CN215276600U - Spray desulfurizing tower - Google Patents

Spray desulfurizing tower Download PDF

Info

Publication number
CN215276600U
CN215276600U CN202023005787.0U CN202023005787U CN215276600U CN 215276600 U CN215276600 U CN 215276600U CN 202023005787 U CN202023005787 U CN 202023005787U CN 215276600 U CN215276600 U CN 215276600U
Authority
CN
China
Prior art keywords
spray
filter screen
room
water pump
tower body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023005787.0U
Other languages
Chinese (zh)
Inventor
苏永刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Yiguang Laboratory Equipment Manufacturing Co ltd
Original Assignee
Anhui Yiguang Laboratory Equipment Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Yiguang Laboratory Equipment Manufacturing Co ltd filed Critical Anhui Yiguang Laboratory Equipment Manufacturing Co ltd
Priority to CN202023005787.0U priority Critical patent/CN215276600U/en
Application granted granted Critical
Publication of CN215276600U publication Critical patent/CN215276600U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model relates to a flue gas desulfurization equipment technical field specifically is a spray desulfurizing tower, which comprises a tower body, the tower body includes the spray chamber of upper portion position, the reacting chamber of spray chamber lower part position and the heavy room of holding of bottom position, it is the toper structure to hold heavy room, reacting chamber internally mounted has the filter screen, the intake pipe is installed to the reacting chamber outer wall position, circulating water pump is installed to spray chamber right side position, circulating water pump intakes the end and passes through pipe and filter screen upper portion intercommunication, circulating water pump goes out the water outlet end and has the shower head through pipe connection, the shower head sets up in spray chamber upper portion position, under the prerequisite of guaranteeing desulfurization effect, can avoid the smoke and dust granule to adhere to shower nozzle outer wall and tower body inner wall.

Description

Spray desulfurizing tower
Technical Field
The utility model relates to a flue gas desulfurization equipment technical field specifically is a spray desulfurizing tower.
Background
The desulfurizing tower is a large-scale desulfurizing device for desulfurizing flue gas, and the desulfurizing tower carries out chemical absorption to the sulfur dioxide in the flue gas, and then reaches the purpose of purifying the flue gas, and spray column, packed tower, plate tower are comparatively the desulfurizing tower type commonly used at present, and wherein, spray column uses one of the most extensive desulfurizing tower type, is applied to large-scale power plant and medium and small-size low sulphur flue gas and administers.
The existing spraying separation tower has poor desulfurization effect, and meanwhile, smoke particles can be attached to the outer wall of the spray head and the inner wall of the tower body.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
In order to solve the above problems in the prior art, the utility model provides a spray desulfurization tower can avoid the smoke and dust granule to adhere to shower nozzle outer wall and tower body inner wall under the prerequisite of guaranteeing desulfurization effect.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a main technical scheme: the tower body comprises a tower body, the tower body includes that the spray chamber of upper portion position, the reaction chamber of spray chamber lower part position and the room of sinking of storing of bottom position, it is the toper structure to store the room of sinking, reaction chamber internally mounted has the filter screen, it installs the intake pipe to store the outdoor wall position of sinking, circulating water pump is installed to spray chamber right side position, circulating water pump intake end passes through pipe and filter screen upper portion intercommunication, circulating water pump goes out the water end and has the shower head through pipe connection, the shower head sets up in spray chamber upper portion position.
Preferably, a switch valve is installed at the bottom position of the accumulation chamber.
Preferably, one end of the air inlet pipe close to the reaction chamber is provided with a one-way air inlet valve.
Preferably, a switch door is installed at the right side of the spray chamber.
(III) advantageous effects
The utility model provides a spray desulfurizing tower. The method has the following beneficial effects:
(1) the intake pipe sets up the lower part at the filter screen, enter into and hold the inside flue gas of heavy room, can react with the reaction liquid, the smoke and dust granule can be filtered by the filter screen, filterable smoke and dust granule finally can hold and sink in holding heavy room bottom, the flue gas that passes the filter screen no longer contains the smoke and dust granule, the smoke and dust granule can not be attached to shower nozzle outer wall and tower body inner wall along with the flue gas, the liquid medicine process that circulating water pump extraction was above the filter screen sprays, continue and pass the flue gas reaction of filter screen, at last, the opening through the tower body top is discharged.
Drawings
Fig. 1 is a front sectional view of the present invention.
In the figure: 1. a spray chamber; 2. a reaction chamber; 3. a storage chamber; 4. a filter screen; 6. an air inlet pipe; 7. a water circulating pump; 8. a shower head; 9. an on-off valve; 10. and (5) opening and closing the door.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1, the spray desulfurization tower of this embodiment, including the tower body, the tower body includes spray chamber 1 of upper portion position, reaction chamber 2 and the bottom position of spray chamber 1 lower part position hold and sink room 3, it is the toper structure to hold and sink room 3, 2 internally mounted of reaction chamber have filter screen 4, it installs intake pipe 6 to hold 3 outer wall positions of sinking room, circulating water pump 7 is installed to spray chamber 1 right side position, circulating water pump 7 intakes the end and passes through pipe and 4 upper portions of filter screen intercommunication, circulating water pump 7 goes out the water end and has shower head 8 through pipe connection, shower head 8 sets up in spray chamber 1 upper portion position. Intake pipe 6 sets up the lower part at filter screen 4, enter into and hold the inside flue gas of heavy room 3, can react with the reaction liquid, the smoke and dust granule can be filtered by filter screen 4, filterable smoke and dust granule finally can be held and sink 3 bottoms in storage heavy room, the flue gas that passes filter screen 4 no longer contains the smoke and dust granule, the smoke and dust granule can not be along with the flue gas is attached to shower nozzle outer wall and tower body inner wall, circulating water pump 7 extracts the liquid medicine that does not contain the smoke and dust granule above filter screen 4 and sprays, continue and pass the flue gas reaction of filter screen 4, at last through the opening discharge at tower body top.
Further, a switch valve 9 is installed at the bottom position of the accumulation chamber 3.
Furthermore, one end of the air inlet pipe 6 close to the reaction chamber 2 is provided with a one-way air inlet valve.
Further, a switch door 10 is installed at the right side position of the shower room 1. The reaction agent is added through the opening and closing door 10.
The working principle is as follows: intake pipe 6 sets up the lower part at filter screen 4, enter into and hold the inside flue gas of heavy room 3, can react with the reaction liquid, the smoke and dust granule can be filtered by filter screen 4, filterable smoke and dust granule finally can be held and sink 3 bottoms in storage heavy room, the flue gas that passes filter screen 4 no longer contains the smoke and dust granule, the smoke and dust granule can not be along with the flue gas is attached to shower nozzle outer wall and tower body inner wall, circulating water pump 7 extracts the liquid medicine that does not contain the smoke and dust granule above filter screen 4 and sprays, continue and pass the flue gas reaction of filter screen 4, at last through the opening discharge at tower body top.

Claims (4)

1. A spray desulfurization tower is characterized in that: the tower body comprises a tower body, the tower body includes spray room (1), the reaction chamber (2) of spray room (1) lower part position of upper portion position and the heavy room (3) of storing of bottom position, it is the toper structure to store heavy room (3), reaction chamber (2) internally mounted has filter screen (4), it installs intake pipe (6) to store heavy room (3) outer wall position, spray room (1) right side position is installed circulating water pump (7), circulating water pump (7) are intake and are held through pipe and filter screen (4) upper portion intercommunication, circulating water pump (7) go out the water end and have shower head (8) through pipe connection, shower head (8) set up in spray room (1) upper portion position, intake pipe (6) set up the lower part in filter screen (4).
2. The spray desulfurization tower of claim 1, wherein: and a switch valve (9) is arranged at the bottom of the accumulation chamber (3).
3. The spray desulfurization tower of claim 1, wherein: and one end of the air inlet pipe (6) close to the reaction chamber (2) is provided with a one-way air inlet valve.
4. The spray desulfurization tower of claim 1, wherein: and a switch door (10) is arranged at the right side of the spray room (1).
CN202023005787.0U 2020-12-14 2020-12-14 Spray desulfurizing tower Active CN215276600U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023005787.0U CN215276600U (en) 2020-12-14 2020-12-14 Spray desulfurizing tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023005787.0U CN215276600U (en) 2020-12-14 2020-12-14 Spray desulfurizing tower

Publications (1)

Publication Number Publication Date
CN215276600U true CN215276600U (en) 2021-12-24

Family

ID=79513402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023005787.0U Active CN215276600U (en) 2020-12-14 2020-12-14 Spray desulfurizing tower

Country Status (1)

Country Link
CN (1) CN215276600U (en)

Similar Documents

Publication Publication Date Title
CN200970507Y (en) Smoke filter
CN206676216U (en) A kind of self-loopa desulfurization case
CN110787568A (en) Spraying mechanism in pneumatic tumble water washing tower
CN202078849U (en) Bubbling device for removing acidic gas
CN215276600U (en) Spray desulfurizing tower
CN207838102U (en) A kind of new indoor fire plant with fire-extinguishing function concurrently
CN201768474U (en) Waste gas absorption plant
CN210385464U (en) Circulating filtration type flue gas desulfurization device
CN217490380U (en) Novel waste gas treatment tower for coal chemical industry
CN213885674U (en) Industrial waste gas treatment tower
CN206996241U (en) Industrial smoke environment protection desulphurization device
CN206965396U (en) A kind of water mist dust-removing system
CN205252873U (en) High -efficient desulfurization dust collecting equipment of single tower duplex skill
CN202823722U (en) Water curtain type manual spraying chamber
CN210874715U (en) Foul gas spraying and washing device for sewage treatment plant
CN210448524U (en) Flue gas desulfurization dust removal spray set
CN205145931U (en) High -efficient whirlwind formula exhaust gas purification device
CN211025790U (en) Plant liquid purifying box
CN213913146U (en) House building decoration is with removing formaldehyde device
CN208627000U (en) A kind of spray desulfurizing tower with multistep treatment for smoke gas treatment
CN108031264A (en) A kind of interior ammonia processing unit
CN208194066U (en) A kind of energy-saving efficient boiler desulfurizer
CN213790929U (en) Spraying device for flue gas desulfurization of petrochemical power plant
CN203155674U (en) Ammonia gas absorption machine for blueprint machine
CN208212866U (en) A kind of smoke directly ventilating desulfuration absorbing tower with air-introduced machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant