing plates (4) are arranged in a concave arc surface, the side wall of the bottom end of each bearing plate (4) is provided with two symmetrically distributed grooves (11), the hinge seat a (5) is connected with the inner portion of each groove (11) in a sliding mode, a spring (12) is fixed inside each groove (11), and the other end of each spring (12) is fixed with the hinge seat a (5).
4. A temporary electricity utilization arrangement device based on site operation according to claim 2, wherein a side wall of the positioning plate a (8) adjacent to the positioning plate b (106) is provided with an arc surface, and the positioning plate b (106) is connected with the top surface of the bracket (2) in a sliding manner.
5. The temporary electricity utilization arrangement device based on field construction is characterized in that a channel (13) is formed in the rotating shaft (108), two clamping grooves (16) which are symmetrically distributed are formed in the outer surface of the rotating shaft (108), the clamping grooves (16) are communicated with the channel (13), the handle (1010) is connected with the channel (13) in a sliding mode, two limiting rods (14) which are symmetrically distributed are fixed on the outer surface of the handle (1010), and the limiting rods (14) are clamped with the clamping grooves (16).
6. The temporary electricity utilization arrangement device based on field construction is characterized in that a plurality of symmetrically distributed hole grooves (15) are formed in the side wall of one side of the mounting plate (1), and the size value of the mounting plate (1) is larger than that of the support (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122930193.9U CN216290009U (en) | 2021-11-26 | 2021-11-26 | Temporary electricity utilization arrangement device based on site operation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122930193.9U CN216290009U (en) | 2021-11-26 | 2021-11-26 | Temporary electricity utilization arrangement device based on site operation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216290009U true CN216290009U (en) | 2022-04-12 |
Family
ID=81039339
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202122930193.9U Active CN216290009U (en) | 2021-11-26 | 2021-11-26 | Temporary electricity utilization arrangement device based on site operation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216290009U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117096800A (en) * | 2023-10-20 | 2023-11-21 | 聊城创智光电科技有限公司 | Cable support frame |
-
2021
- 2021-11-26 CN CN202122930193.9U patent/CN216290009U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117096800A (en) * | 2023-10-20 | 2023-11-21 | 聊城创智光电科技有限公司 | Cable support frame |
CN117096800B (en) * | 2023-10-20 | 2024-03-22 | 聊城创智光电科技有限公司 | Cable support frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN216290009U (en) | Temporary electricity utilization arrangement device based on site operation | |
CN109301780B (en) | Power grid support frame for power transmission | |
CN217028246U (en) | Assembled steel construction building supporting seat | |
CN210926933U (en) | Cable strutting arrangement for electric power | |
CN211229499U (en) | Building template with triangular support device | |
CN215862655U (en) | Communication base station supporting structure | |
CN114421867A (en) | Solar panel fixing device for photovoltaic power generation | |
CN112202397B (en) | Solar photovoltaic panel with snow removing function | |
CN212689917U (en) | Support arrangement for hydraulic jumbolter | |
CN113872072A (en) | Construction cubical switchboard suspension type installed part | |
CN213460945U (en) | Safe cable channel gallows that takes precautions against earthquakes | |
CN211790443U (en) | Building indoor wiring auxiliary device | |
CN209071520U (en) | A kind of cylindrical battery steel shell slot rolling fixture | |
CN110854708A (en) | Switch board for electrical engineering convenient to remove | |
CN208330165U (en) | A kind of folding type aluminum alloy double ladder | |
CN220667079U (en) | Steel structure support | |
CN213546986U (en) | Distributed micro-grid cluster mounting bracket | |
CN210897505U (en) | Bending device for battery production | |
CN221524886U (en) | Auxiliary structure of rock anchor rod | |
CN221282799U (en) | Cable erection support device | |
CN221080832U (en) | Cable support for hydroelectric power generation | |
CN218850672U (en) | Photovoltaic support convenient to installation | |
CN215897083U (en) | Distribution box convenient for wiring | |
CN217789257U (en) | Power transmission and transformation circuit electric wire fixing device | |
CN219477382U (en) | Block terminal with mounting bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |