CN215110935U - Steady pipe device of oil and gas long distance pipeline construction - Google Patents
Steady pipe device of oil and gas long distance pipeline construction Download PDFInfo
- Publication number
- CN215110935U CN215110935U CN202121611600.3U CN202121611600U CN215110935U CN 215110935 U CN215110935 U CN 215110935U CN 202121611600 U CN202121611600 U CN 202121611600U CN 215110935 U CN215110935 U CN 215110935U
- Authority
- CN
- China
- Prior art keywords
- fixed
- oil
- spacing
- backup pad
- fixing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model discloses a steady pipe device of oil and gas long-distance pipeline construction, including being used for carrying out the backup pad that supports to the pipeline, the fixed slot has all been seted up at the center of backup pad both sides, and the backup pad lower half is close to the fixed slot both sides all set up with the fixed orbit of the interior week intercommunication of fixed slot that corresponds, and the interior week of two fixed slots all is equipped with and is connected with the fixed orbit that corresponds and be used for the support's support component, the spacing groove has been seted up at the center of backup pad, and the first portion of backup pad set up two spacing tracks that are central symmetric distribution about the spacing groove, two spacing orbital interior week all communicate with the interior week of spacing groove, and the interior week of spacing groove be equipped with spacing track connection and be used for carrying out fixed hold assembly to the pipeline. This steady pipe device of oil and gas long distance pipeline construction can adjust as required, conveniently uses.
Description
Technical Field
The utility model belongs to the technical field of the pipeline construction equipment, concretely relates to steady pipe device of long-distance pipeline construction of oil and gas.
Background
Petroleum refers to a mixture of hydrocarbons in gaseous, liquid and solid states, with natural occurrence. Petroleum is classified into crude oil, natural gas liquids, natural coke oils, etc., but "petroleum" is still used as the definition of "crude oil" in a conventional manner. Petroleum is a viscous, dark brown liquid known as "industrial blood". The upper part of the crust has petroleum storage, the main component is a mixture of various alkanes, cyclanes and aromatics, and the petroleum storage is one of the main objects of geological exploration. Petroleum is used mainly as fuel and gasoline, and also as a raw material for many chemical industry products such as solutions, fertilizers, pesticides, and plastics. At present stage, oil and gas mostly passes through the long defeated pipeline and carries, because the pipeline is longer, need cooperate to use steady pipe device to support the pipeline to guarantee the stability of carrying, current oil and gas long defeated pipeline construction is surely managed the device, mostly is fixed knot to be constructed, can not adjust as required well at the in-process that uses.
Therefore, in order to meet the current situation, the design and production of the oil and gas long-distance pipeline construction pipe stabilizing device are urgently needed to meet the actual use requirement.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steady pipe device of oil and gas long distance pipeline construction to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a steady pipe device of oil and gas long-distance pipeline construction, includes the backup pad that is used for carrying out the support to the pipeline, the fixed slot has all been seted up at the center of backup pad both sides, and the backup pad lower half is close to the both sides of fixed slot and all sets up the fixed orbit that communicates with the interior week of fixed slot that corresponds, and the interior week of two fixed slots all is equipped with the support component who is connected with the fixed orbit that corresponds and is used for the support, the spacing groove has been seted up at the center of backup pad, and the first half of backup pad set up two spacing tracks that are central symmetric distribution about the spacing groove, two spacing orbital interior week all communicate with the interior week of spacing groove, and the interior week of spacing groove be equipped with spacing track connection and be used for carrying out the clamping component fixed to the pipeline.
Preferably, the support component includes extension rod, hollow seat and the spacing post of periphery and the interior week looks adaptation of hollow seat cavity, the periphery of extension rod and the interior week joggle of the fixed slot that corresponds, and the extension rod is kept away from the one end of fixed slot and is connected with the center of hollow seat side, and the peripheral joggle of the interior periphery of cavity and spacing post of hollow seat.
Preferably, the bottom integrated into one piece of extension rod has periphery and the fixed column of the interior peripheral sliding connection of fixed track, and the periphery threaded connection that the extension rod one end was kept away from to the fixed column has fixation nut.
Preferably, the side surface of the limiting column is provided with a plurality of fixing holes which are distributed at equal intervals, one side of the hollow seat close to the fixing holes is provided with a through hole, and the inner periphery of the through hole is provided with a fixing bolt in threaded connection with one of the fixing holes.
Preferably, the clamping part includes drive gear and driven pinion rack, drive gear's center integrated into one piece has the pivot, and the both ends of pivot all rotate with the spacing groove through the bearing frame and be connected, the both sides of drive gear periphery all mesh driven pinion rack, and two driven pinion racks respectively with the interior circumference sliding connection of spacing groove both sides.
Preferably, the bottom end of the rotating shaft of the driving gear penetrates through the supporting plate and is provided with a fixing plate, the bottom of the supporting plate is provided with a plurality of limiting holes which are distributed in an annular array mode by taking the rotating shaft as a center, and the inner periphery of a connecting hole formed in the fixing plate is provided with a limiting bolt in threaded connection with one limiting hole.
Preferably, the driven toothed plate is kept away from the center integrated into one piece of drive gear one end and is had the spliced pole of first half and the spacing track sliding connection who corresponds, and the splint that are in the backup pad top are installed at the top of spliced pole.
The utility model discloses a technological effect and advantage: according to the pipe stabilizing device for the construction of the petroleum and natural gas long-distance pipeline, the distance between the hollow seat and the supporting plate is adjusted by stretching the hollow seat, the fixing column is driven by the extension rod to move, the fixing nut is in threaded connection with the fixing column, and the hollow seat is stably connected with the supporting plate through the extension rod, so that the pipe stabilizing device is adjusted and fixed according to the terrain of a required use position, is suitable for different terrains and is convenient to use; the vertical distance between the support plate and the ground is adjusted by moving the support plate, so that the top of the support plate is in contact with the bottom of the pipeline, the position of a fixing hole where a fixing bolt is located is changed, the limiting column is stably connected with the hollow seat, and the limiting column and the ground at the position are inserted and buried, so that the height of the pipe is adjusted and fixed as required; through rotating the fixed plate, drive gear by the pivot and rotate, mesh with driven pinion rack through drive gear simultaneously, drive splint by the spliced pole and remove, adjust the distance between two splint, and change the position in the spacing hole that spacing bolt was located, make the distance between two splint fixed, thereby it is spacing to carry out the centre gripping to the pipeline through two splint, adapt to the pipeline of different pipe diameters, conveniently use, this steady pipe device of oil and gas long-distance pipeline construction, can adjust as required, conveniently use.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a cross-sectional view of the present invention;
fig. 3 is a schematic structural view of the support plate of the present invention when it is placed upside down.
In the figure: 1 supporting plate, 21 extension rod, 210 fixing column, 22 hollow seat, 23 spacing column, 31 driving gear, 310 fixing plate, 32 driven toothed plate, 320 connecting column and 321 clamping plate.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
In order to adjust and fix the height of the pipe according to the terrain of the required use position and the requirement, as shown in fig. 1, fig. 2 and fig. 3, fixing grooves are respectively arranged at the centers of two sides of a supporting plate 1 for supporting a pipeline (not shown in the figure), fixing rails communicated with the inner peripheries of the corresponding fixing grooves are respectively arranged at two sides of the lower half part of the supporting plate 1 close to the fixing grooves, supporting components connected with the corresponding fixing rails and used for supporting are respectively arranged at the inner peripheries of the two fixing grooves, the outer periphery of an extension rod 21 is joggled with the inner periphery of the corresponding fixing groove, one end of the extension rod 21 far away from the fixing grooves is connected with the center of the side surface of a hollow seat 22, the specific connecting modes such as fixed welding, fastener connection and the like can be selected according to the actual requirement, the inner periphery of a cavity of the hollow seat 22 is joggled with the outer periphery of a limiting column 23, a fixing column 210 with the outer periphery of the fixed rail and the inner periphery of the fixing rail in sliding connection is integrally formed at the bottom of the extension rod 21, and the periphery of the end of the fixed column 210 far away from the extension rod 21 is connected with a fixed nut by a thread, the hollow seat 22 is stretched, the distance between the hollow seat 22 and the support plate 1 is adjusted, the extension rod 21 drives the fixed column 210 to move, the fixed nut is connected with the fixed column 210 by a thread, so that the hollow seat 22 is stably connected with the support plate 1 by the extension rod 21, thereby adjusting and fixing according to the terrain of the position to be used, the side surface of the limit column 23 is provided with a plurality of fixing holes which are distributed at equal intervals, one side of the hollow seat 22 close to the fixing holes is provided with a through hole, the inner periphery of the through hole is provided with a fixing bolt in threaded connection with one of the fixing holes, the support plate 1 is moved, the vertical distance between the support plate 1 and the ground is adjusted, the top of the support plate 1 is contacted with the bottom of the pipeline, the position of the fixing hole where the fixing bolt is located is changed, so that the limit column 23 is stably connected with the hollow seat 22, thereby adjusting and fixing the height of the pipe stabilizer according to the requirement.
In order to adapt to pipelines with different pipe diameters and conveniently perform pipe stabilizing treatment, as shown in fig. 1, fig. 2 and fig. 3, an H-shaped limiting groove is formed in the center of a supporting plate 1, two limiting rails which are centrosymmetrically distributed about the limiting groove are formed in the upper half part of the supporting plate 1, the inner peripheries of the two limiting rails are communicated with the inner periphery of the limiting groove, a clamping part which is connected with the limiting rails and used for fixing the pipelines is arranged on the inner periphery of the limiting groove, a rotating shaft is integrally formed in the center of a driving gear 31, two ends of the rotating shaft are rotatably connected with the limiting groove through bearing seats, driven toothed plates 32 are meshed with two sides of the outer periphery of the driving gear 31, the two driven toothed plates 32 are respectively in sliding connection with the inner peripheries of two sides of the limiting groove, the bottom end of the rotating shaft of the driving gear 31 penetrates through the supporting plate 1 and is provided with a fixing plate 310, and the bottom of the supporting plate 1 is provided with a plurality of limiting holes which are distributed in an annular array by taking the rotating shaft as the center, and the inner periphery of the connecting hole opened on the fixing plate 310 is provided with a limiting bolt in threaded connection with one of the limiting holes, the center of one end of the driven toothed plate 32 far away from the driving gear 31 is integrally formed with a connecting column 320 of which the upper half is in sliding connection with the corresponding limiting track, the top of the connecting column 320 is provided with a clamping plate 321 positioned at the top of the supporting plate 1, the fixing plate 310 is rotated, the driving gear 31 is driven by a rotating shaft to rotate, meanwhile, the driving gear 31 is meshed with the driven toothed plate 32, the connecting column 320 drives the clamping plate 321 to move, the distance between the two clamping plates 321 is adjusted, the position of the limiting hole where the limiting bolt is positioned is changed, the distance between the two clamping plates 321 is fixed, and therefore, the pipeline is clamped and limited through the two clamping plates 321.
The working principle of the pipe stabilizing device for the construction of the petroleum and natural gas long-distance pipeline is that when the pipe stabilizing device is required to be used, the device is moved to a position required to be installed and used, the top of a supporting plate 1 is positioned below a position required to be stabilized by the pipeline, after the movement is finished, a hollow seat 22 is stretched, the distance between the hollow seat 22 and the supporting plate 1 is adjusted, a fixing column 210 is driven by an extension rod 21 to move, a fixing nut is in threaded connection with the fixing column 210, the hollow seat 22 is stably connected with the supporting plate 1 through the extension rod 21, the pipe stabilizing device is adjusted and fixed according to the terrain of the position required to be used, after the fixing is finished, a limiting column 23 and the ground at the position are inserted and buried, the supporting plate 1 is moved, the vertical distance between the supporting plate 1 and the ground is adjusted, the top of the supporting plate 1 is in contact with the bottom of the pipeline, the position of a fixing hole where the fixing bolt is positioned is changed, and the limiting column 23 and the hollow seat 22 are stably connected, thereby it is as required highly adjusted and fixed to stabilize the pipe, after fixed the completion, rotation fixed plate 310, drive gear 31 by the pivot and rotate, mesh with driven pinion rack 32 through drive gear 31 simultaneously, it removes to drive splint 321 by spliced pole 320, adjust the distance between two splint 321, and change the position in the spacing hole that spacing bolt locates, it is fixed to make the distance between two splint 321, thereby it is spacing to carry out the centre gripping through two splint 321 to the pipeline, after the spacing completion, can stabilize the pipe through backup pad 1's supporting role to the pipeline and handle.
Finally, it should be noted that: the above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention.
Claims (7)
1. The utility model provides a steady pipe device of oil and gas long-distance pipeline construction, includes backup pad (1) that is used for supporting the pipeline, its characterized in that: the fixed slot has all been seted up at the center of backup pad (1) both sides, and backup pad (1) lower half is close to the fixed slot both sides all set up with the fixed slot inner periphery intercommunication's that corresponds fixed track, and the inner periphery of two fixed slots all be equipped with the fixed track connection who corresponds and be used for the support component, the spacing groove has been seted up at the center of backup pad (1), and the first half of backup pad (1) set up two spacing tracks that are central symmetric distribution about the spacing groove, two spacing orbital inner peripheries all communicate with the inner periphery of spacing groove, and the inner periphery of spacing groove be equipped with spacing track connection and be used for carrying out the clamping component fixed to the pipeline.
2. The oil and gas long-distance pipeline construction pipe stabilizing device according to claim 1, characterized in that: the support component comprises an extension rod (21), a hollow seat (22) and a limiting column (23) which is matched with the inner periphery of a cavity of the hollow seat (22) in a peripheral mode, the outer periphery of the extension rod (21) is in joggle joint with the inner periphery of a corresponding fixing groove, one end, far away from the fixing groove, of the extension rod (21) is connected with the center of the side face of the hollow seat (22), and the inner periphery of the cavity of the hollow seat (22) is in joggle joint with the outer periphery of the limiting column (23).
3. The oil and gas long-distance pipeline construction pipe stabilizing device according to claim 2, characterized in that: the bottom integrated into one piece of extension rod (21) has fixed column (210) of periphery and the interior peripheral sliding connection of fixed track, and the periphery threaded connection that extension rod (21) one end was kept away from in fixed column (210) has fixation nut.
4. The oil and gas long-distance pipeline construction pipe stabilizing device according to claim 3, characterized in that: the side of the limiting column (23) is provided with a plurality of fixing holes which are distributed at equal intervals, one side of the hollow seat (22) close to the fixing holes is provided with a through hole, and the inner periphery of the through hole is provided with a fixing bolt in threaded connection with one of the fixing holes.
5. The oil and gas long-distance pipeline construction pipe stabilizing device according to claim 1, characterized in that: the clamping part includes drive gear (31) and driven pinion plate (32), the center integrated into one piece of drive gear (31) has the pivot, and the both ends of pivot all rotate with the spacing groove through the bearing frame and be connected, the both sides of drive gear (31) periphery all mesh driven pinion plate (32), and two driven pinion plate (32) respectively with the interior circumference sliding connection of spacing groove both sides.
6. The oil and gas long-distance pipeline construction pipe stabilizing device according to claim 5, characterized in that: the bottom of the rotating shaft of the driving gear (31) penetrates through the supporting plate (1) and is provided with a fixing plate (310), a plurality of limiting holes which are distributed in an annular array mode by taking the rotating shaft as the center are formed in the bottom of the supporting plate (1), and a limiting bolt in threaded connection with one limiting hole is arranged on the inner periphery of a connecting hole formed in the fixing plate (310).
7. The oil and gas long-distance pipeline construction pipe stabilizing device according to claim 6, characterized in that: driven pinion rack (32) keep away from center integrated into one piece of drive gear (31) one end has first portion and the connecting column (320) of the spacing track sliding connection who corresponds, and splint (321) at backup pad (1) top are installed at the top of connecting column (320).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121611600.3U CN215110935U (en) | 2021-07-15 | 2021-07-15 | Steady pipe device of oil and gas long distance pipeline construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202121611600.3U CN215110935U (en) | 2021-07-15 | 2021-07-15 | Steady pipe device of oil and gas long distance pipeline construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215110935U true CN215110935U (en) | 2021-12-10 |
Family
ID=79319899
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202121611600.3U Active CN215110935U (en) | 2021-07-15 | 2021-07-15 | Steady pipe device of oil and gas long distance pipeline construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215110935U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115267071A (en) * | 2022-07-26 | 2022-11-01 | 南京市锅炉压力容器检验研究院 | Rotary type pipeline defect detection experiment platform and operation method thereof |
-
2021
- 2021-07-15 CN CN202121611600.3U patent/CN215110935U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115267071A (en) * | 2022-07-26 | 2022-11-01 | 南京市锅炉压力容器检验研究院 | Rotary type pipeline defect detection experiment platform and operation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215110935U (en) | Steady pipe device of oil and gas long distance pipeline construction | |
CN214291737U (en) | Natural gas line welding auxiliary device | |
CN103192804B (en) | Fast battery displacement device of battery compartment of large electric vehicle | |
CN101832873B (en) | Test detection device for slender rod piece | |
CN210615300U (en) | Female cutting device of pipe | |
CN109015554B (en) | Working method of machining platform for automobile part production | |
CN113560759B (en) | Anticorrosive natural gas line lays welding auxiliary device | |
CN113578586B (en) | Simple construction pedestal for steel pipe painting and using method thereof | |
CN101813572B (en) | Test and detection device for slender rod | |
CN117047648B (en) | Steel pipe chamfering polishing machine | |
CN113352806A (en) | Teaching is with multi-functional drawing teaching aid convenient to adjust | |
CN107399197B (en) | Automobile tire changing auxiliary device | |
CN212027830U (en) | Supporting device for tunnel | |
CN209067174U (en) | Turnover wheel assembly and vertical oil pumping unit | |
CN112233592A (en) | Drilling engineering safety control information show board | |
CN213034342U (en) | Weld joint removing device | |
CN211162635U (en) | Welding device for petroleum cracking pipe | |
CN117620543B (en) | Welding device for producing wear-resistant steel pipes | |
CN209992278U (en) | Movable support frame for pressure test of mine pipeline | |
CN213871409U (en) | Open flow pipeline fixing device for oil drilling | |
CN113618687A (en) | Automobile engine spare part processingequipment | |
CN220855901U (en) | Multifunctional automobile demonstrating board | |
CN213469664U (en) | Automatic drilling and forming equipment for automobile skylight guide rail | |
CN208487275U (en) | Support device at a kind of oil exploitation oil pipe docking | |
CN221498032U (en) | Pipeline handling device for oil exploitation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |