- CN215630637U CN215630637U CN202121448623.7U CN202121448623U CN215630637U CN 215630637 U CN215630637 U CN 215630637U CN 202121448623 U CN202121448623 U CN 202121448623U CN 215630637 U CN215630637 U CN 215630637U
- Authority
- CN
- China
- Prior art keywords
- connecting plate
- channel steel
- lock catch
- bolt
- strip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 54
- 239000010959 steel Substances 0.000 title claims abstract description 54
- 238000009434 installation Methods 0.000 claims abstract description 8
- 238000010276 construction Methods 0.000 abstract description 6
- 238000004519 manufacturing process Methods 0.000 abstract description 5
- 238000003801 milling Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000012946 outsourcing Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 238000004513 sizing Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model discloses a channel steel lock catch for a building support, which comprises a mounting seat, wherein a first strip-shaped groove is formed in the bottom of the mounting seat, a connecting plate is arranged in the first strip-shaped groove, a first threaded hole is formed in the top of the connecting plate, a first bolt column is in threaded connection with the inside of the first threaded hole and penetrates through the top of the mounting seat, a second strip-shaped groove is formed in the mounting seat at the joint between the first bolt column and the mounting seat, and a knob is connected to the top of the first bolt column; the connecting plate bottom is equipped with the installation cavity, and installation cavity internally mounted has the right-angle plate, is close to and is equipped with the second bolt post on the right-angle plate lateral wall in the connecting plate outside, and the second bolt post runs through the connecting plate setting, is equipped with the third bar groove on the connecting plate of junction between second bolt post and the connecting plate. The channel steel lock catch for the building support is simple in structure and low in manufacturing cost, the width and the depth of the channel steel lock catch can be freely adjusted according to the size of channel steel, the universality of the channel steel lock catch is improved, and the construction operation efficiency is improved.
Description
Technical Field
The utility model relates to the technical field of building supports, in particular to a channel steel lock catch for a building support.
Background
The finished bracket is a bracket system which is directly produced into a sizing channel steel and various connecting pieces by a factory and then delivered to constructors for field assembly, and has the main advantages that: the channel steel and parts realize modularized and standardized production, so that the production efficiency can be improved and the labor cost can be reduced; secondly, the finished product support system is convenient to install and maintain (parts are easy to purchase), and the finished product support system has the advantages of shortening the construction period, reducing the maintenance time and the like; and thirdly, various types meeting production requirements can be flexibly assembled by assembling different accessories, so that various construction environments are met.
We often use the finished product support in the building trade, we often use the channel-section steel hasp at use finished product support in-process, use the outsourcing channel-section steel hasp at perpendicular crossing channel-section steel support at present, because its structure is fixed, unable width regulation or degree of depth, in the field operation in-process, because the channel-section steel model is different, there is the difference in width and thickness, therefore fixed outsourcing channel-section steel hasp can't be suitable for, need purchase again, delays the construction progress, improves the operation cost, reduces the commonality of channel-section steel hasp. Therefore, a channel steel lock catch for a building support is provided.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a channel steel lock catch for a building support, which aims to solve the problems in the background technology.
In order to achieve the purpose, the utility model provides the following technical scheme:
the channel steel lock catch for the building support comprises a mounting seat, wherein a first strip-shaped groove is formed in the bottom of the mounting seat, a connecting plate is arranged in the first strip-shaped groove, a first threaded hole is formed in the top of the connecting plate, a first bolt column is in threaded connection with the inside of the first threaded hole and penetrates through the top of the mounting seat, a second strip-shaped groove is formed in the mounting seat at the connecting part between the first bolt column and the mounting seat, and a knob is connected to the top of the first bolt column;
the connecting plate bottom is equipped with the installation cavity, installation cavity internally mounted has the right angle board, is close to be equipped with the second bolt post on the right angle board lateral wall in the connecting plate outside, the second bolt post runs through the connecting plate setting, be equipped with the third bar groove on the connecting plate of junction between second bolt post and the connecting plate.
Preferably, a first fastening nut is mounted on a first bolt column positioned at the top of the second strip-shaped groove, and a second fastening nut is connected to a second bolt column positioned at the outer side of the third strip-shaped groove.
Preferably, a first mounting hole is formed in the support plate at the bottom of the right-angle plate, and a second mounting hole is connected to the middle position of the mounting seat.
Preferably, the connecting plate and the mounting seat are horizontally movably connected, and the right-angle plate and the connecting plate are vertically movably connected.
Compared with the prior art, the utility model has the beneficial effects that: according to the channel steel lock catch for the building support, through the arrangement of the first strip-shaped groove, the connecting plates, the threaded hole, the first bolt column, the second strip-shaped groove, the knob and the first fastening nut, the distance between the two connecting plates can be transversely adjusted through loosening the first bolt column and the first fastening nut, and the effect of transversely adjusting the width of the channel steel lock catch is achieved; through setting up right-angle plate, second bolt post, third bar groove, second fastening nut, can be through not hard up second fastening nut, and then the height of vertical regulation right-angle plate reaches the effect of vertical regulation channel-section steel hasp degree of depth for this channel-section steel hasp for building support, the structure connects the list, makes with low costs, can effectively according to the width and the thickness of channel-section steel, freely adjusts the width and the degree of depth of channel-section steel hasp, increases the commonality of channel-section steel hasp, improves the construction work efficiency.
Drawings
Fig. 1 is a front cross-sectional view of a channel steel locking structure for a building bracket according to the present invention;
fig. 2 is a bottom view of a channel steel lock catch mounting seat structure for a building support according to the present invention;
fig. 3 is a top view of a channel steel lock mounting seat structure for a building support according to the present invention;
fig. 4 is a side view of a steel channel locking rectangular plate structure for a building support provided by the utility model.
In the figure: the mounting base comprises a mounting base 1, a first strip-shaped groove 2, a connecting plate 3, a threaded hole 4, a first bolt column 5, a second strip-shaped groove 6, a knob 7, a first fastening nut 8, a mounting cavity 9, a right-angle plate 10, a second bolt column 11, a third strip-shaped groove 12, a second fastening nut 13, a first mounting hole 14 and a second mounting hole 15.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a channel-section steel hasp for building support, including mount pad 1, 1 bottom of mount pad mills through the milling machine and grinds and be equipped with first bar groove 2, first bar groove 2 internally mounted has connecting plate 3, 3 tops of connecting plate are equipped with first screw hole 4, 4 internal thread in first screw hole have first bolt post 5, first bolt post 5 runs through 1 top of mount pad, mill through the milling machine on the mount pad 1 of junction between first bolt post 5 and the mount pad 1 and grind and be equipped with second bar groove 6, second bar groove 6 and first bar groove 2 intercommunication, be convenient for pass first bolt post 5, 5 tops of first bolt post are connected with knob 7.
3 bottoms of connecting plate are equipped with installation cavity 9, and installation cavity 9 internally mounted has right angle board 10, is close to and is equipped with second bolt post 11 on the right angle board 10 lateral wall in the 3 outsides of connecting plate, and second bolt post 11 runs through the setting of connecting plate 3, is equipped with third bar groove 12 through milling machine milling on the connecting plate 3 of junction between second bolt post 11 and the connecting plate 3.
Specifically, this channel-section steel hasp for building support is in the use:
firstly, loosening first fastening nuts 8 and first bolt columns 5 at two ends of a channel steel lock catch, and horizontally adjusting the distance between two connecting plates 3 of the channel steel lock catch according to the width of channel steel, so as to ensure that the width of the channel steel lock catch is just clamped at the top of the channel steel;
then, fixing the channel steel lock catch on the channel steel through a second mounting hole 15, a bolt and a gasket, loosening a second fastening nut 13, adjusting the length of the right-angle plate 10, and adjusting the depth of the channel steel lock catch according to the depth of the channel steel;
finally, the channel steel buckle is fixed on the transverse channel steel through the first mounting hole 14, the bolt and the gasket on the straight angle plate 10, and then the channel steel buckle is locked on the channel steel, so that the channel steel buckle for the building support is structurally simple, the manufacturing cost is low, the width and the depth of the channel steel buckle can be effectively adjusted according to the width and the thickness of the channel steel, the universality of the channel steel buckle is improved, and the construction operation efficiency is improved.
Further, be located and install first fastening nut 8 on the first bolt post 5 at 6 tops of second bar groove, first fastening nut 8 can effectively fasten first bolt post 5, prevents that first bolt post 5 is not hard up, and then prevents that connecting plate 3 is not hard up, is connected with second fastening nut 13 above the second bolt post 11 that is located the third bar groove 12 outside, and second fastening nut 13 can effectively fasten second bolt post 11, avoids right-angle plate 10 not hard up.
Furthermore, a first mounting hole 14 is formed in the support plate at the bottom of the rectangular plate 10, a second mounting hole 15 is connected to the center of the mounting seat 1, and the first mounting hole 14 and the second mounting hole 15 are convenient for fastening channel steel through bolts.
Furthermore, the connecting plate 3 is horizontally movably connected with the mounting base 1, and the right-angle plate 10 is vertically movably connected with the connecting plate 3.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.
Claims (4)
1. The utility model provides a channel-section steel hasp for building support, includes mount pad (1), its characterized in that: the mounting base is characterized in that a first strip-shaped groove (2) is formed in the bottom of the mounting base (1), a connecting plate (3) is installed inside the first strip-shaped groove (2), a first threaded hole (4) is formed in the top of the connecting plate (3), a first bolt column (5) is connected with the first threaded hole (4) through threads, the first bolt column (5) penetrates through the top of the mounting base (1), a second strip-shaped groove (6) is formed in the mounting base (1) at the joint between the first bolt column (5) and the mounting base (1), and a knob (7) is connected to the top of the first bolt column (5);
connecting plate (3) bottom is equipped with installation cavity (9), installation cavity (9) internally mounted has right angle board (10), is close to be equipped with second bolt post (11) on right angle board (10) lateral wall in connecting plate (3) outside, second bolt post (11) run through connecting plate (3) and set up, be equipped with third bar groove (12) on connecting plate (3) of junction between second bolt post (11) and connecting plate (3).
2. The channel steel lock catch for the building bracket as claimed in claim 1, wherein: and a first fastening nut (8) is arranged on a first bolt column (5) positioned at the top of the second strip-shaped groove (6), and a second fastening nut (13) is connected onto a second bolt column (11) positioned at the outer side of the third strip-shaped groove (12).
3. The channel steel lock catch for the building bracket as claimed in claim 1, wherein: a support plate at the bottom of the right-angle plate (10) is provided with a first mounting hole (14), and a second mounting hole (15) is connected to the middle position of the mounting seat (1).
4. The channel steel lock catch for the building bracket as claimed in claim 1, wherein: the connecting plate (3) is horizontally and movably connected with the mounting seat (1), and the right-angle plate (10) is vertically and movably connected with the connecting plate (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121448623.7U CN215630637U (en) | 2021-06-28 | 2021-06-28 | Channel steel lock catch for building support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121448623.7U CN215630637U (en) | 2021-06-28 | 2021-06-28 | Channel steel lock catch for building support |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215630637U true CN215630637U (en) | 2022-01-25 |
Family
ID=79946242
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121448623.7U Expired - Fee Related CN215630637U (en) | 2021-06-28 | 2021-06-28 | Channel steel lock catch for building support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215630637U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114876061A (en) * | 2022-05-10 | 2022-08-09 | 浙江海迈材料科技股份有限公司 | Embedded channel steel lock catch and displacement dislocation prevention method |
-
2021
- 2021-06-28 CN CN202121448623.7U patent/CN215630637U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114876061A (en) * | 2022-05-10 | 2022-08-09 | 浙江海迈材料科技股份有限公司 | Embedded channel steel lock catch and displacement dislocation prevention method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100984339B1 (en) | Variable geometry curtain wall fastner | |
CN215630637U (en) | Channel steel lock catch for building support | |
CN201062389Y (en) | Latch hook type curtain wall column mounting regulating structure | |
CN102720291A (en) | Welding-free assembled type framework and bolt latch | |
CN201202191Y (en) | Unit type curtain wall connection structure | |
CN202767299U (en) | Welding-free assembled framework | |
CN203979789U (en) | A kind of crane span structure supporting structure and there is its mixing plant | |
CN108678242A (en) | A kind of two-sided curtain wall of back bolt type | |
CN202644795U (en) | Bolt clamping lock | |
KR101058840B1 (en) | A profile with joint | |
CN208455898U (en) | A kind of two-sided curtain wall of back bolt type | |
CN103352525A (en) | Curtain wall dry hanging multidirection adjusting device | |
CN203514581U (en) | Novel connection structure of transverse beam and vertical column of glass curtain wall | |
CN103469945A (en) | Connection structure for transverse beam and vertical column of novel glass curtain wall | |
CN210629406U (en) | Angle-adjustable photovoltaic support | |
CN216355307U (en) | Low-voltage cabinet frame | |
CN218580965U (en) | Special installation bearing structure of alternating expression arc glass | |
CN220433995U (en) | Stone curtain wall ear-hanging mounting structure | |
CN200999390Y (en) | Fully-assembled base station house | |
CN220248615U (en) | Nuclear power plant large-scale equipment fastening assembly and detachable anti-deflection nut thereof | |
CN214290148U (en) | Auxiliary positioning device of bending machine | |
CN220790245U (en) | Curtain wall connecting device | |
CN218510310U (en) | Pipeline support | |
CN209260984U (en) | A kind of type unitized curtain wall support device convenient for adjusting | |
CN220741123U (en) | Heavy square pipe comprehensive pipe rack |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220125 |