CN214944192U - Oil gas well non-stop pump temporary plugging steering fracturing device - Google Patents

Oil gas well non-stop pump temporary plugging steering fracturing device Download PDF

Info

Publication number
CN214944192U
CN214944192U CN202121166059.XU CN202121166059U CN214944192U CN 214944192 U CN214944192 U CN 214944192U CN 202121166059 U CN202121166059 U CN 202121166059U CN 214944192 U CN214944192 U CN 214944192U
Authority
CN
China
Prior art keywords
pipeline
branch pipeline
way valve
pressure pump
fracturing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121166059.XU
Other languages
Chinese (zh)
Inventor
朱宁
孙波
李邵云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daqing Jiajing Petroleum Engineering Technology Co.,Ltd.
Original Assignee
Daqing Mingyue Petroleum Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daqing Mingyue Petroleum Technology Co ltd filed Critical Daqing Mingyue Petroleum Technology Co ltd
Priority to CN202121166059.XU priority Critical patent/CN214944192U/en
Application granted granted Critical
Publication of CN214944192U publication Critical patent/CN214944192U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pipeline Systems (AREA)

Abstract

The utility model provides an oil gas well does not stop pump and blocks up to turn to fracturing unit temporarily. Relates to the technical field of oil field fracturing operation. Leading liquid tank of high-pressure pump inlet pipe connection, high-pressure pump outlet pipe says and connects a three-way valve, and first branch pipeline and second branch pipeline are connected respectively to two exports of three-way valve, and the import of another three-way valve is connected respectively to first branch pipeline and second branch pipeline rear end, and the outlet pipe of this three-way valve connects fracturing pipeline, all is equipped with on first branch pipeline and the second branch pipeline and throws with the mouth. The utility model discloses following beneficial effect has: two pipelines for switching injection and adding temporary plugging agents are arranged through a three-way valve, the purpose of ceaselessly injecting the high-pressure pump in the operation process is achieved through a backflow pipeline of a pressure release valve, different temporary plugging agents are injected in batches, meanwhile, the high-pressure pump does not need to be stopped, the operation efficiency is improved, and the service lives of the high-pressure pump and electrical equipment are prolonged.

Description

Oil gas well non-stop pump temporary plugging steering fracturing device
The technical field is as follows:
the utility model belongs to the technical field of the oil field fracturing operation technique and specifically relates to an oil gas well does not stop pump and blocks up to turn to fracturing unit temporarily.
Background art:
the successful implementation of the pitching temporary plugging diversion fracturing process is critically dependent on how to inject the particle temporary plugging agent into the stratum in a high-pressure mode through a fracturing pipeline and a high-pressure pump uniformly according to a certain speed, the original fracturing pipeline system is only provided with one main pipeline, and the following defects exist in temporary plugging fracturing construction:
1. if the number of the temporarily blocked particles is large, the temporarily blocked pitching operation needs to be carried out in batches, and the construction requirement of large number of the temporarily blocked particles of the single-layer pitching can not be met on site;
2. the temporary plugging particles are divided into different particle sizes according to different functions, and classification temporary plugging ball throwing operation of different particle sizes cannot be continuously carried out according to a certain sequence;
3. the temporary blocking ball throwing operation is carried out in batches, the high-pressure pump is frequently started, the current impact is large, and the service life of the high-pressure pump and the electric equipment is short.
The utility model has the following contents:
in order to solve the problem, the utility model provides an oil gas well does not stop pump and blocks up to turn to fracturing unit temporarily.
The technical scheme of the utility model is that: oil gas well does not stop pump and temporarily blocks up to turn to fracturing unit, including the high-pressure pump, leading liquid case of high-pressure pump inlet pipe connection, a three-way valve of high-pressure pump outlet pipe connection, first branch pipeline and second branch pipeline are connected respectively to two exports of three-way valve, the import of another three-way valve is connected respectively to first branch pipeline and second branch pipeline rear end, the outlet pipe connection fracturing pipeline of this three-way valve, all be equipped with on first branch pipeline and the second branch pipeline and throw the mouth, it is equipped with the valve on the mouth pipeline to throw.
The high-pressure pump outlet pipeline, the first branch pipeline and the second branch pipeline are respectively connected with a backflow pipeline in a side-by-side mode, each backflow pipeline is connected with a pressure release valve in series, and the terminal of the backflow pipeline is connected to the top of the preposed liquid tank.
And a drain valve and a pressure gauge are arranged on the first branch pipeline and the second branch pipeline.
The fracturing pipeline is provided with a one-way valve.
The high-pressure pump, the liquid placing box, the first branch pipeline, the second branch pipeline and the fracturing pipeline are integrally installed on the bottom pry.
The utility model discloses following beneficial effect has: two pipelines for switching injection and adding temporary plugging agents are arranged through a three-way valve, the purpose of ceaselessly injecting the high-pressure pump in the operation process is achieved through a backflow pipeline of a pressure release valve, different temporary plugging agents are injected in batches, meanwhile, the high-pressure pump does not need to be stopped, the operation efficiency is improved, and the service lives of the high-pressure pump and electrical equipment are prolonged.
Description of the drawings:
fig. 1 is a schematic flow chart of the present invention.
In the figure, 1-a high-pressure pump, 2-a bottom pry, 3-a three-way valve, 4-a first branch pipeline, 5-a second branch pipeline, 6-a preposed liquid tank, 7-a backflow pipeline, 8-a pressure relief valve, 9-a feeding port, 10-a one-way valve and 11-a fracturing pipeline.
The specific implementation mode is as follows:
the present invention will be further explained with reference to the accompanying drawings:
by figure 1, oil gas well does not stop pump and temporarily blocks up diversion fracturing unit, including high-pressure pump 1, 1 inlet pipe of high-pressure pump connects leading liquid case 6, 1 outlet pipe of high-pressure pump connects a three-way valve 3, first branch pipeline 4 and second branch pipeline 5 are connected respectively to two exports of three-way valve 3, another three-way valve 3's import is connected respectively to first branch pipeline 4 and second branch pipeline 5 rear end, this three-way valve 3's outlet pipe connects fracturing pipeline 11, all be equipped with on first branch pipeline 4 and the second branch pipeline 5 and throw feeder 9, it is equipped with the valve on the feeder 9 pipeline.
The outlet pipeline of the high-pressure pump 1, the first branch pipeline 4 and the second branch pipeline 5 are respectively connected with a return pipeline 7 in a side-by-side mode, each return pipeline 7 is connected with a pressure release valve 8 in series, and the terminal of each return pipeline 7 is connected to the top of the front liquid tank 6.
The fracturing pipeline 11 is provided with a one-way valve 10 to prevent high-pressure liquid in the well from flowing back.
And a drain valve and a pressure gauge are arranged on the first branch pipeline 4 and the second branch pipeline 5.
The high-pressure pump 1, the liquid placing box 6, the first branch pipeline 4, the second branch pipeline 5 and the fracturing pipeline 11 are integrally installed on the bottom pry 2, so that the equipment can be integrally hoisted and carried on site conveniently.
In actual use, the high-pressure pump 1 injects the pre-liquid into the first branch pipeline 4 through the three-way valve 3, injects the mixed liquid with the added temporary plugging agent into the fracturing pipeline 11, at the moment, the three-way valves 3 on two sides of the second branch pipeline 5 are in a closed state, opens the pressure release valves 8 on the pipeline for pressure release, adds the temporary plugging agent into the second branch pipeline 5 through adding equipment, switches the valve positions of the two three-way valves 3 after the temporary plugging agent in the first branch pipeline 4 is completely injected, so that the high-pressure pump 1 is communicated with the second branch pipeline 5, during the switching process, the pre-liquid pumped out by the high-pressure pump 1 flows back into the pre-liquid tank through the pressure release valves 8 on the backflow pipeline 7 after the pump, after the switching is completed, the high-pressure pump 1 injects the pre-liquid into the second branch pipeline 5 through the three-way valves 3, injects the mixed liquid with the added temporary plugging agent into the fracturing pipeline 11, and circularly replaces the process pipeline in the way, different temporary plugging agents are injected in batches, meanwhile, the high-pressure pump 1 does not need to be stopped, the operation efficiency is improved, and the service lives of the high-pressure pump and electrical equipment are prolonged.

Claims (5)

1. Oil gas well does not stop pump temporary plugging and turns to fracturing device, including high-pressure pump (1), its characterized in that: leading liquid case (6) of high-pressure pump (1) inlet pipe connection, three-way valve (3) of high-pressure pump (1) outlet pipe connection, first branch pipeline (4) and second branch pipeline (5) are connected respectively to two exports of three-way valve (3), the import of another three-way valve (3) is connected respectively to first branch pipeline (4) and second branch pipeline (5) rear end, the outlet pipe connection fracturing pipeline (11) of this three-way valve (3), all be equipped with on first branch pipeline (4) and second branch pipeline (5) and throw with mouth (9), it is equipped with the valve on mouth (9) pipeline to throw.
2. The oil and gas well pump-uninterrupted steering fracturing device according to claim 1, wherein: the high-pressure pump outlet pipeline, the first branch pipeline (4) and the second branch pipeline (5) are respectively connected with a backflow pipeline (7) in a side-by-side mode, each backflow pipeline (7) is connected with a pressure release valve (8) in series, and the terminal of the backflow pipeline (7) is connected to the top of the front liquid box (6).
3. The oil and gas well pump-uninterrupted steering fracturing device according to claim 1, wherein: the fracturing pipeline (11) is provided with a one-way valve (10).
4. The oil and gas well pump-uninterrupted steering fracturing device according to claim 1, wherein: and a drain valve and a pressure gauge are arranged on the first branch pipeline (4) and the second branch pipeline (5).
5. The oil and gas well pump-uninterrupted steering fracturing device according to claim 1, wherein: high-pressure pump (1), put liquid case (6), first branch pipeline (4), second branch pipeline (5), fracturing pipeline (11) all integrated the installation on sled (2) at the bottom.
CN202121166059.XU 2021-05-27 2021-05-27 Oil gas well non-stop pump temporary plugging steering fracturing device Active CN214944192U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121166059.XU CN214944192U (en) 2021-05-27 2021-05-27 Oil gas well non-stop pump temporary plugging steering fracturing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121166059.XU CN214944192U (en) 2021-05-27 2021-05-27 Oil gas well non-stop pump temporary plugging steering fracturing device

Publications (1)

Publication Number Publication Date
CN214944192U true CN214944192U (en) 2021-11-30

Family

ID=79058875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121166059.XU Active CN214944192U (en) 2021-05-27 2021-05-27 Oil gas well non-stop pump temporary plugging steering fracturing device

Country Status (1)

Country Link
CN (1) CN214944192U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114403113A (en) * 2022-01-13 2022-04-29 山东兆源智能科技有限公司 Plant protection is atomizing system for unmanned aerial vehicle

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114403113A (en) * 2022-01-13 2022-04-29 山东兆源智能科技有限公司 Plant protection is atomizing system for unmanned aerial vehicle
CN114403113B (en) * 2022-01-13 2022-12-09 山东兆源智能科技有限公司 Plant protection is atomizing system for unmanned aerial vehicle

Similar Documents

Publication Publication Date Title
CN203559893U (en) Sand mixing equipment manifold
CN201301466Y (en) Rotary oil supply loop for hydraulic excavator
CN214944192U (en) Oil gas well non-stop pump temporary plugging steering fracturing device
CN206320090U (en) A kind of control device of high-speed hydraulic motor
CN204572610U (en) A kind of new work engine hydraulic starting valve group and the hydraulic activating system set up by it
CN102155312B (en) Sudden stop and fuel cut-off control system of engine
CN208628016U (en) A kind of device of Hand scarf lime pipeline
CN105268574B (en) One kind spraying main frame and its method of work
CN201124756Y (en) Anti-theft diesel oil tank
CN202673878U (en) Filtering device of closed hydraulic driving system of engineering vehicle
CN203403957U (en) Emergency shutdown system for cutting and emptying diesel engine fuel feed
CN104930348A (en) High-low pressure switching and venting skid-mounted device based on large cluster well set
CN210829629U (en) Pressure relief and water drainage device for manifold of diesel water pump unit
CN202315053U (en) Water inlet-outlet pipeline system based on high-low pressure water pump as well as fire fighting apparatus
CN2817979Y (en) Siphon injector for preventing countercurrent
CN209226572U (en) From hybrid prize-mounted refueling device
CN209083588U (en) A kind of automatic water device
CN208643555U (en) A kind of device for flushing pipe in asphalt production
CN201671840U (en) Device for extracting underground liquid
CN206328804U (en) A kind of device for long range water supplying pump system protecting water hammer
CN204785563U (en) It prizes dress device to switch and empty based on big cluster well high -low pressure
CN104746559A (en) Jet secondary water supply equipment of parallel water tank
CN202417867U (en) Hydraulic system of hydraulic type secondary CNG (compressed natural gas) filling station for automobile
CN205224180U (en) Pipe network pressure -superposed water supply system
CN220101248U (en) Ball plug valve is thrown to non-stop pump

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220304

Address after: 163000 incubator 701, No. 3, phase I project of science and technology incubator in Daqing high tech Zone, Heilongjiang Province

Patentee after: Daqing Jiajing Petroleum Engineering Technology Co.,Ltd.

Address before: Room 301, Chuangye building, public entrepreneurship incubation base, Ranghulu District, Daqing City, Heilongjiang Province, 163000

Patentee before: Daqing Mingyue Petroleum Technology Co.,Ltd.

TR01 Transfer of patent right