CN215715234U - River bank foundation protection structure - Google Patents

River bank foundation protection structure Download PDF

Info

Publication number
CN215715234U
CN215715234U CN202122011000.XU CN202122011000U CN215715234U CN 215715234 U CN215715234 U CN 215715234U CN 202122011000 U CN202122011000 U CN 202122011000U CN 215715234 U CN215715234 U CN 215715234U
Authority
CN
China
Prior art keywords
layer
reinforcing
river bank
piles
precast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202122011000.XU
Other languages
Chinese (zh)
Inventor
邓祥雨
杨显娥
李瑞谨
孙道蕊
有东华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Runjing Engineering Technology Group Co ltd
Original Assignee
Yunnan Runjing Engineering Technology Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Runjing Engineering Technology Group Co ltd filed Critical Yunnan Runjing Engineering Technology Group Co ltd
Priority to CN202122011000.XU priority Critical patent/CN215715234U/en
Application granted granted Critical
Publication of CN215715234U publication Critical patent/CN215715234U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to the technical field of river bank protection, in particular to a river bank foundation protection structure which comprises precast concrete tubular piles and cement mixing piles, wherein a plurality of precast concrete tubular piles are buried under a river bank and are arranged in a row to form an impermeable layer; a plurality of cement mixing piles are buried below the river bank and are arranged in a row to form a reinforcing layer, and the reinforcing layer is arranged on one side, far away from river water, of the anti-seepage layer; gravel layers are laid above the impermeable layer and the reinforcing layer, concrete protection feet are laid above the gravel layers, and the concrete protection feet are laid along the river bank. The method aims to reduce the damage of excavation of the foundation pit to the ecological environment by adopting a mode that the prestressed concrete pipe piles are buried in the river bank, thereby reducing the seepage-proofing requirement after excavation of the foundation pit.

Description

River bank foundation protection structure
Technical Field
The utility model belongs to the technical field of river bank protection, and particularly relates to a river bank foundation protection structure.
Background
At present, medium and small river governing engineering is being developed in a large number, the main governing scheme is newly-built river levee, newly-built bank protection, newly-built revetment, river levee reinforcement and the like, and governing engineering has many safety problems and quality problems in the implementation process, and the main problems include: the river bank is long, and the terrain conditions are changed greatly due to river channel evolution and the like; the geological conditions change greatly, and the foundation changes greatly in the construction process and the foundation treatment and foundation pit seepage prevention difficulty is high due to the long river channel and the small exploration section.
The bank protection foundation needs to be excavated below the riverbed, so that the scouring requirement is met, the foundation pit seepage prevention difficulty is high, the river channel is in a natural state, the water level fluctuation of the river channel is large, and the foundation treatment is not favorable. The river bank protection foundation can not meet the requirements of bank protection and bank protection engineering, the treatment of the bank protection foundation can meet the construction requirements, the requirements for reducing construction hidden dangers are met, and the requirements for meeting the flood control requirements of river channels and promoting the social and economic development are met. The existing main methods for treating the bank protection foundation comprise foundation excavation, block stone backfilling and the like, the foundation excavation cost is low, but a foundation pit is deep, the foundation pit is difficult to prevent seepage, temporary supporting is needed, the construction difficulty is high, water and soil loss is caused by foundation excavation, and the influence on the ecological environment is large; the stone block backfilling cost is high, a stone stock ground needs to be opened up, the construction difficulty is high, and the construction quality is difficult to guarantee.
Disclosure of Invention
The utility model provides a river bank foundation protection structure for solving the problem of river bank protection foundation treatment, mainly aiming at the problems of impermeability, ecological environment influence, safety, construction difficulty and short service life of the existing foundation treatment.
The technical scheme adopted by the utility model is as follows: a river bank foundation protection structure comprises precast concrete tubular piles and cement mixing piles, wherein a plurality of precast concrete tubular piles are buried under a river bank and are arranged in a row to form an impermeable layer; a plurality of cement mixing piles are buried below the river bank and are arranged in a row to form a reinforcing layer, and the reinforcing layer is arranged on one side, far away from river water, of the anti-seepage layer; gravel layers are laid above the impermeable layer and the reinforcing layer, concrete protection feet are laid above the gravel layers, and the concrete protection feet are laid along the river bank.
Preferably, a plurality of precast concrete pipe piles are arranged in a row to form a stabilizing layer, and the stabilizing layer is arranged between the impermeable layer and the stabilizing layer; the impermeable layer and the stable layer are connected by first steel bars.
Preferably, a second reinforcing steel bar is arranged in the impermeable layer, and the second reinforcing steel bar penetrates through the impermeable layer.
Preferably, the arrangement density of the reinforcing layer is thinner than that of the impermeable layer; the arrangement density of the stabilizing layer is thinner than that of the reinforcing layer.
Preferably, the distance between the precast concrete tubular piles in the impermeable layer is 0.3-0.5 m; the distance between the precast concrete pipe piles in the stabilizing layer is 1.5-2.5 m; the distance between the cement mixing piles in the reinforcing layer is 0.8-1 m.
Preferably, the distance between the barrier layer and the reinforcing layer and between the reinforcing layer and the stabilizing layer is 1-1.5 m.
The utility model has the advantages that: according to the utility model, the precast concrete pipe piles can be directly buried below the river bank through the precast concrete pipe piles, and the penetration of groundwater in the river bed into the foundation pit can be reduced through the arrangement of the pipe piles in a row; the mode that the tubular pile was buried underground is adopted, foundation excavation can be reduced to reduce the influence to river course quality of water, reduce the excavation and also make and abandon the sediment volume and reduce, corresponding sediment field area of abandoning diminishes, thereby guarantees to reduce the influence to ecological environment.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a plan view.
In the figure: 1-river bank; 2-a stabilizing layer; 3-an impermeable layer; 4-a reinforcing layer; 5-a crushed stone layer; 6-concrete foot protection; 7-a first rebar; 8-second steel bar.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the utility model.
As shown in fig. 1-2, a protective structure for a river bank foundation comprises a precast concrete pipe pile and a cement mixing pile, wherein the precast concrete pipe pile needs to be precast outside the field and is directly driven into soil below the river bank through machinery after being precast.
A plurality of precast concrete tubular piles are buried under a river bank 1, the precast concrete tubular piles are arranged in a row to form an impermeable layer 3, the impermeable layer 3 is close to the position of river water and can play a role in seepage prevention and scour prevention, the distance between the precast concrete tubular piles in the impermeable layer 3 is 0.3-0.5m, and the distance between the precast concrete tubular piles is preferably 0.5 m.
A plurality of cement mixing piles are buried below the river bank 1 and are arranged in a row to form a reinforcing layer 4, so that the foundation is reinforced, the reinforcing layer 4 is arranged on one side, away from river water, of the anti-seepage layer 3, the distance between the cement mixing piles in the reinforcing layer 4 is 0.8-1m, and the distance between the cement mixing piles is preferably 1m in the utility model; the gravel layer 5 is laid above the impermeable layer 3 and the reinforcing layer 4, the gravel layer 5 is used for balancing the stress of the reinforcing layer 4 and the impermeable layer 3, the concrete toe guard 6 is laid above the gravel layer 5, the concrete toe guard 6 is laid along the river bank 1, the concrete toe guard 6 prevents the collapse of the soil bank side slope caused by the damage of the scoured dike toe guard, and the shape of the concrete toe guard 6 can be set according to actual construction requirements.
A plurality of precast concrete pipe piles are arranged in a row to form a stable layer 2, and the reinforcing layer 4 is arranged between the impermeable layer 3 and the stable layer 2; the impermeable layer 3 and the stable layer 2 are connected by a first reinforcing steel bar 7. As shown in fig. 1, a stabilizing layer 2 is provided, and the stabilizing layer 2 is used for pulling the impermeable layer 3 of the front row to enhance the stability of the impermeable layer 3. The barrier layer 3 is connected with the firm barrier layer 2 by first reinforcing bar 7, and the barrier layer 3 is stabilized through first reinforcing bar 7, and first reinforcing bar 7 is buckled and is set up to guarantee the firm to barrier layer 3.
The further technical scheme is that a second steel bar 8 is arranged in the impermeable layer 3, and the second steel bar 8 penetrates through the impermeable layer 3. Be provided with the second reinforcing bar 8 that runs through in barrier layer 3, all precast concrete tubular piles in second reinforcing bar 8 in with barrier layer 3 link into an organic whole, and the connection of the first reinforcing bar 7 of rethread for barrier layer 3 is held to firm layer 2, supports and stabilizes barrier layer 3's whole.
As shown in fig. 2, the arrangement density of the reinforcing layer 4 is thinner than that of the impermeable layer 3; the arrangement density of the stabilizing layer 2 is thinner than that of the reinforcing layer 4. The distance between the precast concrete tubular piles in the stabilizing layer 2 is 1.5-2.5m, and the distance between the precast concrete tubular piles in the stabilizing layer 2 is preferably 2m in the utility model. During connection, the first reinforcing steel bars 7 penetrate through the reinforcing layer 4 after being bent, and the first reinforcing steel bars 7 penetrate between the two cement mixing piles in the reinforcing layer 4 and are separated from the cement mixing piles.
The distances between the impermeable layer 3 and the reinforcing layer 4 and between the reinforcing layer 4 and the stabilizing layer 2 are 1-1.5m, and preferably, in the utility model, the distances between the impermeable layer 3 and the reinforcing layer 4 and between the reinforcing layer 4 and the stabilizing layer 2 are equal and are all 1 m.
The specific working mode is as follows: a construction scheme is formulated according to the specific conditions of the river bank, the precast concrete pipe pile is manufactured according to the design requirements, and after the precast concrete pipe pile meets the construction requirements, the precast concrete pipe pile is conveyed to the site for construction; the precast concrete pipe pile and the cement mixing pile are embedded below the river bank in sequence according to the design point position to form an impermeable layer 3, a reinforcing layer 4 and a stabilizing layer 2, so that the impermeable layer 3 forms a stable impermeable and scour prevention layer to ensure the protection of the river bank foundation; and finally, paving a rubble layer 5 on the anti-seepage layer 3, the reinforcing layer 4 and the stabilizing layer 2, so that the anti-seepage layer 3, the reinforcing layer 4 and the stabilizing layer 2 are stressed uniformly.
This structure reduces basic excavation to reduce the influence to river course quality of water, reduce the excavation and also make and abandon the sediment volume and reduce, the corresponding sediment field area of abandoning diminishes, thereby guarantees to reduce ecological environment's influence.
The above-mentioned embodiments are preferred embodiments, it should be noted that the above-mentioned preferred embodiments should not be considered as limitations to the utility model, and the scope of protection of the present invention should be subject to the scope defined by the claims. It will be apparent to those skilled in the art that various modifications and adaptations can be made without departing from the spirit and scope of the utility model, and these modifications and adaptations should be considered within the scope of the utility model.

Claims (6)

1. The utility model provides a bank foundation protective structure, includes precast concrete tubular pile and cement mixing stake, its characterized in that: a plurality of precast concrete tubular piles are buried under the river bank (1) and are arranged in a row to form an impermeable layer (3); a plurality of cement mixing piles are buried below the river bank (1) and are arranged in a row to form a reinforcing layer (4), and the reinforcing layer (4) is arranged on one side, far away from river water, of the anti-seepage layer (3); gravel layer (5) are laid to barrier layer (3) and back up coat (4) top, concrete banket (6) are laid to gravel layer (5) top, concrete banket (6) are laid along river bank (1).
2. The riparian base protection structure according to claim 1, wherein: a plurality of precast concrete pipe piles are arranged in a row to form a stabilizing layer (2), and the reinforcing layer (4) is arranged between the impermeable layer (3) and the stabilizing layer (2); the impermeable layer (3) and the stabilizing layer (2) are connected by a first steel bar (7).
3. The riparian base protection structure according to claim 2, wherein: and a second reinforcing steel bar (8) is arranged in the impermeable layer (3), and the second reinforcing steel bar (8) penetrates through the impermeable layer (3).
4. The riparian base protection structure according to claim 3, wherein: the arrangement density of the reinforcing layer (4) is thinner than that of the impermeable layer (3); the arrangement density of the stabilizing layer (2) is thinner than that of the reinforcing layer (4).
5. The riparian base protection structure according to claim 4, wherein: the distance between the precast concrete pipe piles in the impermeable layer (3) is 0.3-0.5 m; the distance between the precast concrete pipe piles in the stabilizing layer (2) is 1.5-2.5 m; the distance between the cement stirring piles in the reinforcing layer (4) is 0.8-1 m.
6. The riparian base protection structure according to any one of claims 2 to 5, wherein: the distance between the impermeable layer (3) and the reinforcing layer (4) and the distance between the reinforcing layer (4) and the stabilizing layer (2) are 1-1.5 m.
CN202122011000.XU 2021-08-25 2021-08-25 River bank foundation protection structure Active CN215715234U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202122011000.XU CN215715234U (en) 2021-08-25 2021-08-25 River bank foundation protection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202122011000.XU CN215715234U (en) 2021-08-25 2021-08-25 River bank foundation protection structure

Publications (1)

Publication Number Publication Date
CN215715234U true CN215715234U (en) 2022-02-01

Family

ID=80006906

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202122011000.XU Active CN215715234U (en) 2021-08-25 2021-08-25 River bank foundation protection structure

Country Status (1)

Country Link
CN (1) CN215715234U (en)

Similar Documents

Publication Publication Date Title
CN103981876A (en) Combined member for co-constructing deep soft foundation river way and river embankment and construction method
CN104452829A (en) Piled raft foundation anti-floating structure and construction method
CN111691438A (en) Anti-skidding-drainage comprehensive treatment method for landslide of large-scale accumulation body
CN102966072A (en) Construction method for treating widened and heightened engineering joint surfaces of dikes on soft clay foundation
CN207003421U (en) A kind of steel plate pilework for being seated hard rock top surface
CN104895111A (en) Construction method of integrated pipe trench in soft soil
CN102425179B (en) Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes
CN107165640A (en) Tunnels and underground engineering surely builds method certainly
CN108914959B (en) Foundation structure suitable for mountain house building and construction method thereof
CN113123358B (en) Ship pool deformation prevention and control structure under action of uneven settlement of coal mining and construction method
CN215715234U (en) River bank foundation protection structure
CN103276717A (en) Method for treating soft soil foundations with composite geotechnical synthetic material reinforced cushions
CN107119716B (en) Construction method of highway tunnel in tidal bore area of tidal marsh
CN112049117B (en) Earth-rock binary foundation pit supporting structure system
CN111305050B (en) Protection process for existing piers on two sides in tunnel construction
CN211773608U (en) Prefabricated assembled rectangle friction pile dado
CN204435321U (en) A kind of steam power station water intaking open channel
CN203855972U (en) Combined member used for co-construction of deep soft-foundation riverway and beside-river embankment
CN110984143A (en) Prefabricated rectangular slide-resistant pile retaining wall and construction method thereof
CN206815381U (en) A kind of tidal land tidal bore area vcehicular tunnel builds structure
CN110284511A (en) The cofferdam open cutting construction method of the more storehouse rollers of overlength lake Tunnel
CN218667392U (en) Channel structure suitable for Chengdu clay section
CN114775620B (en) Construction method for progressive excavation of plain riverbank under mucky soil condition
CN217460445U (en) Novel refute bank suitable for soft soil foundation
CN220977858U (en) Urban river ecological environment restoration structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant