CN215055525U CN202121017500.8U CN202121017500U CN215055525U CN 215055525 U CN215055525 U CN 215055525U CN 202121017500 U CN202121017500 U CN 202121017500U CN 215055525 U CN215055525 U CN 215055525U
Authority
CN
China
Prior art keywords
wall
guide rail
steel structure
installation
movable block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121017500.8U
Other languages
Chinese (zh)
Inventor
陈江红
余富忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Zhibang Steel Structure Manufacturing Co ltd
Zhibang Housing Industry Group Co ltd
Original Assignee
Jiangxi Zhibang Housing Industry Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Zhibang Housing Industry Group Co ltd filed Critical Jiangxi Zhibang Housing Industry Group Co ltd
Priority to CN202121017500.8U priority Critical patent/CN215055525U/en
Application granted granted Critical
Publication of CN215055525U publication Critical patent/CN215055525U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a high-rise steel construction installation school beam ware relates to architectural equipment technical field, including the guide rail and the first movable block that is used for installing the riser, the spout has been seted up to the outer wall symmetry of guide rail, one side surface bottom of riser is provided with the connecting plate that is used for connecting the installation axle, the inner wall of installation axle is provided with the installation piece that is used for installing the ink bottle, one side fixed surface of ink bottle installs the connecting pipe. The utility model discloses, through setting up first movable block at the upper surface of guide rail, first movable block realizes driving the lower surface that the installation piece is located the girder steel through slideing along the guide rail to through the cooperation angle of adjustment of connecting plate and installation axle, at this in-process, through removing the connecting rod along the spacing groove, realize driving the cotton that absorbs water and remove along the lower surface of girder steel structure, thereby realize carrying out mark processing to the lower surface of girder steel, can effectively hoisting device's practicality.

Description

High-rise steel structure installation school roof beam ware
Technical Field
The utility model relates to a construction equipment technical field, more specifically relate to a high-rise steel construction installation school roof beam ware.
Background
The steel structure is a structure formed by steel materials, is one of main building structure types, and mainly comprises steel beams, steel columns, steel trusses and other members made of section steel, steel plates and the like, and adopts rust removal and prevention processes such as silanization, pure manganese phosphating, washing drying, galvanization and the like, all the members or parts are usually connected by welding lines, bolts or rivets, and the steel structure is easy to rust due to light weight and simple and convenient to construct and widely applied to the fields of large-scale factory buildings, venues, super-high buildings and the like.
In chinese utility model patent application no: the utility model discloses an instrument support suitable for steel construction measurement correction in CN201820687861.5, the structure includes steel sheet mount and instrument mount, the steel sheet mount includes mounting and connecting piece, mounting and connecting piece body coupling, the mounting is fixed with the girder steel, the connecting piece can be dismantled with the instrument mount and be connected, the instrument mount includes the connecting plate, instrument mounting platform and receives the target, the connecting plate is all fixed with instrument mounting platform and receive the target, and the connecting plate can be dismantled with the connecting piece and be connected, instrument mounting platform passes through the backup pad and receives the relative setting of target. This instrument support suitable for steel construction measurement correction, at the in-service use in-process, what adopt is the measurement structure of easy dismouting formula, be not convenient for carry out erection joint with the girder steel structure, and degree of stability is lower, and the practicality is lower, does not possess the function of carrying out mark processing to the girder steel surface, and the adjustable range of device is narrower, and is lower to the tight degree of clamp of girder steel, and the security is relatively poor.
Therefore, it is necessary to provide a beam corrector for high-rise steel structures to solve the above problems.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model aims to provide a: in order to solve the instrument support who is applicable to steel construction measurement correction, at the in-service use in-process, what adopt is the measurement structure of easy dismouting formula, be not convenient for carry out erection joint with girder steel structure, and degree of stability is lower, and the practicality is lower, does not possess the function of carrying out mark processing to the girder steel surface, and the adjustable range of device is narrower, and is lower to the tight degree of clamp of girder steel, the relatively poor problem of security, the utility model provides a high-rise steel construction installation school beam ware.
(II) technical scheme
The utility model discloses a realize above-mentioned purpose and specifically adopt following technical scheme:
the utility model provides a high-rise steel construction installation school beam ware, includes the guide rail and is used for installing the first movable block of riser, the spout has been seted up to the outer wall symmetry of guide rail, one side surface bottom of riser is provided with the connecting plate that is used for connecting the installation axle, the inner wall of installation axle is provided with the installation piece that is used for installing the ink bottle, one side fixed surface of ink bottle installs the connecting pipe, the inside movable mounting of installation piece has the connecting rod, the installation piece is close to one side inner wall of connecting rod and has seted up the spacing groove, one side outer wall movable mounting of connecting rod has the spring, fixed surface installs the cotton that absorbs water on one side of connecting rod.
Furthermore, the outer wall top of riser is pegged graft and is had the external screw thread pole, one side outer wall fixed mounting of external screw thread pole has the handle.
Further, an inner threaded hole is formed in the outer wall of one side, close to the outer threaded rod, of the vertical plate, and a second movable block is movably mounted on the outer surface of one side of the guide rail.
Furthermore, a rotary sleeve is movably mounted on the outer wall of one side, close to the mounting block, of the external threaded rod, and a clamping plate is fixedly mounted on the outer wall of the rotary sleeve.
Further, the upper surface fixed mounting of second movable block has the electromagnetism dish, the lower surface fixed mounting of second movable block has the spirit level.
Furthermore, the power distributors are symmetrically and fixedly installed on the top of the outer wall of the level gauge, and connecting wires are fixedly installed on the upper surface of one side of each power distributor.
Further, two the connecting wire is connected with the electromagnetism dish, two distributor and connecting wire and electromagnetism dish looks adaptation.
Furthermore, a baffle is fixedly mounted on the outer wall of one side of the guide rail, and a positioning plate is fixedly mounted on the outer wall of one side of the guide rail, which is far away from the baffle.
(III) advantageous effects
The utility model has the advantages as follows:
1. the utility model discloses, through setting up first movable block at the upper surface of guide rail, first movable block realizes driving the lower surface that the installation piece is located the girder steel through slideing along the guide rail to through the cooperation angle of adjustment of connecting plate and installation axle, at this in-process, through removing the connecting rod along the spacing groove, realize driving the cotton that absorbs water and remove along the lower surface of girder steel structure, thereby realize carrying out mark processing to the lower surface of girder steel, can effectively hoisting device's practicality.
2. The utility model discloses, set up the external screw thread pole through the outer wall at the riser, in the in-service use process, rotate through holding the handle, realize driving the external screw thread pole and remove along the internal thread hole to through the cooperation of swivel mount, realize driving splint and finely tune, through the setting of corresponding each other with the locating plate, realize pressing from both sides tightly the girder steel.
3. The utility model discloses, set up the second movable block through the upper surface at the guide rail, in the in-service use process, through slideing the second movable block along the guide rail, realize driving the electromagnetic disk at the lower surface adjustment position of girder steel, through the cooperation of distributor and connecting wire, realize driving the electromagnetic disk and adsorb at the lower surface of girder steel, can effectively promote the stability degree of being connected of device and girder steel, better reinforcing the security when using.
Drawings
FIG. 1 is a schematic perspective view of the structure of the beam corrector of the present invention;
FIG. 2 is a schematic perspective view of the structure of the beam corrector of the present invention;
FIG. 3 is a schematic perspective sectional view of the mounting block structure of the present invention;
FIG. 4 is an enlarged schematic view of the structure of the area A in FIG. 1 according to the present invention;
fig. 5 is an enlarged schematic view of the structure of the area B in fig. 2 according to the present invention.
Reference numerals: 1. a guide rail; 2. a chute; 3. a first movable block; 4. a vertical plate; 5. a connecting plate; 6. installing a shaft; 7. mounting blocks; 8. an ink bottle; 9. a connecting pipe; 10. a connecting rod; 11. a limiting groove; 12. a spring; 13. absorbent cotton; 14. an externally threaded rod; 15. a handle; 16. an internally threaded bore; 17. a rotating sleeve; 18. a splint; 19. a second movable block; 20. an electromagnetic disk; 21. a level gauge; 22. a power distributor; 23. a connecting wire; 24. a baffle plate; 25. and (7) positioning the plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
Please refer to fig. 1-5, a high-rise steel structure installation beam corrector comprises a guide rail 1 and a first movable block 3 for installing a vertical plate 4, wherein the outer wall of the guide rail 1 is symmetrically provided with a chute 2, the bottom of the outer surface of one side of the vertical plate 4 is provided with a connecting plate 5 for connecting an installation shaft 6, the inner wall of the installation shaft 6 is provided with an installation block 7 for installing an ink bottle 8, the outer surface of one side of the ink bottle 8 is fixedly provided with a connecting pipe 9, the inside of the installation block 7 is movably provided with a connecting rod 10, the inner wall of one side of the installation block 7, which is close to the connecting rod 10, is provided with a limiting groove 11, the outer wall of one side of the connecting rod 10 is movably provided with a spring 12, and the surface of one side of the connecting rod 10 is fixedly provided with a water absorption cotton 13.
In this embodiment, set up first movable block 3 through the upper surface at guide rail 1, first movable block 3 is through slideing along guide rail 1, and through connecting plate 5 and installation axle 6's cooperation, realize driving the lower surface that installation piece 7 is located the girder steel, and through installation axle 6's cooperation angle of adjustment, in this process, through removing connecting rod 10 along spacing groove 11, the realization drives cotton 13 that absorbs water and removes along the lower surface of girder steel structure, and realize reseing through spring 12's effort, cotton 13 that absorbs water links to each other through the ink with in the ink bottle 8, thereby realize carrying out mark processing to the lower surface of girder steel, can effectively hoisting device's practicality.
Example 2
Referring to fig. 1-5, the present embodiment is further optimized based on embodiment 1, specifically, an external threaded rod 14 is inserted into the top of the outer wall of the vertical plate 4, and a handle 15 is fixedly mounted on the outer wall of one side of the external threaded rod 14.
Specifically, an inner threaded hole 16 is formed in the outer wall of one side of the vertical plate 4 close to the outer threaded rod 14, and a second movable block 19 is movably mounted on the outer surface of one side of the guide rail 1.
Specifically, a rotary sleeve 17 is movably mounted on the outer wall of one side of the external threaded rod 14 close to the mounting block 7, a clamping plate 18 is fixedly mounted on the outer wall of the rotary sleeve 17, and a positioning plate 25 is fixedly mounted on the outer wall of one side of the guide rail 1 far away from the baffle plate 24.
In this embodiment, through set up external screw thread pole 14 at the outer wall of riser 4, in the in-service use process, rotate through holding handle 15, realize driving external screw thread pole 14 and remove along internal thread hole 16 to through the cooperation of swivel mount 17, realize driving splint 18 and finely tune, through the setting of mutually corresponding with locating plate 25, realize pressing from both sides tightly the girder steel.
Example 3
Referring to fig. 1-5, the present embodiment is optimized based on the embodiment 1 or 2, specifically, an electromagnetic disc 20 is fixedly installed on the upper surface of the second movable block 19, and a level 21 is fixedly installed on the lower surface of the second movable block 19.
Specifically, the power distributors 22 are symmetrically and fixedly installed on the top of the outer wall of the level 21, and the connecting wires 23 are fixedly installed on the upper surface of one side of each of the two power distributors 22.
Specifically, two connecting wires 23 are connected to the electromagnetic panel 20, and two power distributors 22 and the connecting wires 23 are adapted to the electromagnetic panel 20.
Specifically, a baffle 24 is fixedly installed on the outer wall of one side of the guide rail 1, and a positioning plate 25 is fixedly installed on the outer wall of one side of the guide rail 1 far away from the baffle 24.
In this embodiment, set up second movable block 19 through the upper surface at guide rail 1, in the in-service use process, through sliding second movable block 19 along guide rail 1, realize driving electromagnetic disc 20 at the lower surface adjustment position of girder steel, through the cooperation of distributor 22 and connecting wire 23, realize driving electromagnetic disc 20 and adsorb the lower surface at the girder steel, can effectively promote the stability of being connected of device and girder steel, better reinforcing the security when using.
In summary, the following steps: in the utility model, in the actual use process, firstly, the device is placed in a specific steel structure installation operation area through the matching of the guide rail 1, when the steel beam is calibrated, the top of the inner wall of the positioning plate 25 is firstly attached to the outer wall of one side of the steel beam, and the relative position of the second movable block 19 is adjusted, so that the electromagnetic disc 20 corresponds to the middle part of the lower surface of the steel beam, in the process, the handle 15 is held to rotate, the external threaded rod 14 is driven to move along the internal threaded hole 16, the clamping plate 18 is driven to be finely adjusted through the matching of the rotary sleeve 17, the clamping of the steel beam is realized through the mutual corresponding arrangement of the positioning plate 25, the position of the steel beam is calibrated by the starting level gauge 21, the electromagnetic disc 20 is driven to be adsorbed on the lower surface of the steel beam through the matching of the distributor 22 and the connecting wire 23, the connection stability degree of the device and the steel beam can be effectively improved, better reinforcing the security when using, meanwhile, first movable block 3 is through slideing along guide rail 1, and the cooperation through connecting plate 5 and installation axle 6, realize driving the lower surface that installation piece 7 is located the girder steel, and the cooperation angle of adjustment through installation axle 6, at this in-process, through removing connecting rod 10 along spacing groove 11, the realization drives cotton 13 that absorbs water and removes along the lower surface of girder steel structure, and the effort through spring 12 realizes reseing, cotton 13 that absorbs water links to each other through the ink with in the ink bottle 8, thereby the realization is carried out marking to the lower surface of girder steel, can effectively hoisting device's practicality, be suitable for popularization.
Above, only be the preferred embodiment of the present invention, not be used for limiting the present invention, the patent protection scope of the present invention is based on the claims, all the structural changes equivalent to the content of the description and drawings of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. The utility model provides a high-rise steel construction installation school beam ware, includes guide rail (1) and first movable block (3) that are used for installing riser (4), its characterized in that: spout (2) have been seted up to the outer wall symmetry of guide rail (1), one side surface bottom of riser (4) is provided with connecting plate (5) that are used for connecting installation axle (6), the inner wall of installation axle (6) is provided with installation piece (7) that are used for installing ink bottle (8), one side surface fixed mounting of ink bottle (8) has connecting pipe (9), the inside movable mounting of installation piece (7) has connecting rod (10), spacing groove (11) have been seted up to one side inner wall that installation piece (7) are close to connecting rod (10), one side outer wall movable mounting of connecting rod (10) has spring (12), fixed surface installs cotton (13) that absorbs water on one side of connecting rod (10).
2. The high-rise steel structure installation beam corrector of claim 1, wherein: the top of the outer wall of the vertical plate (4) is inserted with an external thread rod (14), and the outer wall of one side of the external thread rod (14) is fixedly provided with a handle (15).
3. The high-rise steel structure installation beam corrector of claim 1, wherein: internal thread hole (16) have been seted up to one side outer wall that riser (4) are close to external screw thread pole (14), one side surface movable mounting of guide rail (1) has second movable block (19).
4. The high-rise steel structure installation beam corrector of claim 2, wherein: the outer screw rod (14) is close to one side outer wall movable mounting of installation piece (7) has swivel sleeve (17), the outer wall fixed mounting of swivel sleeve (17) has splint (18).
5. The high-rise steel structure installation beam corrector of claim 3, wherein: the upper surface fixed mounting of second movable block (19) has electromagnetism dish (20), the lower surface fixed mounting of second movable block (19) has spirit level (21).
6. The high-rise steel structure installation beam corrector of claim 5, wherein: the level gauge is characterized in that power distributors (22) are symmetrically and fixedly mounted at the top of the outer wall of the level gauge (21), and connecting wires (23) are fixedly mounted on the upper surface of one side of each power distributor (22).
7. The high-rise steel structure installation beam corrector of claim 6, wherein: the two connecting wires (23) are connected with the electromagnetic disc (20), and the two power distributors (22) and the connecting wires (23) are matched with the electromagnetic disc (20).
8. The high-rise steel structure installation beam corrector of claim 1, wherein: one side outer wall fixed mounting of guide rail (1) has baffle (24), one side outer wall fixed mounting that baffle (24) were kept away from in guide rail (1) has locating plate (25).
CN202121017500.8U 2021-05-13 2021-05-13 High-rise steel structure installation school roof beam ware Active CN215055525U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121017500.8U CN215055525U (en) 2021-05-13 2021-05-13 High-rise steel structure installation school roof beam ware

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121017500.8U CN215055525U (en) 2021-05-13 2021-05-13 High-rise steel structure installation school roof beam ware

Publications (1)

Publication Number Publication Date
CN215055525U true CN215055525U (en) 2021-12-07

Family

ID=79216704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121017500.8U Active CN215055525U (en) 2021-05-13 2021-05-13 High-rise steel structure installation school roof beam ware

Country Status (1)

Country Link
CN (1) CN215055525U (en)

Similar Documents

Publication Publication Date Title
CN215055525U (en) High-rise steel structure installation school roof beam ware
CN214091150U (en) Auxiliary supporting structure for mounting steel structure column
CN112978589B (en) Tower crane attachment fixing device
CN105180985B (en) A kind of ultrasonic sensor erecting device
CN106758663A (en) Buried rubber fastening band installs positioning construction method in one kind
CN109138001A (en) A kind of assembled architecture support base in architectural engineering
CN214470776U (en) Board inclination measuring device for constructional engineering
CN103953183A (en) Wall ceramic tile fixing tool
CN212986415U (en) Fixing support for pipeline installation
CN210685332U (en) Spraying device convenient to install on climbing frame
CN220934805U (en) Cable hook for secondary structure construction
CN208681533U (en) A kind of building keel installation auxiliary device
CN203783095U (en) Wall body tile sticking tool
CN206809562U (en) A kind of repeatable life line bracket utilized
CN208072547U (en) A kind of platform basin universal adjustment installation tool
CN206873823U (en) A kind of fixing device of installation unit formula panel
CN218072144U (en) Outdoor environment online data centralized control case
CN221741380U (en) Foundation pile fixing device for building engineering detection
CN220414811U (en) Decoration hanging basket for exterior wall decoration
CN205037908U (en) Ultrasonic sensor installation device
CN214771656U (en) Device convenient to box girder installation location
CN220668602U (en) PE water pipe fixing device
CN221143041U (en) Connecting assembly for assembled steel structure
CN219213026U (en) Building roof expansion bolt mounting tool
CN219196585U (en) Aluminum veneer dry-hanging structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: No. 1999 Binhu Avenue, High tech Industrial Park, Jinxian County Economic Development Zone, Nanchang City, Jiangxi Province, 331700

Patentee after: Zhibang Housing Industry Group Co.,Ltd.

Country or region after: China

Address before: 331721 No.48, Qianjin Road, Wenzhen Town, Jinxian County, Nanchang City, Jiangxi Province

Patentee before: Jiangxi Zhibang Housing Industry Group Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address
TR01 Transfer of patent right

Effective date of registration: 20240227

Address after: 2nd Floor, Comprehensive Building, No. 1999 Binhu Avenue, High tech Industrial Park, Jinxian County Economic Development Zone, Nanchang City, Jiangxi Province, 331700

Patentee after: Jiangxi Zhibang Steel Structure Manufacturing Co.,Ltd.

Country or region after: China

Address before: No. 1999 Binhu Avenue, High tech Industrial Park, Jinxian County Economic Development Zone, Nanchang City, Jiangxi Province, 331700

Patentee before: Zhibang Housing Industry Group Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right