CN215252686U - Construction structure of earth-rock dam on deep silt layer - Google Patents

Construction structure of earth-rock dam on deep silt layer Download PDF

Info

Publication number
CN215252686U
CN215252686U CN202120515314.0U CN202120515314U CN215252686U CN 215252686 U CN215252686 U CN 215252686U CN 202120515314 U CN202120515314 U CN 202120515314U CN 215252686 U CN215252686 U CN 215252686U
Authority
CN
China
Prior art keywords
dam
filling
dike
downstream
upstream
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120515314.0U
Other languages
Chinese (zh)
Inventor
刘元勋
陈松滨
王海建
范穗兴
韩小妹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Water Resources Pearl River Planning Surverying & Designing Co ltd
Original Assignee
China Water Resources Pearl River Planning Surverying & Designing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Water Resources Pearl River Planning Surverying & Designing Co ltd filed Critical China Water Resources Pearl River Planning Surverying & Designing Co ltd
Priority to CN202120515314.0U priority Critical patent/CN215252686U/en
Application granted granted Critical
Publication of CN215252686U publication Critical patent/CN215252686U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a construction structure of an earth-rock dam on a deep silt layer, which comprises an upstream dike and a downstream dike, wherein the inner sides of the upstream dike and the downstream dike are respectively provided with dike inner side reverse filters formed by throwing and filling reverse filter materials, an underwater throwing and filling dam body is arranged between the inner side reverse filters of the upstream dike and the downstream dike, and the underwater throwing and filling dam body is a structure formed by throwing and filling coarse sand and fills the dam body to a flood height from the water surface; plastic drainage plates are arranged in the underwater filling dam body and the dam foundation sludge layer for vacuum preloading and vibroflotation encryption treatment; and plastic concrete impervious walls are arranged on the underwater filling dam body and the dam foundation silt layer, and a dam foundation curtain is arranged on the bedrock below the plastic concrete impervious walls. Adopt the utility model discloses a structure need not carry out the foundation ditch excavation, does not need the cofferdam to close the gas and draws water, does not excavate the deep silt layer of riverbed, consolidates the drainage with the silt normal position and combines to shake to dash the partly of rubble stake processing back as the dam foundation, has optimized the work procedure, has practiced thrift a large amount of filling materials.

Description

Construction structure of earth-rock dam on deep silt layer
Technical Field
The utility model relates to a structure of earth and rockfill dam on deep silt layer belongs to hydraulic and hydroelectric engineering technical field.
Background
In the middle and lower river areas, soft foundation strata such as silt and the like are widely distributed, are generally in a soft plastic or flow plastic shape, have the characteristics of low water content, high porosity and easiness in compression deformation, and are not suitable for being directly used as the foundation of a building. On this type of foundation, the construction of hydraulic buildings such as earth-rock dams and the like usually requires the construction of a cofferdam first to form a foundation pit, and then a sludge layer is dug in the foundation pit and the dam is filled.
As in the prior art, the north engineering limited of medium cross roads and bridges; the utility model CN108570996A of Middling road bridge construction Limited company discloses a method for constructing a dam and a cofferdam under the condition of shallow water sludge, and double rows of steel pipe piles are formed at the periphery of a bridge section to be constructed; on the opposite surfaces of the two rows of steel pipe piles, the bamboo chip net is inserted to the bottom by adhering to the outer wall of the steel pipe and is fixed on the steel pipe; vertically inserting the grid geotextile to the bottom along the outer wall of the steel pipe on the opposite surfaces of the two rows of steel pipe piles, and fixing the grid geotextile on the steel pipe; the steel pipes of the two rows of steel pipe piles are pulled up one by adopting a steel wire rope pair zipper, and for each row of steel pipe piles, longitudinal connecting steel pipes are adopted at the outer sides of the steel pipe piles to connect the steel pipe piles; after the dam is built, water in the cofferdam is pumped out by a water pump, and the seepage position of the dam body in the water pumping process or after water pumping is blocked in time; the sludge in the cofferdam is cleaned, and a sand cushion and the coarse residue soil are paved for treatment.
However, the construction method in the prior art needs to treat a large amount of sludge, solidify the sludge and then discard the solidified sludge, and the cost is high. When the sludge layer is thick, a deep foundation pit is formed, the stability is poor, and the supporting engineering quantity is huge. A large amount of waste soil needs to occupy a large area as a waste slag field and corresponding water conservation measures, thereby wasting precious land resources, having low efficiency and high investment, and not meeting the requirements of energy conservation, emission reduction and environmental protection. Therefore, the existing technology for building hydraulic buildings such as earth-rock dams on the deep sludge layer is not suitable for the requirements of the current social and economic development on ecological environment and engineering construction efficiency, and needs to be further improved.
SUMMERY OF THE UTILITY MODEL
For overcoming the weak point of above-mentioned prior art, the utility model aims at providing a need not foundation ditch and strut in the traditional meaning on the deep silt layer, need not to excavate the deep silt layer, the direct earth and rockfill dam who constructs under water constructs the structure.
The utility model discloses a realize like this:
a construction structure of an earth-rock dam on a deep sludge layer comprises an upstream dike and a downstream dike, wherein inner side reverse filters formed by casting and filling reverse filters are respectively arranged on the inner sides of the upstream dike and the downstream dike, an underwater cast-filling dam body is arranged between the inner side reverse filters of the upstream dike and the downstream dike, and the underwater cast-filling dam body is a structure formed by casting and filling materials including medium coarse sand and fills the water surface to a flood height; plastic drainage plates are arranged in the underwater filling dam body and the dam foundation sludge layer for vacuum preloading and vibroflotation encryption treatment; and plastic concrete impervious walls are arranged on the underwater filling dam body and the dam foundation silt layer, and a dam foundation curtain is arranged on the bedrock below the plastic concrete impervious walls.
Wherein, the upper dam impervious core wall of the underwater throwing filling dam body adopts a clay core wall, and a high-plasticity soil transition area is adopted between the plastic concrete impervious wall and the clay core wall; an upstream dam shell and a downstream dam shell are respectively arranged at the upstream side and the downstream side of the impervious core wall of the upper dam body; an upstream slope protection and a downstream drainage body are respectively arranged on the slope surfaces of the upstream dam shell and the downstream dam shell.
Furthermore, vibroflotation gravel piles are arranged at intervals on the plastic drainage plates and are used for vibroflotation treatment of the underwater cast-fill dam body and the dam foundation sludge layer.
Compared with the prior art, the utility model has the following outstanding substantive characteristics and the progress that is showing:
firstly, adopt the utility model discloses a structure need not carry out the foundation ditch excavation, does not need the cofferdam to close the gas and draws water, does not excavate the deep silt layer of riverbed, consolidates the drainage with silt normal position and combines to shake to dash a part of rubble stake processing back as the dam foundation, has optimized the construction process, has practiced thrift a large amount of fillers. Secondly, adopt the utility model discloses a structure need not dig out the deep silt layer, has avoided the silt solidification treatment expense scheduling problem that the deep silt layer excavation produced, has reduced the solidification field, has abandoned the sediment field and has accessioned the land, is favorable to ecological environment protection and soil and water conservation. And, adopt the utility model discloses a construction process can be optimized to the structure, avoids deep basal pit to strut, is favorable to building place safety. The utility model discloses can also save expropriation of land and relevant water conservation, environmental protection measure, show saving time limit for a project and engineering investment.
Drawings
FIG. 1 is a schematic structural view of the earth and rockfill dam body of the present invention;
FIG. 2 is a schematic view of the construction of a plastic drainage plate;
FIG. 3 is a schematic view of vibro-replacement stone column construction;
FIG. 4 is a schematic view of a plastic drain board arrangement;
FIG. 5 is a schematic view of a vibro-replacement stone column arrangement;
FIG. 6 is a schematic view of a transition zone of high plasticity soil.
Description of reference numerals: 1-upstream dike, 2-downstream dike, 3-dike inside reverse filter, 4-underwater cast-fill dam body, 5-medium coarse sand cushion layer, 6-plastic drainage plate, 7-plastic concrete impervious wall, 8-dam foundation curtain, 9-high-plastic soil transition region, 10-upper dam body impervious core wall, 11-upstream dam shell, 12-downstream dam shell, 13-upstream slope protection, 14-downstream drainage body, 15-silt layer, 16-bedrock, 17-drainage blind ditch and 18-gravel pile.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "sleeved/connected", "connected", and the like are to be understood in a broad sense, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The utility model discloses an implement like this:
the utility model discloses a silt in the riverbed need not to be dug and remove, directly throws and packs the lump stone in the riverbed and form upstream berm 1, low reaches berm 2, throws dam material such as coarse sand in the middle of the berm under water, forms construction platform after exposing the surface of water, forms lower part dam body and dam foundation after carrying out on-the-spot drainage consolidation to silt on this platform and encrypting the processing, then carries out prevention of seepage processing to lower part dam body and dam foundation, and the construction is accomplished according to conventional mode to the upper portion dam body.
The detailed technical scheme of the utility model is as follows:
and (3) respectively throwing and filling rock-fill materials at slope toe positions of an upper dam and a lower dam designed on a river bed to form a dike, then throwing and filling medium coarse sand materials between the upper dike and the lower dike, and filling the water surface to a flood height to form the overwater construction platform. And (3) inserting a plastic drainage plate 6 into the dam foundation sludge layer 15 on the platform, performing vacuum preloading to promote the lower sludge to be solidified and drained, and then performing vibroflotation and encryption treatment on the lower dam body filler and the dam foundation sludge layer 15 to meet the compactness and bearing requirements of the dam.
The prop dam is arranged outside the boundary between the dam slope extension line and the dam foundation of the earth-rock dam and serves as a temporary construction channel to provide a still water construction condition for underwater filling of a dam body and form a permanent press platform and a protective body of a dam toe in the later period. The prop dam is preferably filled with stone with good quality. The elevation of the prop dam top is higher than the flood height (h) by more than 0.5m, the width of the prop dam top is generally 6-10 m, and the upstream slope and the downstream slope are 1: 2-1: 2.5. The inside of the dike is filled with the filter material, and the horizontal thickness of the filter material is generally more than 5 m. The consolidation and drainage of the silt generally adopt PVC plastic drainage plates, the interval row spacing (a) can be arranged according to 1m, the treatment range is a dam foundation silt layer 15 between dikes, and the exposed length of the top of the dam foundation silt layer is 0.5 m. As a preferred scheme, a graded broken stone drainage blind ditch 17 is arranged on a construction platform, vacuum preloading is carried out on the lower sludge layer 15, and water drained by the vacuum preloading is drained downstream through the drainage blind ditch 17.
After the dam foundation sludge is subjected to vacuum preloading and preliminary drainage consolidation treatment, vibroflotation gravel piles 18 are arranged on a construction platform, vibroflotation compaction is carried out on the underwater throwing filler and the sludge layer 15 foundation, and the gravel piles can be used as drainage channels. The gravel piles 18 are arranged at intervals on the plastic drainage plates 6, the spacing is generally 3m, and the gravel piles can be adjusted according to actual conditions.
Underwater filling and silt layer 15 foundation vibroflotation and encryption processing, and after the compactness and the dam foundation bearing requirements required by design are met through detection, the dam body and the dam foundation at the lower part of the earth-rock dam are constructed by adopting an underwater foundation-pit-free technology.
And the second step, constructing an upper dam body and an anti-seepage body. The upper dam body is conventionally used without further details. The seepage-proofing body consists of a dam body seepage-proofing body and the seepage-proofing bodies of the lower dam body and the dam foundation. Wherein, the lower dam body and the dam foundation of the silt layer 15 adopt plastic concrete impervious walls 7, and the impervious bedrock adopts curtain grouting to form a dam foundation curtain 8.
The designed compressive strength of the plastic concrete core wall is generally not lower than 3.0MPa, the tensile strength is not lower than 0.5MPa, the elastic modulus is 500-800 MPa, and the permeability coefficient is less than 1 multiplied by 10-7cm/s。
As a preferred scheme, the upper dam body seepage-proofing adopts a clay core wall, and high-plasticity soil is filled at the joint of the core wall and the plastic concrete seepage-proofing wall 7 for transition to form a high-plasticity soil transition area 9. Wherein, the wrapping area formed by the high-plasticity soil on the head part of the impervious wall is more than 5 m.
The construction steps of the present invention will be described in detail with reference to the accompanying drawings:
first, as shown in figure 1, upstream dike 1 and downstream dike 2 are constructed by bank side throwing and filling to advance into the river bed, and the dike top elevation is determined according to the flood water level plus super height. The prop bank toe is positioned outside the extending line of the dam slope, the top width is generally 6-10 m according to the construction requirement, and the upstream slope and the downstream slope are 1: 2-1: 2.5.
Secondly, filling materials from the upstream dike and the downstream dike to the middle of the river bed respectively, and throwing and filling reverse filter materials on the inner sides of the upstream dike 1 and the downstream dike 2 respectively to form a dike inner side reverse filter body 3, wherein the horizontal width is not less than 5 m. And then, continuously throwing and filling medium coarse sand with a certain grading requirement between the upstream and downstream reverse filters 3, and filling the medium coarse sand out of the water surface to a flood height to form an underwater throwing and filling dam body 4.
As shown in fig. 2, the medium coarse sand cushion 5 is paved and filled again on the construction platform formed by the underwater riprap dam body 4 to be used as a drainage channel.
As shown in FIGS. 2 and 3, the plastic drainage plate 6 is constructed, and the lower part of the plastic drainage plate 6 extends to the bottom of the sludge layer 15.
As shown in fig. 2, a drainage blind ditch 17 is constructed.
As shown in fig. 3 and 5, after the drainage consolidation of the lower sludge layer reaches the design requirement, vibroflotation gravel piles 18 are arranged at intervals on the plastic drainage plate 6, and vibroflotation treatment is performed on the lower throwing filling body 4 and the sludge layer 15, so that the sludge layer 15 is further drained and consolidated, and meanwhile, the throwing filling body 4 is encrypted, and the compactness and the dam foundation bearing requirement required by the design are met. And finally, completing construction of the dam body and the dam foundation at the lower part of the earth-rock dam by adopting an underwater foundation-pit-free method.
As shown in figures 1 and 6, a plastic concrete impervious wall 7 and a dam foundation curtain 8 are constructed in the middle of the lower dam body.
As shown in figure 6, in the top downstream area of the impervious wall, a part of the preloading filling material is dug out respectively, and the high plasticity soil transition area 9 and the clay core wall 10 are replaced and filled, and layered rolling and filling are completed.
As shown in FIG. 6, the thickness of the wrapping area formed by the high-plasticity soil transition area 9 on the impervious wall is more than or equal to 5 m.
After the above-mentioned process is accomplished, begin to construct upper portion dam body, include: the construction mode of the upstream dam shell 11, the downstream dam shell 12, the upper clay core wall 10, the upstream revetment 13 and the downstream drainage body 14 is a conventional mode and is not described in detail.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (5)

1. A construction structure of an earth-rock dam on a deep sludge layer is characterized in that: the dam comprises an upstream dike (1) and a downstream dike (2), wherein inner side reverse filters (3) formed by throwing and filling reverse filter materials are respectively arranged on the inner sides of the upstream dike (1) and the downstream dike (2), an underwater throwing and filling dam body (4) is arranged between the inner side reverse filters (3) of the upstream dike and the downstream dike, the underwater throwing and filling dam body (4) is a structure formed by throwing and filling materials including medium coarse sand, and the dam body is filled out of a water surface to a flood height; plastic drainage plates (6) are arranged in the underwater filling dam body (4) and the dam foundation silt layer (15) for vacuum preloading and vibroflotation encryption treatment; the underwater filling dam body (4) and the dam foundation silt layer (15) are provided with a plastic concrete impervious wall (7), and a dam foundation curtain (8) is arranged on a foundation rock (16) below the plastic concrete impervious wall (7).
2. The construction structure of an earth and rockfill dam on a deep sludge layer according to claim 1, wherein: the upper dam impervious core wall (10) of the underwater throwing filling dam body (4) adopts a clay core wall, and a high-plasticity soil transition area (9) is adopted between the plastic concrete impervious wall (7) and the clay core wall.
3. The construction structure of an earth and rockfill dam on a deep sludge layer according to claim 2, wherein: an upstream dam shell (11) and a downstream dam shell (12) are respectively arranged on the upstream side and the downstream side of the upper dam body impervious core wall (10).
4. The construction structure of an earth and rockfill dam on a deep sludge layer according to claim 3, wherein: an upstream protection slope (13) and a downstream drainage body (14) are respectively arranged on the slope surfaces of the upstream dam shell (11) and the downstream dam shell (12).
5. The construction structure of an earth and rockfill dam on a deep sludge layer according to claim 1, wherein: and vibro-replacement gravel piles (18) are arranged at intervals on the plastic drainage plates (6) and are used for vibro-replacement and encryption treatment of the underwater filling dam body (4) and the dam foundation silt layer (15).
CN202120515314.0U 2021-03-11 2021-03-11 Construction structure of earth-rock dam on deep silt layer Active CN215252686U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120515314.0U CN215252686U (en) 2021-03-11 2021-03-11 Construction structure of earth-rock dam on deep silt layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120515314.0U CN215252686U (en) 2021-03-11 2021-03-11 Construction structure of earth-rock dam on deep silt layer

Publications (1)

Publication Number Publication Date
CN215252686U true CN215252686U (en) 2021-12-21

Family

ID=79503545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120515314.0U Active CN215252686U (en) 2021-03-11 2021-03-11 Construction structure of earth-rock dam on deep silt layer

Country Status (1)

Country Link
CN (1) CN215252686U (en)

Similar Documents

Publication Publication Date Title
CN111851505A (en) Construction method and structure of pouring type impervious core earth-rock dam
CN111472326A (en) Method and structure for building gravity dam on deep covering layer
CN112854144A (en) Construction structure of earth-rock dam on deep sludge layer and construction method thereof
CN209816885U (en) Novel cofferdam structure under soft covering layer
CN215669631U (en) Deep overburden foundation structure
CN111733842A (en) Cofferdam construction method and cofferdam structure
CN110552324A (en) Side slope protection structure capable of underwater construction and construction method thereof
CN112195965A (en) Expansive soil cutting retaining wall
CN213143069U (en) Pouring type impervious core earth-rock dam structure
CN215252686U (en) Construction structure of earth-rock dam on deep silt layer
CN115450236A (en) Cofferdam anti-seepage structure and construction method thereof
CN212248171U (en) Offshore artificial island structure suitable for silt foundation
CN103821106B (en) Small-sized fishing port and channel revetment structure
CN113123301A (en) Partition structure of gravel soil core wall dam
CN113338315A (en) Earth-rock cofferdam structure of silt soft soil foundation and construction method thereof
KR100429370B1 (en) Method for constructing revetment dike using a fiber for public works
CN212477620U (en) Structure for building gravity dam on deep and thick covering layer
CN114960730B (en) Method and structure for building asphalt core wall dam base without foundation pit
CN111321706A (en) Clay core wall dam structure and construction method thereof
CN216041253U (en) Soft soil foundation earth-rock cofferdam structure of silt matter
CN220868277U (en) Earth-rock dam preloading structure suitable for sand gravel foundation
CN219840108U (en) Cofferdam structure using clay and membrane bag concrete to jointly prevent seepage
CN217460445U (en) Novel refute bank suitable for soft soil foundation
CN213038294U (en) River bank protective structure
CN220813681U (en) Novel ecological bank protection structure of river course

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant