CN216235948U CN202122274721.XU CN202122274721U CN216235948U CN 216235948 U CN216235948 U CN 216235948U CN 202122274721 U CN202122274721 U CN 202122274721U CN 216235948 U CN216235948 U CN 216235948U
Authority
CN
China
Prior art keywords
well lid
plate
rod
communication engineering
engineering construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122274721.XU
Other languages
Chinese (zh)
Inventor
王桂青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Surui Information Technology Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122274721.XU priority Critical patent/CN216235948U/en
Application granted granted Critical
Publication of CN216235948U publication Critical patent/CN216235948U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Manufacture Of Motors, Generators (AREA)

Abstract

The utility model discloses a well lid extraction device for communication engineering construction, and relates to the technical field of communication engineering. According to the utility model, by arranging the electromagnet, the slide bar, the clamping sleeve, the limiting plate, the telescopic rod and the spring, when a worker needs to extract the well lid, the worker firstly starts the motor to enable the slide bar to move to the top of the well lid, then starts the electric push rod to enable the bottom of the electromagnet to be in close contact with the top of the well lid, meanwhile, the bottom end of the slide bar drives the telescopic rod, the spring and the limiting plate on the outer surface of the slide bar to extend into the through hole in the top of the well lid until the top of the limiting plate penetrates through the through hole, when the top of the limiting plate penetrates through the through hole, the limiting plate clamps the bottom of the well lid, and meanwhile, the worker energizes the electromagnet to enable the electromagnet to generate an adsorption force on the top of the well lid, so that the stability in the extraction process is ensured.

Description

Well lid extraction element is used in communication engineering construction
Technical Field
The utility model relates to the technical field of communication engineering, in particular to a well lid extraction device for communication engineering construction.
Background
The communication construction machine refers to all machines required in the whole communication construction and maintenance, and comprises early-stage survey equipment (measuring instruments such as a total station and a level gauge), early-stage excavation equipment (an excavator, a bulldozer, a scraper, a loader and the like) and a series of mechanized tools for replacing manual operation.
Present well lid extraction element is used in communication engineering construction, carrying out the extraction in-process of well lid, generally through going into the through-hole at well lid top with the fixture block card, then draw the well lid and come, the fixture block is gone into the inside of through-hole a lot of card, can lead to the fact certain wearing and tearing to the inner wall of through-hole, thereby make the diameter of through-hole probably increase, make the connection between fixture block and the well lid not hard up, thereby the condition that the well lid dropped can take place at the extraction in-process, thereby influence the extraction of well lid, on the other hand, the well lid is at the in-process of long-term use, some comparatively smooth impurity of bottom possible adhesion of well lid, and current device is the well lid that will draw usually prevents to place on the board, at the in-process to the well lid removal, the condition that the landing can take place for the well lid.
SUMMERY OF THE UTILITY MODEL
The utility model aims to: in order to solve the problem that the through hole abrasion causes the extraction of unstable and moving process well lid landing, a well lid extraction device for communication engineering construction is provided.
In order to achieve the purpose, the utility model provides the following technical scheme: a well lid extraction device for communication engineering construction comprises a top plate, wherein a motor is installed on one side of the top plate, the output end of the motor penetrates through one side of the top plate and is connected with a threaded rod, a threaded sleeve is sleeved on the outer surface of the threaded rod, a connecting plate is connected to the bottom of the threaded sleeve, an electric push rod is installed at the bottom of the connecting plate, a fixing plate is connected to the bottom end of the electric push rod, a connecting rod is connected to one side of the bottom of the fixing plate, an electromagnet is installed at the bottom end of the connecting rod, a sliding rod is connected to the other side of the bottom of the fixing plate, a clamping sleeve and a telescopic rod are respectively connected to the lower portion of the outer surface of the sliding rod, a limiting plate is connected to one end of the telescopic rod, a spring is sleeved on the outer surface of the telescopic rod, a plurality of supporting legs are connected to the bottom of the top plate, a placing plate is connected to the back of one supporting leg, and a baffle is connected to one side of the placing plate, the outer surface and the back of the baffle are both connected with limiting pieces, the inner part of the placing plate is connected with a limiting rod, the outer surface of the limiting rod is sleeved with a fixing bolt, and a dismounting hole is formed in one side of the top of the placing plate.
Preferably, an operation panel is installed on the outer surface of the top plate, and the operation panel is electrically connected with the motor, the electric push rod and the electromagnet respectively.
Preferably, the number of the electric push rods is two, and the two electric push rods are symmetrically distributed along the longitudinal axis of the fixing plate.
Preferably, the support legs are arranged in a rectangular array, and the bottom of each support leg is connected with a roller.
Preferably, the bottom of the clamping sleeve is provided with a limiting groove, and the top of the limiting plate is matched with the limiting groove.
Preferably, the baffle is rotatably connected with the placing plate through a hinge.
Preferably, the cutting sleeve is internally provided with a sliding groove, and the cutting sleeve is connected with the sliding rod in a sliding manner.
Compared with the prior art, the utility model has the beneficial effects that:
1. by arranging the electromagnet, the slide rod, the clamping sleeve, the limiting plate, the telescopic rod and the spring, when a worker needs to extract the well lid, the worker firstly starts the motor to enable the slide rod to move to the top of the well lid, then the worker starts the electric push rod to enable the bottom of the electromagnet to be in close contact with the top of the well lid, meanwhile, the bottom end of the slide rod drives the telescopic rod, the spring and the limiting plate on the outer surface of the slide rod to extend into the through hole in the top of the well lid, in the process, the clamping sleeve is blocked at the top of the well lid due to the fact that the diameter of the clamping sleeve is larger than that of the through hole, the slide rod drives the telescopic rod, the spring and the limiting plate to extend downwards continuously until the top of the limiting plate penetrates through the through hole, in the process, when the top of the limiting plate penetrates through the through hole, the limiting plate blocks the bottom of the well lid under the action of restoring force of the spring, simultaneously, the staff is to the electro-magnet circular telegram for the electro-magnet produces the adsorption affinity to the top of well lid, has made things convenient for and has drawed the well lid, has guaranteed to draw the stability of in-process.
2. When the worker places the extracted well lid on the placing plate, the worker rotates the baffle plate to enable the fixing hole in the limiting piece to be aligned with the fixing hole in the outer surface of the placing plate, then the worker penetrates the limiting rod into the fixing hole, and finally the limiting rod is fixed through the fixing bolt, so that the normal moving process of the well lid is guaranteed, and the well lid is prevented from slipping.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the internal structure of the top plate of the present invention;
FIG. 3 is an enlarged view taken at A of FIG. 2 in accordance with the present invention;
FIG. 4 is a schematic side view of the top plate of the present invention;
fig. 5 is a schematic top view of the placement board of the present invention.
In the figure: 1. a top plate; 2. an operation panel; 3. a motor; 4. a support leg; 5. a connecting plate; 6. an electric push rod; 7. a fixing plate; 8. a connecting rod; 9. an electromagnet; 10. a card sleeve; 11. a slide bar; 12. a limiting plate; 13. placing the plate; 14. a baffle plate; 15. a limiting sheet; 16. fixing the bolt; 17. disassembling the hole; 18. a limiting rod; 19. a telescopic rod; 20. a spring; 21. a threaded rod; 22. and (4) a threaded sleeve.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance. In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "disposed" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art. The following describes an embodiment of the present invention based on its overall structure.
Referring to fig. 1-5, a manhole cover extracting device for communication engineering construction comprises a top plate 1, an operating panel 2, a motor 3, support legs 4, a connecting plate 5, an electric push rod 6, a fixing plate 7, a connecting rod 8, an electromagnet 9, a clamping sleeve 10, a slide rod 11, a limiting plate 12, a placing plate 13, a baffle 14, a limiting sheet 15, a fixing bolt 16, a dismounting hole 17, a limiting rod 18, a telescopic rod 19, a spring 20, a threaded rod 21 and a threaded sleeve 22, wherein the motor 3 is installed on one side of the top plate 1, an output end of the motor 3 penetrates through one side of the top plate 1 and is connected with the threaded rod 21, the threaded sleeve 22 is sleeved on the outer surface of the threaded rod 21, the connecting plate 5 is connected to the bottom of the threaded sleeve 22, the electric push rod 6 is installed at the bottom of the connecting plate 5, the fixing plate 7 is connected to the bottom end of the electric push rod 6, the connecting rod 8 is connected to one side of the bottom of the fixing plate 7, the electromagnet 9 is installed at the bottom end of the connecting rod 8, the bottom opposite side of fixed plate 7 is connected with slide bar 11, slide bar 11's surface below is connected with cutting ferrule 10 and telescopic link 19 respectively, telescopic link 19's one end is connected with limiting plate 12, spring 20 has been cup jointed to telescopic link 19's surface, the bottom of roof 1 is connected with a plurality of landing legs 4, the back of landing leg 4 is connected with places board 13, the one side of placing board 13 is connected with baffle 14, baffle 14's surface and back all are connected with spacing piece 15, the internal connection who places board 13 has gag lever post 18, fixing bolt 16 has been cup jointed to the surface of gag lever post 18, place top one side of board 13 and seted up dismounting hole 17, the normal clear that the well lid drawed has been guaranteed, prevent to draw the condition that the in-process takes place the well lid and drop.
Please refer to fig. 1-2 and 4, the operation panel 2 is installed on the outer surface of the top plate 1, and the operation panel 2 is electrically connected with the motor 3, the electric push rod 6 and the electromagnet 9 respectively, so that the operation of the working personnel is facilitated, and the operation burden of the working personnel is reduced.
Please refer to fig. 1-4, the plurality of legs 4 are arranged in a rectangular array, and the bottom of the plurality of legs 4 is connected with the roller, so as to ensure the stability of the device, prevent the device from tilting during the extraction process of the well lid, the bottom of the cutting sleeve 10 is provided with a limiting groove, and the top of the limiting plate 12 is matched with the limiting groove, thereby facilitating the limitation of the limiting plate 12 and the subsequent extraction of the well lid.
Please refer to fig. 1-5, the baffle 14 is rotatably connected to the placing plate 13 through a hinge to protect the well lid and prevent the well lid from sliding off during the moving process, a sliding groove is formed in the cutting sleeve 10, and the cutting sleeve 10 is slidably connected to the sliding rod 11, so that the limiting plate 12 can be conveniently extracted from the limiting groove, and the bottom of the well lid can be conveniently supported.
The working principle is as follows: the staff first places the device on the top of well lid, then the staff starts motor 3, make threaded rod 21 take place to rotate, thereby drive thread bush 22 and remove, until slide bar 11 is aligned with the through-hole at well lid top, then the staff starts electric putter 6, make the bottom of electro-magnet 9 and the top of well lid in close contact with, the bottom of slide bar 11 drives its surperficial telescopic link 19 simultaneously, spring 20 and limiting plate 12 stretch into the through-hole at well lid top, in this process, because the diameter of cutting ferrule 10 is greater than the diameter of through-hole, therefore make cutting ferrule 10 be held back at the top of well lid, slide bar 11 drives telescopic link 19, spring 20 and limiting plate 12 and continue to stretch into downwards, until the top of limiting plate 12 passes the through-hole, in this process, spring 20 and telescopic link 19 are in the state of compressed, when the top of limiting plate 12 passes the through-hole, under the action of restoring force of the spring 20, the limiting plate 12 clamps the bottom of the well lid, meanwhile, a worker energizes the electromagnet 9, so that the electromagnet 9 generates adsorption force on the top of the well lid, then the worker starts the electric push rod 6 to extract the well lid, then the worker starts the motor 3 to move the thread bush 22 to the top of the placing plate 13, then the worker starts the electric push rod 6 again to place the well lid on the top of the placing plate 13, the bottom end of the sliding rod 11 with the telescopic rod 19, the spring 20 and the limiting plate 12 penetrates through the dismounting hole 17 on the top of the placing plate 13, then the worker extrudes the limiting plate 12, simultaneously starts the electric push rod 6 to move the sliding rod 11 out of the well lid, finally the top of the limiting plate 12 is clamped into the limiting groove on the bottom of the clamping sleeve 10, then the worker rotates the baffle 14 to align the fixing hole on the limiting sheet 15 with the fixing hole on the outer surface of the placing plate 13, then, the worker inserts the stopper rod 18 into the fixing hole, and finally fixes the stopper rod 18 by the fixing bolt 16.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides a well lid extraction element is used in communication engineering construction, includes roof (1), its characterized in that: the electric iron is characterized in that a motor (3) is installed on one side of the top plate (1), the output end of the motor (3) penetrates through one side of the top plate (1) and is connected with a threaded rod (21), a threaded sleeve (22) is sleeved on the outer surface of the threaded rod (21), a connecting plate (5) is connected to the bottom of the threaded sleeve (22), an electric push rod (6) is installed at the bottom of the connecting plate (5), a fixing plate (7) is connected to the bottom end of the electric push rod (6), a connecting rod (8) is connected to one side of the bottom of the fixing plate (7), an electromagnet (9) is installed at the bottom end of the connecting rod (8), a sliding rod (11) is connected to the other side of the bottom of the fixing plate (7), a clamping sleeve (10) and a telescopic rod (19) are connected to the lower side of the outer surface of the sliding rod (11), and a limiting plate (12) is connected to one end of the telescopic rod (19), the outer surface of telescopic link (19) has cup jointed spring (20), the bottom of roof (1) is connected with a plurality of landing legs (4), one the back of landing leg (4) is connected with places board (13), one side of placing board (13) is connected with baffle (14), the surface and the back of baffle (14) all are connected with spacing piece (15), the internal connection who places board (13) has gag lever post (18), fixing bolt (16) have been cup jointed to the surface of gag lever post (18), the top one side of placing board (13) has been seted up and has been dismantled hole (17).
2. The manhole cover extracting device for communication engineering construction according to claim 1, wherein: the outer surface mounting of roof (1) has operating panel (2), just operating panel (2) respectively with motor (3), electric putter (6) and electro-magnet (9) electric connection.
3. The manhole cover extracting device for communication engineering construction according to claim 1, wherein: the number of the electric push rods (6) is two, and the two electric push rods (6) are symmetrically distributed along the longitudinal axis of the fixing plate (7).
4. The manhole cover extracting device for communication engineering construction according to claim 1, wherein: a plurality of the supporting legs (4) are arranged in a rectangular array shape, and the bottoms of the supporting legs (4) are connected with rollers.
5. The manhole cover extracting device for communication engineering construction according to claim 1, wherein: the bottom of the clamping sleeve (10) is provided with a limiting groove, and the top of the limiting plate (12) is matched with the limiting groove.
6. The manhole cover extracting device for communication engineering construction according to claim 1, wherein: the baffle plate (14) is rotatably connected with the placing plate (13) through a hinge.
7. The manhole cover extracting device for communication engineering construction according to claim 1, wherein: the cutting sleeve (10) is internally provided with a sliding groove, and the cutting sleeve (10) is connected with the sliding rod (11) in a sliding manner.
CN202122274721.XU 2021-09-18 2021-09-18 Well lid extraction element is used in communication engineering construction Active CN216235948U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122274721.XU CN216235948U (en) 2021-09-18 2021-09-18 Well lid extraction element is used in communication engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122274721.XU CN216235948U (en) 2021-09-18 2021-09-18 Well lid extraction element is used in communication engineering construction

Publications (1)

Publication Number Publication Date
CN216235948U true CN216235948U (en) 2022-04-08

Family

ID=80984596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122274721.XU Active CN216235948U (en) 2021-09-18 2021-09-18 Well lid extraction element is used in communication engineering construction

Country Status (1)

Country Link
CN (1) CN216235948U (en)

Similar Documents

Publication Publication Date Title
CN209198106U (en) A kind of well lid loading test instrument
CN216235948U (en) Well lid extraction element is used in communication engineering construction
CN220005915U (en) High arc alignment precision sector segment arc alignment tool
CN208584021U (en) A kind of construction building top plate vertical drilling device
CN215931360U (en) Hydraulic soil taking device capable of preliminarily judging heavy metal pollution degree of soil
CN211904403U (en) Auxiliary device for quickly disassembling and assembling deep hole sensor installation connecting rod
CN212174244U (en) Motor lifting appliance assembled on new energy pure electric transmission assembly
CN213446130U (en) Electric power well lid opening tool
CN210460712U (en) Supporting device for mine excavation
CN213416197U (en) Adjustable detection platform for offshore oil drilling device
CN208419802U (en) A kind of power engineering ruler
CN208456080U (en) A kind of power construction repairing frame
CN218036337U (en) Safety inspection device that green construction of building engineering was used
CN210353476U (en) Safety belt buckle hanging device
CN208826101U (en) A kind of fulcrum bearing drilling jig device
CN217765888U (en) Rock rotation shear testing machine
CN216828390U (en) Portable steel bar bender
CN209591894U (en) A kind of Novel bunk pressure disconnecting switch
CN220708623U (en) Impeller static balancing device
CN221165918U (en) Well lid extraction element is used in communication engineering construction
CN213516625U (en) Static tensile test frock of terminal
CN214527917U (en) Lifting device for construction machinery
CN212363903U (en) Tensile tester convenient to horizontal adjustment
CN216839356U (en) Assemble simple and easy sounding equipment
CN210898524U (en) Short-circuit current limiter

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231116

Address after: 310000, Room 1002, Unit 1, Building 9, Chiyueju, Qingshui Apartment, Gongshu District, Hangzhou City, Zhejiang Province

Patentee after: Chen Pengyuan

Address before: 510000 63 Chuangqi Road, Shilou Town, Panyu District, Guangzhou City, Guangdong Province

Patentee before: Wang Guiqing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231122

Address after: Room 139, 105 Aerospace Avenue, Xiangbao Cooperation Zone, Ningbo City, Zhejiang Province, 315000

Patentee after: Zhejiang Surui Information Technology Co.,Ltd.

Address before: 310000, Room 1002, Unit 1, Building 9, Chiyueju, Qingshui Apartment, Gongshu District, Hangzhou City, Zhejiang Province

Patentee before: Chen Pengyuan