CN215829437U - Keep apart fender pile - Google Patents

Keep apart fender pile Download PDF

Info

Publication number
CN215829437U
CN215829437U CN202122368770.XU CN202122368770U CN215829437U CN 215829437 U CN215829437 U CN 215829437U CN 202122368770 U CN202122368770 U CN 202122368770U CN 215829437 U CN215829437 U CN 215829437U
Authority
CN
China
Prior art keywords
capping beam
pile
drilling
insulation
drilling pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122368770.XU
Other languages
Chinese (zh)
Inventor
缪爱伟
程志成
陈尚荣
何嵩婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Geological And Mineral Engineering Survey Group Co ltd
Original Assignee
Shanghai Geological And Mineral Engineering Survey Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Geological And Mineral Engineering Survey Group Co ltd filed Critical Shanghai Geological And Mineral Engineering Survey Group Co ltd
Priority to CN202122368770.XU priority Critical patent/CN215829437U/en
Application granted granted Critical
Publication of CN215829437U publication Critical patent/CN215829437U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model belongs to the technical field of excavation supporting and specifically relates to an keep apart fender pile is related to, and it includes the drilling pile post that sets up along vertical direction, the top surface of drilling pile post is equipped with the capping beam, still be equipped with the fixed subassembly that is used for fixed capping beam on the drilling pile post, all be equipped with the coupling assembling that is used for connecting the fender board on capping beam length direction's the both ends face. The drilling pile in this application passes through fixed connection in capping beam, and the capping beam can connect in the fender panel through coupling assembling to can play the effect of fender pile, after the foundation ditch need not be strutted, the capping beam can play the effect of support to the building of ground top, thereby the drilling pile no longer is demolishd, has played the effect of saving the resource.

Description

Keep apart fender pile
Technical Field
The application relates to the field of foundation pit support, in particular to an isolation fender pile.
Background
The foundation pit support is a support system formed by connecting enclosure piles with enclosure plates, and adopts support, reinforcement and protection measures for the side wall and the surrounding environment of the foundation pit in order to ensure the safety of the construction of an underground structure and the surrounding environment of the foundation pit.
Super large-scale deep basal pit is also more and more at present, and some foundation pit depths differ, and the foundation pit type is various, for reducing the risk of foundation pit excavation, and a lot of foundation pits have adopted the form of subregion excavation, and after the subregion, generally need set up the fender pile in the middle of the foundation pit, and the fender pile is the enclosure form of using always as fender pile collocation fender board, because foundation pit engineering is temporary engineering, after the underground structure was accomplished, the fender pile chisels out, and the enclosure system is useless, has caused very big wasting of resources.
SUMMERY OF THE UTILITY MODEL
In order to resources are saved, the application provides an isolation fender pile.
The application provides a keep apart fender pile adopts following technical scheme:
the utility model provides an keep apart fender pile, includes the drilling pile that sets up along vertical direction, the top surface of drilling pile is equipped with the capping beam, still be equipped with the fixed subassembly that is used for fixed capping beam on the drilling pile, all be equipped with the coupling assembling that is used for connecting the fender apron on capping beam length direction's the both ends face.
Through adopting above-mentioned technical scheme, the drilling pile sets up under the ground, the capping beam is connected to the drilling pile through fixed subassembly, the drilling pile plays the firm effect of support to the capping beam, coupling assembling on the capping beam can connect the apron board, thereby play the effect of enclosure to the foundation ditch, demolish the bounding wall after, drilling pile and capping beam can play the effect of support to subaerial building, thereby the drilling pile need not to demolish and can continue to use, the effect of save material has been played.
Optionally, a plurality of supporting plates are arranged on the side surface of the drilling pile, and the top surfaces of the supporting plates are abutted to the bottom surface of the capping beam.
Through adopting above-mentioned technical scheme, the backup pad can play the effect of support to the capping beam to can strengthen the stability of capping beam.
Optionally, the fixing assembly includes a main rib inserted into the drilled pile in the vertical direction, the top surface of the main rib is higher than the top surface of the drilled pile, and the capping beam is provided with a ground insertion hole for inserting the main rib.
By adopting the technical scheme, the main ribs are inserted into the bored pile, and the main ribs can enhance the structural strength of the bored pile, so that the stability of the bored pile is improved; the top end of the main rib is inserted into the insertion hole in the capping beam, so that the capping beam is not easy to move and separate from the drilling pile.
Optionally, a plurality of stirrups wound on the main reinforcement are arranged in the drilling pile.
Through adopting above-mentioned technical scheme, the stirrup winding has strengthened the stability of main muscle on the main muscle, and then has strengthened the stability and the structural strength of drilling pile.
Optionally, the connecting assembly comprises a plurality of groups of mounting ribs inserted in the horizontal direction on the end face of the capping beam, and each group of mounting ribs comprises a plurality of mounting ribs arranged in the vertical direction.
Through adopting above-mentioned technical scheme, the structural strength that can strengthen the capping beam in the capping beam is installed to the installation muscle for the capping beam is difficult for the fracture, and two sets of installation muscle can play the effect of centre gripping to the enclosure panel simultaneously, thereby the installation and the demolition of enclosure panel.
Optionally, a plurality of reinforcing ribs are inserted on the capping beam along the width direction of the capping beam.
Through adopting above-mentioned technical scheme, strengthening rib and installation muscle are mutually supported and can be further strengthened the structural strength of capping piece.
Optionally, the connecting assembly comprises a screw rod arranged on the side face of the coping beam in a penetrating mode, a screw cap is arranged on the screw rod, and a mounting groove is formed in the coping beam.
Through adopting above-mentioned technical scheme, the mounting groove supplies the apron board to put into, and the lateral wall of mounting groove carries out the centre gripping to the apron board to make the apron board possess higher stability.
Optionally, the capping beam is provided with a receiving groove for placing a nut.
Through adopting above-mentioned technical scheme, the holding tank is used for holding the nut to make the structure of installing around the cap have the integrality.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the drilling pile column is fixedly connected to the capping beam, the capping beam can be connected to the enclosure plate through the connecting assembly, so that the effect of the enclosure pile can be achieved, and after the foundation pit does not need to be supported, the capping beam can support the building above the ground, so that the drilling pile column is not dismantled, and the effect of saving resources is achieved;
2. this application strengthens the structural strength of drilling stake through inserting the main muscle of establishing in the drilling stake, can play the effect of connecting and fixed coping roof beam through main muscle simultaneously.
Drawings
Fig. 1 is a schematic view of the overall structure of an insulation fender pile according to embodiment 1 of the present application.
Fig. 2 is an exploded view of the capping beam of example 1 of the present application.
Fig. 3 is a schematic structural view of a stirrup according to example 1 of the present application.
Fig. 4 is a schematic view of the overall structure of embodiment 2 of the present application.
Description of reference numerals: 1. drilling a pile; 2. pressing a top beam; 3. a fixing assembly; 31. a main rib; 32. a jack; 33. hooping; 4. reinforcing ribs; 5. a support plate; 6. a connecting assembly; 61. installing ribs; 62. a screw; 63. a nut; 64. accommodating grooves; 65. and (4) mounting the groove.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses an isolation fender post.
Example 1
Referring to fig. 1, an isolation fender pile includes drilling pile 1, and drilling pile 1 sets up along vertical direction, is equipped with capping beam 2 on drilling pile 1's the top surface, still is equipped with the fixed subassembly 3 of connecting capping beam 2 on the commentaries on classics hole pile, and capping beam 2's length direction sets up along the horizontal direction, and drilling pile 1 and capping beam 2 can play the effect of support to subaerial building structure. A plurality of reinforcing ribs 4 are arranged on the top cap 2 along the width direction of the top cap 2, and the reinforcing ribs 4 can enhance the structural strength of the top cap 2. The side wall of the drilling pile column 1 is provided with a plurality of supporting plates 5, the top surface of the supporting plates 5 is abutted to the bottom surface of the capping beam 2, and the supporting plates 5 support and stabilize the capping beam 2. The two ends of the capping beam 2 in the length direction are provided with connecting components 6 for connecting the guard boards.
Referring to fig. 2 and 3, the fixing assembly 3 includes a main rib 31 inserted into the drilling pile 1 in a vertical direction, the top end of the main rib 31 is higher than the top surface of the drilling pile 1, so that the top end of the main rib 31 is inserted into the capping beam 2, the capping beam 2 is provided with an insertion hole 32 for inserting the main rib 31, and the main rib 31 connects the capping beam 2 and the drilling pile 1 together, thereby playing a role of fixing the capping beam 2.
Still be equipped with the stirrup 33 of winding on main muscle 31 in the drilling stake 1, stirrup 33 is to playing the effect of fixed main muscle 31, can further strengthen the structural strength of drilling stake 1.
Referring to fig. 2, coupling assembling 6 includes that two sets of the installation muscle 61 of establishing on the capping beam 2 terminal surface of inserting, and the axial capping beam 2's of installation muscle 61 length direction sets up, and every group installation muscle 61 is equallyd divide and is do not include the installation muscle 61 that a plurality of arranged along vertical direction, can install the fender panel in the middle of two sets of installation muscle 61 to realize the function of fender pile.
The implementation principle of the isolation fender pile in the embodiment of the application is as follows: drilling pile 1 passes through main muscle 31 fixed connection in capping 2, and drilling pile 1 plays the effect of support to capping 2 simultaneously, and capping 2 can play the effect of support to subaerial building. The installation muscle 61 on the capping beam 2 can be used for installing the fender panel to can regard as the function of fender pile, after the enclosure effect, drilling pile 1 and capping beam 2 are as the engineering post that is used for supporting, thereby make drilling pile 1 and capping beam 2 continue to use, reached energy-conserving effect.
Compared with the prior art, drilling pile 1 in this application embodiment passes through fixed connection in capping beam 2, and capping beam 2 can connect in the fender panel through coupling assembling 6 to can play the effect of fender pile, after the foundation ditch need not be strutted, capping beam 2 can play the effect of support to the building of ground top, thereby drilling pile 1 no longer is demolishd, has played the effect of saving the resource.
Example 2
Embodiment 2 and embodiment 1 differ in that, coupling assembling 6 includes the screw rod 62 that wears to establish on capping beam 2 along the width direction of capping beam 2, and the tip of screw rod 62 is equipped with the nut 63 that carries out threaded connection with screw rod 62, offers the holding tank 64 that supplies nut 63 to put into on capping beam 2's the side, has still seted up mounting groove 65 on capping beam 2 length direction's the terminal surface, and screw rod 62 passes mounting groove 65. The mounting groove 65 is used for placing the apron plate, and the lateral wall of mounting groove 65 plays the effect of centre gripping to the apron plate, and screw rod 62 passes the apron plate and plays fixed effect to the apron plate simultaneously, has consequently promoted the stability of apron plate.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. An isolation fender pile, which is characterized in that: including drilling pile (1) along vertical direction setting, the top surface of drilling pile (1) is equipped with capping beam (2), still be equipped with fixed subassembly (3) that are used for fixed capping beam (2) on drilling pile (1), all be equipped with coupling assembling (6) that are used for connecting the apron board on capping beam (2) length direction's the both ends face.
2. An insulation fencing post according to claim 1, wherein: the side surface of the drilling pile column (1) is provided with a plurality of supporting plates (5), and the top surfaces of the supporting plates (5) are abutted to the bottom surface of the capping beam (2).
3. An insulation fencing post according to claim 1, wherein: the fixing assembly (3) comprises a main rib (31) inserted in the drilled pile column (1) in the vertical direction, the top surface of the main rib (31) is higher than that of the drilled pile column (1), and a ground insertion hole (32) for the main rib (31) to be inserted is formed in the compression bar (2).
4. An insulation fencing post according to claim 3, wherein: a plurality of stirrups (33) wound on the main reinforcement (31) are arranged in the drilling pile column (1).
5. An insulation fencing post according to claim 1, wherein: the connecting assembly (6) comprises two groups of mounting ribs (61) inserted in the horizontal direction on the end face of the capping beam (2), and each group of mounting ribs (61) comprises a plurality of mounting ribs (61) arranged in the vertical direction.
6. An insulation fencing post according to claim 1, wherein: and a plurality of reinforcing ribs (4) are inserted on the top-pressing beam (2) along the width direction of the top-pressing beam (2).
7. An insulation fencing post according to claim 1, wherein: coupling assembling (6) are including wearing to establish screw rod (62) on capping beam (2) side, be equipped with nut (63) on screw rod (62), mounting groove (65) have been seted up on capping beam (2).
8. An insulation fencing post according to claim 7, wherein: and the capping beam (2) is provided with an accommodating groove (64) for accommodating a screw cap (63).
CN202122368770.XU 2021-09-28 2021-09-28 Keep apart fender pile Active CN215829437U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122368770.XU CN215829437U (en) 2021-09-28 2021-09-28 Keep apart fender pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122368770.XU CN215829437U (en) 2021-09-28 2021-09-28 Keep apart fender pile

Publications (1)

Publication Number Publication Date
CN215829437U true CN215829437U (en) 2022-02-15

Family

ID=80201574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122368770.XU Active CN215829437U (en) 2021-09-28 2021-09-28 Keep apart fender pile

Country Status (1)

Country Link
CN (1) CN215829437U (en)

Similar Documents

Publication Publication Date Title
CN102704491B (en) Sectional steel and reinforced concrete beam combination foundation pit supporting protection surrounding purlin and construction method of purlin
CN113356551B (en) Cantilever frame structure
CN106401069A (en) Damage repairing assembly type combined column with self-reset function
CN110295669B (en) Reinforced concrete structure and reinforcing method
CN215829437U (en) Keep apart fender pile
CN113585293A (en) Ecological environmental protection pin-connected panel municipal administration side slope reinforced structure
CN211172010U (en) Deep foundation pit supporting device
CN216787149U (en) Green assembled underground structure
CN213952240U (en) Deep foundation pit slope supporting structure
CN214143677U (en) Novel steel retaining wall structure for manual hole digging pile
CN210396760U (en) Assembled supporting system for diversion tunnel construction
CN213508535U (en) Reinforcement type civil engineering pile foundation construction structures
CN211898584U (en) A earthquake-resistant structure for architectural design
CN211816276U (en) Pit supporting structure
CN210217109U (en) Scaffold frame I-steel fixing device encorbelments
CN110258528B (en) Assembled and inserted self-clamping type prefabricated hollow underground continuous wall and construction method thereof
CN215442712U (en) Steel structure bearing pillar for building
CN216130132U (en) Inclined strut underground structure is thrown in soft soil foundation double-deck
CN219315748U (en) Building foundation pit reinforcing support piece
CN219653724U (en) Spliced foundation protection structure
CN214939056U (en) Cement concrete pavement formwork support device
CN114263184B (en) Foundation pit supporting construction method
CN215802676U (en) Reinforced concrete column
CN214574712U (en) Steel construction high ductility antidetonation node
CN218373782U (en) Engineering building foundation pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant