CN216157671U - Spiral unearthed pipe jacking pipe curtain construction equipment - Google Patents

Spiral unearthed pipe jacking pipe curtain construction equipment Download PDF

Info

Publication number
CN216157671U
CN216157671U CN202121654289.0U CN202121654289U CN216157671U CN 216157671 U CN216157671 U CN 216157671U CN 202121654289 U CN202121654289 U CN 202121654289U CN 216157671 U CN216157671 U CN 216157671U
Authority
CN
China
Prior art keywords
pipe
spiral
unearthed
soil
construction equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121654289.0U
Other languages
Chinese (zh)
Inventor
杨丹萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin University of Architecture and Technology
Original Assignee
Jilin University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin University of Architecture and Technology filed Critical Jilin University of Architecture and Technology
Priority to CN202121654289.0U priority Critical patent/CN216157671U/en
Application granted granted Critical
Publication of CN216157671U publication Critical patent/CN216157671U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Catching Or Destruction (AREA)

Abstract

The utility model discloses spiral unearthed pipe-jacking pipe curtain construction equipment which comprises a pipe-jacking frame and a base, wherein the pipe-jacking frame is arranged on the base; when the soil crushing device is used, soil is moistened through the spraying assembly, massive soil is crushed through the soil crushing cutter, the soil is output to the discharge hole of the drill body through the spiral blade under the driving of the driving mechanism, when the soil enters the discharge hole of the drill body, the soil is output through the spiral conveyor communicated with the discharge hole, the soil is effectively conveyed out of the device, the construction efficiency is improved, and meanwhile, the problem that the discharge hole of the drill body is blocked is solved through the arrangement of the vibration motor.

Description

Spiral unearthed pipe jacking pipe curtain construction equipment
Technical Field
The utility model relates to the technical field of engineering construction, in particular to spiral unearthed pipe-jacking curtain construction equipment.
Background
The pipe jacking machine mainly comprises a rotary excavating system, a main jacking hydraulic propulsion system, a soil conveying system, a grouting system, measuring equipment, ground hoisting equipment, an electrical system and the like, and is also provided with a muddy water treatment device along the horizontal balance type pipe jacking machine, the pipe jacking technology is a trenchless tunneling type pipeline laying construction technology for municipal construction, the utility model with the patent application number of CN202021236782.6 discloses a drill bit of a push bench and the push bench, which comprises a drill body, the surface of the drill body is provided with a soil inlet, the interior of the drill body is fixedly connected with a soil discharge pipe, the interior of the soil discharge pipe is rotatably connected with a screw rod, the surface of the screw rod is fixedly connected with two limiting rods which are symmetrically distributed, one end of the screw rod is provided with a motor, one side of the motor is provided with a push bench, and the push bench is fixedly connected with the motor;
general pipe pushing jack needs artifical clear sediment soil, and above-mentioned device transports earth through spiral helicine unearthing mechanism at the in-process that uses, but earth is not convenient for transport to the outside, and uses the back earth for a long time and pile up in a large number, easily produces the jam, influences the construction progress.
SUMMERY OF THE UTILITY MODEL
In order to solve the problems in the prior art, the utility model provides a spiral unearthed pipe-jacking curtain construction device.
In order to achieve the purpose, the utility model adopts the following technical scheme:
a spiral unearthed pipe-jacking pipe curtain construction device comprises a pipe-jacking frame and a base, wherein the pipe-jacking frame is arranged on the base, the spiral unearthed pipe curtain construction device also comprises an unearthed assembly, the unearthed assembly is connected with the pipe-jacking frame, a cavity is formed inside the base, and a spiral conveyor is arranged in the cavity of the base;
the soil discharging assembly comprises a driving mechanism, a helical blade, a soil crushing cutter and a drill body, a cavity is formed in the drill body, the cavity in the drill body is provided with the driving assembly, the output end of the driving assembly is in transmission connection with the helical blade, the end part of the helical blade is provided with the soil crushing cutter, the drill body is close to the bottom of one end of the driving mechanism, a discharge hole is formed in the bottom of one end of the driving mechanism, and the discharge hole of the drill body is communicated with a feed inlet of the screw conveyor.
Furthermore, a baffle plate is arranged at the connecting position of the discharge hole of the drill body and the feed inlet of the screw conveyer.
Furthermore, the end part of the drill body is provided with a spraying assembly, and the spraying assembly is arranged right above the soil crushing knife.
Furthermore, a waste discharge pipe is arranged inside the drill body and sleeved outside the helical blade.
Furthermore, a fixing rod is further arranged on the rotating shaft of the spiral blade.
Further, pulleys are arranged at two ends of the fixing rod, and the pulleys at two ends of the fixing rod are in rolling contact with the inner wall of the waste discharge pipe.
Furthermore, a vibration motor is arranged at the discharge port of the drill body.
Further, the unearthing assembly is detachable.
Compared with the prior art, the utility model has the beneficial effects that:
when using, moisten soil through the spraying subassembly, carry out the breakage with bold soil through the hack sword, under actuating mechanism's drive, export soil to the discharge gate that bores the body through helical blade, when soil enters into the discharge gate of boring the body inside, export soil through the screw conveyer with the discharge gate intercommunication, the effectual outside of transporting out equipment with soil has improved the efficiency of construction, simultaneously, through setting up vibrating motor, avoid boring the discharge gate department of the body problem that the jam appears.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 shows a schematic view of a drill body according to the utility model.
Detailed Description
In order to more clearly understand the technical features, objects and effects of the present invention, the embodiments of the present invention will be described with reference to the accompanying drawings, but the scope of the present invention is not limited to the following.
The present invention will be further described with reference to the following examples, which are intended to illustrate only some, but not all, of the embodiments of the present invention. All other embodiments that can be obtained by a person skilled in the art based on the embodiments of the present invention without any creative effort belong to the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "counterclockwise", "clockwise", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate orientations or positional relationships based on those shown in the drawings, and are used for convenience of description only, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be considered as limiting.
Example (b):
a spiral unearthed pipe-jacking pipe curtain construction device comprises a pipe-jacking pipe frame 1 and a base 2, wherein the pipe-jacking pipe frame 1 is arranged on the base 2, the spiral unearthed pipe curtain construction device also comprises an unearthed component 3, the unearthed component 3 is connected with the pipe-jacking pipe frame 1, a cavity is formed inside the base 2, and a spiral conveyor 21 is arranged in the cavity of the base 2;
as shown in fig. 1-2, in specific implementation, the top pipe support 1 is arranged on the base 2, the unearthing assembly 3 is connected with the top pipe support 1, the unearthed soil is discharged through the unearthed assembly 3, the unearthed soil enters the screw conveyor 21 arranged in the base 2, and the unearthed soil is discharged to the outside of the equipment through the screw conveyor 21.
The soil discharging assembly 3 comprises a driving mechanism 31, a helical blade 32, a soil crushing cutter 33 and a drill body 34, a cavity is formed inside the drill body 34, the cavity inside the drill body 34 is provided with an output end of the driving assembly 31 and is in transmission connection with the helical blade 32, the end part of the helical blade 32 is provided with the soil crushing cutter 33, the bottom of one end, close to the driving mechanism 31, of the drill body 34 is provided with a discharge hole, and the discharge hole of the drill body 34 is communicated with a feed hole of the helical conveyor 21;
as shown in fig. 1-2, in specific implementation, the soil discharging assembly 3 is used for discharging the waste soil, the inside of the drill body 34 is a cavity, when in use, the driving mechanism 31 is used for driving the helical blade 32 and the soil crushing cutter 33 to rotate, the helical blade 32 and the soil crushing cutter 33 are coaxially arranged, the driving mechanism 31 includes components such as a motor and a speed reducer, when in use, the waste soil at the end part is crushed by the soil crushing cutter 33, the crushed waste soil is conveyed to the discharge port of the drill body 34 through the helical blade 32, the waste soil falls from the discharge port of the drill body 34 and enters the inside of the screw conveyor 21, and the waste soil is conveyed out of the equipment through the screw conveyor 21.
Further, the link of the discharge port of the drill body 34 and the feed port of the screw conveyor 21 is provided with a baffle, and the baffle plays a role in guiding flow, so that the muck can accurately enter the screw conveyor 21, and the muck is prevented from dropping to the outside in the process of conveying the muck.
Further, the tip of the brill body 34 is provided with spraying assembly 35, and spraying assembly 35 sets up directly over hack sword 33, and spraying assembly 35 includes components such as atomizer and water pipe, carries water to atomizer through the water pipe, and the water through atomizer spun is moist to soil, and the soil after moist is broken more easily, can effectually reduce the wearing and tearing of equipment.
Furthermore, a waste discharge pipe 36 is arranged inside the drill body 34, the waste discharge pipe is sleeved outside the helical blade 32, a fixing rod 37 is further arranged on the rotating shaft of the helical blade 32, pulleys are arranged at two ends of the fixing rod 37, the pulleys at two ends of the fixing rod 37 are in rolling contact with the inner wall of the waste discharge pipe 36, when the helical blade 32 rotates, the fixing rod 32 synchronously rotates, the fixing rod 32 plays a role in positioning, the pulleys at two ends roll with the waste discharge pipe 36, and meanwhile, a certain bearing effect is achieved.
Furthermore, a vibration motor is arranged at the discharge port of the drill body 34, and by arranging the vibration motor, the blockage of the dregs at the discharge port of the drill body 34 is avoided, the continuity of conveying the dregs is ensured, and the construction efficiency is improved.
Furthermore, the unearthing assembly 3 can be detached, so that cleaning and maintenance can be conveniently carried out after use.
The above description is only a preferred embodiment of the present invention, and certainly should not be taken as limiting the scope of the present invention, which is therefore intended to be covered by the appended claims.

Claims (8)

1. A spiral unearthed pipe-jacking pipe curtain construction device comprises a pipe-jacking pipe frame (1) and is characterized by further comprising a base (2), wherein the pipe-jacking pipe frame (1) is arranged on the base (2), and an unearthed assembly (3) is further included, the unearthed assembly (3) is connected with the pipe-jacking pipe frame (1), a cavity is formed inside the base (2), and a spiral conveyor (21) is arranged in the cavity of the base (2);
unearthed subassembly (3) includes actuating mechanism (31), helical blade (32), hack sword (33) and bores body (34), the inside of boring body (34) is formed with the cavity, bore the inside cavity of body (34) and be provided with actuating mechanism (31), the output of actuating mechanism (31) with helical blade (32) transmission is connected, the tip of helical blade (32) is provided with hack sword (33), it is close to bore body (34) the discharge gate has been seted up to the bottom of actuating mechanism (31) one end, the discharge gate of boring body (34) with the feed inlet intercommunication of screw conveyer (21).
2. The spiral unearthed pipe-roof construction equipment according to claim 1, characterized in that a baffle is arranged at the connection between the discharge hole of the drill body (34) and the feed hole of the spiral conveyor (21).
3. The spiral unearthed pipe-roof construction equipment according to claim 1, characterized in that the end of the drill body (34) is provided with a spray assembly (35), and the spray assembly (35) is arranged right above the soil crushing cutter (33).
4. The spiral unearthed pipe-roof construction equipment according to claim 1, characterized in that a dumping pipe (36) is arranged inside the drill body (34) and is sleeved outside the spiral blade (32).
5. The spiral unearthed pipe-jacking pipe-curtain construction equipment as claimed in claim 4, wherein a fixing rod (37) is further arranged on a rotating shaft of the spiral blade (32).
6. The spiral unearthed pipe-roof construction equipment as claimed in claim 5, characterized in that pulleys are provided at both ends of the fixing rod (37), and the pulleys at both ends of the fixing rod (37) are in rolling contact with the inner wall of the waste pipe (36).
7. The spiral unearthed pipe-jacking screen construction equipment according to claim 1, characterized in that a vibration motor is arranged at the discharge port of the drill body (34).
8. The spiral unearthed pipe-roof construction equipment according to claim 1, characterized in that the unearthed assembly (3) is detachable.
CN202121654289.0U 2021-07-19 2021-07-19 Spiral unearthed pipe jacking pipe curtain construction equipment Active CN216157671U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121654289.0U CN216157671U (en) 2021-07-19 2021-07-19 Spiral unearthed pipe jacking pipe curtain construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121654289.0U CN216157671U (en) 2021-07-19 2021-07-19 Spiral unearthed pipe jacking pipe curtain construction equipment

Publications (1)

Publication Number Publication Date
CN216157671U true CN216157671U (en) 2022-04-01

Family

ID=80836742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121654289.0U Active CN216157671U (en) 2021-07-19 2021-07-19 Spiral unearthed pipe jacking pipe curtain construction equipment

Country Status (1)

Country Link
CN (1) CN216157671U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117646827A (en) * 2024-01-25 2024-03-05 山西水务工程建设监理有限公司 Pipe curtain construction equipment and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117646827A (en) * 2024-01-25 2024-03-05 山西水务工程建设监理有限公司 Pipe curtain construction equipment and construction method
CN117646827B (en) * 2024-01-25 2024-04-09 山西水务工程建设监理有限公司 Pipe curtain construction equipment and construction method

Similar Documents

Publication Publication Date Title
CN108952748B (en) Open TBM bottom comprehensive slag removal system
CN112360495B (en) Equipment for conveying excavated materials in tunneling
CN216157671U (en) Spiral unearthed pipe jacking pipe curtain construction equipment
CN112610271B (en) Drilling tank slurry backfilling device and method for coal mining subsidence area treatment
CN114522789A (en) Coal mine crushing process and coal mine crushing system using same
CN113605912A (en) Tunneling method for tunnel construction
CN202117675U (en) Excavation device for excavator
CN115929336A (en) Tunnel TBM (Tunnel boring machine) mechanized construction device and method thereof
CN108625871A (en) Push-bench based on earth pressure balance and its working method
CN215918619U (en) Pollute soil ecological remediation and administer device
CN214741173U (en) Well drilling detritus collection device
CN213867981U (en) Mining scraper type hydraulic excavator
CN213409310U (en) Shield constructs quick-witted slabstone screening plant
CN212397517U (en) Cleaning device for shield tunnel pipeline
CN208825189U (en) A kind of agrarian restructuring project vehicle
CN211448739U (en) Colliery rescue device that comes to roof in pit
CN210411901U (en) Soil remediation system
CN219953346U (en) Coal mine bottom pulling equipment
CN217474041U (en) Coal mine screening equipment for coal mining
CN206495252U (en) The conveying device and shallow water silt remover of a kind of shallow water silt remover
CN218912894U (en) Heading machine for pipe jacking construction
CN210422462U (en) Impact type spiral conveying drilling machine
CN213807668U (en) Electricity drives portable tunnel excavation desilting industrial robot device
CN205030122U (en) Yunnan paris polyphylla excavates conveyor
CN215632988U (en) Tunneling device for tunnel construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant