CN215715452U - Construction structure for monitoring slope displacement - Google Patents

Construction structure for monitoring slope displacement Download PDF

Info

Publication number
CN215715452U
CN215715452U CN202122034124.XU CN202122034124U CN215715452U CN 215715452 U CN215715452 U CN 215715452U CN 202122034124 U CN202122034124 U CN 202122034124U CN 215715452 U CN215715452 U CN 215715452U
Authority
CN
China
Prior art keywords
rod
push plate
foundation pile
slope displacement
construction structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122034124.XU
Other languages
Chinese (zh)
Inventor
李民
刘菲菲
余文军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia Qichao Surveying And Mapping Co ltd
Original Assignee
Inner Mongolia Qichao Surveying And Mapping Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia Qichao Surveying And Mapping Co ltd filed Critical Inner Mongolia Qichao Surveying And Mapping Co ltd
Priority to CN202122034124.XU priority Critical patent/CN215715452U/en
Application granted granted Critical
Publication of CN215715452U publication Critical patent/CN215715452U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The utility model discloses a construction structure for monitoring side slope displacement, which comprises foundation piles, screws, a mounting seat, mounting rods, a positioning device and a protective structure, wherein the positioning device is arranged in the mounting seat, an inserted rod is inserted into the mounting seat, then a driving piece is rotated, and a clamping rod of the driving piece is inserted into the inserted rod, so that positioning is carried out when the mounting rods are mounted, the mounting is more convenient, labor is reduced, and the beneficial effect of improving the mounting efficiency is achieved; be provided with protective structure through the foundation pile surface, waterproof prevention of seepage permeable blanket is used for preventing that water from permeating in the inside effect of foundation pile, has reached and has carried out waterproof prevention water infiltration in the inside effect of base to the foundation pile, avoids influencing foundation pile life's beneficial effect.

Description

Construction structure for monitoring slope displacement
Technical Field
The utility model particularly relates to a construction structure for monitoring side slope displacement, and relates to the related field of side slope displacement monitoring.
Background
The slope refers to a slope surface with a certain slope, which is formed on two sides of the roadbed to ensure the stability of the roadbed, and in order to master the movement condition of slope rocks and find out a sign of slope damage, slope displacement monitoring equipment is generally used for monitoring the speed, direction and the like of the slope displacement, and is generally installed on the surface of the slope through a construction structure.
But current construction structures need alone to support many people cooperation when the installation and install, and lead to the problem comparatively inconvenient in the installation, be not convenient for protect the foundation pile, lead to the inside infiltration of foundation pile and influence the life's of foundation pile problem.
SUMMERY OF THE UTILITY MODEL
Therefore, in order to solve the above-mentioned disadvantages, the present invention provides a construction structure for monitoring slope displacement.
The utility model is realized in such a way that a construction structure for monitoring side slope displacement is constructed, the device comprises a foundation pile, a screw, an installation seat, an installation rod, a positioning device and a protective structure, the screw is pre-buried in the foundation pile, the positioning device is arranged in the installation seat, the protective structure is arranged on the surface of the foundation pile, the positioning device comprises an insertion rod, a clamping rod, a push plate, a telescopic rod, a sleeve, a fixed seat, a screw rod and a driving piece, the insertion rod is arranged on the surface of the installation rod, the clamping rod is inserted into the insertion rod through the push plate, the telescopic rod is arranged on the surface of the push plate, the telescopic rod is connected with the fixed seat in a sliding mode along the inner wall of the sleeve, the fixed seat is arranged on the surface of the push plate, one end of the screw rod is connected with the fixed seat in a rotating mode, and the driving piece is arranged on the surface of the other end of the screw rod.
Furthermore, the mounting seat is inserted with a screw, and the mounting seat is connected with the mounting rod through a bolt.
Furthermore, protective structure includes waterproof prevention of seepage permeable course, net cloth and protective layer, foundation pile surface is provided with waterproof prevention of seepage permeable course, waterproof prevention of seepage permeable course surface is provided with net cloth, net cloth surface is provided with the protective layer.
Furthermore, the surface of the push plate is provided with two clamping rods, the two clamping rods are positioned on the upper side and the lower side of the surface of the push plate, and the two clamping rods are inserted into the insertion rods.
Furthermore, the surface of the push plate is provided with two telescopic rods, and the two telescopic rods have the same structure and are symmetrical in position.
Furthermore, the screw rods are arranged in two numbers, the two screw rods are located at the left end and the right end of the mounting seat, and the two screw rods are identical in structure.
Furthermore, a cushion ring is arranged on the binding surface of the driving piece and the mounting seat, and an anti-skid structure is arranged on the surface of the cushion ring.
Furthermore, the push pedal is provided with the slipmat with the inserted bar binding face, and the slipmat is located the middle-end on push pedal surface.
Furthermore, the clamping rod is made of metal materials, so that the clamping rod has the effect of high hardness and is not easy to deform.
Furthermore, the telescopic rod is made of an antirust metal material, so that the telescopic rod has the effects of surface antirust and high durability.
The utility model has the following advantages: the utility model provides a construction structure for monitoring slope displacement by improvement, compared with the same type of equipment, the construction structure has the following improvements:
the method has the advantages that: according to the construction structure for monitoring the displacement of the side slope, the positioning device is arranged in the installation seat, the insertion rod is inserted into the installation seat, then the driving piece is rotated, the clamping rod is inserted into the insertion rod, and positioning is achieved when the installation rod is installed, so that the installation is more convenient, the labor is reduced, and the installation efficiency is improved.
The method has the advantages that: according to the construction structure for monitoring the displacement of the side slope, the protection structure is arranged on the surface of the foundation pile, and the waterproof and impermeable layer is used for preventing water from permeating into the foundation pile, so that the effects of preventing water from permeating into the base and preventing the foundation pile from being waterproofed are achieved, and the service life of the foundation pile is prevented from being influenced.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic front view of the positioning device of the present invention;
FIG. 3 is a front view of the push plate of the present invention;
FIG. 4 is a front view of the protective structure of the present invention;
fig. 5 is a schematic structural diagram of the protective structure of the present invention.
Wherein: the foundation pile comprises a foundation pile body-1, a screw-2, a mounting seat-3, a mounting rod-4, a positioning device-5, an inserting rod-51, a clamping rod-52, a push plate-53, a telescopic rod-54, a sleeve-55, a fixed seat-56, a screw rod-57, a driving piece-58, a protection structure-6, a waterproof and impermeable layer-61, a mesh cloth-62 and a protection layer-63.
Detailed Description
The present invention will be described in detail with reference to fig. 1 to 5, and the technical solutions in the embodiments of the present invention will be clearly and completely described, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1, the construction structure for monitoring slope displacement of the present invention includes a foundation pile 1, screws 2, a mounting seat 3, a mounting rod 4, a positioning device 5 and a protection structure 6, wherein the screws 2 are embedded in the foundation pile 1, the mounting seat 3 is inserted into the screws 2, the mounting seat 3 is connected to the mounting rod 4 by bolts, the positioning device 5 is arranged in the mounting seat 3, and the protection structure 6 is arranged on the surface of the foundation pile 1.
Referring to fig. 2 and 3, the positioning device 5 of the construction structure for monitoring slope displacement of the present invention includes an insertion rod 51, a clamping rod 52, a push plate 53, an expansion rod 54, a sleeve 55, a fixing seat 56, a screw 57 and a driving member 58, wherein the insertion rod 51 is disposed on the surface of the installation rod 4, the clamping rod 52 is inserted into the insertion rod 51 through the push plate 53, the clamping rod 52 is used for limiting, the expansion rod 54 is disposed on the surface of the push plate 53, the expansion rod 54 is slidably connected along the inner wall of the sleeve 55, the expansion rod 54 is used for limiting and sliding, the fixing seat 56 is disposed on the surface of the push plate 53, one end of the screw 57 is rotatably connected to the fixing seat 56, the screw 57 is used for pushing the push plate 53, and the driving member 58 is disposed on the surface of the other end of the screw 57; the surface of the push plate 53 is provided with two clamping rods 52, the two clamping rods 52 are positioned at the upper side and the lower side of the surface of the push plate 53, and the two clamping rods 52 are inserted into the insertion rods 51, so that a better reinforcing effect is achieved; the surface of the push plate 53 is provided with two telescopic rods 54, the two telescopic rods 54 have the same structure and symmetrical positions, have limiting sliding pain and further improve the reinforcing effect; the number of the screws 57 is two, the two screws 57 are positioned at the left end and the right end of the mounting base 3, and the two screws 57 have the same structure and have a better fixing function; the binding surface of the driving piece 58 and the mounting seat 3 is provided with a backing ring, and the surface is provided with an anti-skid structure, so that the driving piece 58 is prevented from rotating automatically; the binding surface of the push plate 53 and the inserted rod 51 is provided with an anti-skid pad, the anti-skid pad is positioned at the middle end of the surface of the push plate 53 and has the function of limiting the inserted rod 51; the clamping rod 52 is made of metal, so that the clamping rod 52 has the effects of high hardness and difficult deformation; the telescopic rod 54 is made of rustproof metal, so that the telescopic rod 54 has the effects of surface rust prevention and high durability.
Referring to fig. 4 and 5, in the construction structure for monitoring slope displacement according to the present invention, the protective structure 6 includes a waterproof and impermeable layer 61, a mesh cloth 62 and a protective layer 63, the waterproof and impermeable layer 61 is disposed on the surface of the foundation pile 1, the mesh cloth 62 is disposed on the surface of the waterproof and impermeable layer 61, the waterproof and impermeable layer 61 serves a waterproof function, the protective layer 63 is disposed on the surface of the mesh cloth 62, and the protective layer 63 serves a protective function.
The utility model provides a construction structure for monitoring side slope displacement through improvement, and the working principle is as follows;
firstly, embedding a foundation pile 1 into a side slope, then inserting an installation seat 3 and a screw 2, fixing the installation seat 3 through a nut, attaching an installation rod 4 to the surface of the installation seat 3, and then fixing through a bolt;
secondly, when the installation rod 4 needs to be installed, the installation rod 4 is attached to the surface of the installation seat 3, the insertion rod 51 of the installation rod 4 is inserted into the installation seat 3, then the driving piece 58 is rotated, the screw 57 of the installation rod is rotated along the inner wall of the installation seat 3, due to the fact that the screw 57 is in threaded connection with the installation seat 3, when the screw 57 rotates, the screw 57 slides along the inner wall of the installation seat 3 from outside to inside, when the screw 57 rotates, the screw 57 rotates along the inner wall of the fixing seat 56, the fixing seat 56 is pushed to enable the push plate 53 of the fixing seat to slide, when the push plate 53 slides, the telescopic rod 54 is driven to slide along the inner wall of the sleeve 55, the telescopic rod 54 is used for limiting and sliding the push plate 53, when the push plate 53 slides, the clamping rod 52 is pushed to be inserted into the insertion rod 51, so that the installation rod 4 is positioned, and the installation rod 4 is installed and the stability is strengthened;
thirdly, foundation pile 1 surface waterproof impermeable layer 61 is used for preventing water infiltration in the inside effect of foundation pile 1, and net cloth 62 is used for improving the intensity of foundation pile 1 surface course, promotes foundation pile 1's resistance continuity, and the atress of dispersion foundation pile 1 surface course to and prevent waterproof impermeable layer 61 fracture, to the guard action of waterproof impermeable layer 61, protective layer 63 is used for carrying out the effect of protection to net cloth 62, thereby carries out the effect of protection to foundation pile 1.
According to the construction structure for monitoring the slope displacement, the positioning device 5 is arranged in the mounting seat 3, the insertion rod 51 is inserted into the mounting seat 3, the driving piece 58 is rotated, the clamping rod 52 is inserted into the insertion rod 51, and positioning is achieved when the mounting rod 4 is mounted, so that the construction structure is more convenient to mount, labor is reduced, and the mounting efficiency is improved; foundation pile 1 surface is provided with protective structure 6, and waterproof prevention of seepage permeable barrier 61 is used for preventing that water from permeating in the inside effect of foundation pile 1, has reached and has carried out waterproof effect of preventing that water from permeating in foundation pile 1 inside to foundation pile 1, avoids influencing 1 life's of foundation pile beneficial effect.

Claims (8)

1. The utility model provides a side slope displacement monitoring's construction structures, includes foundation pile (1), screw (2), mount pad (3) and installation pole (4), foundation pile (1) inside pre-buried screw (2), its characterized in that: also comprises a positioning device (5) and a protective structure (6), the positioning device (5) is arranged in the mounting seat (3), the surface of the foundation pile (1) is provided with a protective structure (6), the positioning device (5) comprises an inserted bar (51), a clamping bar (52), a push plate (53), an expansion bar (54), a sleeve (55), a fixed seat (56), a screw rod (57) and a driving piece (58), the surface of the mounting rod (4) is provided with an inserted link (51), the clamping rod (52) is inserted into the inserted link (51) through a push plate (53), the surface of the push plate (53) is provided with a telescopic rod (54), the telescopic rod (54) is connected with the inner wall of the sleeve (55) in a sliding way, the surface of the push plate (53) is provided with a fixed seat (56), one end of the screw rod (57) is rotatably connected with the fixed seat (56), and the surface of the other end of the screw rod (57) is provided with a driving piece (58).
2. The construction structure of slope displacement monitoring of claim 1, characterized in that: the mounting seat (3) is connected with the screw (2) in an inserting mode, and the mounting seat (3) is connected with the mounting rod (4) through a bolt.
3. The construction structure of slope displacement monitoring of claim 1, characterized in that: the protective structure (6) comprises a waterproof and anti-seepage layer (61), grid cloth (62) and a protective layer (63), wherein the waterproof and anti-seepage layer (61) is arranged on the surface of the foundation pile (1), the grid cloth (62) is arranged on the surface of the waterproof and anti-seepage layer (61), and the protective layer (63) is arranged on the surface of the grid cloth (62).
4. The construction structure of slope displacement monitoring of claim 1, characterized in that: the surface of the push plate (53) is provided with two clamping rods (52), the two clamping rods (52) are positioned on the upper side and the lower side of the surface of the push plate (53), and the two clamping rods (52) are inserted into the insertion rod (51).
5. The construction structure of slope displacement monitoring of claim 1, characterized in that: the surface of the push plate (53) is provided with two telescopic rods (54), and the two telescopic rods (54) have the same structure and are symmetrical in position.
6. The construction structure of slope displacement monitoring of claim 1, characterized in that: the two screws (57) are arranged, the two screws (57) are positioned at the left end and the right end of the mounting seat (3), and the two screws (57) are identical in structure.
7. The construction structure of slope displacement monitoring of claim 1, characterized in that: a cushion ring is arranged on the binding surface of the driving piece (58) and the mounting seat (3), and an anti-skid structure is arranged on the surface of the cushion ring.
8. The construction structure of slope displacement monitoring of claim 1, characterized in that: the push plate (53) and the binding surface of the inserted link (51) are provided with anti-slip pads, and the anti-slip pads are positioned at the middle end of the surface of the push plate (53).
CN202122034124.XU 2021-08-26 2021-08-26 Construction structure for monitoring slope displacement Active CN215715452U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122034124.XU CN215715452U (en) 2021-08-26 2021-08-26 Construction structure for monitoring slope displacement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122034124.XU CN215715452U (en) 2021-08-26 2021-08-26 Construction structure for monitoring slope displacement

Publications (1)

Publication Number Publication Date
CN215715452U true CN215715452U (en) 2022-02-01

Family

ID=80007846

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122034124.XU Active CN215715452U (en) 2021-08-26 2021-08-26 Construction structure for monitoring slope displacement

Country Status (1)

Country Link
CN (1) CN215715452U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115404858A (en) * 2022-10-09 2022-11-29 福建宏盛建设集团有限公司 Foundation pile with good permeability prevention performance for green building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115404858A (en) * 2022-10-09 2022-11-29 福建宏盛建设集团有限公司 Foundation pile with good permeability prevention performance for green building

Similar Documents

Publication Publication Date Title
CN215715452U (en) Construction structure for monitoring slope displacement
CN212689718U (en) Concrete pole with prefabricated base
CN214695652U (en) Novel deep foundation pit side slope supporting structure
CN211036760U (en) Warning device for tunnel pipe gallery
CN212534134U (en) Foundation pit supporting and reinforcing device
CN217977970U (en) Anti-collapse device for water supply and drainage construction of building engineering
CN217651862U (en) Park is reformed transform with synthesizing pipe network slot protector
CN221000865U (en) Slope protection net for water conservancy
CN212656353U (en) Side wall water drainage device of underground garage
CN220318449U (en) Airport embankment afforestation landslide reinforcement device
CN214116399U (en) Town road guardrail
CN218115999U (en) Roadbed drainage structure
CN217785495U (en) Base device of solar water heater
CN221328583U (en) Pre-buried structure of cable protection pipe
CN218952154U (en) Foundation pit drainage structure
CN213682191U (en) Water conservancy retaining wall
CN212104135U (en) Structure is administered to side slope that friction pile combines with anchor rope, anchor hole
CN217267259U (en) Hydraulic engineering design slope protection structure
CN216586581U (en) Anchor cable arrangement structure of steel sheet pile slope protection area
CN214832700U (en) Pile foundation construction concrete pouring enclosure device
CN221072496U (en) Seepage-proofing structure for dam
CN221193632U (en) Well cover for sewer
CN214940240U (en) Slope protection device
CN218118877U (en) Pipeline protection reinforced structure
CN219932200U (en) Colliery underworkings prevents outstanding supporting equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant