CN215897132U - GW4-110 type isolation switch maintenance operation platform - Google Patents

GW4-110 type isolation switch maintenance operation platform Download PDF

Info

Publication number
CN215897132U
CN215897132U CN202121784019.1U CN202121784019U CN215897132U CN 215897132 U CN215897132 U CN 215897132U CN 202121784019 U CN202121784019 U CN 202121784019U CN 215897132 U CN215897132 U CN 215897132U
Authority
CN
China
Prior art keywords
hole
bearing
cross arm
platform
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121784019.1U
Other languages
Chinese (zh)
Inventor
王志方
姚楠
苏长宝
张泽中
王文明
周航
张骏安
王白冰
靳福悦
赵展
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Nanyang Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN202121784019.1U priority Critical patent/CN215897132U/en
Application granted granted Critical
Publication of CN215897132U publication Critical patent/CN215897132U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a GW4-110 type disconnecting switch overhauling operation platform, which belongs to the technical field of electric power overhauling facilities and comprises a bearing platform and a suspension device, wherein the bearing platform comprises a bearing rod and a bearing plate, the bearing plate is connected with the bearing rod through a clamping piece, the suspension device comprises a base, an upright post and a cross arm, the bottom of the upright post is connected with the base, the top of the upright post is connected with the cross arm, the base is connected with the bearing plate, and the bearing rod is connected with a channel steel on a disconnecting switch framework through a channel steel clamp. The utility model is used for the overhauling operation of the GW4-110 type isolating switch, increases the moving space of the maintainer on the upper part of the framework, can effectively ensure that the maintainer is always in the safety protection when the maintainer starts to move the operation position, and improves the safety of the overhauling operation of the GW4-110 type isolating switch.

Description

GW4-110 type isolation switch maintenance operation platform
Technical Field
The utility model relates to the technical field of electric power overhaul facilities, in particular to a GW4-110 type isolating switch overhaul operation platform.
Background
The GW4-110 type disconnecting switch is widely used in 110kV systems in 110kV substations and 220kV substations, and as shown in fig. 10, the disconnecting switch device may have various defects related to parts such as conductive parts and transmission systems after long-term operation, and needs to be overhauled. According to the relevant regulations of the national grid company electric power safety work regulations: all the operations performed at the height of the falling height reference plane 2m and above are regarded as high-altitude operations; when the scaffold works on the scaffold without a scaffold or a railing and the height exceeds 1.5m, a safety belt is used or other reliable safety measures are taken; the hook or rope of the safety belt should be hung on a firm component or a steel wire rope specially used for hanging the safety belt, and a mode of hanging the safety belt in a high mode or a low mode should be adopted.
In the maintenance process, in order to ensure the safety of the operating personnel, a hanger is usually required to be installed for fixing a safety belt. During single-phase maintenance operation, generally set up the safety belt hanger on defect looks one side framework channel-section steel, the safety belt couple is hung on the link in hanger upper end. As shown in fig. 10, in two-phase or three-phase maintenance work, considering personal safety of maintenance personnel, the length of the safety belt is limited, and generally two hangers are needed to be used in cooperation, that is, a hanger (called hanger i) is installed on a framework channel steel between a phase a and a phase B and used for completing the operation of the phase a or the phase B, then a hanger (called hanger ii) is installed on a framework channel steel between the phase B and the phase C and used for completing the maintenance operation of the phase B or the phase C, when the maintenance personnel moves from the position of the hanger i to the position of the hanger ii in work, the safety belt needs to be taken down from a hanging ring of the hanger i and moved to the position between the phase B and the phase C, and then the safety belt is hung on a hanging ring of the hanger ii, and during the process, the maintenance personnel can lose safety protection temporarily; when the hanger is transferred from the position of the hanger II to the position of the hanger I, no safety protection measures are taken. The GW4-110 type isolation switch has the advantages that the upper part of the framework is completely hollow except the upper surface of the channel steel, the position where a user can stand is very limited, and a high-place falling accident is very easy to happen when a maintainer transfers an operation position.
Therefore, the safety of operators cannot be completely ensured by simply adopting the safety belt hanger to overhaul the GW4-110 type disconnecting switch, and the high-altitude falling accident is very easily caused under the condition that other safety protection measures or incomplete safety protection measures do not exist, so that great potential safety hazards exist. How to ensure the personal safety of operators is an urgent safety requirement in the field of overhaul of GW4-110 type disconnecting switches, and a special operation platform for carrying out overhaul of GW4-110 type disconnecting switches is indispensable.
Chinese patent application publication No. CN 109412059A discloses an isolator overhaul training platform, which comprises a supporting mechanism, a traversing mechanism arranged on the supporting mechanism, a first lifting column arranged on the traversing mechanism, a working platform arranged on the first lifting column, a replacing mechanism arranged on the working platform, a second lifting column arranged on the traversing mechanism, an overhaul platform arranged on the second lifting column, an overhaul mechanism arranged on the overhaul platform, and a control mechanism arranged on the supporting mechanism and used for controlling the traversing mechanism, the first lifting column, the second lifting column, the replacing mechanism and the overhaul mechanism; the utility model adopts a real maintenance platform for simulation, and the maintenance platform can be provided to quickly maintain the isolating switch, and simultaneously, temporary power supply can be provided to reduce the power failure time. However, this patent overhauls training platform and is unfavorable for operation personnel's operation position to remove, and the security is general, lays the position in addition below isolator, and both sides wire influences the lift of overhauing the platform, need tear isolator open and just can overhaul, and the practicality is poor.
Disclosure of Invention
In view of this, the utility model provides a GW4-110 type isolation switch maintenance operation platform, which increases the activity space of the maintenance personnel on the upper part of the framework, can effectively ensure that the maintenance personnel is always in the safety protection when the maintenance personnel starts to move the operation position, and improves the safety of the GW4-110 type isolation switch maintenance operation.
In order to solve the technical problems, the technical scheme adopted by the utility model is as follows: the utility model provides a GW4-110 type isolator overhauls operation platform, includes bearing platform and linkage, the bearing platform includes bearing bar and bearing plate, the bearing plate with the bearing bar passes through the joint spare to be connected, linkage includes base, stand and cross arm, the stand bottom with the base is connected, the stand top with the cross arm is connected, the base with the bearing plate is connected, the bearing bar passes through the channel-section steel connection on channel-section steel folder and the isolator framework.
Further, the bearing plate includes the frame, the frame bottom sets up a plurality of strengthening ribs, frame upper portion sets up insulating bakelite board, and is a plurality of the joint spare symmetry respectively sets up the frame four corners, the frame adopts epoxy square pipe to constitute.
Furthermore, a first through hole is formed in the center of the bearing plate, and a plurality of second through holes are formed in the periphery of the first through hole.
Furthermore, the bearing bar adopts the epoxy pipe, the symmetry sets up first round hole respectively on the lateral wall of bearing bar both ends, the external diameter of bearing bar with the joint diameter phase-match of joint spare.
Further, the channel-section steel folder includes folder main part and connecting cylinder, the folder main part is n shaped steel plate structure, the connecting cylinder lateral wall with folder main part top fixed connection, the internal diameter of connecting cylinder with the external diameter looks adaptation of bearing bar, connecting cylinder lateral wall middle part sets up the second round hole, the second round hole with first round hole size looks adaptation.
Furthermore, a first threaded hole is formed in the upper portion of the side wall of the clamp body, a bolt is arranged on the first threaded hole, two third through holes are symmetrically formed in the lower portion of the two side walls of the clamp body, an L-shaped locking plug-in is arranged on each third through hole, a second threaded hole is formed in each L-shaped locking plug-in, and a bolt is arranged on each second threaded hole.
Furthermore, the end part of the bolt is provided with a jacking sheet, and the surface of the jacking sheet is provided with a rubber cushion pad.
Further, the base is a cylindrical steel plate, a fourth through hole is formed in the middle of the cylindrical steel plate, a plurality of fifth through holes are formed in the periphery of the fourth through hole, the lower portion of the fourth through hole is connected with a cylinder with the bottom sealed, the outer diameter of the cylinder is matched with the size of the first through hole, internal threads are formed in the inner wall of the cylinder, and the number, the diameter and the distribution of the fifth through holes are all consistent with those of the second through holes.
Furthermore, the stand main part is the epoxy pipe, the stand bottom is circular steel pipe, circular steel pipe outer wall sets up the external screw thread, external screw thread on the circular steel pipe with the internal thread adaptation of drum connects soon, the stand top sets up the grafting pipe, the grafting pipe can be around the vertical axial of stand main part rotatory, the fixed safety belt link that sets up in grafting pipe upper portion.
Furthermore, the cross arm main part is the epoxy pipe, the cross arm both ends respectively set up two at least lock joint formula staple bolts, set up a plurality of portable mechanisms that articulate in the middle of the cross arm, the external diameter of cross arm main part with the internal diameter looks adaptation of grafting pipe.
The utility model has the beneficial effects that: the utility model is applied to the overhaul of the GW4-110 type disconnecting switch, can ensure that the maintainer is always in safety protection when transferring the operation position, and greatly improves the safety of the overhaul operation of the GW4-110 type disconnecting switch.
In addition, the hard cross arm and the steel base structure adopted by the utility model further improve the operation safety.
In addition, the position of the fixed point of the bearing rod can be adjusted by moving the channel steel clamp, so that the maintenance platform can be compatible with GW4-110 type isolation switch equipment of different manufacturers, and the universality is good.
In addition, the utility model adopts a modular structure design, and is convenient to transport, carry and assemble.
In addition, when the cross arm is provided with 2 or more movable hanging mechanisms, the maintenance platform can be used for two persons to carry out maintenance operation at multiple points simultaneously, the work is not influenced mutually, and the maintenance efficiency is greatly improved.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings.
Fig. 1 is a schematic view of the structure of the present invention in a two-phase or three-phase inspection operation.
Fig. 2 is a schematic structural view during single-phase maintenance work according to the present invention.
Fig. 3 is a schematic structural view of a channel clip according to the present invention.
Fig. 4 is a schematic view of the structure of the load-bearing bar of the present invention.
Fig. 5 is a schematic structural view of the bearing plate of the present invention.
Fig. 6 is a schematic structural view of the base of the present invention.
Fig. 7 is a schematic structural view of the column of the present invention.
Fig. 8 is a schematic structural diagram of the cross arm of the present invention.
Fig. 9 is a schematic structural view of the fastening type hoop of the present invention.
Fig. 10 is a schematic diagram of the framework of a GW4-110 type disconnector.
Wherein: 1-bearing plate, 101-bakelite plate, 102-reinforcing rib, 103-clamping piece, 104-clamping piece handle, 105-frame, 106-first through hole, 107-second through hole, 2-base, 201-cylindrical steel plate, 202-fourth through hole, 203-fifth through hole, 204-cylinder, 3-bearing rod, 301-first round hole, 4-upright column, 401-round steel pipe, 402-plug pipe, 403-safety belt hanging ring, 5-channel steel clamping piece, 501-clamping piece main body, 502-connecting cylinder, 503-second round hole, 504-bolt, 505-L-shaped locking and inserting piece, 506-spring positioning pin, 507-pressing piece, 508-rubber buffer cushion, 509-first threaded hole, 510-second threaded hole, 511-a third through hole, 6-a cross arm, 601-a cross arm main body, 602-a movable hanging mechanism, 603-a buckling type hoop, 7-a bearing platform, 8-a suspension device and 9-channel steel.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to fig. 1 to 10 of the embodiments of the present invention. It is to be understood that the embodiments described are only a few embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the described embodiments of the utility model, are within the scope of the utility model.
Example one
As shown in fig. 1-10, this embodiment provides a GW4-110 type disconnecting switch maintenance operation platform, which includes a bearing platform 7 and a suspension device 8, where the bearing platform 7 includes a bearing rod 3 and a bearing plate 1, the bearing plate 1 is connected to the bearing rod 3 through a joint 103, the suspension device 8 includes a base 2, an upright 4 and a cross arm 6, the bottom of the upright 4 is connected to the base 2, the top of the upright 4 is connected to the cross arm 6, the base 2 is connected to the bearing plate 1, and the bearing rod 3 is connected to a channel steel on a disconnecting switch framework through a channel steel clamp 5.
In the utility model, for example, GW4-110 type isolator single-phase maintenance operation is taken as an example, the bearing plate 1 comprises a rectangular frame 105, the bottom of the frame 105 is provided with a plurality of reinforcing ribs 102, the upper part of the frame 105 is provided with an insulated bakelite plate 101, the upper surface of the insulated bakelite plate 101 is ground to exert an anti-skid effect, four clamping members 103 are respectively and symmetrically arranged at four corners of the frame 105, and the frame 105 is composed of epoxy resin square tubes to ensure the overall bearing strength.
In the present invention, a first through hole 106 is disposed at the center of the bearing plate 1, and four second through holes 107 are disposed around the first through hole 106.
In the utility model, the bearing rod 3 is an epoxy resin circular tube, the side walls of two ends of the bearing rod 3 are respectively and symmetrically provided with a first circular hole 301, and the outer diameter of the bearing rod 3 is matched with the clamping diameter of the clamping piece 103.
In the utility model, the channel steel clamp 5 comprises a clamp main body 501 and a connecting cylinder 502, the clamp main body 501 is of an n-shaped steel plate structure, the side wall of the connecting cylinder 502 is fixedly connected with the top of the clamp main body 501, the inner diameter of the connecting cylinder 502 is matched with the outer diameter of the bearing rod 3, a second round hole 503 is formed in the middle of the side wall of the connecting cylinder 502, and the second round hole 503 is matched with the first round hole 301 in size.
In the utility model, a first threaded hole 509 is formed in the upper portion of the side wall of the clamp body 501, a bolt 504 is arranged on the first threaded hole 509, two third through holes 511 are symmetrically formed in the lower portions of the two side walls of the clamp body 501, an L-shaped locking plug 505 is arranged on the third through holes 511, a second threaded hole 510 is formed in the L-shaped locking plug 505, and the bolt 504 is arranged on the second threaded hole 510.
In the utility model, the end part of the bolt 504 is provided with a top pressing sheet 507, the surface of the top pressing sheet 507 is provided with a rubber buffer pad 508, and the rubber buffer pad has mechanical buffering and anti-skid functions and can increase the friction force between the rubber buffer pad and the channel steel.
In the utility model, the base 2 is a cylindrical steel plate 201, a fourth through hole 202 is arranged in the middle of the cylindrical steel plate 201, four fifth through holes 203 are arranged around the fourth through hole 202, the lower part of the fourth through hole 202 is connected with a cylinder 204 with a sealed bottom, the outer diameter of the cylinder 204 is matched with the size of the first through hole 106, inner threads are arranged on the inner wall of the cylinder 204, and the number, the diameter and the distribution of the fifth through holes 203 are all kept consistent with those of the second through holes 107.
In the utility model, the main body of the upright post 4 is an epoxy resin round pipe, the bottom of the upright post 4 is a round steel pipe 401, the outer wall of the round steel pipe 401 is provided with external threads, the external threads on the round steel pipe 401 are matched and screwed with the internal threads of the cylinder 204, the top of the upright post 4 is provided with an inserting pipe 402, the inserting pipe 402 can rotate around the main body of the upright post 4 in the vertical axial direction, and the upper part of the inserting pipe 402 is fixedly provided with a safety belt hanging ring 403.
In the utility model, the cross arm main body 601 is an epoxy resin circular tube, two fastening type hoops 603 are respectively arranged at two ends of the cross arm 6 and used for fixing the cross arm and preventing the cross arm from falling off due to lateral movement, a movable hanging mechanism 602 is arranged in the middle of the cross arm 6 and used for hanging a safety belt hook, and the outer diameter of the cross arm main body 601 is matched with the inner diameter of the inserting tube 402.
When the single-phase maintenance is carried out, the use process comprises the following five steps: the mounting method comprises the following steps of channel steel clamping piece 5 mounting, bearing rod 3 mounting, base 2 mounting, bearing plate 1 mounting and upright post 4 mounting.
Channel steel clamp installation
1. The L-shaped locking plug 505 is pulled out, the channel clip 5 is clipped on the framework channel 9 between the isolating switches A, B (or B, C), and the L-shaped locking plug 505 is inserted again.
2. By rotating the bolt 504 on the left side wall of the clamp body 501, the pressing piece 507 connected with the clamp body can tightly press the framework channel steel 9, so that the channel steel clamp 5 is fixed in the horizontal direction.
3. By rotating the bolt on the L-shaped locking plug 505, the top pressing piece connected with the L-shaped locking plug can be tightly pressed against the frame channel 9, so that the channel clamp 5 is fixed in the vertical direction.
4. And respectively mounting a channel clip between A, B (or B, C) and close to 4 porcelain bottles, wherein 4 channel clips are mounted in total.
Mounting of bearing rod
1. Set up the spring locating pin that a model is freezing point crown brand PT-56-61 type on second round hole 503 on the connecting cylinder 502 lateral wall, pull open the spring locating pin, insert the connecting cylinder 503 on two channel-section steel folder of A looks or B looks vase department respectively with bearing bar 3 both ends, make first round hole 301 and second round hole 503 coincidence, make the spring locating pin round head insert first round hole 301 in, loosen the spring locating pin, make bearing bar 3 and connecting cylinder 502 two be connected the locking, thereby with bearing bar 3 and framework channel-section steel 9 fixed connection.
2. The other bearing rod is installed in the same way and is not described in detail.
Thirdly, base installation
The cylinder 204 on the base 2 is made to pass through the first through hole 106 on the bearing plate 1, and simultaneously, the four fifth through holes 203 of the base 2 are respectively made to correspond to the four second through holes on the bearing plate one by one, and the base 2 is fixed on the bearing plate 1 by fasteners through the fifth through holes 203.
Four, fast-assembling type bearing plate installation
The four clamping piece handles 104 are respectively pulled open, so that the four clamping pieces 103 are clamped and locked with the two bearing rods 3.
Fifth, the column mounting
The round steel tube 401 at the bottom of the upright post 4 is inserted into the cylinder 204 on the base 2 and screwed firmly.
Installation effect is schematically shown in fig. 2, and a maintenance worker can mount the isolating switch framework through the insulating ladder, stand on the bearing plate 1, and hang a safety belt on the safety belt hanging ring 403 of the upright post 4 to perform maintenance operation.
Example two
When two-phase or three-phase maintenance is carried out, the using process comprises the following six steps: channel steel clamp installation, bearing bar installation, base installation, bearing plate installation, stand column installation, cross arm installation.
The first five steps are the same as those in the first embodiment, and are not described again here, and an overhaul platform as shown in fig. 2 is respectively set up between a and B, B and C according to the first five steps.
The cross arm installation steps are as follows:
1. two ends of the cross arm 6 are respectively inserted into the insertion pipes 402 at the upper parts of the two upright posts 4.
2. Two sides of each inserting pipe 402 are respectively fastened and locked by two fastening type hoops 603 which tightly press the inserting pipe 402, so that the cross arm 6 is firmly connected with the upright post 4.
Installation effect schematic diagram as shown in fig. 1, the maintainer can mount the isolating switch framework through the insulating ladder, stand on the bearing plate 1, and hang the safety belt hook on the hanging ring of the movable hanging mechanism 602 on the cross arm 6, and then can carry out maintenance operation.
While the foregoing is directed to the preferred embodiment of the present invention, it will be understood by those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the utility model as defined in the appended claims.

Claims (10)

1. The utility model provides a GW4-110 type isolator overhauls operation platform, includes bearing platform and linkage, its characterized in that: the bearing platform includes bearing bar and bearing plate, the bearing plate with the bearing bar passes through the joint spare to be connected, linkage includes base, stand and cross arm, the stand bottom with the base is connected, the stand top with the cross arm is connected, the base with the bearing plate is connected, the bearing bar passes through the channel-section steel folder and is connected with the channel-section steel on the isolator framework.
2. The GW4-110 type isolator service work platform of claim 1, wherein: the bearing plate comprises a frame, a plurality of reinforcing ribs are arranged at the bottom of the frame, an insulating bakelite plate is arranged on the upper portion of the frame, the clamping pieces are symmetrically arranged at the four corners of the frame respectively, and the frame is formed by epoxy resin square tubes.
3. The GW4-110 type isolator service work platform of claim 2, wherein: the bearing plate is characterized in that a first through hole is formed in the center of the bearing plate, and a plurality of second through holes are formed in the periphery of the first through hole.
4. A GW4-110 type disconnector service work platform of claim 3, wherein: the bearing bar adopts the epoxy pipe, the symmetry sets up first round hole respectively on the lateral wall of bearing bar both ends, the external diameter of bearing bar with the joint diameter phase-match of joint spare.
5. The GW4-110 type isolator service work platform of claim 4, wherein: the channel-section steel folder includes folder main part and connecting cylinder, the folder main part is n shaped steel plate structure, the connecting cylinder lateral wall with folder main part top fixed connection, the internal diameter of connecting cylinder with the external diameter looks adaptation of bearing bar, connecting cylinder lateral wall middle part sets up the second round hole, the second round hole with first round hole size looks adaptation.
6. The GW4-110 type isolator service work platform of claim 5, wherein: the clamping piece is characterized in that a first threaded hole is formed in the upper portion of the side wall of the clamping piece main body, a bolt is arranged in the first threaded hole, two third through holes are symmetrically formed in the lower portions of the two side walls of the clamping piece main body, an L-shaped locking plug-in unit is arranged on each third through hole, a second threaded hole is formed in each L-shaped locking plug-in unit, and a bolt is arranged in each second threaded hole.
7. The GW4-110 type isolator service work platform of claim 6, wherein: the bolt end is provided with a jacking sheet, and the surface of the jacking sheet is provided with a rubber buffer pad.
8. The GW4-110 type isolator service work platform of claim 7, wherein: the base is cylindrical steel sheet, set up the fourth through-hole in the middle of the cylindrical steel sheet, the fourth through-hole sets up a plurality of fifth through-holes all around, the cylinder that a fourth through-hole sub-unit connection bottom was sealed, the cylinder external diameter with first through-hole size phase-match, the cylinder inner wall sets up the internal thread, the quantity, diameter, the distribution of fifth through-hole all with the second through-hole keeps unanimous.
9. The GW4-110 type isolator service work platform of claim 8, wherein: the stand main part is the epoxy pipe, the stand bottom is circular steel pipe, circular steel pipe outer wall sets up the external screw thread, external screw thread on the circular steel pipe with the internal thread adaptation of drum connects soon, the stand top sets up the grafting pipe, the grafting pipe can be around the vertical axial of stand main part rotation, the fixed safety belt link that sets up in grafting pipe upper portion.
10. The GW4-110 type isolator service work platform of claim 9, wherein: the cross arm main part is the epoxy pipe, the cross arm both ends respectively set up two at least lock joint formula staple bolts, set up a plurality of portable hooking mechanism in the middle of the cross arm, the external diameter of cross arm main part with the internal diameter looks adaptation of grafting pipe.
CN202121784019.1U 2021-08-02 2021-08-02 GW4-110 type isolation switch maintenance operation platform Active CN215897132U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121784019.1U CN215897132U (en) 2021-08-02 2021-08-02 GW4-110 type isolation switch maintenance operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121784019.1U CN215897132U (en) 2021-08-02 2021-08-02 GW4-110 type isolation switch maintenance operation platform

Publications (1)

Publication Number Publication Date
CN215897132U true CN215897132U (en) 2022-02-22

Family

ID=80501930

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121784019.1U Active CN215897132U (en) 2021-08-02 2021-08-02 GW4-110 type isolation switch maintenance operation platform

Country Status (1)

Country Link
CN (1) CN215897132U (en)

Similar Documents

Publication Publication Date Title
CN105398990B (en) Electric power angle steel tower auxiliary lifting apparatus
CN201862167U (en) Safety belt hanging stand for overhaul of isolating switch
CN201565749U (en) Special maintenance platform for isolating switch
CN111346317B (en) Safety belt hanging device for maintenance of isolating switch
CN215897132U (en) GW4-110 type isolation switch maintenance operation platform
CN216451045U (en) Fast-assembling type switch overhauls platform and safety belt linkage
CN106450835A (en) Shoe manufacturer high voltage wire landing device
CN113209513A (en) Protective suspension device for transformer safety maintenance and use method
CN107069533B (en) A kind of super UHV Overhead Transmission Line tangent tower ground wire lifting tool
CN201533117U (en) Safety belt hanging bracket
CN103332608A (en) Special suspender for replacing GW6 disconnector knob insulator
CN201295476Y (en) Substation equipment maintenance and repair safety belt suspension device
CN203284094U (en) Rod hanger special for GW6 knife switch porcelain column replacement
CN206148852U (en) Post insulators and arrester maintenance safety belt stores pylon
CN212450250U (en) Special lifting appliance for outdoor construction of transformer substation
CN212198245U (en) Universal type disconnecting link overhauling hanging bracket
CN104399203B (en) fixed safety belt hanger
CN112439139A (en) Special stores pylon based on 35kV framework formula equipment safety belt
CN217548823U (en) Safety belt hanger special for lightning arrester, voltage transformer and main transformer neutral point disconnecting link
CN210409280U (en) Safety belt hanging frame for isolating switch framework
CN214112343U (en) Composite connection type post porcelain insulator
CN218841488U (en) Support for placing mill sling
CN215733199U (en) 33kV GIS cable terminal mounting tool
CN204732754U (en) For the safety hanging special stand of outdoor framework equipment
CN216451044U (en) Switch cabinet top operation safety device