CN215926292U CN202122195310.1U CN202122195310U CN215926292U CN 215926292 U CN215926292 U CN 215926292U CN 202122195310 U CN202122195310 U CN 202122195310U CN 215926292 U CN215926292 U CN 215926292U
Authority
CN
China
Prior art keywords
house
floor
fixedly connected
adjusting screw
quickly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122195310.1U
Other languages
Chinese (zh)
Inventor
贺云峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongqi Construction Engineering Group Co ltd
Original Assignee
Zhongqi Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongqi Construction Engineering Group Co ltd filed Critical Zhongqi Construction Engineering Group Co ltd
Priority to CN202122195310.1U priority Critical patent/CN215926292U/en
Application granted granted Critical
Publication of CN215926292U publication Critical patent/CN215926292U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the technical field of container buildings, in particular to a quickly-spliced container house, which comprises a first-floor house and a second-floor house, wherein the bottoms of the first-floor house and the second-floor house are fixedly connected with a connecting mechanism, and the top of the second-floor house is provided with a roof; the connecting mechanism comprises a fixed frame, a movable block, a connecting block, an adjusting screw rod and a nut, the fixed frame is fixedly connected with the bottoms of the first-floor house and the second-floor house, and movable grooves are formed in four corners of the fixed frame. The utility model has the advantages that: through setting up coupling mechanism and rings, reached the purpose of the built-up mounting on house and roof of can being convenient for to convenience when increasing the installation, and the rings that set up can be convenient for wholly remove the house, practicality when effectual increase uses, through setting up adjusting screw, reached and can be convenient for carry out the leveling to the house when meetting ground unevenness, thereby the travelling comfort when effectual increase house uses.

Description

Quickly-spliced container house
Technical Field
The utility model relates to the technical field of container buildings, in particular to a container house capable of being spliced quickly.
Background
In the aspects of engineering construction, oil exploration, army field operations, disaster relief and the like, during operation and training, the problem of camping is usually solved by a method of building a temporary shed or a tent, the building of the shed is a feasible method, but can only be used once, the labor cost, the time and the cost are consumed, the tent is built, the wind resistance, the rain resistance, the cold resistance and the sunstroke resistance are poor, and the service life is short.
The formula container house of can splicing fast that discloses in chinese patent CN213741618U, this formula container house of can splicing fast, it will be fixed between extension medium plate and the concatenation sideboard through construction bolt to have realized, splice fast between lower container house and the last container house, the efficiency of concatenation installation between lower container house and the last container house has been increased, and set up the heat insulating mattress, can increase the heat-proof quality when container house uses, however, this formula container house of can splicing fast, when solving the problem, have following shortcoming:
1. when the container house is assembled, the box body and the roof top plate and the box body are not convenient to butt, and the container house is inconvenient to assemble and connect after being butted;
2. when the ground of the container house is uneven, the container house is not convenient to level, so that the stability and the living comfort of the house after installation are influenced.
SUMMERY OF THE UTILITY MODEL
The utility model aims to overcome the defects of the prior art and provide a container house capable of being spliced quickly.
The purpose of the utility model is realized by the following technical scheme: a container house capable of being spliced quickly comprises a first-floor house and a second-floor house, wherein the bottoms of the first-floor house and the second-floor house are fixedly connected with connecting mechanisms, and the top of the second-floor house is provided with a roof;
coupling mechanism includes fixed frame, movable block, connecting block, adjusting screw and nut, the fixed frame of the equal fixedly connected with in bottom in one deck house and two layers of house, the activity groove has all been seted up to the four corners department of fixed frame, the equal swing joint in inside in activity groove has the movable block, the equal fixedly connected with connecting block in one side of movable block, the equal swing joint in one side of connecting block has adjusting screw, the equal fixedly connected with nut in adjusting screw's top.
Preferably, the equal fixedly connected with fixed block in the left and right sides in one deck house and two layers of house, the equal fixedly connected with rings in top of fixed block, the clamping groove has all been seted up to the position that fixed frame is located rings.
Through adopting above-mentioned technical scheme, introduced the mounted position and the relation of connection of fixed block and rings to both can be convenient for remove the house when using, the butt joint work between the house of can being convenient for again simultaneously.
Preferably, slotted holes are formed in the two sides of the movable block, connecting bolts are movably connected inside the slotted holes, and threaded holes are formed in the positions, located on the connecting bolts, of the first-floor house and the second-floor house.
Through adopting above-mentioned technical scheme, can be connected with the screw hole through connecting bolt to increase the connection effect in one deck house and two-storey house.
Preferably, the positions, located at the connecting blocks, of the first-floor house and the second-floor house are both provided with sliding grooves, and the connecting blocks are matched with the sliding grooves in a homogeneous mode.
Through adopting above-mentioned technical scheme, can be convenient for control the removal of connecting block, can be convenient for make the movable block aim at with the screw hole in house fast again simultaneously.
Preferably, a threaded hole is formed in one side, located on the adjusting screw, of the connecting block, and the connecting block is in threaded connection with the adjusting screw through the threaded hole.
Through adopting above-mentioned technical scheme, can control the connecting block and reciprocate when making to rotate adjusting screw to let the connecting block drive the movable block and remove.
Preferably, the top of nut has all been seted up the cross recess, the one deck house all has seted up the activity hole with the position that the two-storey house is located adjusting screw and nut.
Through adopting above-mentioned technical scheme, can let the staff adjust the nut through electronic electric hand drill to control adjusting screw rotates.
Preferably, the sliding grooves are provided with bearings at the positions of the adjusting screws, and the adjusting screws are fixedly connected with the inner walls of the bearings.
Through adopting above-mentioned technical scheme, frictional force when can reducing adjusting screw and rotate to increase transmission effect.
Preferably, the bottom of the roof is provided with a heat insulation plate, and the bottom of the heat insulation plate is fixedly connected with a connecting mechanism.
Through adopting above-mentioned technical scheme, can increase the heat-proof quality in house.
The utility model has the following advantages:
1. the quickly-spliced container house is characterized in that the connecting mechanism and the hanging ring are arranged, the connecting mechanism is fixedly connected to the bottoms of the first-floor house and the second-floor house, the fixed blocks are fixedly connected to the left side and the right side of the first-floor house and the second-floor house, the hanging ring is fixedly connected to the tops of the fixed blocks, when the quickly-spliced container house is installed, the first-floor house is placed on the ground, the hanging hook of a crane is connected with the hanging ring of the second-floor house, the second-floor house is connected with the first-floor house, the first-floor house firstly enters the clamping groove of the fixed frame under the action of the hanging ring of the first-floor house, the fixed frame of the second-floor house is connected with the roof of the first-floor house, after the connection is completed, the nut at the four corners of the second-floor house is rotated through the electric hand drill, the connecting block is moved due to the rotation of the adjusting screw rod, the movable block is driven to move, when the slotted hole of the movable block is aligned with the threaded hole of the house, the house is installed by connecting the connecting bolt with the threaded hole of the first floor of the house, and the roof is installed and connected through the steps, so that the purpose of facilitating the combined installation of the house and the roof is achieved, the convenience in installation is improved, the lifting ring can facilitate the overall movement of the house, and the practicability in use is effectively improved;
2. this but quick concatenation formula container house, through setting up adjusting screw, the equal swing joint in one side of connecting block has adjusting screw, when meetting the ground of unevenness, rotate the nut of one deck house four corners department through electronic pistol drill, thereby let the movable block support ground, adjust four angles in one deck house respectively this moment, and then the leveling in complete house, and easy operation has reached and can be convenient for carry out the leveling to the house when meetting ground unevenness, thereby the travelling comfort when effectual increase house uses.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural diagram of a first operating state of the movable block according to the present invention;
FIG. 3 is a schematic structural diagram of a second operating state of the movable block according to the present invention;
FIG. 4 is a top plan view of a floor of the present invention;
fig. 5 is a schematic bottom structure of a one-storey house according to the utility model.
In the figure: 1-first-floor house, 2-second-floor house, 3-connecting mechanism, 301-fixing frame, 3011-clamping groove, 302-movable block, 303-connecting block, 3031-sliding groove, 304-adjusting screw, 305-nut, 4-roof, 401-heat insulation board, 5-fixing block, 501-hanging ring and 6-connecting bolt.
Detailed Description
The utility model will be further described with reference to the accompanying drawings, but the scope of the utility model is not limited to the following.
As shown in fig. 1-5, a container house capable of being quickly spliced comprises a first-floor house 1 and a second-floor house 2, wherein the bottoms of the first-floor house 1 and the second-floor house 2 are fixedly connected with connecting mechanisms 3, and the top of the second-floor house 2 is provided with a roof 4;
coupling mechanism 3 includes fixed frame 301, movable block 302, connecting block 303, adjusting screw 304 and nut 305, the fixed frame 301 of the equal fixedly connected with in bottom in one deck house 1 and two-storey house 2, the activity groove has all been seted up to fixed frame 301's four corners department, the equal swing joint in inside in activity groove has movable block 302, the equal fixedly connected with connecting block 303 in one side of movable block 302, the equal swing joint in one side of connecting block 303 has adjusting screw 304, the equal fixedly connected with nut 305 in top of adjusting screw 304.
As a preferred technical scheme of the utility model, the left side and the right side of the first-floor house 1 and the second-floor house 2 are both fixedly connected with the fixed blocks 5, the tops of the fixed blocks 5 are both fixedly connected with the hanging rings 501, the positions of the fixed frames 301 on the hanging rings 501 are both provided with the clamping grooves 3011, and by arranging the hanging rings 501 and the clamping grooves 3011, the houses can be moved conveniently through the hanging rings 501, and meanwhile, the butt joint work between the houses can be facilitated through the butt joint of the hanging rings 501 and the clamping grooves 3011.
As a preferred technical scheme of the utility model, both sides of the movable block 302 are provided with slotted holes, the insides of the slotted holes are movably connected with the connecting bolts 6, the positions of the first-floor house 1 and the second-floor house 2 at the connecting bolts 6 are provided with threaded holes, and the connecting bolts 6 are arranged, so that the connection firmness of the first-floor house 1 and the second-floor house 2 can be increased, and the safety in use is improved.
As a preferable technical scheme of the utility model, sliding grooves 3031 are formed in the positions, located at the connecting blocks 303, of the first-floor house 1 and the second-floor house 2, the connecting blocks 303 are matched with the sliding grooves 3031, the sliding grooves 3031 are arranged, so that the control over the connecting blocks 303 can be facilitated, and after the connecting blocks 303 are attached to one side of the sliding grooves 3031, the auxiliary mounting of the connecting bolts 6 can be facilitated.
As a preferable technical scheme of the utility model, a threaded hole is formed in one side of the connecting block 303, which is positioned on the adjusting screw 304, the connecting block 303 is in threaded connection with the adjusting screw 304 through the threaded hole, and the adjusting screw 304 can drive the connecting block 303 to move when rotating through the threaded hole of the connecting block 303, so that the movable block 302 is controlled to move, thereby achieving the effects of facilitating the increase of the connection effect between houses, facilitating the leveling of the houses and effectively increasing the comfort during living.
As a preferable technical scheme of the utility model, the top of the nut 305 is provided with a cross groove, the positions of the adjusting screw 304 and the nut 305 of the first floor house 1 and the second floor house 2 are provided with movable holes, and the cross groove is arranged, so that when the house is used conveniently, a worker can control the nut 305 to rotate the adjusting screw 304.
As a preferred technical solution of the present invention, the sliding groove 3031 is provided with bearings at positions of the adjusting screw 304, the adjusting screw 304 is fixedly connected to an inner wall of the bearing, and the bearings are provided to reduce friction when the adjusting screw 304 rotates, thereby increasing a transmission effect and facilitating control of the connecting block 303.
As a preferable technical scheme of the utility model, the bottom of the roof 4 is provided with the heat insulation board 401, the bottom of the heat insulation board 401 is fixedly connected with the connecting mechanism 3, on one hand, the heat insulation board 401 is arranged, so that the house has certain heat insulation performance when in use, thereby increasing the comfort when a user inhales, and on the other hand, the connecting mechanism 3 is arranged at the bottom of the heat insulation board 401, so that the roof 4 and the house can be conveniently combined and connected, thereby increasing the installation efficiency.
The working principle of the utility model is as follows:
s1, during installation, placing the first floor of house 1 on the ground;
s2, rotating the screw caps 305 at the four corners of the first floor of house 1 through the electric pistol drill, so as to respectively adjust the four corners of the first floor of house 1 and further level the complete house;
s3, connecting the second floor house 2 with the first floor house 1 by connecting a lifting hook of a crane with a lifting ring 501 of the second floor house 2;
s4, the hanging ring 501 of the first floor house 1 will first enter the fastening slot 3011 of the fixed frame 301, so that the fixed frame 301 of the second floor house 2 will be connected to the roof of the first floor house 1;
and S5, rotating the screw caps 305 at the four corners of the second-floor house 2 through the electric pistol drill to align the slotted holes of the movable blocks 302 with the threaded holes of the first-floor house 1, and then connecting the slotted holes of the movable blocks with the threaded holes of the first-floor house 1 through the connecting bolts 6, thereby completing the mounting work of the houses.
To sum up, by arranging the connecting mechanism 3 and the hanging ring 501, the connecting mechanism 3 is fixedly connected to the bottom of each of the first floor building 1 and the second floor building 2, the fixing blocks 5 are fixedly connected to the left and right sides of each of the first floor building 1 and the second floor building 2, and the hanging ring 501 is fixedly connected to the tops of the fixing blocks 5, when the building is installed, the first floor building 1 is placed on the ground, the hanging hook of the crane is connected to the hanging ring 501 of the second floor building 2, so that the second floor building 2 is connected to the first floor building 1, at this time, the hanging ring 501 of the first floor building 1 firstly enters the clamping groove 3011 of the fixing frame 301, so that the fixing frame 301 of the second floor building 2 is connected to the roof of the first floor building 1, after the connection is completed, the nut 305 at the four corners of the second floor building 2 is rotated by the electric hand drill, so that the connecting block 303 is moved by the rotation of the adjusting screw 304, so as to drive the movable block 302 to move, when the slotted hole of the movable block 302 is aligned with the threaded hole of the house, the movable block is connected with the threaded hole of the house 1 by using the connecting bolt 6, thereby completing the installation work of the house, at the moment, the roof 4 is installed and connected by the steps, thereby achieving the purpose of facilitating the combined installation of the house and the roof, thereby increasing the convenience during the installation, and the arranged hanging ring 501 can facilitate the integral movement of the house, effectively increasing the practicability during the use, by arranging the adjusting screw 304, one side of the connecting block 303 is movably connected with the adjusting screw 304, when encountering the uneven ground, the nut 305 at the four corners of the house 1 of one floor is rotated by the electric hand gun drill, thereby leading the movable block 302 to support the ground, respectively adjusting the four corners of the house 1 of one floor at the moment, further leveling the complete house, the operation is simple, thereby achieving the convenience for leveling the house when encountering the uneven ground, thereby effectively improving the comfort of the house when in use.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a but splice formula container house fast which characterized in that: the house comprises a first-floor house (1) and a second-floor house (2), wherein the bottoms of the first-floor house (1) and the second-floor house (2) are both fixedly connected with a connecting mechanism (3), and the top of the second-floor house (2) is provided with a roof (4);
coupling mechanism (3) are including fixed frame (301), movable block (302), connecting block (303), adjusting screw (304) and nut (305), the fixed frame (301) of the equal fixedly connected with in bottom in one deck house (1) and two layers house (2), the activity groove has all been seted up to the four corners department of fixed frame (301), the equal swing joint in inside in activity groove has movable block (302), the equal fixedly connected with connecting block (303) in one side of movable block (302), the equal swing joint in one side of connecting block (303) has adjusting screw (304), the equal fixedly connected with nut (305) in top of adjusting screw (304).
2. The quickly-spliced container house as set forth in claim 1, wherein: the equal fixedly connected with fixed block (5) in both sides about one deck house (1) and two-storey house (2), the equal fixedly connected with rings (501) in top of fixed block (5), block groove (3011) have all been seted up to the position that fixed frame (301) are located rings (501).
3. The quickly-spliced container house as set forth in claim 1, wherein: slotted holes are formed in the two sides of the movable block (302), the inside of each slotted hole is movably connected with a connecting bolt (6), and threaded holes are formed in the positions, located on the connecting bolts (6), of the first-floor house (1) and the second-floor house (2).
4. The quickly-spliced container house as set forth in claim 1, wherein: sliding grooves (3031) are formed in the positions, located in the connecting blocks (303), of the first-floor house (1) and the second-floor house (2), and the connecting blocks (303) are matched with the sliding grooves (3031) in a homogeneous mode.
5. The quickly-spliced container house as set forth in claim 1, wherein: one side of the connecting block (303) which is positioned on the adjusting screw rod (304) is provided with a threaded hole, and the connecting block (303) is in threaded connection with the adjusting screw rod (304) through the threaded hole.
6. The quickly-spliced container house as set forth in claim 1, wherein: the cross slot has all been seted up at the top of nut (305), the activity hole has all been seted up to the position that one deck house (1) and second floor house (2) are located adjusting screw (304) and nut (305).
7. The quickly-spliced container house as set forth in claim 4, wherein: the sliding grooves (3031) are provided with bearings at the positions of the adjusting screws (304), and the adjusting screws (304) are fixedly connected with the inner walls of the bearings.
8. The quickly-spliced container house as set forth in claim 1, wherein: the roof is characterized in that a heat insulation plate (401) is arranged at the bottom of the roof (4), and a connecting mechanism (3) is fixedly connected to the bottom of the heat insulation plate (401).
CN202122195310.1U 2021-09-11 2021-09-11 Quickly-spliced container house Active CN215926292U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122195310.1U CN215926292U (en) 2021-09-11 2021-09-11 Quickly-spliced container house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122195310.1U CN215926292U (en) 2021-09-11 2021-09-11 Quickly-spliced container house

Publications (1)

Publication Number Publication Date
CN215926292U true CN215926292U (en) 2022-03-01

Family

ID=80415912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122195310.1U Active CN215926292U (en) 2021-09-11 2021-09-11 Quickly-spliced container house

Country Status (1)

Country Link
CN (1) CN215926292U (en)

Similar Documents

Publication Publication Date Title
CN111424994A (en) Steel construction interfacing apparatus for construction
CN215926292U (en) Quickly-spliced container house
CN113511583B (en) Multifunctional high-safety assembled building lifting clamp
CN214273048U (en) Supporting equipment for construction engineering construction
CN211286346U (en) Intelligent electric folding awning for steel box type house
CN112900913A (en) Auxiliary reinforcing device for building wall
CN215445804U (en) Construction elevator safety monitoring system
CN217500552U (en) Assembled steel construction building
CN218715240U (en) Prefabricated wallboard mobile device
CN219158173U (en) Steel structure beam
CN220686302U (en) Assembled beam column connection structure
CN214868193U (en) House main body construction is with light gauge steel fixed establishment
CN215760556U (en) Temporary fixing frame for mounting assembly type building wall
CN117306683B (en) Low-energy-consumption assembled building
CN218522304U (en) Wallboard auxiliary mounting mechanism
CN216030500U (en) Steel construction installation device that can install fast
CN217918356U (en) Scaffold frame is used in boats and ships installation convenient to equipment
CN213477741U (en) Supporting structure for floor plate in building construction fabricated residence
CN219887713U (en) Ginseng canopy skeleton and cement wall connected node
CN217000483U (en) Multifunctional steel column for high-rise building
CN214899910U (en) Indoor and outdoor dual-purpose cable bridge with reinforcing structure
CN216195459U (en) Novel movable house with adjustable height
CN110759288B (en) Building wall detects and repairs manned elevating gear
CN213774468U (en) Building templates link for civil engineering
CN216921287U (en) Anti-falling butt strap suitable for steel structure roof construction