CN215232297U - Movable three-stage sedimentation tank - Google Patents

Movable three-stage sedimentation tank Download PDF

Info

Publication number
CN215232297U
CN215232297U CN202121730281.8U CN202121730281U CN215232297U CN 215232297 U CN215232297 U CN 215232297U CN 202121730281 U CN202121730281 U CN 202121730281U CN 215232297 U CN215232297 U CN 215232297U
Authority
CN
China
Prior art keywords
sedimentation tank
pipe
box body
water
tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121730281.8U
Other languages
Chinese (zh)
Inventor
赵如安
严后喜
王春磊
马俊
孙燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Original Assignee
Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd filed Critical Third Construction Co Ltd of China Construction Eighth Engineering Divison Co Ltd
Priority to CN202121730281.8U priority Critical patent/CN215232297U/en
Application granted granted Critical
Publication of CN215232297U publication Critical patent/CN215232297U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to the field of sewage purification, in particular to a movable three-stage sedimentation tank which is installed at an underground water pipeline by hoisting, comprising a first box body, a second box body and a rainwater detection well, wherein an intermediate pipe is connected between the first box body and the second box body, a first sedimentation tank is arranged in the first box body, and a water inlet pipe communicated with the first sedimentation tank is installed outside the first box body; be equipped with the baffle of vertical setting in the second box, the baffle is split into two parts space to the second box, is equipped with second sedimentation tank and third sedimentation tank in the two parts space respectively, and first sedimentation tank is linked together with the second sedimentation tank through the intermediate pipe, sets up the through-hole of intercommunication second sedimentation tank and third sedimentation tank on the baffle, and the third sedimentation tank is linked together through outlet pipe and rainwater detection well, and rainwater detection well is linked together with underground water pipeline, the utility model discloses an above-mentioned structure has can be along with place conversion used repeatedly, and the little advantage of area.

Description

Movable three-stage sedimentation tank
Technical Field
The utility model relates to a sewage purification field, specificly a portable tertiary sedimentation tank.
Background
The construction scheme of the three-stage sewage purification tank in the prior art is that three foundation pits are dug on the ground, then a brick is laid on a cast-in-situ sedimentation tank, and finally a pipeline is communicated. However, the structure has the defects of incapability of moving along with site conversion, large occupied area, poor waterproofness, easiness in permeation and long construction period, so that the third sedimentation tank which can move and is small in construction time period and occupied area is designed aiming at the defects.
Disclosure of Invention
To the above problem, the utility model designs a can remove along with the place conversion, area is little and be convenient for sedimentation tank of construction, concrete structure as follows:
a movable three-stage sedimentation tank is installed at an underground water pipeline through hoisting and comprises a first box body, a second box body and a rainwater detection well, wherein the first box body and the second box body are of a cubic structure, the cubic structure is formed by welding six steel plates, lifting lugs are welded on the steel plates at the tops of the first box body and the second box body, an intermediate pipe is connected between the first box body and the second box body, a first sedimentation tank is arranged in the first box body, and a water inlet pipe communicated with the first sedimentation tank is installed outside the first box body; be equipped with the baffle of vertical setting in the second box, the baffle is split into two parts space to the second box, is equipped with second sedimentation tank and third sedimentation tank in the two parts space respectively, and first sedimentation tank is linked together with the second sedimentation tank through the intermediate pipe, sets up the through-hole of intercommunication second sedimentation tank and third sedimentation tank on the baffle, and the third sedimentation tank is linked together through outlet pipe and rainwater detection well, and rainwater detection well is linked together with underground water pipeline.
Further, a first cover plate movably connected with the top steel plate is arranged at the top of the first box body; a second cover plate movably connected with the top steel plate is arranged at the position, corresponding to the second sedimentation tank, of the top of the second box body; and a third cover plate movably connected with the top steel plate is arranged at the position, corresponding to the third sedimentation tank, of the top of the second box body.
Furthermore, two ends of the middle pipe are respectively positioned at the upper parts of the first box body and the second box body where the middle pipe is positioned.
Furthermore, a water outlet pipe is positioned at the lower part of the second box body, the water outlet pipe is 200mm higher than the bottom of the third sedimentation tank, and a third water valve and a third water pump are sequentially arranged in the water outlet pipe.
Furthermore, the through hole and the middle tube are positioned on the same plane, and the through hole on the partition board is far away from the point of the middle tube projected on the partition board.
Further, a first emptying pipe connected with the first sedimentation tank is arranged at the lower part of the first box body, the first emptying pipe is 200mm higher than the bottom of the first sedimentation tank, the first emptying pipe is communicated with a rainwater detection well, and a first water valve and a first water pump are sequentially installed in the first emptying pipe; and a second emptying pipe connected with a second sedimentation tank is arranged at the lower part of the second box body, the second emptying pipe is 200mm higher than the bottom of the second sedimentation tank, the second emptying pipe is communicated with a rainwater detection well, and a second water valve and a second water pump are sequentially installed in the second emptying pipe.
Furthermore, a water level early warning line is arranged in the second box body, an overflow pipe is arranged above the water level early warning line and connected with the three-way pipe, a first outlet of the three-way pipe is connected into the rainwater detection well, and a second outlet of the three-way pipe is connected with the high-pressure water gun.
Compared with the prior art, the utility model has the advantages as follows:
1. the utility model provides a sedimentation tank is connected through first box and second box and constitutes, and the box comprises six steel sheet welding, and the box top is equipped with the lug, has simple structure, and the construction of being convenient for, and can follow the advantage that the place conversion removed.
2. The utility model discloses a set up the apron at each box top, the workman clears up the floater on sedimentation tank surface through opening the apron.
3. The utility model discloses outlet pipe, first blow-down pipe and second blow-down pipe leave the distance with the sedimentation tank bottom that corresponds respectively, can avoid in the sediment admission pipe of bottom of the pool.
4. The utility model discloses in can open the interior external pressure differential of apron balance box body when the drainage, guarantee the smooth drainage of blow-down pipe.
5. The utility model discloses a place the water level through setting up the overflow pipe and too high spilling over to can carry out the dust fall to three grade sedimentation tank external environment through overflow pipe and high-pressure squirt intercommunication, have air-purifying's effect.
Drawings
Fig. 1 is a cross-sectional view of the present invention;
FIG. 2 is a side view of FIG. 1;
fig. 3 is an external side view of the present invention;
fig. 4 is an external top view of the present invention.
Reference numerals
1. A first case; 2. a second case; 3. a partition plate; 4. a first sedimentation tank; 5. a second sedimentation tank; 6. a third sedimentation tank; 7. a through hole; 8. lifting lugs; 91. a first cover plate; 92. a second cover plate; 93. a third cover plate; 10. a water inlet pipe; 11. an intermediate pipe; 12. a water outlet pipe; 13. a rainwater detection well; 14. a first blow-down pipe; 15. a first water valve; 16. a first water pump; 17. a second blow-down pipe; 18. a second water valve; 19. a second water pump; 20. a third water valve; 21. a third water pump; 22. an overflow pipe; 23. a high pressure water gun; 24. a water level warning line.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention.
Example 1
As shown in fig. 1, the movable three-stage sedimentation tank is installed at an underground water pipeline through hoisting, and comprises a first box body, a second box body and a rainwater detection well, wherein the first box body and the second box body are both of a cubic structure, and the cubic structure is formed by welding six steel plates; as shown in fig. 3, lifting lugs are welded on the top steel plates of the first box body and the second box body; a middle pipe is connected between the first box body and the second box body, two ends of the middle pipe are respectively positioned at the upper parts of the first box body and the second box body where the middle pipe is positioned, a first sedimentation tank is arranged in the first box body, and a water inlet pipe communicated with the first sedimentation tank is arranged outside the first box body; be equipped with the baffle of vertical setting in the second box, the baffle is split into two parts space to the second box, is equipped with second sedimentation tank and third sedimentation tank in the two parts space respectively, and first sedimentation tank is linked together with the second sedimentation tank through the intermediate pipe, sets up the through-hole of intercommunication second sedimentation tank and third sedimentation tank on the baffle, and the third sedimentation tank is linked together through outlet pipe and rainwater detection well, and rainwater detection well is linked together with underground water pipeline. The water outlet pipe is positioned at the lower part of the second box body, is 200mm higher than the bottom of the third sedimentation tank, and is internally provided with a third water valve and a third water pump in sequence.
As shown in fig. 4, a first cover plate movably connected with the top steel plate is arranged at the top of the first box body; the position that the second box top corresponds the second sedimentation tank is equipped with the second apron with top steel sheet swing joint, and the position that the second box top corresponds the third sedimentation tank is equipped with the third apron with top steel sheet swing joint, can clear up the floater on first sedimentation tank, second sedimentation tank and the third sedimentation tank respectively through opening three apron.
As shown in fig. 2, the through holes are located on the same plane as the intermediate pipe, and preferably, in order to prevent the preliminary sedimentation water in the first sedimentation tank from directly flowing into the third sedimentation tank, the through holes on the partition plate are far from the point where the intermediate pipe projects on the partition plate.
The sedimentation tank bottom needs regularly clear up the deposit, consequently need arrange ponding in the sedimentation tank futilely, the utility model discloses an at each sedimentation tank bottom installation blow-down pipe drainage, when the drainage, can open the corresponding apron on each sedimentation tank water upper portion, make the inside and outside air pressure keep balance of each box, it helps the smooth drainage of blow-down pipe, and concrete structure is as follows:
as shown in fig. 1 and 2, a first emptying pipe connected with a first sedimentation tank is arranged at the lower part of the first box body, the first emptying pipe is 200mm higher than the bottom of the first sedimentation tank, the first emptying pipe is communicated with a rainwater detection well, and a first water valve and a first water pump are sequentially installed in the first emptying pipe; the lower part of the second box body is provided with a second emptying pipe connected with a second sedimentation tank, the second emptying pipe is 200mm higher than the bottom of the second sedimentation tank, the second emptying pipe is communicated with a rainwater detection well, a second water valve and a second water pump are sequentially installed in the second emptying pipe, and the third sedimentation tank drains water through a water outlet pipe.
As shown in fig. 1 and 2, a water level early warning line is arranged in the second box body, an overflow pipe is arranged above the water level early warning line and connected with a three-way pipe, a first outlet of the three-way pipe is connected into the rainwater detection well, and a second outlet of the three-way pipe is connected with a high-pressure water gun.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; such modifications and substitutions do not depart from the spirit and scope of the present invention.

Claims (7)

1. A movable three-stage sedimentation tank is characterized by being installed at an underground water pipeline through hoisting and comprising a first box body, a second box body and a rainwater detection well, wherein the first box body and the second box body are both of a cubic structure, the cubic structure is formed by welding six steel plates, lifting lugs are welded on the steel plates at the tops of the first box body and the second box body, an intermediate pipe is connected between the first box body and the second box body, a first sedimentation tank is arranged in the first box body, and a water inlet pipe communicated with the first sedimentation tank is installed outside the first box body; be equipped with the baffle of vertical setting in the second box, the baffle is split into two parts space to the second box, is equipped with second sedimentation tank and third sedimentation tank in the two parts space respectively, and first sedimentation tank is linked together with the second sedimentation tank through the intermediate pipe, sets up the through-hole of intercommunication second sedimentation tank and third sedimentation tank on the baffle, and the third sedimentation tank is linked together through outlet pipe and rainwater detection well, and rainwater detection well is linked together with underground water pipeline.
2. The movable three-stage sedimentation tank according to claim 1, wherein a first cover plate movably connected with a top steel plate is provided at the top of the first tank; a second cover plate movably connected with the top steel plate is arranged at the position, corresponding to the second sedimentation tank, of the top of the second box body; and a third cover plate movably connected with the top steel plate is arranged at the position, corresponding to the third sedimentation tank, of the top of the second box body.
3. The mobile tertiary sedimentation tank of claim 1, wherein both ends of the intermediate pipe are respectively located at upper portions of the first tank and the second tank where the intermediate pipe is located.
4. The movable three-stage sedimentation tank according to claim 1, wherein a water outlet pipe is positioned at the lower part of the second tank body, the water outlet pipe is 200mm higher than the bottom of the third sedimentation tank, and a third water valve and a third water pump are sequentially arranged in the water outlet pipe.
5. The mobile tertiary sedimentation tank of claim 3, wherein the through-holes are located on the same plane as the intermediate pipe, and the through-holes in the partition are located away from a point on the partition where the intermediate pipe projects.
6. The movable three-stage sedimentation tank according to claim 1, wherein a first emptying pipe connected with the first sedimentation tank is arranged at the lower part of the first tank body, the first emptying pipe is 200mm higher than the bottom of the first sedimentation tank, the first emptying pipe is communicated with a rainwater detection well, and a first water valve and a first water pump are sequentially arranged in the first emptying pipe; and a second emptying pipe connected with a second sedimentation tank is arranged at the lower part of the second box body, the second emptying pipe is 200mm higher than the bottom of the second sedimentation tank, the second emptying pipe is communicated with a rainwater detection well, and a second water valve and a second water pump are sequentially installed in the second emptying pipe.
7. The movable three-stage sedimentation tank according to claim 1, wherein a water level early warning line is provided in the second tank, an overflow pipe is provided above the water level early warning line, the overflow pipe is connected with a three-way pipe, a first outlet of the three-way pipe is connected into the rainwater detection well, and a second outlet of the three-way pipe is connected with a high-pressure water gun.
CN202121730281.8U 2021-07-28 2021-07-28 Movable three-stage sedimentation tank Active CN215232297U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121730281.8U CN215232297U (en) 2021-07-28 2021-07-28 Movable three-stage sedimentation tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121730281.8U CN215232297U (en) 2021-07-28 2021-07-28 Movable three-stage sedimentation tank

Publications (1)

Publication Number Publication Date
CN215232297U true CN215232297U (en) 2021-12-21

Family

ID=79495215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121730281.8U Active CN215232297U (en) 2021-07-28 2021-07-28 Movable three-stage sedimentation tank

Country Status (1)

Country Link
CN (1) CN215232297U (en)

Similar Documents

Publication Publication Date Title
CN105668700A (en) Desilting and deoiling device
CN215232297U (en) Movable three-stage sedimentation tank
CN212974282U (en) Movable three-stage settling tank
CN201778388U (en) Automatic rainwater-sewage intercepting device
CN104878823A (en) Combined pipeline initial rainwater interception, storage and drainage system and storage and drainage method
KR101588201B1 (en) Rainwater utilization system
CN211550776U (en) River course flows promotion engineering construction and flows steel pipe guiding device automatically
CN201111510Y (en) Gas, water and mud three-phase separator of anaerobic sewage treatment equipment
CN112031169A (en) Assembled box type house with rainwater collecting function
CN101948227A (en) Unit barrel integrated assembly type septic tank
CN201770583U (en) Unit bucket integrated assembled type septic tank
CN206631277U (en) The outer filter of tower
CN217794699U (en) Lower hanging type three-stage sedimentation tank based on reinforced concrete inner support
CN208870160U (en) A kind of straight waterfall formula drain well lid
CN111794318A (en) High-rise water supply device capable of preventing secondary water pollution
CN205712440U (en) A kind of tunneling formula rainwater storage structure
CN204850003U (en) Rainwater sinks mud inspection shaft
CN211499096U (en) Ecological water bank with river-following pollution self-control function
CN216713618U (en) Roof siphon drainage system
CN219156592U (en) Simple three-stage oil separation tank for construction temporary construction
CN218911592U (en) Initial rainwater collecting device
CN213979240U (en) Waterproof composite well lid
CN216276059U (en) Back flush waste water breakwater of air water back flush filtering pond
CN211999365U (en) Vertical shaft sewage treatment system
CN214005901U (en) Garden rainwater collecting system