CN215329886U CN202120701525.3U CN202120701525U CN215329886U CN 215329886 U CN215329886 U CN 215329886U CN 202120701525 U CN202120701525 U CN 202120701525U CN 215329886 U CN215329886 U CN 215329886U
Authority
CN
China
Prior art keywords
foundation pile
supporting seat
connecting rod
rod
stopper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120701525.3U
Other languages
Chinese (zh)
Inventor
赵锐
刘瑶
谢强生
韩艳
李树权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 14 Co Ltd
Original Assignee
Sinohydro Bureau 14 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 14 Co Ltd filed Critical Sinohydro Bureau 14 Co Ltd
Priority to CN202120701525.3U priority Critical patent/CN215329886U/en
Application granted granted Critical
Publication of CN215329886U publication Critical patent/CN215329886U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a positioning foundation pile device for civil building construction, and belongs to the technical field of building construction. The bilateral symmetry of foundation pile bottom seted up the spout, sliding connection has the stopper in the spout, the supporting seat cover is established on the foundation pile, the stopper tip alternates the joint support seat, be equipped with positioner on the stopper, connect stopper and supporting seat, on the supporting seat symmetry be equipped with two vertical through-holes, the dead lever alternates on the supporting seat through the through-hole, the dead lever bottom is equipped with the drill bit, the top all overlaps and is equipped with fixed cover, fixed cover both sides are equipped with the rotation handle. According to the foundation pile, the supporting seat is placed on the ground, the worker rotates the rotating handle to drive the fixing rod to rotate, so that the drill bit rotates to enter soil, the supporting seat is fixed with the ground, the fixing block and the limiting block are respectively pulled out of the groove and the sliding groove, the foundation pile is convenient to install and control, the situation that the foundation pile needs to be installed by manpower in the installation process is avoided, and the construction efficiency is improved.

Description

Positioning foundation pile device for civil construction
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to a positioning foundation pile device for civil building construction.
Background
The foundation pile refers to a single pile in a pile group, is a foundation in civil construction, and is mainly classified into a friction pile, an end-bearing pile, a precast pile and the like, the foundation pile has the characteristics of good stability, less material consumption, high bearing capacity, good earthquake resistance and the like, the material of the foundation pile is generally used for being driven into the ground, so that the structure of the integral support cannot collapse, the supporting structure is stabilized, the application is wide in high-rise buildings, the foundation pile is more in types and is influenced by the complex installation and construction environment, if sufficient preparation cannot be made before installation, the risks of pile breaking, mud clamping and the like are easily caused.
Present location foundation pile generally adopts the hoist and mount to install in the installation, and the foundation pile is difficult to fix in hoist and mount process for the foundation pile bumps in the inconvenient soil that gets into easily in the installation, and the foundation pile collision then causes the stake itself to break easily and can not use, and the foundation pile is installed beside owing to rocking need expending unnecessary manpower in the installation simultaneously, makes and causes inconvenient delay time in the installation, thereby influences the installation effectiveness of location foundation pile.
Therefore, it is necessary to provide a foundation pile positioning device for civil construction, which is convenient to install and control foundation piles, avoids the need of manpower consumption in the installation process, and improves the construction efficiency.
SUMMERY OF THE UTILITY MODEL
In order to solve the problem that the installation efficiency of the positioning foundation pile is affected due to inconvenience and time delay in the installation process of the foundation pile in the background technology, the utility model provides the positioning foundation pile device for civil construction, the foundation pile is convenient to install and control, the installation process is prevented from being performed by consuming manpower, and the construction efficiency is improved.
In order to realize the purpose, the utility model is realized by the following technical scheme:
the utility model provides a positioning foundation pile device for civil construction, which comprises a foundation pile 1, a limiting block 3, a supporting seat 7, a fixed sleeve 11, a rotating handle 12, a fixed rod 13, a first connecting ring 14, a third connecting rod 15, a second connecting ring 16 and a spring 17.
The bilateral symmetry of 1 bottom of foundation pile seted up spout 2, sliding connection has stopper 3 in spout 2, 7 covers of supporting seat are established on foundation pile 1, stopper 3 tip interlude joint support seat 7, be equipped with positioner on the stopper 3, connect stopper 3 and supporting seat 7, the symmetry is equipped with two vertical through-holes 10 on the supporting seat 7, dead lever 13 wears to inlay on supporting seat 7 through-hole 10, dead lever 13 bottom is equipped with the drill bit, the top all overlaps and is equipped with fixed cover 11, fixed cover 11 both sides are equipped with rotation handle 12.
The top cover of foundation pile 1 be equipped with first connecting ring 14, the outer wall of first connecting ring 14 is connected with second go-between 16 through third connecting rod 15, the even second accommodation hole of having seted up of outer wall of first connecting ring 14, the even cross arrangement of second accommodation hole and third connecting rod 15 is provided with the spliced pole corresponding with the second accommodation hole on the 16 inner walls of second go-between, spring 17 cover is established on the spliced pole, one end is fixed on second accommodation hole inner wall.
Preferably, the positioning device comprises a first connecting rod 4, a second connecting rod 5 and a fixing block 6, the first connecting rod 4 is fixedly arranged at the top of the limiting block 3, the first connecting rod 4 penetrates through a first accommodating hole 9 in the top surface of the supporting seat 7, the second connecting rod 5 is fixedly connected with one side horizontally, a vertical through hole is formed in the second connecting rod 5 and is connected with the fixing block 6, and the fixing block 6 is embedded in a groove 8 in the top surface of the supporting seat 7 in a sliding mode.
Preferably, the outer wall of the rotating handle 12 is sleeved with a rubber sleeve.
The utility model has the beneficial effects that:
according to the foundation pile, the supporting seat is placed on the ground, the worker rotates the rotating handle to drive the fixing rod to rotate, so that the drill bit rotates to enter soil, the supporting seat is fixed with the ground, the fixing block and the limiting block are respectively pulled out of the groove and the sliding groove, the foundation pile is convenient to install and control, the situation that the foundation pile needs to be installed by manpower in the installation process is avoided, and the construction efficiency is improved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the supporting base and the connection structure thereof according to the present invention;
FIG. 3 is a schematic view of the stopper of the present invention and its connection structure;
FIG. 4 is an enlarged view of the structure of FIG. 1 at A according to the present invention;
fig. 5 is an enlarged view of the structure of fig. 1 at B.
In the figure, 1-foundation pile, 2-chute, 3-limiting block, 4-first connecting rod, 5-second connecting rod, 6-fixing block, 7-supporting seat, 8-groove, 9-first accommodating hole, 10-through hole, 11-fixing sleeve, 12-rotating handle, 13-fixing rod, 14-first connecting ring, 15-third connecting rod, 16-second connecting ring and 17-spring.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings to facilitate understanding of the skilled person.
As shown in fig. 1 to 5, the positioning foundation pile device for civil construction includes a foundation pile 1, a limiting block 3, a supporting seat 7, a fixing sleeve 11, a rotating handle 12, a fixing rod 13, a first connecting ring 14, a third connecting rod 15, a second connecting ring 16, and a spring 17.
The foundation pile is characterized in that sliding grooves 2 are symmetrically formed in two sides of the bottom end of the foundation pile 1, limiting blocks 3 are connected in the sliding grooves 2 in a sliding mode, a supporting seat 7 is sleeved on the foundation pile 1, the end portions of the limiting blocks 3 are connected with the supporting seat 7 in an inserting mode, a positioning device is arranged on the limiting blocks 3 and connected with the limiting blocks 3 and the supporting seat 7, the positioning device comprises a first connecting rod 4, a second connecting rod 5 and a fixing block 6, the first connecting rod 4 is fixedly arranged at the top of the limiting blocks 3, the first connecting rod 4 penetrates through a first accommodating hole 9 in the top surface of the supporting seat 7, the second connecting rod 5 is horizontally and fixedly connected with one side of the supporting seat, a vertical through hole is formed in the second connecting rod 5 and connected with the fixing block 6, the fixing block 6 is embedded in a groove 8 in the top surface of the supporting seat 7 in a sliding mode, through installation fixed block 6 for stopper 3 can not remove at will when spacing to foundation pile 1, makes foundation pile 1 more stable at the drop in-process.
Supporting seat 7 on the symmetry be equipped with two vertical through-holes 10, dead lever 13 wears to inlay on supporting seat 7 through-hole 10, dead lever 13 bottom is equipped with the drill bit, the top all is equipped with fixed cover 11, fixed cover 11 both sides are equipped with rotatory handle 12, rotatory handle 12 outer wall cover is equipped with the rubber sleeve.
1 top cover of foundation pile be equipped with first connecting ring 14, the outer wall of first connecting ring 14 is connected with second go-between 16 through third connecting rod 15, the even second accommodation hole of having seted up of outer wall of first connecting ring 14, the even cross arrangement of second accommodation hole and third connecting rod 15, be provided with the spliced pole corresponding with the second accommodation hole on the 16 inner walls of second go-between, spring 17 cover is established on the spliced pole, one end is fixed on the second accommodation hole inner wall, through installing first connecting ring 14, second go-between 16, spring 17 makes foundation pile 1 in the installation, reduce the range of rocking in the 1 installation of location foundation pile through spring 17, avoid foundation pile 1 to be difficult to control.
The working process of the utility model is as follows:
when in use, when the foundation pile 1 is installed, the supporting seat 7 is firstly placed on the ground, a worker drives the fixed rod 13 to rotate by rotating the rotating handle 12 through rotating the rotating handle 12, the fixed rod 13 drives the drill bit to rotate in the rotating process so as to enter soil, so that the supporting seat 7 is fixed with the ground, the two fixed blocks 6 are respectively pulled out from the two grooves 8, the first connecting rods 4 are respectively slid towards the two sides of the supporting seat 7, the two first connecting rods 4 respectively drive the two limit blocks 3 to slide, so that the two limit blocks 3 are respectively pulled out from the two chutes 2, so that the foundation pile 1 can be moved, the foundation pile 1 is conveniently limited in the installation process, the swinging in the installation process is avoided, the foundation pile 1 can vertically enter the ground, and meanwhile, the foundation pile 1 is prevented from being supported by consuming redundant manpower in the installation process, influence the efficiency of construction, make foundation pile 1 in the installation through installing first connecting ring 14, second connecting ring 16, spring 17, reduce the range of rocking in the installation of location foundation pile 1 through spring 17, avoid foundation pile 1 to be difficult to control.
According to the foundation pile 1, the supporting seat 7, the first connecting rod 14, the second connecting rod 16, the limiting block 3 and the fixing block 6 are installed conveniently by workers, the supporting seat 7 is placed on the ground, the workers drive the fixing rod 13 to rotate by rotating the rotating handle 12, so that the drill bit rotates to enter soil, the supporting seat 7 is fixed with the ground, the fixing block 6 and the limiting block 3 are pulled out of the groove 8 and the sliding groove 2 respectively, the foundation pile 1 is convenient to install and control, the situation that manpower is consumed in the installation process is avoided, and the construction efficiency is improved.
Finally, it is noted that the above-mentioned preferred embodiments illustrate rather than limit the utility model, and that, although the utility model has been described in detail with reference to the above-mentioned preferred embodiments, it will be understood by those skilled in the art that various changes in form and detail may be made therein without departing from the scope of the utility model as defined by the appended claims.

Claims (3)

1. The utility model provides a civil construction is with location foundation pile device which characterized in that: the positioning foundation pile device for civil construction comprises a foundation pile (1), a limiting block (3), a supporting seat (7), a fixing sleeve (11), a rotating handle (12), a fixing rod (13), a first connecting ring (14), a third connecting rod (15), a second connecting ring (16) and a spring (17);
the pile foundation structure is characterized in that sliding grooves (2) are symmetrically formed in two sides of the bottom end of a foundation pile (1), limiting blocks (3) are connected in the sliding grooves (2) in a sliding mode, a supporting seat (7) is sleeved on the foundation pile (1), the end portions of the limiting blocks (3) are connected with the supporting seat (7) in an inserting mode, a positioning device is arranged on the limiting blocks (3), the limiting blocks (3) and the supporting seat (7) are connected, two vertical through holes (10) are symmetrically formed in the supporting seat (7), a fixing rod (13) is embedded on the supporting seat (7) in an inserting mode through the through holes (10), a drill bit is arranged at the bottom of the fixing rod (13), a fixing sleeve (11) is sleeved at the top of the fixing rod, and rotating handles (12) are arranged on two sides of the fixing sleeve (11);
foundation pile (1) top cover be equipped with first go-between (14), the outer wall of first go-between (14) is connected with second go-between (16) through third connecting rod (15), the second accommodation hole has been seted up to the outer wall of first go-between (14) is even, second accommodation hole and third connecting rod (15) are even alternately arranged, be provided with the spliced pole corresponding with the second accommodation hole on second go-between (16) inner wall, spring (17) cover is established on the spliced pole, one end is fixed on second accommodation hole inner wall.
2. The foundation pile device for civil construction according to claim 1, characterized in that: positioner include head rod (4), second connecting rod (5) and fixed block (6), head rod (4) are fixed and are located the top of stopper (3), head rod (4) pass first accommodation hole (9) of supporting seat (7) top surface, horizontal fixedly connected with second connecting rod (5) of one side, set up vertical through-hole on second connecting rod (5), be connected with fixed block (6), fixed block (6) slide to inlay and establish in recess (8) of supporting seat (7) top surface.
3. The spud device according to claim 1 or 2, wherein: the outer wall of the rotating handle (12) is sleeved with a rubber sleeve.
CN202120701525.3U 2021-04-07 2021-04-07 Positioning foundation pile device for civil construction Active CN215329886U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120701525.3U CN215329886U (en) 2021-04-07 2021-04-07 Positioning foundation pile device for civil construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120701525.3U CN215329886U (en) 2021-04-07 2021-04-07 Positioning foundation pile device for civil construction

Publications (1)

Publication Number Publication Date
CN215329886U true CN215329886U (en) 2021-12-28

Family

ID=79592891

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120701525.3U Active CN215329886U (en) 2021-04-07 2021-04-07 Positioning foundation pile device for civil construction

Country Status (1)

Country Link
CN (1) CN215329886U (en)

Similar Documents

Publication Publication Date Title
KR102160514B1 (en) Photovoltaic power generator with softground installation
CN107246242A (en) Dual-purpose drill bit and its application method for holing with slurry wall protection filling pile construction
CN215329886U (en) Positioning foundation pile device for civil construction
CN111809631A (en) Ultra-deep foundation pit supporting device and using method
CN214695564U (en) A protect a structure more for construction of karst cave area bridge pile foundation
CN212742520U (en) High stability weak soil geology positioner for pile foundation installation
JP2003213686A (en) Construction method of earth retaining wall
JP2002030658A (en) Support for hammer drill
CN206891759U (en) A kind of damage caused by water on asphalt pavement detection sampler
CN217298889U (en) Stable installation pile foundation structure for building construction
CN218759746U (en) Novel bored pile equipment frame with leading truck
JPS63223218A (en) Driving work of pile
CN215252898U (en) But reuse's underground structure
CN219386381U (en) Composite pile foundation for soft soil building foundation
CN220058046U (en) Foundation pit water-stop supporting device for foundation construction
JP2009108578A (en) Pile erecting apparatus connecting implement used as precast pile hanging metal fitting
CN217030495U (en) A install combination base fast for fixing monitoring rod
CN218493548U (en) Drilling guide device for green construction of pile foundation
CN215060454U (en) Protection supporting structure of existing underground pipeline of shield machine hoisting operation field
CN217583406U (en) Pipe jacking device for municipal construction
CN219547770U (en) Prefabricated formula carrier stake of high strength
CN219863488U (en) Assembled shear wall structure
CN214738117U (en) Super high-rise building foundation pit supporting structure
CN219568871U (en) Pile foundation construction is with protecting a section of thick bamboo holder
CN111502005B (en) Suspension structure suspender, node and construction method thereof