CN215055178U - Steel construction high altitude welding operation platform - Google Patents
Steel construction high altitude welding operation platform Download PDFInfo
- Publication number
- CN215055178U CN215055178U CN202120710947.7U CN202120710947U CN215055178U CN 215055178 U CN215055178 U CN 215055178U CN 202120710947 U CN202120710947 U CN 202120710947U CN 215055178 U CN215055178 U CN 215055178U
- Authority
- CN
- China
- Prior art keywords
- plate
- plate body
- operation platform
- welding operation
- frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Ladders (AREA)
Abstract
The utility model relates to an operation platform field specifically is a steel construction high altitude welding operation platform. Through the frame plate that sets up and assorted auxiliary structure, can provide better four sides plate body structure, the connection between each plate body structure is stable, the condition of structural damage can not appear to conveniently install and dismantle, avoid the installation to dismantle required step more and cause the progress slow. Overall structure restricts through the limit post, and the ladder frame is seted up at the top and is assisted fixedly, provides and carries out spacing structure with both sides about to the frame plate, and stability is higher, and each sideboard all restricts the limit post in addition, and the limit post restricts the sideboard simultaneously, has reduced the impact that the limit post received alone, has disperseed the impact force when single structure receives the impact, has further improved holistic stability, possesses certain beneficial effect.
Description
Technical Field
The utility model relates to an operation platform field specifically is a steel construction high altitude welding operation platform.
Background
The aerial work platform is a movable aerial work product for serving aerial work, equipment installation, maintenance and the like in various industries.
Different aerial working platforms have different fixed and elevation structure, and aerial working platform is simple plate body structure usually, and its structure has certain problem when practical application:
the structure of current high altitude welding operation platform is the structure of four sides plate body and bottom plate joint usually, and the handrail structure is not installed at its top, can't provide supplementary stress point when the operation to the connection between each plate body of current high altitude welding operation platform's four sides plate body is stable inadequately, the condition of damage appears easily.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a steel construction high altitude welding operation platform to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a steel construction high altitude welding operation platform, includes the bottom plate, its characterized in that: each corner of bottom plate upper surface has the side post through welded mode fixed mounting, the upper surface of bottom plate has the frame plate through the side post joint, the inboard upside that is located the frame plate of side post has seted up the ladder frame, the sideboard has all been welded to the upper and lower both sides of ladder frame.
Preferably, the frame plate includes plate body, rail groove, fixed plate, fixed slot, joint structure, and the plate body upper end is provided with the rail groove, plate body left side fixed connection fixed plate, the inside fixed slot that is provided with in plate body right side, the inside joint structure that is provided with in plate body right side, the joint structure runs through the plate body and extends to the fixed slot, and the fixed plate corresponds the joint structure and is provided with the joint groove.
Preferably, the joint structure includes activity chamber, spring, push pedal, fixture block, connecting rod, draws the piece, and the activity chamber is located the plate body, and activity intracavity portion is provided with the spring, spring bottom fixed connection push pedal, push pedal bottom fixed connection fixture block, and in the fixture block ran through the plate body and extended the box fixed slot, fixture block bottom right side set up to the inclined plane, push pedal right side upper end fixed connection connecting rod, and the plate body is run through and extend to the outside to the connecting rod upper end fixed connection draws the piece.
Preferably, limiting plates are welded at the two ends of each side plate, limiting notches penetrating through the top of each side column to the inside are formed in the top of each side column, and the limiting notches are matched with the limiting plates.
Preferably, the both sides of the limit notch of the side column are also provided with clamping grooves matched with the side plates, and the depth of the limit notch and the clamping grooves is matched with the length of the ladder frame.
Preferably, the bottom plate, the side columns and the frame plate are all made of stainless steel materials, and the ladder frame and the side plates are made of hard plastics.
Compared with the prior art, the beneficial effects of the utility model are that:
1. through the frame plate that sets up and assorted auxiliary structure, can provide better four sides plate body structure, the connection between each plate body structure is stable, the condition of structural damage can not appear to conveniently install and dismantle, avoid the installation to dismantle required step more and cause the progress slow.
2. Overall structure restricts through the limit post, and the ladder frame is seted up at the top and is assisted fixedly, provides and carries out spacing structure with both sides about to the frame plate, and stability is higher, and each sideboard all restricts the limit post in addition, and the limit post restricts the sideboard simultaneously, has reduced the impact that the limit post received alone, has disperseed the impact force when single structure receives the impact, has further improved holistic stability, possesses certain beneficial effect.
Drawings
Fig. 1 is a front view of the present invention;
fig. 2 is a top view of the present invention;
FIG. 3 is a front sectional view of the shelf of the present invention;
fig. 4 is a top sectional view of the frame plate of the present invention;
FIG. 5 is a schematic view of the clamping structure of the present invention;
fig. 6 is a schematic view of the ladder frame structure of the present invention.
In the figure: the device comprises a bottom plate 10, a frame plate 11, bolts 12, side columns 13, a frame ladder 14, side plates 15, a limiting plate 16, a plate body 111, a rail groove 112, a fixing plate 113, a fixing groove 114, a clamping structure 115, a movable cavity 1151, a spring 1152, a push plate 1153, a clamping block 1154, a connecting rod 1155 and a pull block 1156.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 6, the present invention provides a technical solution: the utility model provides a steel construction high altitude welding operation platform, includes bottom plate 10, its characterized in that: each corner of bottom plate 10 upper surface has side column 13 through welded mode fixed mounting, and the upper surface of bottom plate 10 has frame plate 11 through the side column joint, and ladder frame 14 has been seted up to the inboard upside that is located frame plate 11 of side column 13, and sideboard 15 has all been welded to the upper and lower both sides of ladder frame 14.
Limiting plates 16 are welded at two ends of the side plate 15, limiting notches penetrating to the inside are formed in the top of the side column 13, the limiting notches are matched with the limiting plates 16, and the limiting plates 16 are convenient for fixing the side column 13.
The both sides of the limit notch of the side column 13 are also provided with clamping grooves matched with the side plates 15, and the depth of the limit notch and the clamping grooves is matched with the length of the ladder frame 14.
The bottom plate 10, the side columns 13 and the frame plate 11 are made of stainless steel materials, the ladder frame 14 and the side plates 15 are made of hard plastics, the limiting plates 16 at the top are limited by the side columns 13, the rail grooves 111 and the side plates 15 limit the frame plate 11, and overall stability is further enhanced.
The working principle is as follows:
during the use, at first, aim at fixed slot 114 in another frame plate 11 with the left fixed plate 113 of one frame plate 11 and push in, after fixed block 113 got into fixed slot 114, through the friction with the inclined plane of fixture block 1154 right side, make fixture block 1154 get back to in the activity chamber 1151, after fixed block 113 got into fixed slot 114 completely, spring 1152 promoted fixture block 1154 and removed, fixture block 1154 card goes into the joint inslot, go into the inboard of side column 13 with a plurality of frame plates 11 card, then install each ladder frame 14 at the top of frame plate 11, side plate 15 card goes into rail groove 111 and goes into the inboard of side column 13 with each limiting plate 16 card, fix through bolt 12, accomplish the installation, when certain structure received the impact, can form the restriction through riveted structure and corresponding bolt 12, disperse the impact that whole received, reduce the damage.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a steel construction high altitude welding operation platform, includes bottom plate (10), its characterized in that: each corner of bottom plate (10) upper surface has side post (13) through welded mode fixed mounting, the upper surface of bottom plate (10) has frame plate (11) through the side post joint, ladder frame (14) have been seted up to the upside that the inboard of side post (13) is located frame plate (11), sideboard (15) have all been welded to the upper and lower both sides of ladder frame (14).
2. The steel structure high-altitude welding operation platform as claimed in claim 1, wherein: frame plate (11) are including plate body (111), rail groove (112), fixed plate (113), fixed slot (114), joint structure (115), plate body (111) upper end is provided with rail groove (112), plate body (111) left side fixed connection fixed plate (113), plate body (111) right side inside is provided with fixed slot (114), plate body (111) right side inside is provided with joint structure (115), joint structure (115) run through plate body (111) and extend to in fixed slot (114), fixed plate (113) correspond joint structure (115) and are provided with the joint groove.
3. The steel structure high-altitude welding operation platform as claimed in claim 2, wherein: clamping structure (115) is including activity chamber (1151), spring (1152), push pedal (1153), fixture block (1154), connecting rod (1155), draw piece (1156), activity chamber (1151) is located plate body (111), activity chamber (1151) is inside to be provided with spring (1152), spring (1152) bottom fixed connection push pedal (1153), push pedal (1153) bottom fixed connection fixture block (1154), fixture block (1154) runs through plate body (111) and extends in box fixed slot (114), fixture block (1154) bottom right side sets up to the inclined plane, push pedal (1153) right side upper end fixed connection connecting rod (1155), connecting rod (1155) upper end runs through plate body (111) and extends to the outside, connecting rod (1155) upper end fixed connection draws piece (1156).
4. The steel structure high-altitude welding operation platform as claimed in claim 1, wherein: limiting plates (16) are welded at two ends of the side plates (15), limiting notches penetrating to the inside are formed in the tops of the side columns (13), and the limiting notches are matched with the limiting plates (16).
5. The steel structure high altitude welding operation platform of claim 4, characterized in that: the limiting notch of the side column (13) is provided with clamping grooves matched with the side plates (15) on two sides, and the depth of the limiting notch and the clamping grooves is matched with the length of the ladder frame (14).
6. The steel structure high-altitude welding operation platform as claimed in claim 1, wherein: the bottom plate (10), the side columns (13) and the frame plate (11) are all made of stainless steel materials, and the ladder frame (14) and the side plate (15) are made of hard plastics.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120710947.7U CN215055178U (en) | 2021-04-07 | 2021-04-07 | Steel construction high altitude welding operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120710947.7U CN215055178U (en) | 2021-04-07 | 2021-04-07 | Steel construction high altitude welding operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN215055178U true CN215055178U (en) | 2021-12-07 |
Family
ID=79150785
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120710947.7U Active CN215055178U (en) | 2021-04-07 | 2021-04-07 | Steel construction high altitude welding operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN215055178U (en) |
-
2021
- 2021-04-07 CN CN202120710947.7U patent/CN215055178U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN215055178U (en) | Steel construction high altitude welding operation platform | |
CN216272988U (en) | ARJ21 airplane tail cabin approaching platform | |
CN214169488U (en) | Assembled steel construction factory building support frame | |
CN214393864U (en) | Dedicated mechanical clamping device of hauler production | |
CN211058302U (en) | High-efficiency climbing formwork steel frame | |
CN211080774U (en) | Energy-saving damping steel structure | |
CN204703741U (en) | Ladder stand | |
CN209872065U (en) | Knapsack frame structure of steel band ladder | |
CN113968559A (en) | ARJ21 airplane tail cabin approaching platform | |
CN109278957B (en) | Intelligent broadside supporting device | |
CN205290306U (en) | Track traffic rolling stock's no inserted sheet wheel pair decomposes pressure equipment machine | |
CN212682849U (en) | Special supporter of laser cutting machine | |
CN215737529U (en) | Foldable display device for information technology classroom | |
CN214246250U (en) | Multi-groove embedded building curtain wall mounting structure | |
CN215814660U (en) | Integrated practical training rack | |
CN210183256U (en) | Fixing structure under solar panel | |
CN216505691U (en) | Chassis base structure of computer panel saw | |
CN211141309U (en) | Base convenient to fixed hoisting equipment | |
CN211342658U (en) | Protective net fixed connection spare | |
CN215979156U (en) | Foundation pit safety ladder | |
CN211919030U (en) | Frame section bar for mooring integrated box and connecting piece thereof | |
CN217683957U (en) | Frame roof beam bearing structure | |
CN216839086U (en) | Noise control partition wall of convenient combination | |
CN216788260U (en) | Electric power overhauls cat ladder | |
CN219905170U (en) | Print separating device for protecting heavy mobile print collection |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |