CN215797729U - Coal mine machine cable moving device - Google Patents

Coal mine machine cable moving device Download PDF

Info

Publication number
CN215797729U
CN215797729U CN202122297882.0U CN202122297882U CN215797729U CN 215797729 U CN215797729 U CN 215797729U CN 202122297882 U CN202122297882 U CN 202122297882U CN 215797729 U CN215797729 U CN 215797729U
Authority
CN
China
Prior art keywords
cable
fixedly connected
water
moving device
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202122297882.0U
Other languages
Chinese (zh)
Inventor
姜剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202122297882.0U priority Critical patent/CN215797729U/en
Application granted granted Critical
Publication of CN215797729U publication Critical patent/CN215797729U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cleaning In General (AREA)

Abstract

The utility model relates to the technical field of coal mines, in particular to a coal mine coal machine cable moving device, which solves the problem that in the prior art, as a large amount of silt still remains on the side wall of a cable, the outer wall of the cable is damaged due to extrusion between the cable and the side wall of a winding roller during winding. The utility model provides a coal mine machine cable mobile device, is equipped with a plurality of gyro wheels from the base including the bottom, the upper end of base is equipped with the open slot, the right-hand member fixedly connected with mounting panel of base, be equipped with the mechanism of rolling up that is used for withdrawing the cable on the mounting panel, be equipped with the leading wheel of a plurality of direction cables in the open slot, fixedly connected with install bin on the base, be equipped with the clearance mechanism that is used for clearing up the cable lateral wall in the install bin. The cable side wall cleaning device can clean the side wall of the cable, and avoids the damage to the outer wall of the cable caused by silt reserved on the side wall of the cable when the cable is wound by the winding roller.

Description

Coal mine machine cable moving device
Technical Field
The utility model relates to the technical field of coal mines, in particular to a coal mine coal machine cable moving device.
Background
The coal mine is an area where people mine coal resources in a coal-rich mining area, and is generally divided into an underground coal mine and an open-pit coal mine, and the coal mine is required to be used during coal mining, wherein the coal mine mainly comprises a coal mining machine, and a cable is connected to the coal mining machine and used for providing electric power required by an internal circuit of the coal mining machine.
The utility model discloses a coal mine machine cable conductor machinery that publication number CN210710169U provided moves device certainly, it solves because in the colliery working process, coal mine machine needs to remove the operation, and the cable is also along with removing, but the cable drags in ground, lead to the cable outer wall impaired easily, the cable is thick more heavy simultaneously, be difficult to the problem of dragging, it realizes that the cable breaks away from ground through the cooperation of wind-up roll and trough, avoid the cable to drag in ground, it is only simple to carry out the cable and breaks away from ground, but in the coal mining process, still there are a lot of silt to fall on the cable, when the rolling, still can persist more silt on the lateral wall of cable, when the rolling, there is the extrusion on the cable between the lateral wall with the wind-up roll, when silt, still can cause the damage of cable outer wall. Therefore, a coal mining machine cable moving device is needed to solve the problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a coal mine machine cable moving device, which solves the problem that in the prior art, as a large amount of silt still remains on the side wall of a cable, the outer wall of the cable is damaged due to extrusion between the cable and the side wall of a winding roller during winding.
In order to achieve the purpose, the utility model adopts the following technical scheme:
the utility model provides a coal mine machine cable mobile device, is equipped with a plurality of gyro wheels from the base including the bottom, the upper end of base is equipped with the open slot, the right-hand member fixedly connected with mounting panel of base, be equipped with the mechanism of rolling up that is used for withdrawing the cable on the mounting panel, be equipped with the leading wheel of a plurality of direction cables in the open slot, fixedly connected with install bin on the base, be equipped with the clearance mechanism that is used for clearing up the cable lateral wall in the install bin.
Preferably, the winding mechanism comprises a motor arranged on the lower end face of the mounting plate, and a winding roller is arranged on an output shaft of the motor.
Preferably, the cleaning mechanism comprises a partition plate fixedly connected in the installation box, a plurality of filter screens are arranged on the partition plate, a cleaning ring fixedly connected to the top in the installation box is arranged at the inner part of the cleaning ring, and a plurality of pump water gaps penetrating through the cleaning ring are formed in the inner wall of the cavity.
Preferably, the left end of the open slot is fixedly connected with a circular ring, a hairbrush is arranged in the circular ring, and the right end of the open slot is provided with absorbent cotton.
Preferably, fixedly connected with cam on the center pin of wind-up roll, the equal fixedly connected with L shape loading board of front and back end of mounting panel, two equal fixedly connected with pump water section of thick bamboo on the loading board, two equal sealing sliding connection has the piston in the pump water section of thick bamboo, the piston passes through spring and the inside elastic connection of pump water section of thick bamboo, fixedly connected with runs through the push rod of pump water section of thick bamboo on the piston, fixedly connected with supports the piece with cam matched with on the push rod.
Preferably, the non-spring end of the pump water cylinder is provided with a water inlet pipe in sealed communication with the lower end of the installation box, and the non-spring end of the pump water cylinder is provided with a water outlet pipe in sealed communication with the cavity.
Preferably, a single valve for water inlet is arranged in the water inlet pipe, and a one-way valve for water outlet is arranged in the water outlet pipe.
The utility model has at least the following beneficial effects:
1. through setting up around rolling up mechanism and clearance mechanism, realize that the brush on the ring falls with the large granule silt brush on the cable lateral wall at cable process ring, then when the cable passes through the clean ring in the install bin, a plurality of pump mouths of a river spray the lateral wall of cable with water, carry out the washing of cable, further clear up the silt on the cable lateral wall, wind-up roll rolling after the cotton that absorbs water at last.
2. Through setting up cam, pump water section of thick bamboo, push rod etc. the realization is when the cam rotates, the cooperation spring for reciprocating motion around the push rod, thereby reciprocating motion around the piston, with the water of install bin lower extreme through the inlet tube pump water section of thick bamboo, then advance the cavity through the outlet pipe pump, spout the lateral wall of cable through a plurality of pump mouths of a river, realize carrying out the pump water in the rolling, avoid external power, realize the saving of power resource.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
Fig. 1 is a first perspective view illustrating an external structure of a cable moving device for a coal mining machine according to the present invention;
FIG. 2 is a second perspective view of the external structure of a cable moving device for a coal mining machine according to the present invention;
FIG. 3 is a schematic view of the internal structure of an installation box of a coal mining machine cable moving device according to the present invention;
fig. 4 is a schematic diagram of an internal structure of a cleaning ring of a coal mining machine cable moving device provided by the utility model.
In the figure: 1. a base; 2. an open slot; 3. mounting a plate; 4. a water inlet pipe; 5. installing a box; 6. a motor; 7. a wind-up roll; 8. a water outlet pipe; 9. a filter screen; 10. cleaning the ring; 11. a cavity; 12. a pump nozzle; 13. a circular ring; 14. absorbent cotton; 15. a carrier plate; 16. a water pumping cylinder; 17. a spring; 18. a push rod; 19. a cam.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the utility model.
Referring to fig. 1-4, a coal mine machine cable mobile device, be equipped with a plurality of gyro wheels including the bottom from base 1, base 1's upper end is equipped with open slot 2, base 1's right-hand member fixedly connected with mounting panel 3, be equipped with the mechanism of rolling up that is used for withdrawing the cable on the mounting panel 3, be equipped with the leading wheel of a plurality of direction cables in the open slot 2, fixedly connected with install bin 5 on the base 1, the lower extreme of install bin 5 here is equipped with water, be equipped with the clearance mechanism that is used for clearing up the cable lateral wall in the install bin 5, the upper end of install bin 5 is equipped with the chamber door, conveniently pass install bin 5 with the cable, be equipped with the directive wheel on the lateral wall of install bin 5 simultaneously, and all run through on the lateral wall about install bin 5 and be equipped with the trompil that is used for the cable to pass.
Further, as can be known by referring to fig. 1 and 2, the winding mechanism includes a motor 6 disposed on the lower end surface of the mounting plate 3, a winding roller 7 is disposed on an output shaft of the motor 6, and the motor 6 rotates to drive the winding roller 7 to rotate to wind the cable.
Further, refer to fig. 3 and 4 and can learn, clearance mechanism includes the division board of fixed connection in install bin 5, be equipped with a plurality of filter screens 9 on the division board, clean ring 10 of top fixedly connected with in install bin 5, clean ring 10 inside is equipped with cavity 11, be equipped with a plurality of pump water gaps 12 that run through clean ring 10 on the 11 inner walls of cavity, through setting up pump water gap 12, cavity 11, filter screen 9 etc., when realizing spouting the lateral wall of cable at pump water gap 12, carry out the washing of cable, wash the water that drops and filter the back through filter screen 9, get back to install bin 5's lower extreme again, and the reuse is avoided causing the waste of water resource.
Further, as can be known by referring to fig. 1 and 2, the left end of the open slot 2 is fixedly connected with the ring 13, the inside of the ring 13 is provided with the brush, the right end of the open slot 2 is provided with the water absorbing cotton 14, the brush can brush down large-particle dust on the side wall of the cable, the water absorbing cotton 14 can absorb water on the side wall of the cable, the outer wall of the cable is provided with waterproof rubber, and water cannot enter the cable.
Further, as can be seen from fig. 1 and 2, a cam 19 is fixedly connected to the central shaft of the wind-up roll 7, the front end and the rear end of the mounting plate 3 are fixedly connected with the L-shaped bearing plates 15, the two bearing plates 15 are fixedly connected with the pump water cylinders 16, the pistons are hermetically and slidably connected in the two pump water cylinders 16, the pistons are elastically connected with the interior of the pump water cylinders 16 through springs 17, push rods 18 penetrating the pump water cylinders 16 are fixedly connected to the pistons, abutting blocks matched with the cam 19 are fixedly connected to the push rods 18, through the arrangement of the cam 19, the push rod 18 and the spring 17, when the cam 19 rotates, the push rod 18 is matched with the spring 17 to reciprocate back and forth, so that the piston reciprocates back and forth, water at the lower end of the installation box 5 is pumped into the water pumping cylinder 16 through the water inlet pipe 4, then the water is pumped into the cavity 11 through the water outlet pipe 8 and sprayed to the side wall of the cable through a plurality of pump water gaps 12 to clean the cable.
Further, as can be known from fig. 2 and 3, the end of the pump water cylinder 16, which is not provided with the spring 17, is provided with the water inlet pipe 4 in a sealing manner, the end of the pump water cylinder 16, which is not provided with the spring 17, is provided with the water outlet pipe 8 in a sealing manner, the water outlet pipe is communicated with the cavity 11, and the lower end of the water inlet pipe 4 is close to the lower end face of the installation box 5.
Further, as can be known by referring to fig. 2 and 3, a single valve for water inlet is arranged in the water inlet pipe 4, a check valve for water outlet is arranged in the water outlet pipe 8, and the arrangement of the two check valves avoids water backflow, ensures that water can enter the water pumping cylinder 16 from the lower end of the installation box 5, and finally enters the cavity 11.
The working principle is as follows: when the cable is wound, firstly, a box door at the upper end of the installation box 5 is opened, then the cable passes through a through hole on the side wall of the installation box 5, a steering wheel is used for guiding, then the cable is fixed on a cable winding roller 7, a motor 6 is opened, the motor 6 rotates to drive the cable winding roller 7 to rotate, and the cable is wound, in the cable winding process, the cable firstly passes through a circular ring 13, a hairbrush on the circular ring 13 brushes off large-particle dust on the side wall of the cable, then the cable passes through the installation box 5, the winding roller 7 can drive a cam 19 to rotate while rotating, a push rod 18 is matched with a spring 17 to reciprocate back and forth, so that a piston reciprocates back and forth, water at the lower end of the installation box 5 is pumped into a pump water cylinder 16 through a water inlet pipe 4, then is pumped into a cavity 11 through a water outlet pipe 8, and is sprayed to the side wall of the cable through a plurality of pump water inlets 12 to clean the cable, and the cleaned and dropped water is filtered by a filter screen 9, get back to the lower extreme of install bin 5 again, used repeatedly avoids causing the waste of water resource, then after the cotton 14 that absorb water, at last by the wind-up roll rolling to avoid silt on the cable to cause the wearing and tearing of rolling in-process cable.
The foregoing shows and describes the general principles, essential features, and advantages of the utility model. It will be understood by those skilled in the art that the present invention is not limited to the embodiments described above, which are merely illustrative of the principles of the utility model, but that various changes and modifications may be made without departing from the spirit and scope of the utility model, which fall within the scope of the utility model as claimed. The scope of the utility model is defined by the appended claims and equivalents thereof.

Claims (7)

1. The utility model provides a coal mine machine cable mobile device, is equipped with a plurality of gyro wheels including the bottom from base (1), its characterized in that, the upper end of base (1) is equipped with open slot (2), right-hand member fixedly connected with mounting panel (3) of base (1), be equipped with the mechanism of rolling up that is used for withdrawing the cable on mounting panel (3), be equipped with the leading wheel of a plurality of direction cables in open slot (2), fixedly connected with install bin (5) on base (1), be equipped with the clearance mechanism that is used for clearing up the cable lateral wall in install bin (5).
2. The cable moving device for the coal mining machine according to claim 1, wherein the winding mechanism comprises a motor (6) arranged on the lower end face of the mounting plate (3), and a winding roller (7) is arranged on an output shaft of the motor (6).
3. The coal mining machine cable moving device according to claim 1, wherein the cleaning mechanism comprises a partition plate fixedly connected in the installation box (5), the partition plate is provided with a plurality of filter screens (9), a cleaning ring (10) is fixedly connected to the inner top of the installation box (5), a cavity (11) is formed in the cleaning ring (10), and a plurality of water pumping ports (12) penetrating through the cleaning ring (10) are formed in the inner wall of the cavity (11).
4. The coal mining machine cable moving device as claimed in claim 1, wherein a circular ring (13) is fixedly connected to the left end of the open slot (2), a hairbrush is arranged in the circular ring (13), and water absorption cotton (14) is arranged at the right end of the open slot (2).
5. The coal mining machine cable moving device according to claim 2, wherein a cam (19) is fixedly connected to a central shaft of the winding roller (7), the front end and the rear end of the mounting plate (3) are fixedly connected with L-shaped bearing plates (15), pump water cylinders (16) are fixedly connected to the two bearing plates (15), pistons are hermetically and slidably connected to the two pump water cylinders (16), the pistons are elastically connected to the inside of the pump water cylinders (16) through springs (17), push rods (18) penetrating through the pump water cylinders (16) are fixedly connected to the pistons, and abutting blocks matched with the cam (19) are fixedly connected to the push rods (18).
6. The coal mining machine cable moving device as claimed in claim 5, wherein the non-spring (17) end of the pump water cylinder (16) is provided with a water inlet pipe (4) in sealed communication with the lower end of the installation box (5), and the non-spring (17) end of the pump water cylinder (16) is provided with a water outlet pipe (8) in sealed communication with the cavity (11).
7. The coal mining machine cable moving device according to claim 6, wherein a single valve for water inlet is arranged in the water inlet pipe (4), and a one-way valve for water outlet is arranged in the water outlet pipe (8).
CN202122297882.0U 2021-09-23 2021-09-23 Coal mine machine cable moving device Expired - Fee Related CN215797729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122297882.0U CN215797729U (en) 2021-09-23 2021-09-23 Coal mine machine cable moving device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122297882.0U CN215797729U (en) 2021-09-23 2021-09-23 Coal mine machine cable moving device

Publications (1)

Publication Number Publication Date
CN215797729U true CN215797729U (en) 2022-02-11

Family

ID=80165319

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122297882.0U Expired - Fee Related CN215797729U (en) 2021-09-23 2021-09-23 Coal mine machine cable moving device

Country Status (1)

Country Link
CN (1) CN215797729U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114643247A (en) * 2022-03-23 2022-06-21 山西卡乐仕汽车服务有限公司 Full-automatic container cleaning equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114643247A (en) * 2022-03-23 2022-06-21 山西卡乐仕汽车服务有限公司 Full-automatic container cleaning equipment
CN114643247B (en) * 2022-03-23 2024-06-21 山西卡乐仕汽车服务有限公司 Full-automatic container cleaning equipment

Similar Documents

Publication Publication Date Title
CN215797729U (en) Coal mine machine cable moving device
CN206902007U (en) The sludge dewatering equipment that a kind of flat is made an uproar and prevents spiral from damaging
CN112452879A (en) Environment-friendly building field is with high-efficient desilt device that washs of stone material
CN109078888A (en) Channel side slopes algae removal device
CN115672898B (en) Intelligent cleaning device and cleaning method for petrochemical engineering pipeline
CN211816875U (en) Non-excavation pipeline silt cleaning device
CN210408289U (en) Cleaning equipment for 5A-level office building
CN113511172B (en) Intelligent car washing equipment with multiple brushes
CN101085524A (en) Glass wall adsorption device with built-in cleaning mechanism
CN205032274U (en) Slot type log washer with circulating water system
CN116378603A (en) Hydrogeology well-forming segmented well-flushing device and use method thereof
CN217288584U (en) Stone crusher is used in mine
CN209144851U (en) A kind of equipment that Road Bridge Pile Foundation plinth mud recycles
CN111167779A (en) Environment-friendly water-saving ore cleaning machine
CN210407032U (en) Ginger cleaning equipment
CN212285066U (en) Energy-saving display device for engineering budget
CN111535384A (en) Crawler-type underwater trash remover
CN215290490U (en) Intelligent drainage device
CN218309608U (en) Accessory cleaning platform is used in production of coal mine equipment machine parts
CN217664827U (en) Converter radiator fan separation net belt cleaning device
CN221472785U (en) Mining machinery flushing equipment
CN213915091U (en) Belt cleaning device is used in coal mining
CN212715303U (en) Dredging vehicle and hidden culvert dredging system
CN118007727B (en) Breaking hammer
CN218466445U (en) Road and bridge curing means

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220211

CF01 Termination of patent right due to non-payment of annual fee