CN216196058U - Wind-resistant uncovering and reinforcing structure of metal roof flashing - Google Patents

Wind-resistant uncovering and reinforcing structure of metal roof flashing Download PDF

Info

Publication number
CN216196058U
CN216196058U CN202122744093.7U CN202122744093U CN216196058U CN 216196058 U CN216196058 U CN 216196058U CN 202122744093 U CN202122744093 U CN 202122744093U CN 216196058 U CN216196058 U CN 216196058U
Authority
CN
China
Prior art keywords
flashing
metal
board
metal roof
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122744093.7U
Other languages
Chinese (zh)
Inventor
樊忱
胡春明
赵晋光
薛新刚
罗永祥
辛晋东
樊士成
李林
谢壮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN202122744093.7U priority Critical patent/CN216196058U/en
Application granted granted Critical
Publication of CN216196058U publication Critical patent/CN216196058U/en
Priority to JP2022002744U priority patent/JP3239482U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The utility model belongs to the technical field of wind prevention of metal roof flashing, and solves the problems that a local cavity is formed between the existing flashing and a metal roof board, local negative pressure is formed when wind power is large, the flashing is easily lifted, and particularly, large hidden danger exists when the flashing is large in width. The utility model provides a reinforced structure is taken off in anti wind of metal roofing apron, including installing the metal roofing board in roofing purlin upper end, the metal roofing board is by a plurality of metal sheet consecutive serging formation in proper order, and the outside overlap joint of metal roofing board has the apron, and the apron is fixed in the upper end of metal roofing board through the X-shaped cross piece that a plurality of intervals set up, and a plurality of X-shaped cross pieces are connected as a whole through a word connecting piece. The utility model effectively enhances the integrity between the metal roof board and the flashing board, achieves the wind-resistant enhancement effect of the flashing board and avoids the hidden trouble that the flashing board is easy to blow up.

Description

Wind-resistant uncovering and reinforcing structure of metal roof flashing
Technical Field
The utility model belongs to the technical field of wind prevention of metal roof flashing, and particularly relates to a wind uncovering resistant reinforcing structure of a metal roof flashing.
Background
With the vigorous development of national construction, more and more public buildings use large-span and large-space design techniques to construct a large number of buildings with the characteristics of functionality, systematicness, modernization and novelty, metal roofs are more and more used for large-span and large-space building structures due to the superior performance of the metal roofs, and the following modes are adopted for fixing the metal roof boards at present: fixing to purlins by means of brackets with self-tapping screws, with the wide use of this system, comes with some consequent quality drawbacks: firmness and wind resistance.
The existing technical scheme is mainly that the wind-resistant measures aiming at the metal roof are a wind-resistant clamp and a pressing bar, the wind-resistant measures aiming at the flashing are mainly bolt fixing and the pressing bar, and generally no strengthening measures are taken between the metal roof and the flashing.
Therefore, a wind uncovering resistant reinforcing structure of a metal roof flashing needs to be researched.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a wind uncovering resistant reinforcing structure of a metal roof flashing, which aims to overcome the defects that a local cavity exists between the existing flashing and a metal roof flashing, local negative pressure is formed when wind power is large, the flashing is easy to lift in extreme windy weather, and particularly, large hidden danger exists when the width of the flashing is large.
In order to achieve the purpose, the utility model adopts the following technical scheme that the wind uncovering resistant reinforcing structure of the metal roof flashing comprises a metal roof flashing arranged above a roof purline, wherein the metal roof flashing is formed by sequentially and continuously seaming a plurality of metal plates, the outer side of the metal roof flashing is lapped and provided with the flashing, the flashing is fixed at the upper end of the metal roof flashing through a plurality of X-shaped cross pieces arranged at intervals, and the X-shaped cross pieces are connected into a whole through a straight connecting piece.
Preferably, the metal roof plate is connected with the roof purline through an aluminum alloy T-shaped fastener, the upper end of the aluminum alloy T-shaped fastener is embedded in the vertical lock edge of the metal roof plate and is clamped and fixed through a rib fixing clamp sleeved on the outer side of the vertical lock edge, and the lower end of the aluminum alloy T-shaped fastener is anchored on the roof purline through a bolt; the X-shaped cross piece is arranged between two adjacent vertical lock edges on the metal roof board and is positioned on the inner side and the outer side above the flashing board, the end part of the X-shaped cross piece positioned on the inner side of the flashing board, the flashing board and the rib fixing clamp at the corresponding position are sequentially connected through bolts, and the end part of the X-shaped cross piece positioned on the outer side of the flashing board and the rib fixing clamp at the corresponding position are connected through bolts.
Preferably, the rib fixing clip comprises a clip body wrapped around the periphery of the lockrand and an upper support plate fixed to the upper end of the clip body, and the end of the X-shaped cross member is mounted on the upper support plate.
Preferably, the X-shaped cross member comprises two cross-bolted connecting plates, the cross points of the connecting plates are bent upwards, U-shaped clamps are connected to the upper ends of the connecting plates through bolts, and the I-shaped connecting piece is mounted on the X-shaped cross member through the U-shaped clamps.
Preferably, the straight connecting piece is a through long square tube and is locked by bolts arranged on two sides of the U-shaped clamp.
Preferably, the straight connecting piece is a steel wire rope with a full length, the U-shaped clamp is provided with through holes for the straight connecting piece to pass through, and two ends of the straight connecting piece are provided with clamping heads for locking the straight connecting piece on the U-shaped clamp.
Compared with the prior art, the utility model has the beneficial effects that:
1. by arranging the X-shaped cross pieces and the straight connecting pieces, the integrity between the metal roof panel and the flashing board is effectively enhanced, the wind-resistant enhancement effect of the flashing board is achieved, and the hidden danger that the flashing board is easily blown up is avoided;
2. the X-shaped cross piece bolted by two connecting plates is adopted, when the device is installed, the purpose of adjusting the distance can be achieved by adjusting the angle between the connecting plates, and the device is suitable for metal roof boards and flashing boards with various sizes of board breadth;
3. the X-shaped cross piece is simple in structure and convenient to install and replace, the X-shaped cross piece and the straight connecting piece are connected through the U-shaped fixture, stability is high, and installation is convenient.
The parts of the structure not involved are the same as or can be realized by the prior art.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
FIG. 1 is a schematic view of an overall mounting structure of embodiment 1;
FIG. 2 is a perspective view of the X-shaped cross member in example 1;
FIG. 3 is a cross-sectional view taken at A-A of FIG. 2;
FIG. 4 is a cross-sectional view taken at B-B of FIG. 2;
FIG. 5 is a perspective view of the X-shaped cross member in example 2;
FIG. 6 is a cross-sectional view taken at C-C of FIG. 5;
fig. 7 is a cross-sectional view taken at D-D in fig. 5.
In the figure: 1-metal roof panels; 2-a flashing; a 3-X shaped cross; 4-a straight connecting piece; 5-aluminum alloy T code; 6-rib retainer clips; 6.1-a clip body; 6.2-upper supporting plate; 7-U-shaped clamps; 8-roof purlin.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, are only for convenience in describing the present invention and simplifying the description, and do not indicate or imply that the structures or elements referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, are not to be construed as limiting the present invention.
Example 1: as shown in fig. 1, fig. 2, fig. 3, fig. 4, a reinforced structure is taken off in wind-resistance of metal roofing apron, including installing the metal roof boarding 1 above the roofing purlin, metal roof boarding 1 is by a plurality of metal sheet consecutive serging formation, the outside overlap joint of metal roof boarding 1 is provided with apron 2, apron 2 is fixed in the upper end of metal roof boarding 1 through the X-shaped cross member 3 that a plurality of intervals set up, a plurality of X-shaped cross members 3 set up and connect as a whole through a word connecting piece 4 along the length direction interval of apron 2.
In this embodiment, the X-shaped cross member 3 includes two cross bolted connection plates, before the installation, the purpose of adjusting the interval can be achieved by adjusting the included angle of the two connection plates, thereby being suitable for metal roof panels 1 of various sizes of sheet widths, the intersection of the connection plates bends upward, enough space can be reserved for the installation of subsequent bolts, the upper end of the intersection is bolted with a U-shaped fixture 7, the thickness of the U-shaped fixture 7 is 4mm, the U-shaped fixture 7 and the two connection plates are connected and fixed through the same bolt, the straight connecting member 4 is a full-length square tube, the specification is 50mm X50 mm, the straight connecting member 4 is locked through the bolts arranged at two sides of the U-shaped fixture 7, for convenient installation, the straight connecting member 4 is arranged in full length, and the length is greater than the distance between the two U-shaped fixtures 7 which are farthest apart.
The metal roof board 1 is connected with the roof purline through an aluminum alloy T-shaped fastener 5, the upper end of the aluminum alloy T-shaped fastener 5 is embedded in the vertical lock edge of the metal roof board and is clamped and fixed through a rib fixing clamp 6 sleeved on the outer side of the vertical lock edge, the lower end of the aluminum alloy T-shaped fastener 5 is anchored on the roof purline through a bolt, the large lock edge of two adjacent metal boards is wrapped with the small lock edge, and the rib fixing clamp 6 is wrapped on the outer side of the large lock edge;
the corresponding two aluminium alloy T sign indicating number 5 that are provided with of one vertical lockrand department of metal roof boarding 1, be located the inside and outside both sides of apron flashing 2 below respectively, rib fixation clamp 6 and aluminium alloy T sign indicating number 5 one-to-one, X shape cross 3 sets up on metal roof boarding 1 between the two adjacent vertical lockrand and is located the inside and outside both sides of apron flashing 2 top, the tip that is located the X shape cross 3 of apron flashing 2 inboard, apron flashing 2 and the rib fixation clamp 6 that corresponds the position connect gradually through the bolt, the tip that is located the X shape cross 3 in apron flashing 2 outside and the rib fixation clamp 6 that corresponds the position pass through bolted connection.
Aluminum alloy T sign indicating number 5 and rib fixation clamp 6 are current products, and specific structure does not do the perplexing, and in this implementation, rib fixation clamp 6 is including the inclusion 6.1 of parcel in the lockrand periphery and fix at upper bracket 6.2 of inclusion 6.1 upper end, and the tip of X-shaped cross 3 is installed on upper bracket 6.2.
Example 2: as shown in fig. 5, 6 and 7, embodiment 2 differs from embodiment 1 only in that: the steel wire rope is characterized in that the straight-line connecting piece 4 is a through-long steel wire rope, through holes for the straight-line connecting piece 4 to be connected in a penetrating mode are formed in the U-shaped clamping apparatus 7 in a penetrating mode, clamping heads used for locking the straight-line connecting piece 4 on the U-shaped clamping apparatus 7 are arranged at two ends of the straight-line connecting piece 4, the clamping heads are common steel wire rope clamping heads, the steel wire rope is prevented from moving horizontally, connection stability is guaranteed, and the effect that all parts are connected into a whole in a pulling mode is achieved.
The method comprises the following specific operation steps:
installing the metal roof panel 1 → installing the flashing panel 2 → installing the rib fixing clip 6 and the X-shaped cross member 3 → installing the I-shaped connecting member 4 → checking and accepting.
Before installation, whether materials such as the X-shaped cross piece 3, the straight connecting piece 4, the aluminum alloy T-shaped connector 5, the rib fixing clamp 6, the U-shaped clamp 7, the bolt, the waterproof gasket and the like are qualified is checked, and the materials can be used after the materials are qualified.
Installing a metal roof panel 1: actually measuring the actual length of the sheet material for mounting the metal roof panel 1, checking the length and the width of the sheet material corresponding to the plate number according to the actually measured length, cutting the sheet material as required, placing the metal sheet according to the starting line of the row plate, enabling the width of the sheet material to cover the marking line and align the starting line, and discharging the designed structural length at the two ends in the length direction of the sheet material;
the lower layer plate is fixed on a roof purline by self-tapping screws, the metal roof plate 1 is arranged above the lower layer plate, the roof purline is C-shaped in the embodiment, a central line and a positioning line of a bottom plate of an aluminum alloy T code 5 are arranged on the roof purline to be used as a fixing and controlling line of the aluminum alloy T code 5, after the aluminum alloy T code 5 is in place, a hole is drilled on the roof purline, the aluminum alloy T code 5 is fixed by bolts,
after the aluminum alloy T code 5 is installed, the non-woven fabric, the heat-insulating layer and the like are paved, the non-woven fabric, the heat-insulating layer and the like can be cut off by a knife to make the aluminum alloy T code 5 out, the heat-insulating coil layer should be paved in a rain and snow-free weather, and the metal plate should be installed on the coil which is paved every day.
The method comprises the following steps of pressing and forming a metal plate by a special plate pressing machine, after the metal plate is laid on a roof, seaming at 360 degrees by using a special seaming machine, after the position of the metal plate is adjusted, seaming, connecting an aluminum alloy T code 5 with the metal plate, checking that the two metal plates are buckled and flat before seaming, forcibly jointing the seamed edges tightly within the range of about 1 m in front of the seaming machine in the advancing process of seaming, wherein the seamed edges are required to be continuous and flat and cannot be twisted or split, installing the seamed edges at a next pay-off mark point, rechecking the installation deviation of the plate, performing comprehensive inspection on the plate after the design requirement is met, adjusting the plate in the next mark section when the requirement is not met, adjusting the plate when the plate is adjustable in the mark section, adjusting the mark section and then performing comprehensive locking, and sequentially seaming the plurality of metal plates to form the metal roof plate 1;
installing a flashing board 2: according to the requirements and the geometric dimensions of a design drawing, a control line is placed at the installation position of a flashing 2, before the flashing 2 is installed, a supporting framework below the flashing 2 is installed, the supporting framework is fixed on a roof purline, the flashing 2 and the supporting framework below the flashing 2 are fixed through self-tapping screws and structural adhesive, the supporting framework is subjected to corrosion prevention treatment in advance, the installation supporting framework needs to be accurate in position and firm in combination, after the installation, the central line, the surface elevation and the like need to be checked comprehensively, a plurality of flashing 2 plates are arranged and installed from two sides to the middle in sequence, 10 plates are laid when the installation is finished, and the stay wire check is performed once so as to eliminate errors in time and form the flashing 2;
mounting rib fixing clip 6 and X-shaped cross member 3: installing a rib fixing clamp 6 which plays a role in locking at the installed upright lockrand, sequentially connecting the end part of the X-shaped cross piece 3 positioned on the inner side of the flashing 2, the flashing 2 and the rib fixing clamp 6 at the corresponding position through bolts, connecting the end part of the X-shaped cross piece 3 positioned on the outer side of the flashing 2 and the rib fixing clamp 6 at the corresponding position through bolts, and arranging a waterproof gasket at the bolt on the end part when the X-shaped cross piece 3 is installed to avoid corrosion;
installing a straight connecting piece 4: the upper end of the cross point of the X-shaped cross piece 3 is connected with a U-shaped clamp 7 through a bolt, and a through long straight connecting piece 4 is arranged on the U-shaped clamp 7 to be fixed, so that the metal roof board 1 and the flashing board 2 are connected into a whole through the X-shaped cross piece 3 and the straight connecting piece 4;
checking and accepting: after the whole structure is installed, the constructor carries out self-checking, and on the basis of the self-checking qualification, the inspection and supervision unit carries out inspection and acceptance.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and equivalent alternatives or modifications according to the technical solution of the present invention and the inventive concept thereof should be covered by the scope of the present invention.

Claims (6)

1. The utility model provides a reinforced structure is taken off in anti-wind of metal roofing apron flashing which characterized in that: including installing metal roof boarding (1) above the roofing purlin, metal roof boarding (1) is by a plurality of metal sheet consecutive serging formation in proper order, and the outside overlap joint of metal roof boarding (1) is provided with apron flashing (2), and X shape that apron flashing (2) set up through a plurality of intervals crosses piece (3) to be fixed in the upper end of metal roof boarding (1), and a plurality of X shape crosses piece (3) to connect as a whole through a word connecting piece (4).
2. The wind uncovering resistant reinforcing structure of the metal roofing flashing as defined in claim 1, wherein: the metal roof board (1) is connected with the roof purline through an aluminum alloy T-shaped fastener (5), the upper end of the aluminum alloy T-shaped fastener (5) is embedded in the upright lockrand of the metal roof board and is clamped and fixed through a rib fixing clamp (6) sleeved on the outer side of the upright lockrand, and the lower end of the aluminum alloy T-shaped fastener (5) is anchored on the roof purline through a bolt; the metal roof board (1) one vertical serging department corresponds and is provided with two aluminum alloy T sign indicating number (5), be located the inside and outside both sides of apron flashing (2) below respectively, rib fixation clamp (6) and aluminum alloy T sign indicating number (5) one-to-one, X shape cross member (3) set up on metal roof board (1) adjacent two vertical serging between and be located the inside and outside both sides of apron flashing (2) top, be located the tip of the X shape cross member (3) of apron flashing (2) inboard, apron flashing (2) and the rib fixation clamp (6) that correspond the position connect gradually through the bolt, the tip that is located the X shape cross member (3) in apron flashing (2) outside and the rib fixation clamp (6) that corresponds the position pass through bolted connection.
3. The wind uncovering resistant reinforcing structure of the metal roofing flashing as defined in claim 2, wherein: the rib fixing clamp (6) comprises a clamp body (6.1) fixed on the periphery of the lock edge in a wrapping mode and an upper supporting plate (6.2) fixed at the upper end of the clamp body (6.1), and the end portion of the X-shaped cross piece (3) is installed on the upper supporting plate (6.2).
4. The wind uncovering resistant reinforcing structure of the metal roofing flashing as defined in claim 3, wherein: the X-shaped cross piece (3) comprises two cross bolted connecting plates, the cross points of the connecting plates are bent upwards, the upper ends of the connecting plates are connected with U-shaped clamps (7) through bolts, and the straight connecting piece (4) is installed on the X-shaped cross piece (3) through the U-shaped clamps (7).
5. The wind uncovering resistant reinforcing structure of the metal roofing flashing as defined in claim 4, wherein: the straight connecting piece (4) is a through long square tube and is locked by bolts arranged on two sides of the U-shaped fixture (7).
6. The wind uncovering resistant reinforcing structure of the metal roofing flashing as defined in claim 4, wherein: the straight connecting piece (4) is a steel wire rope with a through length, through holes for the straight connecting piece (4) to be connected are formed in the U-shaped clamping apparatus (7) in a penetrating mode, and clamping heads used for locking the straight connecting piece (4) on the U-shaped clamping apparatus (7) are arranged at two ends of the straight connecting piece (4).
CN202122744093.7U 2021-11-10 2021-11-10 Wind-resistant uncovering and reinforcing structure of metal roof flashing Active CN216196058U (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202122744093.7U CN216196058U (en) 2021-11-10 2021-11-10 Wind-resistant uncovering and reinforcing structure of metal roof flashing
JP2022002744U JP3239482U (en) 2021-11-10 2022-08-19 Reinforcing structure to prevent wind peeling of impermeable plates for metal roofs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122744093.7U CN216196058U (en) 2021-11-10 2021-11-10 Wind-resistant uncovering and reinforcing structure of metal roof flashing

Publications (1)

Publication Number Publication Date
CN216196058U true CN216196058U (en) 2022-04-05

Family

ID=80908314

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122744093.7U Active CN216196058U (en) 2021-11-10 2021-11-10 Wind-resistant uncovering and reinforcing structure of metal roof flashing

Country Status (2)

Country Link
JP (1) JP3239482U (en)
CN (1) CN216196058U (en)

Also Published As

Publication number Publication date
JP3239482U (en) 2022-10-17

Similar Documents

Publication Publication Date Title
CN113846805A (en) Wind uncovering resistant reinforcing structure and construction method of metal roof flashing
US20110192098A1 (en) Solar Panel mounting system and installation
CN215631101U (en) System for continuously welding seamless metal roof panels
CN110552450A (en) Construction method of large-span short-vertical-edge vertical double-lock-edge titanium-zinc alloy metal roof
CN109469233B (en) Special-shaped curtain wall system and construction method thereof
CN216196058U (en) Wind-resistant uncovering and reinforcing structure of metal roof flashing
CN112196280B (en) Construction method of curved surface suspended ceiling structure
CN211621284U (en) Subway insertion type totally-enclosed sound barrier
CN210658907U (en) Large-span aluminium system furred ceiling structure
CN209083007U (en) A kind of 360 ° of standing-seam profiled sheet devices
US9587859B1 (en) Strap mount for solar panels
CN207453284U (en) A kind of roofing bottom plate and roof board system for improving water resistance
CN206698159U (en) A kind of photovoltaic bracket for tile-roofed house roof
CN114108834A (en) Connecting component of special-shaped double-layer metal roof
CN110778036B (en) Combined roof system of metal tiles and metal eaves rafters
CN111608328B (en) Wind-resistant structure for metal roof
CN212613309U (en) Pull rod fixing component for mounting and fixing light steel keel
CN208415732U (en) A kind of standing-seam color steel roofing photovoltaic support structure
JPH10245952A (en) Frame mounting metal piece of solar power generating panel
CN207776530U (en) A kind of photovoltaic shed structure with Hyperbolic Feature
CN212534830U (en) High-altitude large-gradient roof metal tile structure
CN220673663U (en) Photovoltaic structure for sloping tile roof of existing building
CN219718172U (en) Inverter support suitable for angle-relaxation type color steel tile roof
CN219732558U (en) Photovoltaic support and photovoltaic system
CN218061670U (en) Novel steel construction factory building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant