CN214992946U CN202120884577.9U CN202120884577U CN214992946U CN 214992946 U CN214992946 U CN 214992946U CN 202120884577 U CN202120884577 U CN 202120884577U CN 214992946 U CN214992946 U CN 214992946U
Authority
CN
China
Prior art keywords
motor
workbin
asphalt pavement
pit repairing
running gear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120884577.9U
Other languages
Chinese (zh)
Inventor
陈伟
王国相
周婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Ronghui Construction Co ltd
Original Assignee
Zhejiang Ronghui Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Ronghui Construction Co ltd filed Critical Zhejiang Ronghui Construction Co ltd
Priority to CN202120884577.9U priority Critical patent/CN214992946U/en
Application granted granted Critical
Publication of CN214992946U publication Critical patent/CN214992946U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Repair (AREA)

Abstract

The utility model discloses a repairing device for pits on asphalt pavement, which comprises a walking mechanism; the top of the travelling mechanism is provided with a material box through a welding rod, the output end of the bottom of the material box is provided with a material discharging mechanism, one end of the material discharging mechanism extends to the front side of the travelling mechanism, the central position of one side of the material box is provided with a cleaning mechanism, and the front side of the bottom of the travelling mechanism is provided with a flattening mechanism; the utility model discloses set up shakeout mechanism, after the personnel filled the pit slot inside with the pitch material, thrust unit removed, then shakeout mechanism can be directly once only shakeout work with the pitch material, can carry out accurate control to the height of shakeout moreover, improvement work efficiency that simultaneously also can be great.

Description

Asphalt pavement pit repairing device
Technical Field
The utility model relates to a bituminous paving hole groove repair technical field specifically is bituminous paving hole groove patching device.
Background
Asphalt pavement is various types of pavement paved by asphalt materials mixed in mineral materials, asphalt binder improves the capability of paving aggregate to resist damage of running and natural factors to the pavement, and makes the pavement smooth, dustless, waterproof and durable, so that the asphalt pavement is a high-grade pavement which is most widely adopted in road construction, pit grooves often appear in the asphalt pavement in long-term use, and a pit groove repairing device is required to be used for repairing the pit grooves.
The existing asphalt pavement pit repairing device has the following defects:
1. the existing asphalt pavement pit repairing device is lack of a cleaning mechanism, and when an asphalt material is filled into the pit to repair the pit, the dust in the pit cannot be adhered to the inner wall of the pit tightly if the dust is not cleaned, so that the filling effect is poor.
2. The existing asphalt pavement pit repairing device needs manual work to flatten asphalt after filling asphalt materials into the pit, the manual work flattening precision is poor, the asphalt flattening thickness cannot be accurately controlled, and the efficiency is low.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an asphalt pavement pot hole patching device to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the asphalt pavement pit repairing device comprises a walking mechanism; the workbin is installed through the welding pole in running gear's top, the output of workbin bottom is installed and is arranged material mechanism, and arranges the one end of material mechanism and extend to running gear's front side, the central point department of putting of workbin one side installs clearance mechanism, the front side of running gear bottom is installed and is shakeouts the mechanism.
Preferably, the top central point department of workbin is equipped with the material mouth, and there is the top cap at the top of material mouth through hinged mounting, the central point department of workbin one side installs first motor, and the axostylus axostyle is installed to the output of first motor, and the axostylus axostyle is located the inside of workbin, and the surface of axostylus axostyle is equipped with the stirring frame, the front of workbin is equipped with two sets of L type racks.
Preferably, arrange material mechanism including arranging material pipe, second motor, auger delivery pole and bearing bracket, and arrange the output intercommunication of one side and workbin bottom at material pipe top, and arrange the one end of material pipe and install the second motor, and the output of second motor installs the auger delivery pole, and the one end that the second motor was kept away from to the auger delivery pole installs the bearing bracket, and the inner wall fixed connection of bearing bracket and row material pipe.
Preferably, clearance mechanism is including clearance case, sealed lid, third motor, flabellum and dust removal pipe, and the bottom of clearance case installs sealed lid through helicitic texture, and the internally mounted of clearance case has the third motor, and the flabellum is installed to the output of third motor, and the top of clearance case has the dust removal pipe through hose connection, and the dust removal pipe is placed on L type rack.
Preferably, the flattening mechanism comprises a flattening plate, an insertion pipe and an electric push rod, the insertion pipe is arranged at the two ends of the rear side of the flattening plate, the electric push rod is arranged inside the insertion pipe, and the electric push rod is fixedly connected with the front side and the back side of the walking mechanism.
Preferably, running gear includes walking car and handle, and the handle is installed to the rear side of walking car, and the front department of handle installs the electric cabinet, and the electric cabinet passes through wire and first motor, second motor, third motor and electric putter electric connection, and the front of electric cabinet is equipped with control panel, and the bottom of electric cabinet is connected with the plug through the wire.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses set up clearance mechanism, before filling bituminous paving hole groove, personnel can clear up the dust of hole inslot portion through clearance mechanism, guarantee the cleanness of hole inslot portion, then fill into hole inslot portion back with the pitch material, the pitch material can carry out inseparable connection with the inner wall in hole groove, guarantees the filling quality in hole groove.
2. The utility model discloses set up shakeout mechanism, after the personnel filled the pit slot inside with the pitch material, thrust unit removed, then shakeout mechanism can be directly once only shakeout work with the pitch material, can carry out accurate control to the height of shakeout moreover, improvement work efficiency that simultaneously also can be great.
Drawings
FIG. 1 is a front sectional view of the present invention;
fig. 2 is a front view of the present invention;
fig. 3 is a top view of the present invention.
In the figure: 1. a traveling mechanism; 101. a walking vehicle; 102. a handle; 103. an electric cabinet; 104. a control panel; 105. a plug; 2. welding a rod; 3. a material box; 301. a material port; 302. a top cover; 303. a first motor; 304. a shaft lever; 305. a stirring frame; 306. an L-shaped placing rack; 4. a discharge mechanism; 401. a discharge pipe; 402. a second motor; 403. a screw conveying rod; 404. a bearing bracket; 5. a cleaning mechanism; 501. cleaning the box; 502. a sealing cover; 503. a third motor; 504. a fan blade; 505. a dust removal pipe; 6. a flattening mechanism; 601. flattening; 602. inserting a tube; 603. an electric push rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-3, the present invention provides an embodiment: the pitch road surface pit repairing device comprises a walking mechanism 1; workbin 3 is installed through welding pole 2 at running gear 1's top, and discharge mechanism 4 is installed to the output of workbin 3 bottom, and the one end of discharging mechanism 4 extends to running gear 1's front side, and cleaning mechanism 5 is installed to the central point department of workbin 3 one side, and shakeout mechanism 6 is installed to the front side of running gear 1 bottom.
It is specific, when the personnel promoted the device to pot hole department, then the personnel cleared away the inside dust of pot hole through clearance mechanism 5, after the inside dust clearance of pot hole is accomplished, then discharge the inside pitch material of workbin 3 through row material mechanism 4, then the pitch material is discharged inside the pot hole, adjust shakeout mechanism 6's height, then personnel thrust unit removes once more, shakeout mechanism 6 can once only be with filling in the inside pitch material shakeout of pot hole, guarantee pitch material shakeout's thickness and accuracy.
Further, the top central point department of workbin 3 is equipped with material mouth 301, and there is top cap 302 at the top of material mouth 301 through the hinge mounting, and the central point department of workbin 3 one side installs first motor 303, and axostylus axostyle 304 is installed to the output of first motor 303, and axostylus axostyle 304 is located the inside of workbin 3, and the surface of axostylus axostyle 304 is equipped with stirring frame 305, and the front of workbin 3 is equipped with two sets of L type racks 306.
Specifically, open top cap 302, with the pitch material through material mouth 301 add the workbin 3 inside, then control first motor 303 and drive axostylus axostyle 304 and rotate, axostylus axostyle 304 drives stirring frame 305 and rotates, and stirring frame 305 stirs the pitch material, avoids the pitch material to condense in workbin 3 insides.
Further, row material mechanism 4 is including arranging material pipe 401, second motor 402, screw conveyor pole 403 and bearing bracket 404, and arrange the output intercommunication of one side and workbin 3 bottom at material pipe 401 top, and arrange the one end of material pipe 401 and install second motor 402, and screw conveyor pole 403 is installed to the output of second motor 402, and screw conveyor pole 403 keeps away from the one end of second motor 402 and installs bearing bracket 404, and bearing bracket 404 and the inner wall fixed connection who arranges material pipe 401.
Specifically, the asphalt material in the bin 3 enters the discharge pipe 401, the second motor 402 is controlled to drive the spiral conveying rod 403 to rotate, and then the spiral conveying rod 403 discharges the asphalt material out of the discharge pipe 401 and fills the asphalt material into the pit groove.
Further, the cleaning mechanism 5 includes a cleaning box 501, a sealing cover 502, a third motor 503, fan blades 504 and a dust removing pipe 505, the sealing cover 502 is installed at the bottom of the cleaning box 501 through a threaded structure, the third motor 503 is installed inside the cleaning box 501, the fan blades 504 are installed at the output end of the third motor 503, the dust removing pipe 505 is connected to the top of the cleaning box 501 through a hose, and the dust removing pipe 505 is placed on the L-shaped placing frame 306.
Specifically, a person takes off the dust removal pipe 505 on the L-shaped placing rack 306, then controls the third motor 503 to drive the fan blades 504 to rotate, generates a strong suction force, then holds the dust removal pipe 505 by hand to suck dust in the pit into the cleaning box 501, and when the dust in the cleaning box 501 is too much, the sealing cover 502 can be unscrewed to discharge the dust in the cleaning box 501.
Further, the flattening mechanism 6 includes a flattening plate 601, an insertion tube 602 and an electric push rod 603, the insertion tube 602 is disposed at two ends of the rear side of the flattening plate 601, the electric push rod 603 is mounted inside the insertion tube 602, and the electric push rod 603 is fixedly connected with the front side and the rear side of the traveling mechanism 1.
Specifically, drive the height that the board 601 of making a stand reciprocated and adjusted the board 601 through electric putter 603, then personnel thrust unit removes the in-process, the board 601 of making a stand can be disposable will fill out the pitch material shakeout of pot hole inside, and the accuracy that can guarantee the shakeout on one hand, and the shakeout thickness that can adjust the pitch material according to the use needs on the other hand.
Further, running gear 1 includes walking car 101 and handle 102, and the handle 102 is installed to the rear side of walking car 101, and the front department of handle 102 installs electric cabinet 103, and electric cabinet 103 passes through wire and first motor 303, second motor 402, third motor 503 and electric putter 603 electric connection, and electric cabinet 103's front is equipped with control panel 104, and electric cabinet 103's bottom is connected with plug 105 through the wire.
Specifically, a person holds the handle 102 to push the walking vehicle 101 to move, then the electric cabinet 103 is connected with a power supply through the plug 105, and the control panel 104 is used for controlling the working state of the electric components on the device.
The working principle is as follows: when the device is used, a power supply is connected through the plug 105, the top cover 302 is opened, the asphalt material is added into the bin 3 through the material port 301, the first motor 303 is controlled to drive the shaft lever 304 to rotate, the shaft lever 304 drives the stirring frame 305 to rotate, the stirring frame 305 stirs the asphalt material to prevent the asphalt material from being condensed in the bin 3, when a person pushes the device to a pit, the person takes off the dust removing pipe 505 on the L-shaped placing frame 306, then the third motor 503 is controlled through the control panel 104 to drive the fan blades 504 to rotate to generate strong suction, then the person holds the dust removing pipe 505 to suck dust in the pit into the cleaning box 501, when the dust in the cleaning box 501 is excessive, the sealing cover 502 can be unscrewed to discharge the dust in the cleaning box 501, after the pit is cleaned, the asphalt material in the bin 3 enters the discharge pipe 401, then the control panel 104 controls the second motor 402 to drive the spiral conveying rod 403 to rotate, then screw conveyor 403 discharges the pitch material and arranges material pipe 401 to fill into inside the pot hole, control electric putter 603 through control panel 104 and drive the height that dull and stereotyped 601 of stand reciprocated regulation well shakeout board 601, then the in-process that personnel thrust unit removed, the dull and stereotyped 601 can be disposable will fill into the pitch material shakeout of pot hole inside, one can guarantee the accuracy of shakeout, two can adjust the shakeout thickness of pitch material as required.
The details of the present invention are well known to those skilled in the art.
Finally, it is to be noted that: the above embodiments are only used for illustrating the technical solutions of the present invention and not for limiting, and although the present invention has been described in detail with reference to the examples, it should be understood by those skilled in the art that the technical solutions of the present invention can be modified and replaced with equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should be covered by the scope of the claims of the present invention.

Claims (6)

1. The asphalt pavement pit repairing device comprises a traveling mechanism (1); the method is characterized in that: workbin (3) are installed through welding pole (2) at the top of running gear (1), the output of workbin (3) bottom is installed and is expected mechanism (4), and the one end of arranging material mechanism (4) extends to the front side of running gear (1), the central point department of putting of workbin (3) one side installs clearance mechanism (5), the front side of running gear (1) bottom is installed and is shakeouts mechanism (6).
2. The asphalt pavement pit repairing apparatus according to claim 1, characterized in that: the top central point department of workbin (3) is equipped with material mouth (301), and there is top cap (302) at the top of material mouth (301) through the hinge mounting, the central point department of workbin (3) one side installs first motor (303), and the output of first motor (303) installs axostylus axostyle (304), and axostylus axostyle (304) are located the inside of workbin (3), and the surface of axostylus axostyle (304) is equipped with stirring frame (305), the front of workbin (3) is equipped with two sets of L type racks (306).
3. The asphalt pavement pit repairing apparatus according to claim 1, characterized in that: arrange material mechanism (4) including arranging material pipe (401), second motor (402), screw conveyor pole (403) and bearing bracket (404), and arrange the output intercommunication of one side and workbin (3) bottom at material pipe (401) top, and arrange the one end of material pipe (401) and install second motor (402), and screw conveyor pole (403) are installed to the output of second motor (402), and screw conveyor pole (403) are kept away from the one end of second motor (402) and are installed bearing bracket (404), and bearing bracket (404) and the inner wall fixed connection who arranges material pipe (401).
4. The asphalt pavement pit repairing apparatus according to claim 1, characterized in that: clearance mechanism (5) are including clearance case (501), sealed lid (502), third motor (503), flabellum (504) and dust removal pipe (505), and sealed lid (502) are installed through helicitic texture to the bottom of clearance case (501), and the internally mounted of clearance case (501) has third motor (503), and flabellum (504) are installed to the output of third motor (503), and there is dust removal pipe (505) at the top of clearance case (501) through hose connection, and place on L type rack (306) dust removal pipe (505).
5. The asphalt pavement pit repairing apparatus according to claim 1, characterized in that: flattening mechanism (6) are including flattening board (601), intubate (602) and electric putter (603), and the both ends of flattening board (601) rear side are equipped with intubate (602), and the internally mounted of intubate (602) has electric putter (603), and electric putter (603) and running gear (1) front and the front end fixed connection at the back.
6. The asphalt pavement pit repairing apparatus according to claim 1, characterized in that: running gear (1) is including walking car (101) and handle (102), and handle (102) are installed to the rear side of walking car (101), and the front department of handle (102) installs electric cabinet (103), and electric cabinet (103) pass through wire and first motor (303), second motor (402), third motor (503) and electric putter (603) electric connection, and the front of electric cabinet (103) is equipped with control panel (104), and the bottom of electric cabinet (103) is connected with plug (105) through the wire.
CN202120884577.9U 2021-04-27 2021-04-27 Asphalt pavement pit repairing device Active CN214992946U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120884577.9U CN214992946U (en) 2021-04-27 2021-04-27 Asphalt pavement pit repairing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120884577.9U CN214992946U (en) 2021-04-27 2021-04-27 Asphalt pavement pit repairing device

Publications (1)

Publication Number Publication Date
CN214992946U true CN214992946U (en) 2021-12-03

Family

ID=79092023

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120884577.9U Active CN214992946U (en) 2021-04-27 2021-04-27 Asphalt pavement pit repairing device

Country Status (1)

Country Link
CN (1) CN214992946U (en)

Similar Documents

Publication Publication Date Title
CN210507084U (en) Multifunctional highway maintenance device
CN214992946U (en) Asphalt pavement pit repairing device
CN208307534U (en) A kind of asphalt storing apparatus
CN216688955U (en) Road surface gap slip casting patching device with deashing function
CN213742145U (en) Automatic pointing device for paving and pasting building tiles
CN112854030A (en) Bridge maintenance equipment and use method thereof
CN216688956U (en) Be used for road crack slip casting patching device
CN215561759U (en) Highway subgrade construction maintenance road surface cementation of fissures device
CN112048982A (en) Road and bridge crack repairing and reinforcing device
CN219992150U (en) Highway crack processing apparatus
CN219195599U (en) Highway road surface construction maintenance device
CN217266857U (en) Road and bridge construction road surface curing means
CN215947828U (en) Highway maintenance cementation of fissures device
CN220952834U (en) Road paving device for road and bridge
CN216196369U (en) Plastering device for building
CN218492250U (en) Pavement maintenance trolley
CN217052961U (en) Anti-skid asphalt pavement construction equipment
CN219297928U (en) Road crack pouring device for traffic engineering
CN218027115U (en) Highway is road surface maintenance device for bridge construction management
CN219010913U (en) Road crack repairing mechanism
CN216156332U (en) Construction marking device of convenient clearance
CN220035151U (en) Cement pavement crack quick repair device
CN218466290U (en) Crack asphalt repair trolley
CN219527292U (en) Road marking repair tool
CN216156322U (en) Gap filling device for road and bridge restoration

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant