CN215558333U - Reusable hanging bar device - Google Patents

Reusable hanging bar device Download PDF

Info

Publication number
CN215558333U
CN215558333U CN202121964881.0U CN202121964881U CN215558333U CN 215558333 U CN215558333 U CN 215558333U CN 202121964881 U CN202121964881 U CN 202121964881U CN 215558333 U CN215558333 U CN 215558333U
Authority
CN
China
Prior art keywords
hanging
steel bar
section
positioning
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121964881.0U
Other languages
Chinese (zh)
Inventor
林其涛
安道尧
刘小青
段文辉
亢永明
剌文飞
崔杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd filed Critical First Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Priority to CN202121964881.0U priority Critical patent/CN215558333U/en
Application granted granted Critical
Publication of CN215558333U publication Critical patent/CN215558333U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The utility model belongs to the technical field of auxiliary lifting appliances for pile foundation construction, and particularly relates to a reusable steel bar lifting device, aiming at solving the problems of large using amount of steel bar lifting steel bars, high cost, complicated construction and the like during construction of an engineering pile; the steel wire rope positioning device comprises a steel wire rope, a positioning ladder and a plurality of sections of hanging bars which are connected end to form a straight chain, wherein the hanging bars are movably buckled through steel bar rings, the first section of hanging bars are welded at the tail part of the positioning ladder, and the tail part of the tail section of hanging bars is connected with a clamping hook; a plurality of positioning rings are welded on the hanging ribs and the positioning ladder along the length direction, and the steel wire rope sequentially penetrates through the positioning rings from top to bottom to be connected with the unhooking brake of the clamping hook. According to the reusable steel bar hanging device, the length of the steel bar hanging chain can be freely combined according to the depth of an empty pile in the construction process, the operation is simple, the device is detachable and foldable, the welding time of the steel bar hanging chain is shortened, the device can be repeatedly used for many times, after a steel bar cage is lowered, a steel wire rope is lifted up to automatically unhook, the steel bar hanging amount is saved, and the construction cost is reduced.

Description

Reusable hanging bar device
Technical Field
The utility model belongs to the technical field of auxiliary lifting appliances for pile foundation construction, and particularly relates to a reusable lifting bar device.
Background
At present, the muscle that hangs of wide application in building engineering pile construction all is ordinary reinforcing bar lug weld, and the reinforcing bar welding is on the steel reinforcement cage, hangs into the stake downthehole with the steel reinforcement cage through the reinforcing bar, and the reinforcing bar is disposable, can't take out the multiplexing, when meetting the darker condition of empty stake, hangs the muscle reinforcing bar use amount bigger, and is with high costs, the loaded down with trivial details of construction.
SUMMERY OF THE UTILITY MODEL
The utility model provides a rib hanging device capable of being repeatedly used for solving the problems of large consumption of rib hanging steel bars, high cost, complicated construction and the like during construction of an engineering pile.
The utility model is realized by adopting the following technical scheme: a reusable hanging bar device comprises a steel wire rope, a positioning ladder and a plurality of sections of hanging bars which are connected end to form a straight chain, wherein the hanging bars are movably fastened through reinforcing bar rings, the first section of hanging bars are welded at the tail part of the positioning ladder, and the tail part of the tail section of hanging bars is connected with a clamping hook; a plurality of positioning rings are welded on the hanging ribs and the positioning ladder along the length direction, and the steel wire rope sequentially penetrates through the positioning rings from top to bottom to be connected with the unhooking brake of the clamping hook.
Further, the pothook hangs the last coupler body and the lower coupler body of muscle afterbody including the welding at the tail section, go up the coupler body and open the opening that link up from top to bottom on the coupler body down, the holding surface of lower coupler body slopes downwards to become domatic, the welding has the guide cylinder on the tail section hangs the muscle, a unhook locking lever has been inserted to the slidable in the guide cylinder, the unhook locking lever is as the unhook floodgate, be provided with the position cap above the guide cylinder on the unhook locking lever, wire rope is connected with the head of unhook locking lever, the afterbody of unhook locking lever inserts in the opening of coupler body and lower coupler body or takes out.
Furthermore, the lower hook body is formed by bending a steel bar, the lower hook body comprises a V-shaped section, side rods on two sides of the V-shaped section are folded upwards, and the folded sections are welded on the tail section hanging ribs; the upper hook body is formed by bending a steel bar and comprises a V-shaped section, and the tail part of the side rod of the V-shaped section is welded on the tail section hanging rib.
Furthermore, the positioning ladder is formed by bending a reinforcing steel bar, and comprises a U-shaped section, the opening end of the U-shaped section is closed, two side rods of the U-shaped section are welded with the first section of hanging ribs, a plurality of transverse rods are welded between the two side rods of the U-shaped section, the distance between the transverse rods is equal, and the distance is 10 cm.
Compared with the prior art, the utility model has the advantages that:
according to the reusable steel bar hanging device, the length of the steel bar hanging chain can be freely combined according to the depth of an empty pile in the construction process, the operation is simple, the device is detachable and foldable, the welding time of the steel bar hanging chain is shortened, the device can be repeatedly used for many times, after a steel bar cage is lowered, a steel wire rope is lifted up to automatically unhook, the steel bar hanging amount is saved, and the construction cost is reduced.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a partially enlarged schematic view of a portion a of fig. 1.
Fig. 3 is a schematic diagram of reinforcement cage unhooking.
Fig. 4 is a schematic structural view of the lower hook body.
In the figure: 1-positioning a ladder; 2-a steel wire rope; 3-hanging the first section of the reinforcement; 4-a positioning ring; 5-reinforcing steel bar ring; 6-hanging ribs at the tail section; 7-a guide cylinder; 8-unhooking locking bar; 9-hook; 9.1-upper hook body; 9.2-lower hook body; and (10) a reinforcement cage.
Detailed Description
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
As shown in fig. 1; a reusable hanging bar device comprises a steel wire rope 2, a positioning ladder 1 and a plurality of sections of hanging bars which are connected end to form a straight chain, wherein the hanging bars are movably buckled through a bar ring 5, the upper end of the positioning ladder 1 is connected with a lifting rope of a crane, the first section of hanging bar 3 is welded at the tail part of the positioning ladder 1, and the tail part of the tail section of hanging bar 6 is connected with a clamping hook 9; a plurality of positioning rings 4 are welded on the hanging ribs and the positioning ladder 1 along the length direction, and the steel wire rope 2 sequentially penetrates through the positioning rings 4 from top to bottom to be connected with the unhooking brake of the hook 9.
As shown in fig. 2 and 3; the pothook 9 hangs last coupler body 9.1 and lower coupler body 9.2 of muscle 6 afterbody including the welding at the tail section, go up the coupler body 9.1 and open on the coupler body 9.2 down and have the opening that link up from top to bottom, the supporting surface of lower coupler body 9.2 inclines downwards and becomes domatic, the welding has guide cylinder 7 on the tail section hangs the muscle 6, a unhook locking lever 8 has been inserted to the slidable in the guide cylinder 7, unhook locking lever 8 is as the unhook floodgate, be provided with the position cap above guide cylinder 7 on the unhook locking lever 8, wire rope 2 is connected with the head of unhook locking lever 8, the afterbody of unhook locking lever 8 inserts in the opening of coupler body 9.1 and lower coupler body 9.2 or takes out. Support when lower coupler body 9.2 is as hoist and mount steel reinforcement cage, go up the supplementary locking unhook locking lever 8 of coupler body 9.1, when the link of steel reinforcement cage hangs down coupler body 9.2, unhook locking lever 8 inserts down coupler body 9.2, prevents hoist and mount in-process steel reinforcement cage slippage, after the steel reinforcement cage is put into the position down, lift wire rope 2, extract unhook locking lever 8 from last coupler body 9.1 and lower coupler body 9.2, the steel reinforcement cage landing from pothook 9.
As shown in fig. 4; the lower hook body 9.2 is formed by bending a steel bar, the lower hook body 9.2 comprises a V-shaped section, side rods on two sides of the V-shaped section are folded upwards, and the folded sections are welded on the tail section hanging rib 6; the upper hook body 9.1 is formed by bending a steel bar, the upper hook body 9.1 comprises a V-shaped section, and the tail part of the side rod of the V-shaped section is welded on the tail section hanging rib 6.
Location ladder 1 is bent the shaping by a reinforcing bar, and location ladder 1 includes a U type section, and the open end binding off of U type section, the both sides pole and the first section of U type section hang 3 welded connection of muscle, and the welding has several horizontal poles between the both sides pole of U type section, and the interval between the horizontal pole equals, and the interval is 10cm, and the degree of depth is gone into in hanging of convenient control steel reinforcement cage, according to the quantity of going into the stake hole under the horizontal pole on observing location ladder 1, the degree of depth is gone into in hanging of control steel reinforcement cage.
Hoisting process
1. The crane is used for hoisting the steel bar hanging device, and the steel bar cage is connected with the tail section hanging steel bar by utilizing the clamping hook and the unhooking lock rod.
2. After the steel bar hanging device and the steel bar cage are connected, the steel bar hanging device is placed to enable the steel bar cage to reach the designed depth, concrete is poured to the designed elevation, and then pouring operation is started.
3. And after the pouring is finished and the steel reinforcement cage is stable, the steel reinforcement hanging device is pulled by a crane, the clamping hook is loosened, the steel reinforcement hanging device is separated from the steel reinforcement cage, the steel reinforcement hanging device is pulled out from the hole, and the steel reinforcement hanging device is washed by water and can be continuously reused.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the utility model. Thus, the present invention is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (4)

1. A reusable hanging bar device is characterized in that: the steel wire rope positioning ladder comprises a steel wire rope (2), a positioning ladder (1) and a plurality of sections of hanging ribs which are connected end to form a straight chain, wherein the hanging ribs are movably buckled through a steel bar ring (5), the first section of hanging ribs (3) are welded at the tail part of the positioning ladder (1), and the tail part of the tail section of hanging ribs (6) is connected with a clamping hook (9); a plurality of positioning rings (4) are welded on the lifting rib and the positioning ladder (1) along the length direction, and the steel wire rope (2) sequentially penetrates through the positioning rings (4) from top to bottom to be connected with the unhooking brake of the hook (9).
2. A reusable rebar device as claimed in claim 1, wherein: pothook (9) are including welding last coupler body (9.1) and lower coupler body (9.2) that tail section hung muscle (6) afterbody, go up coupler body (9.1) and open on coupler body (9.2) down and have the opening of lining up from top to bottom, the holding surface downward slope of lower coupler body (9.2) becomes domatic, the welding has guide cylinder (7) on tail section hung muscle (6), a unhook locking lever (8) has been inserted in guide cylinder (7) slidable, unhook locking lever (8) are as the unhook floodgate, be provided with the position cap above guide cylinder (7) on unhook locking lever (8), wire rope (2) are connected with the head of unhook locking lever (8), the afterbody of unhook locking lever (8) is inserted in the opening of coupler body (9.1) and lower coupler body (9.2) or is taken out.
3. A reusable rebar device as claimed in claim 2, wherein: the lower hook body (9.2) is formed by bending a steel bar, the lower hook body (9.2) comprises a V-shaped section, side rods on two sides of the V-shaped section are folded upwards, and the folded sections are welded on the tail section lifting rib (6); the upper hook body (9.1) is formed by bending a steel bar, the upper hook body (9.1) comprises a V-shaped section, and the tail part of a side rod of the V-shaped section is welded on the tail section hanging rib (6).
4. A reusable rebar device as claimed in claim 3, wherein: the positioning ladder (1) is formed by bending a reinforcing steel bar, the positioning ladder (1) comprises a U-shaped section, the opening end of the U-shaped section is closed, two side rods of the U-shaped section are welded with the first section of hanging ribs (3), a plurality of transverse rods are welded between the two side rods of the U-shaped section, the distance between the transverse rods is equal, and the distance is 10 cm.
CN202121964881.0U 2021-08-20 2021-08-20 Reusable hanging bar device Active CN215558333U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121964881.0U CN215558333U (en) 2021-08-20 2021-08-20 Reusable hanging bar device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121964881.0U CN215558333U (en) 2021-08-20 2021-08-20 Reusable hanging bar device

Publications (1)

Publication Number Publication Date
CN215558333U true CN215558333U (en) 2022-01-18

Family

ID=79839807

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121964881.0U Active CN215558333U (en) 2021-08-20 2021-08-20 Reusable hanging bar device

Country Status (1)

Country Link
CN (1) CN215558333U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116281566A (en) * 2023-05-18 2023-06-23 中铁城建集团第一工程有限公司 Automatic hoisting equipment for bored pile reinforcement cage

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116281566A (en) * 2023-05-18 2023-06-23 中铁城建集团第一工程有限公司 Automatic hoisting equipment for bored pile reinforcement cage
CN116281566B (en) * 2023-05-18 2023-08-11 中铁城建集团第一工程有限公司 Automatic hoisting equipment for bored pile reinforcement cage

Similar Documents

Publication Publication Date Title
CN215558333U (en) Reusable hanging bar device
CN210366620U (en) A hang muscle system for steel reinforcement cage
CN210341961U (en) Pile stabilizing platform for offshore wind power single-pile foundation pile sinking construction
CN108222006B (en) Construction method of square underground continuous wall
CN202530444U (en) Bayonet pin type pile foundation reinforcing cage positioning lock
CN210737522U (en) Recoverable deep hole pile steel reinforcement cage anti-floating and hoisting device
CN210505223U (en) Bored concrete pile steel reinforcement cage hangs puts device
CN213653457U (en) Steel reinforcement cage lifts by crane and mounting structure
CN214653024U (en) Staple bolt formula tubular pile hoist device
CN208577351U (en) A kind of pile cover boom hoisting
CN112193984B (en) Steel reinforcement cage lifting and fixing device and steel reinforcement cage lifting method
CN212356217U (en) Steel bar lifting appliance for building construction
CN210655785U (en) But reuse's pile foundation steel reinforcement cage hangs muscle device
CN114590697A (en) High-span concrete support dismantling method based on reserved lifting hook for closed space
CN217126648U (en) Overhead hoist suitable for bridge template and bridge
CN208265624U (en) A kind of heavy type pile cover boom hoisting
CN108996383B (en) Hoisting device for steel reinforcement cage hanging bars of deep-buried underground diaphragm wall and construction method thereof
CN210395670U (en) Steel bar pull ring and pre-buried steel bar pull ring structure
CN109132842B (en) Pipe fitting hoisting structure
CN210655792U (en) Auxiliary device is hung with reinforcing bar is erect
CN214459651U (en) Steel platform construction hanging flower basket on water
CN110510503A (en) A kind of cavity column hanging method
CN217078715U (en) Tip beating frame for steel reinforcement cage
CN210619998U (en) But recycle's pile foundation steel reinforcement cage hangs muscle device
CN210064931U (en) Prefabricated T roof beam template hoist device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant