CN215888147U - Spillway plane steel gate suppressing and leakage-stopping construction device - Google Patents

Spillway plane steel gate suppressing and leakage-stopping construction device Download PDF

Info

Publication number
CN215888147U
CN215888147U CN202121677383.8U CN202121677383U CN215888147U CN 215888147 U CN215888147 U CN 215888147U CN 202121677383 U CN202121677383 U CN 202121677383U CN 215888147 U CN215888147 U CN 215888147U
Authority
CN
China
Prior art keywords
steel gate
plane steel
spillway
leakage
install
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121677383.8U
Other languages
Chinese (zh)
Inventor
何明富
杜驰
角玉峰
冯宪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Energy Investment Yuanda Construction Group Co ltd
Original Assignee
Yunnan Energy Investment Yuanda Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Energy Investment Yuanda Construction Group Co ltd filed Critical Yunnan Energy Investment Yuanda Construction Group Co ltd
Priority to CN202121677383.8U priority Critical patent/CN215888147U/en
Application granted granted Critical
Publication of CN215888147U publication Critical patent/CN215888147U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Barrages (AREA)

Abstract

The utility model discloses a spillway plane steel gate suppressing and leakage-stopping construction device, which relates to the technical field of steel gate leakage-preventing construction devices and comprises a spillway and a plane steel gate arranged on the spillway, wherein two natural rubbers are arranged on the side wall of the plane steel gate, a position adjusting assembly for adjusting the elastic extrusion degree of the two natural rubbers is arranged on the spillway, two symmetrically-arranged extrusion units for adjusting the elastic extrusion degree are arranged on the leakage-stopping adjusting assembly, and both the two extrusion units are in contact with the plane steel gate. The structure of the utility model is reasonable, through construction, water can not leak out from the space between the plane steel gate and the installation groove, so that the plane steel gate can better block the water, the plane steel gate and the natural rubber have better leakage stopping effect after being pressed, personnel can not need to replace the natural rubber, and the construction difficulty and the construction time are reduced.

Description

Spillway plane steel gate suppressing and leakage-stopping construction device
Technical Field
The utility model relates to the technical field of steel gate leakage-proof construction devices, in particular to a spillway plane steel gate elastic pressure leakage-proof construction device.
Background
At present, the gate in China is the flat gate which is the most widely applied, the steel gate with the best use effect is the steel gate, the steel gate is usually a movable structure used for opening and closing a water passing port in a local hydraulic building, the steel gate can achieve the effects of adjusting flow, controlling water level and transporting ships, and the steel gate needs to be maintained after being used for a long time.
The current plane steel gate is after long-time the use, and sealing rubber on the steel gate is corroded easily, leads to the steel gate to descend the ability of blockking of water, leads to water to take place to leak, and personnel are when suppressing the leak-stopping to the steel gate, change rubber usually, have increased the construction degree of difficulty and engineering time, for this we have proposed a spillway plane steel gate suppression leak-stopping construction equipment.
SUMMERY OF THE UTILITY MODEL
An object of the application is to provide a spillway plane steel gate suppress leak-stopping construction equipment to solve the problem that provides among the above-mentioned background art.
In order to achieve the above purpose, the present application provides the following technical solutions: the utility model provides a spillway plane steel gate suppress leak-stopping construction equipment, include spillway, install in plane steel gate on the spillway, install two natural rubber on the lateral wall of plane steel gate, install on the spillway and be used for adjusting two natural rubber receives the position control assembly of elasticity extrusion degree, install the extrusion unit that is used for adjusting elasticity extrusion degree that two symmetries set up on the leak-stopping adjusting assembly, two the extrusion unit all with plane steel gate contacts.
Borrow by above-mentioned structure, through the position control subassembly, can adjust the position of extrusion unit, make extrusion unit extrude the plane steel gate, make natural rubber have better leak protection effect, what make the plane steel gate can be better blocks water, make plane steel gate and natural rubber after carrying out the suppress, have better leak-stopping effect, make personnel need not to change natural rubber, reduce the construction degree of difficulty and engineering time.
Preferably, the position control subassembly is including seting up in the lift groove on two relative inner walls of spillway, two all correspond on the top of lift groove and the bottom inner wall and rotate and install the lift lead screw, two equal threaded sleeve has gone up and down the fixture block, two on the lift lead screw the regulation crossbeam is installed to one side that the lift fixture block is close to each other, install two on the regulation crossbeam the extrusion unit.
Furthermore, through the position adjusting assembly, the lifting screw rod is rotated, the lifting clamping block is driven to move, the adjusting beam is driven to stably move up and down, the extrusion unit is driven to stably move, and the construction device can better achieve a leakage stopping effect through the elastic pressing mode.
Preferably, L shape motor frame is installed at the top of spillway, elevator motor is installed to the bottom of L shape motor frame, one of them the top of lift lead screw install in elevator motor's output, two all cup joint on the lift lead screw and install the connection band pulley, two the tensioning has the connection belt on the connection band pulley, two the lift fixture block difference adaptation install in two on the inner wall of lift groove.
Further, through connecting the band pulley, when making one of them connection band pulley take place to rotate, can make two connection band pulleys all take place to rotate under the drive of connecting the belt, and then make two synchronous emergence rotations of lift lead screw, more stable smooth and easy when making personnel's construction leak-stopping.
Preferably, the extrusion unit is including installing in adjust the crossbeam and keep away from the extrusion motor of plane steel gate one side, accommodate the lead screw is installed to the output of extrusion motor, the flexible square cylinder of screw thread cover has been gone up to accommodate the lead screw, the stripper plate is installed to the one end of flexible square cylinder, the stripper plate with the plane steel gate contacts.
Furthermore, through the extrusion unit, make the extrusion motor take place to rotate, and then drive accommodate the lead screw and take place to rotate, make flexible square tube take place stable removal on accommodate the lead screw, and then make the extrusion plate extrusion plane steel gate that can be more steady, make the construction equipment construction back, the plane steel gate can not take place the phenomenon of leaking, makes the leak-stopping effect better.
Preferably, two limiting guide rods are installed on one side, close to the plane steel gate, of the adjusting beam, limiting grooves are formed in two opposite side walls of the telescopic square cylinder, and the two limiting guide rods are matched with the inner walls of the two limiting grooves in a sliding mode respectively.
Furthermore, through the limiting guide rod, the telescopic square cylinder is more stable when moving, so that the plane steel gate can better prevent water from leaking, and the leakage stopping effect of the plane steel gate is better.
Preferably, two limit stop is all installed to the one side that limit guide pole kept away from each other, two spill card frame is all installed to the one side that flexible square tube kept away from each other, two spill card frame respectively with two limit stop contacts.
Further, through limit stop, the spill card frame can produce to limit stop and block, makes flexible square tube when removing, can not deviate from, makes the difficult emergence of construction equipment damage, and is more stable during the use.
Preferably, all seted up the mounting groove on two relative inner walls of spillway, the plane steel gate passes through installation mechanism to be installed in two on the inner wall of mounting groove, two natural rubber respectively with two the inner wall of mounting groove contacts.
Through natural rubber's setting, make natural rubber can better laminating mounting groove, make water can not spill between plane steel gate and the mounting groove, make the leak-stopping effect of plane steel gate better.
In conclusion, the technical effects and advantages of the utility model are as follows:
1. the structure of the utility model is reasonable, when the natural rubber is not tightly attached to the installation groove, the lifting motor is started to enable the two extrusion units to move up and down, when the two extrusion units move to proper positions, the lifting motor is stopped, the extrusion motor is started to enable the adjusting screw rod to rotate, the extrusion plate moves to extrude the plane steel gate, the natural rubber is enabled to be more attached to the installation groove, water cannot leak out from the position between the plane steel gate and the installation groove, the plane steel gate can better block the water, after the plane steel gate leaks, the extrusion plate can extrude the plane steel gate and the natural rubber, the plane steel gate and the natural rubber have better leakage stopping effect after being elastically pressed, personnel do not need to replace the natural rubber, and the construction difficulty and the construction time are reduced;
2. according to the utility model, the lifting fixture block can be moved more stably by the lifting groove, so that the construction is more stable after the plane steel gate leaks water, the sealing performance of two natural rubbers can be better adjusted by the two extrusion units, the construction device can better suppress and stop leakage of the plane steel gate, the telescopic square tube can be moved more stably by the limit guide rod, the extrusion plate can be moved more smoothly, the extrusion plate can better extrude the plane steel gate, the leakage stopping effect is better, the concave clamping frame can block the limit stop, the adjusting screw rod cannot be separated from the telescopic square tube when the telescopic square tube is moved, the construction device is not easy to damage, and the construction device is more stable in use.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present application, and other drawings can be obtained by those skilled in the art without creative efforts.
FIG. 1 is a first perspective view of a spillway planar steel gate suppressing leakage prevention construction device;
FIG. 2 is a schematic view of a second perspective structure of the spillway plane steel gate suppressing leakage-stopping construction device;
FIG. 3 is a schematic view of a partially cut-away perspective structure of a spillway plane steel gate suppressing leakage-stopping construction device;
fig. 4 is an enlarged schematic view of a portion a in fig. 3.
In the figure: 1. a spillway; 2. a planar steel gate; 3. adjusting the cross beam; 4. an extrusion motor; 5. a lifting motor; 6. connecting a belt; 7. an L-shaped motor frame; 8. a telescopic square cylinder; 9. a pressing plate; 10. natural rubber; 11. a lifting screw rod; 12. a lifting fixture block; 13. a connecting belt wheel; 14. a limiting guide rod; 15. a concave clamping frame; 16. adjusting the screw rod; 17. and a limit stop.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example (b): referring to fig. 1-4, a spillway plane steel gate suppress leak-stopping construction device comprises a spillway 1 and a plane steel gate 2 installed on the spillway 1, wherein two natural rubbers 10 are installed on the side wall of the plane steel gate 2, a position adjusting component for adjusting the elastic extrusion degree of the two natural rubbers 10 is installed on the spillway 1, two extrusion units which are symmetrically arranged and used for adjusting the elastic extrusion degree are installed on the leak-stopping adjusting component, and the two extrusion units are all in contact with the plane steel gate 2. Through the setting of position control subassembly, can adjust the position of extrusion unit, make extrusion unit extrude planar steel gate 2, make natural rubber 10 have better leak protection effect, what make planar steel gate 2 can be better blocks water, make planar steel gate 2 and natural rubber 10 after carrying out the suppress, have better leak-stopping effect, make personnel need not to change natural rubber 10, reduce the construction degree of difficulty and engineering time.
As a preferred embodiment of this embodiment, the position control subassembly is including seting up the lift groove on two relative inner walls of spillway 1, all corresponds on the top of two lift grooves and the bottom inner wall and rotates and install lift lead screw 11, and equal threaded sleeve has the lift fixture block 12 on two lift lead screw 11, and two lift fixture blocks 12 are close to each other one side and are installed adjusting beam 3, install two extrusion units on adjusting beam 3. Through the setting of position control assembly, make lift lead screw 11 take place to rotate, drive lift fixture block 12 and take place to remove, drive and adjust crossbeam 3 and take place stable reciprocating, and then drive the extrusion unit and take place stable removal, make the mode through suppressing that construction equipment can be better play the leak-stopping effect.
In this embodiment, L shape motor frame 7 is installed at the top of spillway 1, and elevator motor 5 is installed to the bottom of L shape motor frame 7, and the output in elevator motor 5 is installed on the top of one of them lift lead screw 11, all cup joints on two lift lead screws 11 and installs connection band pulley 13, and the tensioning has connection belt 6 on two connection band pulleys 13, and two lift fixture blocks 12 difference adaptations are installed on the inner wall in two lift grooves. Through the setting, when making one of them connection band pulley 13 take place to rotate, can make two connection band pulleys 13 all take place to rotate under the drive of connecting belt 6, and then make two lift lead screws 11 take place to rotate in step, more stable smooth and easy when making personnel's construction leak-stopping.
In this embodiment, the extrusion unit includes the extrusion motor 4 that installs in adjusting beam 3 and keep away from plane steel gate 2 one side, and accommodate the lead screw 16 is installed to the output of extrusion motor 4, and the flexible square tube 8 has been cup jointed to accommodate the lead screw 16 upper thread, and stripper plate 9 is installed to the one end of flexible square tube 8, and stripper plate 9 contacts with plane steel gate 2. Through the setting of extrusion unit, make extrusion motor 4 take place to rotate, and then drive accommodate the lead screw 16 and take place to rotate, make flexible square cylinder 8 take place stable removal on accommodate the lead screw 16, and then make the extrusion plane steel gate 2 that stripper plate 9 can be more steady, make construction equipment construction back, plane steel gate 2 can not take place the phenomenon of leaking water, make the leak-stopping effect better.
In this embodiment, two limiting guide rods 14 are installed on one side of the adjusting beam 3 close to the planar steel gate 2, limiting grooves are formed in two opposite side walls of the telescopic square tube 8, and the two limiting guide rods 14 are respectively matched with the inner walls of the two limiting grooves in a sliding manner. Through the setting of spacing guide arm 14, it is more stable when making flexible square tube 8 remove, what make plane steel gate 2 can be better blocks water and spills, makes plane steel gate 2's leak-stopping effect better.
In this embodiment, limit stop 17 is all installed to the one side that two spacing guide arms 14 kept away from each other, and concave card frame 15 is all installed to the one side that two flexible square barrels 8 kept away from each other, and two concave card frames 15 contact with two limit stop 17 respectively. Through limit stop 17's setting, spill card frame 15 can produce to limit stop 17 and block, makes flexible square tube 8 when removing, can not deviate from, makes the difficult emergence of construction equipment damage, and is more stable during the use.
As a preferred embodiment of this embodiment, two opposite inner walls of the spillway 1 are provided with mounting grooves, the planar steel gate 2 is mounted on the inner walls of the two mounting grooves by a mounting mechanism, and the two natural rubbers 10 are respectively in contact with the inner walls of the two mounting grooves. Through natural rubber 10's setting, make natural rubber 10 can better laminating mounting groove, make water can not spill between plane steel gate 2 and the mounting groove, make plane steel gate 2's leak-stopping effect better.
This practical theory of operation: when the natural rubber 10 is not tightly attached to the installation groove, the lifting motor 5 is started to rotate one of the lifting screw rods 11 and further drive one of the connecting belt wheels 13 to rotate, the two connecting belt wheels 13 are driven to rotate by the connecting belt 6, and further the two lifting screw rods 11 are simultaneously rotated to synchronously move the two lifting fixture blocks 12 and further drive the adjusting beam 3 to move and further drive the two extrusion units to move, when the two extrusion units move to proper positions, the lifting motor 5 is stopped, the extrusion motor 4 is started to rotate the adjusting screw rod 16, so that the telescopic square tube 8 moves on the adjusting screw rod 16, the extrusion plate 9 moves towards the plane steel gate 2, the extrusion motor 4 is continuously started to continuously move the extrusion plate 9 to extrude the plane steel gate 2, and further the natural rubber 10 can be attached to the installation groove, make water can not spill between plane steel gate 2 and the mounting groove, make plane steel gate 2 better block water, make plane steel gate 2 take place to leak the back, can extrude through stripper plate 9, make plane steel gate 2 and natural rubber 10 after carrying out the suppress, have better leak-stopping effect.
Through the lift groove, can make the more stable removal of lift fixture block 12, make plane steel gate 2 leak the back, it is more stable when being under construction, two extrusion units can be better adjust two natural rubber 10's leakproofness, make construction equipment can better suppress plane steel gate 2 and stop leaking, spacing guide arm 14 is more stable when making flexible square tube 8 remove, it is more smooth and easy when making stripper plate 9 remove, make stripper plate 9 can be better produce the extrusion to plane steel gate 2, make the leak-stopping effect better, spill card frame 15 can produce stop spacing dog 17, make flexible square tube 8 when removing, can not deviate from accommodate the lead screw 16, make the difficult emergence of construction equipment damage, it is more stable during the use.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the utility model.

Claims (7)

1. The utility model provides a spillway plane steel gate suppress leak-stopping construction equipment, include spillway (1), install in plane steel gate (2) on spillway (1), its characterized in that: install two natural rubber (10) on the lateral wall of plane steel gate (2), install on spillway (1) and be used for adjusting two natural rubber (10) receive the position control assembly of elasticity extrusion degree, install the extrusion unit that is used for adjusting elasticity extrusion degree that two symmetries set up on the leak-stopping adjusting part, two the extrusion unit all with plane steel gate (2) contact.
2. The spillway plane steel gate suppressing and leakage-stopping construction device of claim 1, wherein: position control subassembly is including seting up in the lift groove on two relative inner walls of spillway (1), two all correspond on the top of lift groove and the bottom inner wall and rotate and install lift lead screw (11), two equal screw thread has cup jointed lift fixture block (12), two on lift lead screw (11) one side that lift fixture block (12) are close to each other is installed and is adjusted crossbeam (3), install two on adjusting crossbeam (3) the extrusion unit.
3. The spillway plane steel gate suppressing and leakage-stopping construction device of claim 2, wherein: l shape motor frame (7) are installed at the top of spillway (1), elevator motor (5), one of them are installed to the bottom of L shape motor frame (7) the top of lift lead screw (11) install in the output of elevator motor (5), two all cup joint on lift lead screw (11) and install connection band pulley (13), two the tensioning has connection belt (6), two on connecting band pulley (13) lift fixture block (12) adaptation respectively install in two on the inner wall of lift groove.
4. The spillway plane steel gate suppressing and leakage-stopping construction device of claim 2, wherein: the extrusion unit is including installing in adjust crossbeam (3) and keep away from extrusion motor (4) of plane steel gate (2) one side, accommodate the lead screw (16) are installed to the output of extrusion motor (4), flexible square tube (8) have been cup jointed to accommodate the lead screw (16) upper thread, stripper plate (9) are installed to the one end of flexible square tube (8), stripper plate (9) with plane steel gate (2) contact.
5. The spillway plane steel gate suppressing and leakage-stopping construction device of claim 4, wherein: two limiting guide rods (14) are installed on one side, close to the plane steel gate (2), of the adjusting beam (3), limiting grooves are formed in two opposite side walls of the telescopic square tube (8), and the two limiting guide rods (14) are matched with the two limiting grooves in a sliding mode respectively on the inner walls of the limiting grooves.
6. The spillway plane steel gate suppressing and leakage-stopping construction device of claim 5, wherein: two limit stop (17) are all installed to the one side that keeps away from each other of limit guide pole (14), two spill card frame (15) are all installed to the one side that keeps away from each other of flexible square tube (8), two spill card frame (15) contact with two limit stop (17) respectively.
7. The spillway plane steel gate suppressing and leakage-stopping construction device of claim 1, wherein: all seted up the mounting groove on two relative inner walls of spillway (1), install in two through installation mechanism plane steel gate (2) on the inner wall of mounting groove, two natural rubber (10) respectively with two the inner wall of mounting groove contacts.
CN202121677383.8U 2021-07-22 2021-07-22 Spillway plane steel gate suppressing and leakage-stopping construction device Active CN215888147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121677383.8U CN215888147U (en) 2021-07-22 2021-07-22 Spillway plane steel gate suppressing and leakage-stopping construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121677383.8U CN215888147U (en) 2021-07-22 2021-07-22 Spillway plane steel gate suppressing and leakage-stopping construction device

Publications (1)

Publication Number Publication Date
CN215888147U true CN215888147U (en) 2022-02-22

Family

ID=80501413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121677383.8U Active CN215888147U (en) 2021-07-22 2021-07-22 Spillway plane steel gate suppressing and leakage-stopping construction device

Country Status (1)

Country Link
CN (1) CN215888147U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351658A (en) * 2022-02-25 2022-04-15 四川华能涪江水电有限责任公司 Hydraulic construction steel gate

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351658A (en) * 2022-02-25 2022-04-15 四川华能涪江水电有限责任公司 Hydraulic construction steel gate
CN114351658B (en) * 2022-02-25 2024-02-27 四川华能涪江水电有限责任公司 Hydraulic construction steel gate

Similar Documents

Publication Publication Date Title
CN215888147U (en) Spillway plane steel gate suppressing and leakage-stopping construction device
CN109057284B (en) Automatic aluminum-plastic plate mounting equipment and automatic aluminum-plastic plate mounting method
CN109339000B (en) Gate driving sealing mechanism
CN209925665U (en) Self-compensating sealed electric gate valve
CN218067564U (en) Performance detection device for waterproof coating
CN109778794B (en) Multi-stage type folding hydraulic dam
CN105089845B (en) The engine of plugging device and the application plugging device
CN201546581U (en) Airtight sliding window
CN214301597U (en) Water flow control device for water channel gate
CN216664036U (en) Water blocking device that hydraulic engineering used
CN218233386U (en) Hydraulic engineering gate
CN220620000U (en) Gate valve
CN220318471U (en) Electric water outlet structure
CN215673977U (en) Hydraulic pipeline strutting arrangement for hydraulic engineering
CN220909986U (en) Spliced screw pump bushing
CN215367139U (en) Novel reverse hydraulic water stop steel gate
CN220890484U (en) Water pump connecting piece
CN220435072U (en) Self-priming magnetic pump
CN212896209U (en) Over-and-under type water sluicegate for hydraulic engineering
CN117782444B (en) Airtight check out test set of ripple compensator
CN220664484U (en) Digital intelligent cable arranging device
CN212614426U (en) Subway platform flood prevention breakwater
CN219300059U (en) Flow regulating valve
CN220353046U (en) Down-opening type weir gate
CN220079923U (en) Glass fiber reinforced plastic gateway with efficient sealing structure

Legal Events

Date Code Title Description
GR01 Patent grant