CN216109689U - Template for pouring bare wood grain concrete wall - Google Patents
Template for pouring bare wood grain concrete wall Download PDFInfo
- Publication number
- CN216109689U CN216109689U CN202122703012.9U CN202122703012U CN216109689U CN 216109689 U CN216109689 U CN 216109689U CN 202122703012 U CN202122703012 U CN 202122703012U CN 216109689 U CN216109689 U CN 216109689U
- Authority
- CN
- China
- Prior art keywords
- pouring
- wood grain
- concrete wall
- limiting
- clamping screw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses a template for pouring a bare wood grain concrete wall, which relates to the field of concrete wall pouring and comprises a plurality of pouring plates and an installation rod detachably connected with the pouring plates, wherein one side of each pouring plate, which faces towards the installation rod, is connected with a limiting column, one side of each installation rod, which faces towards the pouring plates, is provided with a plurality of limiting holes for the insertion of the limiting columns at intervals along the length direction, and one end of each limiting column, which is far away from the pouring plates, is provided with a fixing piece for limiting the separation of the limiting columns from the limiting holes. When the template is poured in the transportation mode, the fixing part is removed, the limiting columns on the pouring plate are pulled out of the limiting holes in the mounting rods, and the pouring plate can be detached from the mounting rods, so that the template is convenient to transport in batches, and the damage to the pouring template is reduced.
Description
Technical Field
The application relates to the field of concrete wall pouring, in particular to a template for pouring a bare wood grain concrete wall.
Background
The integral formwork for the bare wood grain concrete wall is a cast-in-place concrete project which realizes an attractive effect by utilizing the texture and characteristics of concrete such as flowing, solidifying and hardening of the concrete and the appearance quality of a natural state formed by combining bolt holes, open seams, buddhist seams, decorative plates and the like which are well designed and constructed.
As-cast finish wood grain concrete wall need make before pouring and pour and use the template, people use the concatenation of a plurality of wood grain board to make usually and pour the board, pour the board concatenation with a plurality of again and make and pour the template, transport whole template of pouring to the construction site at last.
With respect to the above-described related art, the inventors consider that the following drawbacks exist: the pouring formwork often occupies a large area and is inconvenient to transport, so that the pouring formwork is easy to be accidentally damaged in the transportation process, and needs to be improved.
SUMMERY OF THE UTILITY MODEL
In order to make the template of pouring be convenient for transport, this application provides a clear water wood grain concrete wall pours and uses template.
The utility model provides a clear water wood grain concrete wall pours and uses template, includes that a plurality of pours the board, still includes and pours the board and can dismantle the installation pole of being connected, it all is connected with spacing post towards one side of installation pole to pour the board, the installation pole is towards one side of pouring the board and is equipped with the spacing hole of a plurality of confession spacing post male, every along self length direction interval spacing one end of pouring the board is kept away from to spacing post is provided with the mounting that is used for restricting spacing post and breaks away from spacing hole.
Through adopting above-mentioned technical scheme, when the template is pour in the transportation, remove the mounting, will pour spacing post on the board and pull out the spacing hole on the installation pole, can will pour the board and pull down from the installation pole to be convenient for transport in batches, reduce the damage of pouring the template.
Optionally, the mounting includes clamping screw and two fixed blocks, the connecting hole that supplies clamping screw to pass is seted up to the one end that the board was pour to spacing post was kept away from, clamping screw's both ends all stretch out the connecting hole, two the fixed block sets up respectively in clamping screw's both ends, all set up the fixed orifices that supplies clamping screw to pass on the fixed block, the equal threaded connection in clamping screw's both ends has the fixation nut who is used for supporting tight fixed block.
By adopting the technical scheme, after the limiting post passes through the limiting hole, the fixing screw penetrates through the limiting hole on the limiting post, then the two fixing blocks are respectively sleeved at the two ends of the fixing screw, so that the two ends of the fixing screw respectively pass through the fixing holes on the fixing blocks, and then the fixing nut is screwed, so that the fixing blocks are tightly attached to the two sides of the limiting post, and the limiting post is limited to be separated from the limiting hole.
Optionally, the two ends of one side of the fixing block, which is far away from the installation rod, are both connected with fastening bolts in a threaded manner, and one ends of the fastening bolts extend out of the fixing block towards one end of the installation rod and abut against the installation rod.
Through adopting above-mentioned technical scheme, install the fixed block in clamping screw's both ends back, screw fastening bolt for clamping bolt's one end supports tightly the installation pole, thereby it is taut with spacing post through clamping screw, make to pour the board and support tightly with the installation pole, and the board is pour in the restriction accident and rotates, guarantees to pour the effect.
Optionally, the fastening bolt is sleeved with a spring washer, one end of the spring washer abuts against the fixing block, and the other end of the spring washer abuts against a nut of the fastening bolt.
By adopting the technical scheme, after the fastening bolt is screwed, the spring washer is extruded and deformed, so that the nut of the fastening bolt is abutted, and the fastening bolt is limited from being loosened accidentally.
Optionally, the fastening bolt is a butterfly bolt.
Through adopting above-mentioned technical scheme, the workman is bare-handed can screw fastening bolt, need not with the help of extra instrument, improves fastening bolt's installation effectiveness, labour saving and time saving.
Optionally, one end of the fastening bolt facing the mounting rod is connected with a supporting plate, and one side of the supporting plate facing away from the fastening bolt is connected with a rubber pad.
Through adopting above-mentioned technical scheme, backup pad and rubber pad can reduce fastening bolt's one end to the wearing and tearing of installation pole, prolong the life of installation pole.
Optionally, the inner side wall of the limiting hole is connected with a positioning block, and a positioning groove for clamping and sliding the positioning block is formed in the outer side wall of the limiting column along the length direction of the positioning block.
Through adopting above-mentioned technical scheme, can confirm fast behind the locating piece card income constant head tank that pour the position of board relative to the installation pole to it is the same to ensure that the line orientation on each board of pouring.
Optionally, the locating piece all is connected with the friction pad towards all being connected with on the wall of the back of the body both sides of constant head tank inside, the friction pad deviates from one side of locating piece and hugs closely with the inside wall of constant head tank.
Through adopting above-mentioned technical scheme, with spacing post insert spacing downthehole back, the locating piece card is gone into in the constant head tank, has frictional force between the inside wall of friction pad and constant head tank to with spacing post preliminary be fixed in spacing downthehole, the installation of the follow-up mounting of being convenient for.
In summary, the present application includes at least one of the following beneficial technical effects:
when the template is poured in the transportation mode, the fixing part is removed, the limiting columns on the pouring plate are pulled out of the limiting holes in the mounting rods, and the pouring plate can be detached from the mounting rods, so that the template is convenient to transport in batches, and the damage to the pouring template is reduced.
After the limiting post penetrates through the limiting hole, the fixing screw penetrates through the limiting hole in the limiting post, then the two fixing blocks are sleeved at the two ends of the fixing screw respectively, the two ends of the fixing screw penetrate through the fixing holes in the fixing blocks respectively, and then the fixing nut is screwed, so that the fixing blocks are attached to the two ends of the limiting post, and the limiting post is limited from being separated from the limiting hole.
After installing the fixed block in the both ends of clamping screw rod, screw fastening bolt for fastening bolt's one end is supported tight installation pole, thereby is taut with spacing post through clamping screw, makes to pour the board and supports tightly with the installation pole, and the board is poured in the restriction accident and is rotated, guarantees to pour the effect.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present application.
Fig. 2 is an exploded view of a portion of the structure of an embodiment of the present application.
Fig. 3 is a schematic structural view of a fastening bolt in the embodiment of the present application.
Description of reference numerals:
1. pouring a plate; 2. mounting a rod; 21. a limiting hole; 3. a limiting column; 31. connecting holes; 32. positioning a groove; 4. a fixing member; 41. fixing the screw rod; 42. a fixed block; 421. a fixing hole; 43. fixing a nut; 44. fastening a bolt; 45. a spring washer; 46. a support plate; 47. a rubber pad; 5. positioning blocks; 51. a friction pad.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses template for pouring bare wood grain concrete wall. Referring to fig. 1, including a plurality of be the board 1 and the installation pole 2 of pouring of rectangle, all pour board 1 and all can dismantle with installation pole 2 and be connected, pour one side that board 1 deviates from installation pole 2 and be equipped with the wood grain. When the pouring template is transported, all the pouring plates 1 are detached from the mounting rods 2, so that the pouring plates 1 and the mounting rods 2 are transported to a construction site in batches, time and labor are saved, and the damage of the pouring plates 1 is reduced.
Referring to fig. 2, pour board 1 and be the spacing post 3 of rectangle towards the equal perpendicular fixedly connected with cross-section in middle part of one side of installation pole 2, installation pole 2 is equipped with the spacing hole 21 that the spacing post 3 of a plurality of confession male towards one side of pouring board 1 along self length direction interval, and the circumference inside wall of spacing hole 21 all hugs closely with the lateral wall of spacing post 3. The length direction fixedly connected with location strip along spacing post 3 on the inside wall of spacing hole 21, set up along self length direction on the lateral wall of spacing post 3 and supply 5 cards to go into and gliding constant head tank 32 of locating piece, the friction pad 51 that equal fixedly connected with was made by the silica gel material on the wall of the back of the body both sides of locating piece 5 orientation constant head tank 32 inside, one side that friction pad 51 deviates from locating piece 5 is hugged closely with the inside wall of constant head tank 32. When the limiting column 3 passes through the limiting hole 21, the positioning groove 32 needs to be aligned to the positioning block 5, so that the relative positions of the pouring plate 1 and the mounting rod 2 are quickly determined, and the wood grain directions of all the pouring plates 1 are kept consistent; after the positioning block 5 is clamped in the positioning groove 32, a friction force exists between the friction pad 51 and the inner side wall of the positioning groove 32, so that the installation rod 2 is limited to be easily separated from the limiting column 3.
Referring to fig. 2, a fixing part 4 for limiting the separation of the limiting column 3 from the limiting hole 21 is arranged at one end of each limiting column 3, which is far away from the pouring plate 1, the fixing part 4 comprises a fixing screw 41 and two rectangular fixing blocks 42, a connecting hole 31 for the fixing screw 41 to pass through is formed in one end of each limiting column 3, which is far away from the pouring plate 1, and the axis of the connecting hole 31 is parallel to the length direction of the mounting rod 2. Connecting hole 31 all stretches out at fixing screw 41's both ends, and two fixed blocks 42 are installed respectively in fixing screw 41's both ends, all set up the fixed orifices 421 that supply fixing screw 41 to pass on the fixed block 42, and the equal threaded connection in both ends of fixing screw 41 has fixation nut 43. After the two ends of the fixing screw 41 respectively pass through the fixing holes 421 on the two fixing blocks 42, the fixing nut 43 is screwed tightly, so that the fixing nut 43 abuts against the fixing blocks 42, the two fixing blocks 42 are respectively tightly attached to the two opposite sides of the limiting column 3, and the limiting column 3 is limited to be separated from the limiting hole 21.
Referring to fig. 2 and 3, both ends of one side of the fixing block 42 away from the mounting rod 2 are both connected with fastening bolts 44 in a threaded manner, the fastening bolts 44 are butterfly bolts, one end of each fastening bolt 44 away from the corresponding nut extends out of one end of the fixing block 42 towards the mounting rod 2 and is fixedly connected with a circular supporting plate 46, and one side of each supporting plate 46 away from the corresponding fixing bolt is fixedly connected with a rubber pad 47. After the fixing blocks 42 are installed on the fixing screw rods 41, the two fastening bolts 44 are screwed by hands, so that the rubber pads 47 on the supporting plate 46 support the installation rods 2 tightly, the two fixing blocks 42 tension the limiting columns 3 through the fixing screw rods 41, the pouring plate 1 is supported with the installation rods 2 tightly, the looseness of the pouring plate 1 is limited, and the pouring effect is guaranteed.
Referring to fig. 2 and 3, each fastening bolt 44 is sleeved with a spring washer 45, and after the fastening bolt 44 is screwed by hand, one end of the spring washer 45 abuts against the fixing block 42, and the other end abuts against the nut of the fastening bolt 44, so that the external thread on the fastening bolt 44 abuts against the internal thread on the fixing block 42, thereby limiting the accidental loosening of the fastening bolt 44.
The embodiment of the application provides an as-cast finish wood grain concrete wall pours and uses template's implementation principle does: the pouring plates 1 and the mounting rods 2 are transported to a construction site in batches and then assembled, so that the loss of the pouring plates 1 in the transportation process is reduced;
when the pouring template is assembled, all pouring plates 1 are sequentially installed on the installation rod 2 along the length direction of the installation rod 2, the limiting columns 3 on the pouring plates 1 are inserted into the limiting holes 21 on the installation rod 2, the pouring plates 1 are tightly attached to the installation plate, then the fixing screws 41 penetrate through the limiting holes 21, the fixing blocks 42 are respectively sleeved at two ends of the fixing screws 41, then the fixing nuts 43 are screwed, and finally the fastening bolts 44 are screwed by hands, so that all the pouring plates 1 are installed on the installation rod 2, and the pouring template is formed.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.
Claims (8)
1. The utility model provides a clear water wood grain concrete wall pours and uses template, includes that a plurality of pours board (1), its characterized in that: still include and pour board (1) and can dismantle installation pole (2) of being connected, pour board (1) and all be connected with spacing post (3) towards one side of installation pole (2), installation pole (2) are equipped with spacing hole (21) that a plurality of confession spacing post (3) were inserted towards one side of pouring board (1) along self length direction interval, every spacing post (3) keep away from the one end of pouring board (1) and be provided with mounting (4) that are used for restricting spacing post (3) and break away from spacing hole (21).
2. The form for pouring as clean water wood grain concrete wall as claimed in claim 1, wherein: mounting (4) include clamping screw (41) and two fixed blocks (42), connecting hole (31) that supply clamping screw (41) to pass are seted up to the one end of pouring board (1) is kept away from in spacing post (3), clamping screw (41) both ends all stretch out connecting hole (31), two clamping screw (42) set up respectively in the both ends of clamping screw (41), all set up fixed orifices (421) that supply clamping screw (41) to pass on clamping screw (42), the equal threaded connection in both ends of clamping screw (41) has fixation nut (43) that are used for supporting tight fixed block (42).
3. The form for pouring as clean water wood grain concrete wall as claimed in claim 2, wherein: both ends of one side of the fixing block (42) far away from the installation rod (2) are in threaded connection with fastening bolts (44), and one end of each fastening bolt (44) extends out from one end of the fixing block (42) towards the installation rod (2) and abuts against the installation rod (2).
4. The form for pouring as clean water wood grain concrete wall as claimed in claim 3, wherein: the fastening bolt (44) is sleeved with a spring washer (45), one end of the spring washer (45) abuts against the fixing block (42), and the other end of the spring washer abuts against a nut of the fastening bolt (44).
5. The form for pouring as clean water wood grain concrete wall as claimed in claim 3, wherein: the fastening bolt (44) is a butterfly bolt.
6. The form for pouring as clean water wood grain concrete wall as claimed in claim 3, wherein: one end, facing the mounting rod (2), of the fastening bolt (44) is connected with a supporting plate (46), and one side, facing away from the fastening bolt (44), of the supporting plate (46) is connected with a rubber pad (47).
7. The form for pouring as clean water wood grain concrete wall as claimed in claim 1, wherein: the locating piece (5) is connected to the inner side wall of the limiting hole (21), and a locating groove (32) for clamping and sliding the locating piece (5) is formed in the outer side wall of the limiting column (3) along the length direction of the locating piece.
8. The form for pouring as clean water wood grain concrete wall as claimed in claim 7, wherein: the positioning block (5) is connected with friction pads (51) on two opposite side walls facing the inner side wall of the positioning groove (32), and one side of each friction pad (51) departing from the positioning block (5) is tightly attached to the inner side wall of the positioning groove (32).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122703012.9U CN216109689U (en) | 2021-11-01 | 2021-11-01 | Template for pouring bare wood grain concrete wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202122703012.9U CN216109689U (en) | 2021-11-01 | 2021-11-01 | Template for pouring bare wood grain concrete wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN216109689U true CN216109689U (en) | 2022-03-22 |
Family
ID=80713757
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202122703012.9U Active CN216109689U (en) | 2021-11-01 | 2021-11-01 | Template for pouring bare wood grain concrete wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN216109689U (en) |
-
2021
- 2021-11-01 CN CN202122703012.9U patent/CN216109689U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201165756Y (en) | Single side wall moulding board apparatus | |
CN216109689U (en) | Template for pouring bare wood grain concrete wall | |
CN207905122U (en) | A kind of novel locating device of built-in fitting for building | |
CN213710393U (en) | Municipal administration road bridge construction is with novel template fastening device | |
KR101383355B1 (en) | Clamp for supporter of form-shore | |
CN215717125U (en) | Based on detachable pre-buried wall spare that links of steel sleeve | |
CN215801771U (en) | Portable reinforcing apparatus of tower crane basis lattice column | |
CN104264989B (en) | A kind of fixing to the device drawing metal rod | |
CN201162350Y (en) | Water stop screw in underground shearing force wall | |
JP2555799Y2 (en) | Horizontal net stretching equipment | |
CN204174910U (en) | A kind of wall-connecting device of scaffold | |
CN2534292Y (en) | Counter screw shuttering | |
CN201460191U (en) | Combined screwed support | |
KR20090092929A (en) | A form wedge pin for structure | |
CN221502661U (en) | Connection structure of wall connecting piece on outer protection frame | |
CN213499967U (en) | Main rib positioning plate | |
CN205751435U (en) | A kind of exhibition background painting canvas quick-fitting device | |
JPH101917A (en) | Support device of various kinds of sign boards | |
CN221922281U (en) | PVC pipeline clamp | |
CN213710392U (en) | Cast in situ concrete embeds split bolt for heat preservation wall body | |
CN217630120U (en) | Stagnant water steel sheet fixed mounting structure | |
CN210073151U (en) | Convenient fingerpost support device who dismantles | |
CN217711763U (en) | Combined steel formwork drawknot piece device | |
CN214696928U (en) | Concrete vibrating spear | |
CN216108608U (en) | Embedded part fixing and combining device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |