CN215168384U - Building engineering formwork support system - Google Patents

Building engineering formwork support system Download PDF

Info

Publication number
CN215168384U
CN215168384U CN202121024010.0U CN202121024010U CN215168384U CN 215168384 U CN215168384 U CN 215168384U CN 202121024010 U CN202121024010 U CN 202121024010U CN 215168384 U CN215168384 U CN 215168384U
Authority
CN
China
Prior art keywords
support column
support
roof
wall
linking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121024010.0U
Other languages
Chinese (zh)
Inventor
江小林
沈洪鹰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian New Huaxia Construction Engineering Group Co ltd
Original Assignee
Fujian New Huaxia Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian New Huaxia Construction Engineering Group Co ltd filed Critical Fujian New Huaxia Construction Engineering Group Co ltd
Priority to CN202121024010.0U priority Critical patent/CN215168384U/en
Application granted granted Critical
Publication of CN215168384U publication Critical patent/CN215168384U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a building engineering formwork support system, including supporting the base and the roof support, the last fixed surface of supporting the base installs first support column, the lower fixed surface of roof support is connected with the second support column, the external screw thread has all been seted up on the surface of first support column and second support column looks remote site, the looks remote site threaded connection of first support column and second support column has adjusting sleeve, the internal thread that screw thread opposite direction was seted up respectively at the both ends of adjusting sleeve inner wall, the inserting groove has been seted up to the side of roof support, the inner wall of inserting groove is inserted and is equipped with the connection board. This building engineering formwork support system is through seting up the inserting groove in the side of roof support to be connected with other roof supports through linking up the fishplate bar, through linking up sleeve and linking pole, make the second support column be connected with other bearing structure, form the whole of a mutual dependence between each bearing structure, improve bearing structure's steadiness, avoid causing the condition of the template concrete leakage that collapses to take place.

Description

Building engineering formwork support system
Technical Field
The utility model relates to a building energy saving technology field specifically is building engineering template support system.
Background
In the formwork support structure for concrete cast-in-place construction in construction, steel or wood beams are generally assembled into a formwork bracket, steel or wood rods are used for building a scaffold to form bracket support, concrete construction is carried out by matching with the steel formwork, the formwork is used as a main structure for supporting and forming concrete, and the quality and the effect of concrete pouring are often influenced when the formwork is supported and fixed.
The existing supporting structures are mutually geographical, an interdependent supporting system is not formed, stability among single supporting structures is poor, the supporting structures are prone to collapse, concrete leakage is prone to occurring, waste of resources is caused, and meanwhile building cost is increased.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building engineering template support system to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: building engineering formwork support system, including supporting base and roof support, the last fixed surface of supporting base installs first support column, roof support's lower fixed surface is connected with the second support column, the external screw thread has all been seted up on the surface of first support column and second support column looks remote site, the looks remote site threaded connection of first support column and second support column has adjusting sleeve, the internal thread that screw thread opposite direction is seted up respectively at the both ends of adjusting sleeve inner wall, the inserting groove has been seted up to the side of roof support, the inner wall of inserting groove is inserted and is equipped with linking plate, the fixed surface of second support column installs linking sleeve, linking telescopic inner wall is inserted and is equipped with linking rod.
Preferably, threaded holes are formed in the lower surface of the supporting top plate and the surface of the connecting sleeve, and threaded jackscrews are connected to the inner wall of the threaded holes in a threaded mode.
Preferably, the number of the adapter sleeves is four, and the adapter sleeves are circumferentially arranged on the surface of the second support column at equal intervals.
Advantageous effects
The utility model provides a building engineering template supports system possesses following beneficial effect:
1. this building engineering formwork support system is through seting up the inserting groove in the side of roof support to be connected with other roof supports through linking up the fishplate bar, simultaneously through linking up sleeve and linking pole, make the second support column be connected with other bearing structure, form the whole that relies on each other between each bearing structure, improve bearing structure's steadiness, avoid causing the condition of the concrete leakage that collapses of pouring the template to take place.
2. This building engineering template support system through set up adjusting sleeve between first support column and second support column, rotates adjusting sleeve, can change the distance between roof and the support base, makes it can adjust the support height according to the floor height of difference, and the suitability is strong, has reduced bearing structure's manufacturing cost.
Drawings
FIG. 1 is a schematic view of a front cross-sectional structure of the present invention;
FIG. 2 is a schematic perspective view of the present invention;
fig. 3 is a schematic view of the bottom section of the top support plate.
In the figure: the support device comprises a support base 1, a support top plate 2, a first support column 3, a second support column 4, an adjusting sleeve 5, a connecting plate 6, a connecting sleeve 7 and a connecting rod 8.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides a technical solution: building engineering template support system, including supporting base 1 and roof support 2, the concrete balancing weight has been pour to the inside of supporting base 1, the last fixed surface of supporting base 1 installs first support column 3, the lower fixed surface of roof support 2 is connected with second support column 4, the external screw thread has all been seted up on the surface of first support column 3 and the 4 looks remote departments of second support column, the looks remote departments threaded connection of first support column 3 and second support column 4 has adjusting sleeve 5, the internal thread that screw thread opposite direction was seted up respectively at the both ends of 5 inner walls of adjusting sleeve.
Through set up adjusting sleeve 5 between first support column 3 and second support column 4, rotate adjusting sleeve 5, can change the distance between roof 2 and the support base 1, make it can be according to the high adjustment support height of the building of difference, the suitability is strong, has reduced bearing structure's manufacturing cost.
The inserting groove has been seted up to the side of roof support 2, the inner wall of inserting groove is inserted and is equipped with linking plate 6, the fixed surface of second support column 4 installs linking sleeve 7, threaded hole has all been seted up on the lower surface of roof support 2 and the surface that links up sleeve 7, the inner wall threaded connection of screw hole has the screw thread jackscrew, the inner wall that links up sleeve 7 is inserted and is equipped with linking pole 8, the quantity that links up sleeve 7 is four, four linking sleeve 7 circumference equidistance set up on the surface of second support column 4, linking plate 6 and linking pole 8 are fixed through the screw thread jackscrew.
Offer the inserting groove through the side at roof 2 to be connected with other roof 2 through linking up the fishplate bar 6, simultaneously through linking up sleeve 7 and linking pole 8, make second support column 4 be connected with other bearing structure, form the whole that relies on each other between each bearing structure, improve bearing structure's steadiness, avoid causing the condition of pouring the template and collapsing the concrete leakage to take place.
The working principle is as follows: when the building engineering formwork support system is used for formwork support, the height of the whole support structure is adjusted by rotating the adjusting sleeve 5, the supporting top plate 2 supports the lower surface of a poured formwork, and meanwhile, the connecting plates 6 and the connecting rods 8 are used for connecting the support structures, so that the stability of the whole support system is improved, the phenomenon that the poured formwork collapses and concrete leaks is avoided, and the construction process is accelerated.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (3)

1. Building engineering template support system is including supporting base (1) and roof board (2), its characterized in that: the support structure is characterized in that a first support column (3) is fixedly mounted on the upper surface of the support base (1), a second support column (4) is fixedly connected to the lower surface of the support top plate (2), external threads are formed in the surfaces of opposite ends of the first support column (3) and the second support column (4), an adjusting sleeve (5) is connected to the opposite ends of the first support column (3) and the second support column (4) through threads, internal threads with opposite thread directions are formed in two ends of the inner wall of the adjusting sleeve (5) respectively, an insertion groove is formed in the side surface of the support top plate (2), a connecting plate (6) is inserted into the inner wall of the insertion groove, a connecting sleeve (7) is fixedly mounted on the surface of the second support column (4), and a connecting rod (8) is inserted into the inner wall of the connecting sleeve (7).
2. The construction project formwork support system of claim 1, wherein: threaded holes are formed in the lower surface of the supporting top plate (2) and the surface of the connecting sleeve (7), and threaded jackscrews are connected to the inner wall of each threaded hole in a threaded mode.
3. The construction project formwork support system of claim 1, wherein: the number of the engagement sleeves (7) is four, and the engagement sleeves (7) are circumferentially arranged on the surface of the second support column (4) at equal intervals.
CN202121024010.0U 2021-05-13 2021-05-13 Building engineering formwork support system Active CN215168384U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121024010.0U CN215168384U (en) 2021-05-13 2021-05-13 Building engineering formwork support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121024010.0U CN215168384U (en) 2021-05-13 2021-05-13 Building engineering formwork support system

Publications (1)

Publication Number Publication Date
CN215168384U true CN215168384U (en) 2021-12-14

Family

ID=79369573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121024010.0U Active CN215168384U (en) 2021-05-13 2021-05-13 Building engineering formwork support system

Country Status (1)

Country Link
CN (1) CN215168384U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115030548A (en) * 2022-05-25 2022-09-09 中国建筑第二工程局有限公司 Construction material conveying port plugging device and using method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115030548A (en) * 2022-05-25 2022-09-09 中国建筑第二工程局有限公司 Construction material conveying port plugging device and using method

Similar Documents

Publication Publication Date Title
CN215168384U (en) Building engineering formwork support system
CN112709430A (en) Template device based on BIM
CN111980222A (en) Steel construction assembled wallboard is built in room
CN113047666A (en) Limiting device is supported in installation of assembled PC wall
CN213952961U (en) Green's waterproof anticorrosive template device
CN212642117U (en) Tool type supporting device for laminated bottom plate supporting system
CN212896972U (en) Steel construction assembled wallboard is built in room
CN114197941A (en) Calculation method for inverted cone water tank all-section steel supporting template system
CN212865962U (en) Foundation pit supporting and reinforcing device
CN214658863U (en) Long inclined plane fair-faced concrete formwork support system with inclination angle larger than 45 degrees
CN210946829U (en) Regularization standard festival sectional shelf-unit
CN109667418B (en) Template platform of beam column integration installation
CN218667606U (en) Suspension steel pipe supporting leg of main pier steel hanging box
CN218991037U (en) Novel beam slab aluminum alloy template supporting structure for building construction
CN205224579U (en) Steel framework template and self -supporting truss board combination concrete quick detach system
CN211598034U (en) Interim enclosure is built with consolidating stand
CN212154215U (en) Take prefabricated wallboard bearing structure to one side of entrance to a cave
CN216516860U (en) Independent supporting base for laminated slab
CN218406476U (en) Assembled template for batter post
CN217054477U (en) Y-shaped supporting device for temporary support of prefabricated wall
CN214034840U (en) Space steel structure assembling jig frame
CN213806570U (en) Cantilever formwork for high-rise cast-in-place wall
CN217897287U (en) Constructional column template system for synchronous construction of external wall constructional column and main body
CN210976332U (en) High stability steel construction box post
CN220889645U (en) Supporting device for prefabricated shear wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant