CN215666734U - Simple hanging bracket for wind power installation platform union pile-flushing hose - Google Patents

Simple hanging bracket for wind power installation platform union pile-flushing hose Download PDF

Info

Publication number
CN215666734U
CN215666734U CN202121317592.1U CN202121317592U CN215666734U CN 215666734 U CN215666734 U CN 215666734U CN 202121317592 U CN202121317592 U CN 202121317592U CN 215666734 U CN215666734 U CN 215666734U
Authority
CN
China
Prior art keywords
sleeve
union
pile
hose
wind power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121317592.1U
Other languages
Chinese (zh)
Inventor
程真学
刘卓玉
李磷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Dajin Heavy Industry Co ltd
Original Assignee
Jiangsu Dajin Heavy Industry Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Dajin Heavy Industry Co ltd filed Critical Jiangsu Dajin Heavy Industry Co ltd
Priority to CN202121317592.1U priority Critical patent/CN215666734U/en
Application granted granted Critical
Publication of CN215666734U publication Critical patent/CN215666734U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a simple hanging bracket for a wind power installation platform union pile-punching hose, which relates to the technical field of ship construction and comprises a stand column; the sleeve is rotatably sleeved on the upper part of the upright post, a hanging rod perpendicular to the sleeve is fixedly arranged on the sleeve, and a hanging ring is arranged on the hanging rod; and the positioning piece is used for fixing the sleeve in the outer side of the upright post, the positioning piece comprises a positioning screw rod arranged on the side wall of the sleeve in a penetrating mode through threads, and the end part of the positioning screw rod can extend into the sleeve and is abutted against the side wall of the upright post. According to the utility model, the hand chain block is hoisted on the hoisting ring, and the union hose is hoisted by the hand chain block, so that the labor intensity of operators can be greatly reduced, the sleeve can be rotatably sleeved outside the upright post, the orientation of the union hose can be adjusted by rotating the sleeve, the union hose is conveniently connected with the union joint in the pile leg, time and labor are saved, and the installation efficiency is improved.

Description

Simple hanging bracket for wind power installation platform union pile-flushing hose
Technical Field
The utility model relates to the technical field of ship construction, in particular to a simple hanger for a union pile-punching hose of a wind power installation platform.
Background
In a conventional wind power installation platform, union hoses are manually carried and operated and installed. The union hose in general wind-powered electricity generation mounting platform is 5 inches, 6 meters long, needs 6 people at least can lift completely, when the union hose is connected with the union joint in the spud leg, needs to remove the union hose to the orientation of adjustment hose, therefore operating personnel intensity of labour is too big, and the efficiency of construction is lower.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem of overcoming the defects of the prior art and provides a simple hanging bracket for a union pile-flushing hose of a wind power installation platform.
In order to solve the technical problems, the technical scheme of the utility model is as follows:
a simple hanger for a union pile-flushing hose of a wind power installation platform, which comprises,
a column;
the sleeve is rotatably sleeved on the upper part of the upright post, a hanging rod perpendicular to the sleeve is fixedly arranged on the sleeve, and a hanging ring is arranged on the hanging rod; and the number of the first and second groups,
the setting element, be used for with the sleeve pipe is fixed in the outside of stand, the setting element includes that the screw thread wears to establish positioning screw on the sleeve pipe lateral wall, positioning screw's tip can extend in the sleeve pipe, and with the lateral wall butt of stand.
As a preferred scheme of the simple hanging bracket for the union pile-flushing hose of the wind power installation platform, the utility model comprises the following steps: the side wall of the upright post is provided with a plurality of positioning holes for the positioning screws to extend into, the positioning holes are positioned in the same horizontal plane, and the distance between any two adjacent positioning holes is equal.
As a preferred scheme of the simple hanging bracket for the union pile-flushing hose of the wind power installation platform, the utility model comprises the following steps: the side wall of the upright post is provided with a plurality of groups of positioning holes, each group of positioning holes comprises a plurality of positioning holes which are uniformly distributed in the same horizontal plane, and the plurality of groups of positioning holes are sequentially arranged at equal intervals along the length direction of the upright post.
As a preferred scheme of the simple hanging bracket for the union pile-flushing hose of the wind power installation platform, the utility model comprises the following steps: the lifting rings are at least two and are sequentially arranged along the length direction of the lifting rods.
As a preferred scheme of the simple hanging bracket for the union pile-flushing hose of the wind power installation platform, the utility model comprises the following steps: the hanger rod is fixedly provided with a sliding guide rail along the length direction of the hanger rod, and the hanging ring is slidably mounted on the sliding guide rail through a sliding seat.
As a preferred scheme of the simple hanging bracket for the union pile-flushing hose of the wind power installation platform, the utility model comprises the following steps: and one end of the suspender, which is far away from the sleeve, is fixedly provided with a limiting end plate.
As a preferred scheme of the simple hanging bracket for the union pile-flushing hose of the wind power installation platform, the utility model comprises the following steps: and a reinforcing rib is fixedly arranged between the sleeve and the hanging rod.
The utility model has the beneficial effects that:
(1) according to the utility model, the hand chain block is hoisted on the hoisting ring, and the union hose is hoisted by the hand chain block, so that the labor intensity of operators can be greatly reduced, the sleeve can be rotatably sleeved outside the upright post, the orientation of the union hose can be adjusted by rotating the sleeve, the union hose is conveniently connected with the union joint in the pile leg, time and labor are saved, and the installation efficiency is improved.
(2) The sleeve can be fixed at different heights of the upright post through the positioning piece, and meanwhile, the suspender can be fixed in different directions, so that the union hose can be conveniently installed and butted.
(3) According to the utility model, the sliding guide rail is fixedly arranged on the suspension rod, the suspension ring is slidably arranged on the sliding guide rail, and the position of the suspension ring can be adjusted according to the use requirement. If the hose with the small hoisting length is hoisted, the distance between the two hoisting rings can be shortened, and the distance between the two hoisting rings can be increased when the hose with the large hoisting length is hoisted, so that the stability of the hose in the hoisting process is improved.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without inventive exercise.
Fig. 1 is a schematic structural diagram of a simple hanger for a union pile-flushing hose of a wind power installation platform provided by the utility model;
FIG. 2 is a schematic structural disassembly view of a simple hanger for a union pile-flushing hose of a wind power installation platform provided by the utility model;
wherein: 1. a column; 2. a sleeve; 3. a boom; 4. a hoisting ring; 5. positioning a screw rod; 6. positioning holes; 7. a sliding guide rail; 8. a sliding seat; 9. a limiting end plate; 10. and (5) reinforcing ribs.
Detailed Description
In order that the present invention may be more readily and clearly understood, a more particular description of the utility model briefly described above will be rendered by reference to specific embodiments that are illustrated in the appended drawings.
This embodiment provides a wind-powered electricity generation mounting platform union is towards simple and easy gallows for stake hose, including the stand 1 that sets up along vertical direction, the coaxial cover in the outside of the upper end of stand 1 is equipped with sleeve pipe 2, and sleeve pipe 2's internal diameter is greater than the external diameter of stand 1, makes the sleeve can rotate around the axis of stand 1. Fixed mounting has jib 3 along the horizontal direction on the lateral wall of sleeve pipe 2, and installs two rings 4 on jib 3, and these two rings 4 arrange in proper order along jib 3's length direction.
In order to fix the sleeve 2 on the outer side of the upright post 1, a positioning screw 5 is vertically arranged on the side surface of the sleeve 2, and the end of the positioning screw 5 passes through the side wall of the sleeve 2 and extends into the sleeve 2. By rotating the positioning screw 5 inward, the end of the positioning screw 5 abuts against the sidewall of the column 1, and the sleeve 2 is fixed outside the column 1 by the friction force between the positioning screw 5 and the column 1.
Preferably, a plurality of positioning holes 6 are correspondingly formed on the side wall of the upright post 1. Each group of positioning holes 6 comprises a plurality of positioning holes 6 which are uniformly distributed at the same height of the upright post 1, and the distance between any two adjacent positioning holes 6 in the plurality of positioning holes 6 is equal. When the positioning screw 5 on the sleeve 2 is aligned with one positioning hole 6 of the group of positioning holes 6, the end of the positioning screw 5 can extend into the positioning hole 6 by rotating the positioning screw 5 inwards, so that the sleeve 2 is fixed outside the upright post 1. When the sleeve 2 needs to be rotated, the positioning screw 5 can be screwed out, and after the sleeve 2 rotates by a preset angle, the positioning screw 5 is rotated inwards until the end part of the positioning screw 5 extends into the positioning hole 6 aligned after rotation.
Wherein, the multiunit locating hole 6 is arranged along the direction of height of stand 1 equidistance in proper order. After the height of the sleeve 2 is adjusted, the positioning screw rods 5 on the side surface of the sleeve 2 can be aligned with the positioning holes 6 at different heights, so that the sleeve 2 is fixed at different heights of the upright post 1, and the heights of the hanging rod 3 and the hanging ring 4 are adjusted.
The lower end face of the suspender 3 is also fixedly provided with a sliding guide rail 7 along the length direction of the suspender 3, and the two hoisting rings 4 are both arranged on the sliding guide rail 7 in a sliding way through a sliding seat 8. The position of the hanging ring 4 can be adjusted according to the use requirement. If the hose with the smaller hoisting length is hoisted, the distance between the two hoisting rings 4 can be reduced, and the distance between the two hoisting rings 4 can be increased when the hose with the larger hoisting length is hoisted, so that the stability of the hose in the hoisting process is improved.
Preferably, a positioning rod is threaded on each sliding seat 8 of the hanging ring 4, and the end of the positioning rod can abut against the sliding guide 7 or the hanging rod 3 by rotating the positioning rod, so that the position of the hanging ring 4 is fixed.
In addition, the end part of the suspender 3 is also fixedly provided with a limit end plate 9, the suspension ring 4 can be limited by the limit end plate 9, and the suspension ring 4 is prevented from falling off from the sliding guide rail 7.
An operator lifts the hose through a chain block hung on the hanging ring 4, the hose can be lifted or lowered through the chain block, meanwhile, the sleeve 2 can be rotated to enable the hanging rod 3 to rotate, the orientation of the hose can be adjusted, the union hose is butted with a union joint in a pile leg, and the installation is more convenient and labor-saving.
In addition to the above embodiments, the present invention may have other embodiments; all technical solutions formed by adopting equivalent substitutions or equivalent transformations fall within the protection scope of the claims of the present invention.

Claims (7)

1. The utility model provides a wind-powered electricity generation mounting platform union is towards a simple and easy gallows for hose, its characterized in that: comprises the steps of (a) preparing a mixture of a plurality of raw materials,
a column (1);
the sleeve (2) is rotatably sleeved on the upper part of the upright post (1), a suspension rod (3) perpendicular to the sleeve (2) is fixedly arranged on the sleeve (2), and a hanging ring (4) is arranged on the suspension rod (3); and the number of the first and second groups,
the locating piece is used for fixing the sleeve (2) on the outer side of the stand column (1), the locating piece comprises a positioning screw rod (5) which is arranged on the side wall of the sleeve (2) in a penetrating mode through threads, and the end portion of the positioning screw rod (5) can extend into the sleeve (2) and is abutted to the side wall of the stand column (1).
2. The simple hanger for the union pile-flushing hose of the wind power installation platform according to claim 1, characterized in that: the side wall of the upright post (1) is provided with a plurality of positioning holes (6) for the positioning screws (5) to extend into, the positioning holes (6) are located in the same horizontal plane, and the distance between any two adjacent positioning holes (6) is equal.
3. The simple hanger for the union pile-flushing hose of the wind power installation platform as claimed in claim 2, wherein: a plurality of groups of positioning holes (6) are arranged on the side wall of the upright post (1), each group of positioning holes (6) comprises a plurality of positioning holes (6) uniformly distributed in the same horizontal plane,
the plurality of groups of positioning holes (6) are sequentially arranged at equal intervals along the length direction of the upright post (1).
4. The simple hanger for the union pile-flushing hose of the wind power installation platform according to claim 1, characterized in that: the hanging rings (4) are at least provided with two hanging rings and are sequentially arranged along the length direction of the hanging rods (3).
5. The simple hanger for the union pile-flushing hose of the wind power installation platform as claimed in claim 4, wherein: the hanger rod (3) is fixedly provided with a sliding guide rail (7) along the length direction of the hanger rod, and the hanging ring (4) is slidably mounted on the sliding guide rail (7) through a sliding seat (8).
6. The simple hanger for the union pile-flushing hose of the wind power installation platform as claimed in claim 5, wherein: and one end of the suspender (3) far away from the sleeve (2) is fixedly provided with a limiting end plate (9).
7. The simple hanger for the union pile-flushing hose of the wind power installation platform according to claim 1, characterized in that: and a reinforcing rib (10) is fixedly arranged between the sleeve (2) and the hanging rod (3).
CN202121317592.1U 2021-06-15 2021-06-15 Simple hanging bracket for wind power installation platform union pile-flushing hose Active CN215666734U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121317592.1U CN215666734U (en) 2021-06-15 2021-06-15 Simple hanging bracket for wind power installation platform union pile-flushing hose

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121317592.1U CN215666734U (en) 2021-06-15 2021-06-15 Simple hanging bracket for wind power installation platform union pile-flushing hose

Publications (1)

Publication Number Publication Date
CN215666734U true CN215666734U (en) 2022-01-28

Family

ID=79975129

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121317592.1U Active CN215666734U (en) 2021-06-15 2021-06-15 Simple hanging bracket for wind power installation platform union pile-flushing hose

Country Status (1)

Country Link
CN (1) CN215666734U (en)

Similar Documents

Publication Publication Date Title
CN110902579A (en) Hydraulic lifting device for construction
CN113291974B (en) Safe and convenient vertical and sliding hoisting device for supporting pile cage
CN215666734U (en) Simple hanging bracket for wind power installation platform union pile-flushing hose
CN111591904A (en) Support arrangement that power equipment lifted by crane
CN213059942U (en) Light simple hoisting equipment for sound barrier
CN212609167U (en) Anticorrosive support that hangs of adjustable width
CN114635423A (en) Pile sinking device for precast pile construction
CN211171941U (en) Manual hole digging operation frame based on full-sleeve full-slewing drilling machine
CN211444792U (en) Can dismantle civil air defense engineering protective apparatus hoist device
CN210049270U (en) Mounting structure of tower crane and peripheral floor and foundation
CN209797325U (en) Tongs suspension arm driven by swing hydraulic cylinder
CN209940316U (en) Simply rotate curtain hoist device
CN106608596A (en) Outdoor equipment lifting device
CN206958386U (en) A kind of fire water-supply Pipe installing standpipe mounting bracket
CN208577368U (en) Quickly dismantled on-pole switch installs boom hoisting
CN210710448U (en) Hoisting device for X-ray detection equipment of strain clamp of power transmission line
CN217759930U (en) Wind-proof vibration-proof hanging basket
CN218025101U (en) Building site building materials lifting machine
CN220098355U (en) Double-shaft hinged arm support type offshore crane
CN220223275U (en) Pile foundation drill core sampling verticality location promotes support
CN218619996U (en) Plain type glass lifts by crane instrument
CN219469435U (en) Hoisting device for fire-fighting equipment installation
CN217627218U (en) Power head installation mechanism
CN220725724U (en) Outer wall hanging flower basket reinforcing apparatus
CN214780361U (en) Building construction is with novel heavy object hoist device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant