CN214996660U - Municipal works road is construction in short term with enclosing fender - Google Patents

Municipal works road is construction in short term with enclosing fender Download PDF

Info

Publication number
CN214996660U
CN214996660U CN202120504080.XU CN202120504080U CN214996660U CN 214996660 U CN214996660 U CN 214996660U CN 202120504080 U CN202120504080 U CN 202120504080U CN 214996660 U CN214996660 U CN 214996660U
Authority
CN
China
Prior art keywords
plate
threaded rod
short
wall
riser
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120504080.XU
Other languages
Chinese (zh)
Inventor
张文杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Guangsheng Group Co ltd
Original Assignee
Zhejiang Guangsheng Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Guangsheng Group Co ltd filed Critical Zhejiang Guangsheng Group Co ltd
Priority to CN202120504080.XU priority Critical patent/CN214996660U/en
Application granted granted Critical
Publication of CN214996660U publication Critical patent/CN214996660U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a municipal works road short-term construction is with enclosing fender, including the riser, adjustment mechanism is installed at the top of riser, adjustment mechanism includes swash plate, spout, plectane, set-square, first threaded rod and handle, the bottom of swash plate is rotated with the top of riser and is linked to each other, the right side processing of swash plate has the spout, the inner wall top of spout and the outer wall slip joint of plectane. Through the angle rotation of adjustment mechanism control swash plate, the top protection of enclosing the fender has been realized, the grit has been prevented to collapse out, it is injured to have avoided the pedestrian, the security has been improved, control the straight-bar through the joint mechanism and control and remove, two center reinforcement connections of enclosing the fender have been realized, the gap production has been prevented, it is not hard up to have avoided, normal use has been ensured, through supporting mechanism, the cooperation of flange and bolt, the dismantlement of bracing piece has been realized, can repetitious usage, the waste is avoided, the cost is reduced, the practicability is improved, and the promotion is convenient.

Description

Municipal works road is construction in short term with enclosing fender
Technical Field
The utility model relates to a short-term construction of municipal works road is with enclosing fender technical field specifically is a short-term construction of municipal works road is with enclosing fender.
Background
The enclosure means measures taken to isolate a construction site from the external environment and make the construction site a relatively closed space, and includes enclosures built by various masonry materials, maintenance bodies formed by various formed plates, and the like.
For example, a municipal works road short-term construction of patent number "201920324902.9" is with enclosing fender includes the steel-pipe column, the bottom plate, artificial turf, couple and crossbeam engineering time are short, the dismouting is fast, be difficult for being damaged, the later maintenance is simple and convenient, current municipal works road short-term construction is with enclosing fender top and not protecting, construction equipment collapses out the grit at the top easily, hit the pedestrian of passing by in the middle of pounding, the security has been reduced, and two enclose to keep off the connection, the middle gap that produces easily for a long time, cause to connect not hard up, influence normal use, bracing piece and enclosing fender fixed connection simultaneously, can only use once, it is comparatively extravagant, the cost is improved, the practicality is reduced, be not conform to modern's user demand.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a sampling device for gas chromatography-mass spectrometer to it does not have the protection with enclosing the fender top to propose current short-term construction of municipal works road in the above-mentioned background art to solve, and construction equipment collapses out the grit at the top easily, pounces the past pedestrian in, has reduced the problem of security.
In order to achieve the above object, the utility model provides a following technical scheme: a fence for short-term construction of municipal engineering roads comprises a vertical plate, wherein the top of the vertical plate is provided with an adjusting mechanism;
the adjusting mechanism comprises an inclined plate, a chute, a circular plate, a triangular plate, a first threaded rod and a handle;
the bottom of swash plate rotates with the top of riser and links to each other, the right side processing of swash plate has the spout, the inner wall top of spout and the outer wall slip joint of plectane, the front of plectane rotates with the top of set-square and links to each other, the bottom of set-square rotates with the top of first threaded rod and links to each other, the bottom of first threaded rod and the top looks rigid coupling of handle. The angle of the inclined plate is adjusted to meet the construction requirements.
Preferably, the top left side rigid coupling of riser has the arc board, the right side top rigid coupling of riser has straight board, the inner wall of straight board and the outer wall threaded connection of first threaded rod. The first threaded rod rotates up and down through the straight plate.
Preferably, the sliding groove and the circular plate form a sliding mechanism. The circular plate is stressed to slide up and down through the inner wall of the sliding chute.
Preferably, the right side of the vertical plate is provided with a clamping mechanism;
the clamping mechanism comprises a square frame, a second threaded rod, a round ball, a sleeve plate and a straight rod;
the left side of square frame and the right side looks rigid coupling of riser, the right side of square frame links to each other with the outer wall right side activity of second threaded rod, the left side of second threaded rod rotates with the right side of riser and links to each other, the right side of second threaded rod and the left side looks rigid coupling of ball, the outer wall of second threaded rod and the inner wall threaded connection of lagging, the upper and lower both sides of lagging laminate with the upper and lower both sides of the inner wall of square frame respectively mutually, the upper and lower both sides in front of lagging respectively with the right side looks rigid coupling of straight-bar. The two risers are clamped together.
Preferably, the second threaded rod and the sleeve plate form a translation mechanism. The sleeve plate is stressed to move left and right through the outer wall of the second threaded rod.
Preferably, a convex plate is attached to the lower portion of the right side of the vertical plate, the upper side and the lower side of the convex plate are respectively in threaded connection with the lower portion of the right side of the vertical plate through bolts, and a supporting mechanism is mounted on the front surface of the convex plate;
the supporting mechanism comprises a long plate, a short plate, a press pin and a concave plate;
the top of the long plate is rotatably connected with the front face of the convex plate, the bottom of the long plate is rotatably connected with the left side of the short plate, the inner wall of the short plate is inserted with the outer wall of the press nail, and the top of the press nail is fixedly connected with the bottom of the concave plate. The supporting risers remain vertical.
Preferably, a round rod is fixedly connected to the lower portion of the front face of the vertical plate. And other enclosing barriers are convenient to connect.
Preferably, the bottom of the vertical plate is fixedly connected with a base. The base supports the whole stable work.
Compared with the prior art, the beneficial effects of the utility model are that: this municipal works road construction for a short time is with enclosing the angle that keeps off through adjustment mechanism control swash plate and rotate, has realized enclosing the top protection of keeping off, has prevented that the grit from collapsing out, has avoided pedestrian's injury, has improved the security.
The straight rod is controlled to move left and right through the clamping mechanism, so that the central reinforced connection of the two enclosing baffles is realized, the gap is prevented from being generated, the looseness is avoided, and the normal use is ensured.
Through the cooperation of supporting mechanism, flange and bolt, realized the dismantlement of bracing piece, can repetitious usage, avoided extravagant, the cost is reduced has improved the practicality, the facilitate promotion.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the connection structure of the inclined plate, the chute and the circular plate in FIG. 1;
FIG. 3 is a schematic view of the connection between the square frame, the second threaded rod and the round ball in FIG. 1;
fig. 4 is a schematic view showing a connection relationship between the long plate, the short plate and the snap pin in fig. 1.
In the figure: 1. the vertical plate, 2, the adjustment mechanism, 201, the swash plate, 202, the spout, 203, the plectane, 204, the set square, 205, first threaded rod, 206, the handle, 3, latch mechanism, 301, square frame, 302, the second threaded rod, 303, the ball, 304, the lagging, 305, the straight-bar, 4, supporting mechanism, 401, the long slab, 402, the short slab, 403, press the nail, 404, the concave plate, 5, the arc board, 6, the straight board, 7, the round bar, 8, the base, 9, the convex plate, 10, the bolt.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a fence for short-term construction of municipal engineering roads comprises a vertical plate 1, an adjusting mechanism 2 is arranged at the top of the vertical plate 1, the adjusting mechanism 2 comprises an inclined plate 201, a chute 202 and a circular plate 203, set-square 204, first threaded rod 205 and handle 206, the bottom of swash plate 201 rotates with the top of riser 1 and links to each other, the swash plate 201 atress rotates through the round pin axle at riser 1 top, spout 202 has been processed on the right side of swash plate 201, the outer wall slip joint of inner wall top and plectane 203 of spout 202, the front of plectane 203 rotates with the top of set-square 204 and links to each other, set-square 204 atress rotates through the round pin axle that plectane 203 is positive, the bottom of set-square 204 rotates with the top of first threaded rod 205 and links to each other, first threaded rod 205 atress rotates through the round pin axle of set-square 204 bottom, the bottom of first threaded rod 205 and the top of handle 206 looks rigid coupling, handle 206 is convenient for rotate first threaded rod 205.
An arc plate 5 is fixedly connected to the left side of the top of a vertical plate 1, a straight plate 6 is fixedly connected to the upper portion of the right side of the vertical plate 1, the inner wall of the straight plate 6 is in threaded connection with the outer wall of a first threaded rod 205, a sliding mechanism is formed by a sliding groove 202 and a circular plate 203, the circular plate 203 is stressed to slide left and right through the inner wall of the sliding groove 202, a clamping mechanism 3 is installed on the right side of the vertical plate 1, the clamping mechanism 3 comprises a square frame 301, a second threaded rod 302, a ball 303, a sleeve plate 304 and a straight rod 305, the left side of the square frame 301 is fixedly connected with the right side of the vertical plate 1, the right side of the square frame 301 is movably connected with the right side of the outer wall of the second threaded rod 302, the left side of the second threaded rod 302 is rotatably connected with the right side of the vertical plate 1, the second threaded rod 302 is stressed to rotate through a bearing on the right side of the vertical plate 1, the right side of the second threaded rod 302 is fixedly connected with the left side of the ball 303, the ball 303 is convenient for rotating the second threaded rod 302, the outer wall of the second threaded rod 302 is in threaded connection with the inner wall of the sleeve plate 304, the upper side and the lower side of the sleeve plate 304 are respectively attached to the upper side and the lower side of the inner wall of the square frame 301, the sleeve plate 304 is stressed to slide left and right through the inner wall of the square frame 301, the upper side and the lower side of the front surface of the sleeve plate 304 are respectively fixedly connected with the right side of the straight rod 305, the second threaded rod 302 and the sleeve plate 304 form a translation mechanism, the sleeve plate 304 is stressed to move left and right through the outer wall of the second threaded rod 302, the convex plate 9 is attached to the lower side of the right side of the vertical plate 1, the upper side and the lower side of the convex plate 9 are respectively connected with the lower side of the right side of the vertical plate 1 through bolts 10, the front surface of the convex plate 9 is provided with a support mechanism 4, the support mechanism 4 comprises a long plate 401, a short plate 402, a press nail 403 and a concave plate 404, the top of the long plate 401 is rotationally connected with the front surface of the convex plate 9, the long plate 401 is stressed to rotate through a pin shaft on the front surface of the convex plate 9, the bottom of the long plate 401 is rotationally connected with the left side of the short plate 402, the short plate 402 is stressed to rotate through a pin shaft on the bottom of the long plate 401, the inner wall of the short plate 402 is inserted with the outer wall of the press nail 403, the top of the press nail 403 is fixedly connected with the bottom of the concave plate 404, the round rod 7 is fixedly connected below the front face of the vertical plate 1, and the base 8 is fixedly connected with the bottom of the vertical plate 1.
In this example, when the fence is used, the vertical plate 1 is moved to a designated position, then the bottom 8 is in stable contact with the ground, then the convex plate 9 is attached to the lower part of the right side of the vertical plate 1, the two are stably connected by the bolt 10, then the long plate 401 is rotated downwards, the bottom of the short plate 402 is attached to the ground, the press nail 403 penetrates through the short plate 402 and is inserted into the ground, so that the short plate 402 is stably connected with the ground, then the upper handle 206 is rotated to drive the first threaded rod 205 to rotate upwards, the triangular plate 204 is driven to move upwards, so that the circular plate 203 slides upwards on the inner wall of the sliding groove 202, the inclined plate 201 is driven to rotate upwards, when the rotation angle of the inclined plate 201 meets the requirement, the handle 206 is stopped to rotate, then the rear end face of the other vertical plate 1 is inserted into the round rod 7, the two vertical plates 1 are combined, then the round ball 303 is rotated to drive the second threaded rod 302 to rotate, thereby make the lagging 304 slide to the left side at the inner wall of square frame 301, gliding lagging 304 drives two straight-bars 305 and moves to the left side, and then injects the right side of second riser 1 inside to it is stable to make two riser 1 connect, then carries out a plurality of riser 1 concatenations according to above-mentioned method and can accomplish and enclose the fender installation.
In the description of the present invention, it is to be understood that the terms "coaxial", "bottom", "one end", "top", "middle", "other end", "upper", "one side", "top", "inner", "front", "center", "both ends", and the like, indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "disposed," "connected," "fixed," "screwed" and the like are to be construed broadly, e.g., as meaning fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through an intermediate medium, and may be connected through the inside of two elements or in an interaction relationship between two elements, unless otherwise specifically defined, and the specific meaning of the above terms in the present invention will be understood by those skilled in the art according to specific situations.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides a municipal works road is short-term construction with enclosing fender, includes riser (1), its characterized in that: the top of the vertical plate (1) is provided with an adjusting mechanism (2);
the adjusting mechanism (2) comprises a sloping plate (201), a sliding groove (202), a circular plate (203), a triangular plate (204), a first threaded rod (205) and a handle (206);
the bottom of swash plate (201) rotates with the top of riser (1) and links to each other, the right side processing of swash plate (201) has spout (202), the inner wall top of spout (202) and the outer wall slip joint of plectane (203), the front of plectane (203) rotates with the top of set-square (204) and links to each other, the bottom of set-square (204) rotates with the top of first threaded rod (205) and links to each other, the bottom of first threaded rod (205) and the top looks rigid coupling of handle (206).
2. The fence according to claim 1, wherein the fence is used for short-term construction of municipal engineering roads and is characterized in that: the top left side rigid coupling of riser (1) has arc board (5), the right side top rigid coupling of riser (1) has straight board (6), the inner wall of straight board (6) and the outer wall threaded connection of first threaded rod (205).
3. The fence according to claim 1, wherein the fence is used for short-term construction of municipal engineering roads and is characterized in that: the sliding groove (202) and the circular plate (203) form a sliding mechanism.
4. The fence according to claim 1, wherein the fence is used for short-term construction of municipal engineering roads and is characterized in that: a clamping mechanism (3) is arranged on the right side of the vertical plate (1);
the clamping mechanism (3) comprises a square frame (301), a second threaded rod (302), a round ball (303), a sleeve plate (304) and a straight rod (305);
the left side of side frame (301) and the right side looks rigid coupling of riser (1), the right side of side frame (301) links to each other with the outer wall right side activity of second threaded rod (302), the left side of second threaded rod (302) rotates with the right side of riser (1) and links to each other, the right side of second threaded rod (302) and the left side looks rigid coupling of ball (303), the outer wall of second threaded rod (302) and the inner wall threaded connection of lagging (304), the upper and lower both sides of lagging (304) laminate with the upper and lower both sides of the inner wall of side frame (301) respectively, the upper and lower both sides in front of lagging (304) respectively with the right side looks rigid coupling of straight-bar (305).
5. The fence for the short-term construction of municipal engineering roads according to claim 4, wherein: the second threaded rod (302) and the sleeve plate (304) form a translation mechanism.
6. The fence according to claim 1, wherein the fence is used for short-term construction of municipal engineering roads and is characterized in that: a convex plate (9) is attached to the lower portion of the right side of the vertical plate (1), the upper side and the lower side of the convex plate (9) are respectively connected with the lower portion of the right side of the vertical plate (1) through bolts (10) in a threaded manner, and a supporting mechanism (4) is installed on the front surface of the convex plate (9);
the supporting mechanism (4) comprises a long plate (401), a short plate (402), a press pin (403) and a concave plate (404);
the top of the long plate (401) is rotatably connected with the front of the convex plate (9), the bottom of the long plate (401) is rotatably connected with the left side of the short plate (402), the inner wall of the short plate (402) is inserted into the outer wall of the press nail (403), and the top of the press nail (403) is fixedly connected with the bottom of the concave plate (404).
7. The fence according to claim 1, wherein the fence is used for short-term construction of municipal engineering roads and is characterized in that: and a round rod (7) is fixedly connected below the front surface of the vertical plate (1).
8. The fence according to claim 1, wherein the fence is used for short-term construction of municipal engineering roads and is characterized in that: the bottom of riser (1) is rigid coupling has base (8).
CN202120504080.XU 2021-03-10 2021-03-10 Municipal works road is construction in short term with enclosing fender Active CN214996660U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120504080.XU CN214996660U (en) 2021-03-10 2021-03-10 Municipal works road is construction in short term with enclosing fender

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120504080.XU CN214996660U (en) 2021-03-10 2021-03-10 Municipal works road is construction in short term with enclosing fender

Publications (1)

Publication Number Publication Date
CN214996660U true CN214996660U (en) 2021-12-03

Family

ID=79156355

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120504080.XU Active CN214996660U (en) 2021-03-10 2021-03-10 Municipal works road is construction in short term with enclosing fender

Country Status (1)

Country Link
CN (1) CN214996660U (en)

Similar Documents

Publication Publication Date Title
CN214783976U (en) Foundation pit support structure
CN214996660U (en) Municipal works road is construction in short term with enclosing fender
CN212027406U (en) Building site is with enclosing fender
CN217923623U (en) Inner supporting structure of foundation pit
CN215114653U (en) Water area flow and flow velocity monitoring device
CN213896699U (en) Earthwork breaker is used in road construction with splashproof function
CN212743592U (en) Warning rail is used in landscape construction
CN211851222U (en) Municipal works are with combination formula protection rail convenient to folding transportation
CN221461890U (en) Protective shed for constructional engineering
CN112695677A (en) Road guardrail stand
CN215443435U (en) Building engineering protective bracket
CN209849064U (en) Feeding device of pulverizer
CN219817560U (en) Straightening device for steel structure column beam
CN221346395U (en) Detachable guard rail
CN217106404U (en) Steel frame convenient to disassemble and assemble for electric power tower
CN221627260U (en) Steel construction rotation node with convenient locking device
CN215717812U (en) Adjustable safety device of municipal works foundation ditch
CN217231540U (en) Safety warning device is used in hydraulic engineering construction
CN216766966U (en) Civil engineering is with stake strutting arrangement of being convenient for adjust size
CN221696848U (en) Steel structure part placing tool
CN221567820U (en) Scaffold for decoration
CN219548601U (en) Temporary enclosure device for building engineering construction
CN216429477U (en) Hydraulic engineering overhauls uses staircase
CN214372880U (en) Resource tax management system
CN219138381U (en) Supporting equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: Enclosure for short-term construction of municipal engineering road

Effective date of registration: 20221006

Granted publication date: 20211203

Pledgee: Zhejiang Tailong commercial bank Quzhou branch of Limited by Share Ltd.

Pledgor: Zhejiang Guangsheng Group Co.,Ltd.

Registration number: Y2022330002444

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230710

Granted publication date: 20211203

Pledgee: Zhejiang Tailong commercial bank Quzhou branch of Limited by Share Ltd.

Pledgor: Zhejiang Guangsheng Group Co.,Ltd.

Registration number: Y2022330002444

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A type of enclosure for short-term construction of municipal engineering roads

Effective date of registration: 20230718

Granted publication date: 20211203

Pledgee: Zhejiang Tailong commercial bank Quzhou branch of Limited by Share Ltd.

Pledgor: Zhejiang Guangsheng Group Co.,Ltd.

Registration number: Y2023980048804

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20211203

Pledgee: Zhejiang Tailong commercial bank Quzhou branch of Limited by Share Ltd.

Pledgor: Zhejiang Guangsheng Group Co.,Ltd.

Registration number: Y2023980048804

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A type of enclosure for short-term construction of municipal engineering roads

Granted publication date: 20211203

Pledgee: Zhejiang Tailong commercial bank Quzhou branch of Limited by Share Ltd.

Pledgor: Zhejiang Guangsheng Group Co.,Ltd.

Registration number: Y2024980011230