CN214941470U - Fixed connection mechanism for building curtain wall engineering - Google Patents

Fixed connection mechanism for building curtain wall engineering Download PDF

Info

Publication number
CN214941470U
CN214941470U CN202121309991.3U CN202121309991U CN214941470U CN 214941470 U CN214941470 U CN 214941470U CN 202121309991 U CN202121309991 U CN 202121309991U CN 214941470 U CN214941470 U CN 214941470U
Authority
CN
China
Prior art keywords
curtain wall
plate
angle steel
connecting plate
vertical mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202121309991.3U
Other languages
Chinese (zh)
Inventor
田艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shuangquan Construction Engineering Co ltd
Original Assignee
Anhui Shuangquan Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Shuangquan Construction Engineering Co ltd filed Critical Anhui Shuangquan Construction Engineering Co ltd
Priority to CN202121309991.3U priority Critical patent/CN214941470U/en
Application granted granted Critical
Publication of CN214941470U publication Critical patent/CN214941470U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses a fixed connection mechanism for building curtain wall engineering, which comprises a vertical mounting plate, wherein the top and the bottom of the two sides of the vertical mounting plate are fixedly connected with a right angle steel plate, the right angle steel plate is provided with a mounting hole, the front side of the vertical mounting plate is provided with a mounting groove, the two sides of the mounting groove are correspondingly provided with a through hole, the inner cavity of the mounting groove is fixedly connected with a connecting plate, the inner cavity of the connecting plate is provided with a screw hole, the front side of the connecting plate is welded with a horizontal steel frame, the top and the bottom of the horizontal steel frame are provided with a clamping groove, the inner cavity of the clamping groove is provided with a curtain wall plate, the curtain wall plate is connected with an expansion screw lamp connecting part through the connection of the vertical mounting plate, the right angle steel plate and the horizontal steel frame, and finally the curtain wall plate is clamped in the inner cavity of the clamping groove and sealed, and the fixed connection mechanism for building curtain wall engineering is provided, simple structure, easy installation and dismantlement, stability is good, and the security performance is high.

Description

Fixed connection mechanism for building curtain wall engineering
Technical Field
The utility model relates to a building curtain technical field specifically is a fixed connection mechanism for building curtain engineering.
Background
The curtain wall is the outer wall enclosure of the building, does not bear the weight, hangs like a curtain, so is also called as a curtain wall, and is a light wall with decorative effect commonly used by modern large-scale and high-rise buildings. The building external enclosure structure or the decorative structure consists of a panel and a supporting structure system, can have certain displacement capacity or certain deformation capacity relative to a main structure, and does not bear the action of the main structure, and under the comparison of the same area of the building curtain wall, the mass of the glass curtain wall is 1/10-1/12 of a painted brick wall, is 1/15 of a marble and granite facing wet construction method wall, and is 1/5-1/7 of a concrete hanging plate. In a general building, the mass of the inner wall and the outer wall is 1/4-1/5 of the total weight of the building. The curtain wall can greatly reduce the weight of the building, thereby reducing the cost of foundation engineering.
Because the curtain is in the outer wall department of building, so the installation requirement to the curtain is very strict, otherwise appear dropping the phenomenon consequence and dare not imagine, the fixed mechanism in succession of curtain installation of current has all reached the standard even stability, but the structure is all more complicated, has increased the cost of installation.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building curtain is fixed connection mechanism for engineering to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a fixed connection mechanism for building curtain wall engineering, includes vertical mounting panel, the equal fixedly connected with right angle steel sheet in top and the bottom of vertical mounting panel both sides, the mounting hole has been seted up on the right angle steel sheet, the mounting groove has been seted up in the front of vertical mounting panel, the through hole has been seted up to the mounting groove both sides correspondence, the inner chamber fixedly connected with connecting plate of mounting groove, the screw has been seted up to the inner chamber of connecting plate, the front welding of connecting plate has horizontal steel frame, the joint groove has all been seted up to the top and the bottom of horizontal steel frame, the inner chamber in joint groove is provided with the curtain board.
Preferably, the size of the connecting plate corresponds to the size of the mounting groove, and the position of the screw hole corresponds to the position of the through hole.
Preferably, reinforcing holes are formed in the inner cavity of the transverse steel frame and in the positions corresponding to the middle of the connecting plate, and reinforcing screws are fixedly connected to the inner cavities of the reinforcing holes.
Preferably, the right-angle steel plate is made of a 2cm steel plate, the right-angle steel plate is fixedly connected with the wall body through an expansion screw rod, and the other side of the right-angle steel plate is fixedly connected with the vertical mounting plate through a screw rod.
Preferably, the curtain wall board is provided with the strip of sealing with the connector gap department in joint groove, the strip of sealing is the triangle strip of paper used for sealing.
Compared with the prior art, the beneficial effects of the utility model are that:
1. this fixed connection mechanism for building curtain wall engineering, through vertical mounting panel, the right angle steel sheet, horizontal steel frame's connection, when installing building curtain, at first confirm the position of first vertical mounting panel, then fix the right angle steel sheet in the top and the bottom of vertical mounting panel both sides through the screw rod, then adopt inflation screw rod with another face and the building wall fixed connection of right angle steel sheet, and with the steel sheet in this installation four corners, the installation of horizontal steel frame carries out again, carry out the secondary through the reinforcement screw rod and consolidate, improve horizontal steel frame's bearing capacity and stability, at last with the curtain board joint in the inner chamber in joint groove and seal can, a structure is simple, easily install and dismantle, good stability, high safety performance.
2. This fixed connection mechanism for building curtain engineering seals the effect mainly used binding off of strip, avoids falling the right angled corner as far as possible for the wholeness of whole curtain is better, and is more pleasing to the eye.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a left side view of the present invention;
fig. 3 is an enlarged view of a portion a in fig. 1 according to the present invention.
In the figure: 1. a vertical mounting plate; 2. a right-angle steel plate; 3. mounting holes; 4. mounting grooves; 5. a through hole; 6. a connecting plate; 7. a screw hole; 8. a transverse steel frame; 9. a clamping groove; 10. a curtain wall plate; 11. reinforcing holes; 12. reinforcing the screw rod; 13. an expansion screw; 14. a screw; 15. and (4) sealing strips.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example (b): referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a fixed connection mechanism for building curtain wall engineering, including vertical mounting panel 1, the top and the equal fixedly connected with right angle steel sheet 2 in bottom of 1 both sides of vertical mounting panel, the mounting hole 3 has been seted up on right angle steel sheet 2, mounting groove 4 has been seted up in vertical mounting panel 1's front, the through hole 5 has been seted up in the correspondence of 4 both sides of mounting groove, the inner chamber fixedly connected with connecting plate 6 of mounting groove 4, screw 7 has been seted up to the inner chamber of connecting plate 6, the front welding of connecting plate 6 has horizontal steel framework 8, joint groove 9 has all been seted up to horizontal steel framework 8's top and bottom, the inner chamber in joint groove 9 is provided with curtain wall board 10.
The right-angle steel plate 2 is made of a 2cm steel plate, the right-angle steel plate 2 is fixedly connected with a wall body through an expansion screw 13, and the other side of the right-angle steel plate is fixedly connected with the vertical mounting plate 1 through a screw 14.
In this embodiment, when installing the building curtain wall, first determine the position of a first vertical mounting plate 1, then fix the right-angle steel plate 2 at the top and the bottom of the two sides of the vertical mounting plate 1 through the screw 14, then adopt the expansion screw 13 to fixedly connect the other surface of the right-angle steel plate 2 with the building wall, and install the steel plates at the four corners.
The size of the connecting plate 6 corresponds to that of the mounting groove 4, the position of the screw hole 7 corresponds to that of the through hole 5, a reinforcing hole 11 is formed in the position, corresponding to the middle of the connecting plate 6, of the inner cavity of the transverse steel frame 8, and a reinforcing screw 12 is fixedly connected to the inner cavity of the reinforcing hole 11.
In this embodiment, after fixing 1 frame of vertical mounting panel, insert connecting plate 6 to the inner chamber of mounting groove 4, then run through the inner chamber that passes through hole 5 through horizontal screw rod and fix connecting plate 6, then install curtain board 10 in the inner chamber of joint groove 9, wherein connecting plate 6 and horizontal steel frame 8 are through the welded connected mode, carry out the secondary through reinforcement screw rod 12 and consolidate, improve horizontal steel frame 8's bearing capacity and stability.
Wherein, the joint of curtain wall board 10 and joint groove 9 is provided with sealing strip 15, and sealing strip 15 is the triangle strip of paper used for sealing.
In this embodiment, the effect of sealing strip 15 is mainly used for binding off, avoids falling the right-angled corner as far as possible for the wholeness of whole curtain is better, and is more pleasing to the eye.
The working principle is as follows: when installing the building curtain, at first confirm the position of first vertical mounting panel 1, then fix right angle steel sheet 2 in the top and the bottom of vertical mounting panel 1 both sides through screw rod 14, then adopt expansion screw 13 with another face and building wall fixed connection of right angle steel sheet 2, and with the steel sheet in this installation four corners, after fixing vertical mounting panel 1 frame, insert connecting plate 6 to the inner chamber of mounting groove 4, then pass through the inner chamber of through hole 5 through horizontal screw rod and fix connecting plate 6, then install the inner chamber at joint groove 9 with curtain board 10, wherein connecting plate 6 and horizontal steel frame 8 are through welded connected mode, carry out the secondary through reinforcement screw rod 12, improve horizontal steel frame 8's bearing capacity and stability, then seal the installation that can accomplish the curtain again.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a fixed connection mechanism for building curtain engineering, includes vertical mounting panel (1), its characterized in that: the utility model discloses a curtain wall board, including vertical mounting panel (1), mounting hole (3) have been seted up on right angle steel sheet (2), mounting groove (4) have been seted up in the front of vertical mounting panel (1), through hole (5) have been seted up in mounting groove (4) both sides correspondence, inner chamber fixedly connected with connecting plate (6) of mounting groove (4), screw (7) have been seted up to the inner chamber of connecting plate (6), the front welding of connecting plate (6) has horizontal steel frame (8), joint groove (9) have all been seted up to the top and the bottom of horizontal steel frame (8), the inner chamber of joint groove (9) is provided with curtain wall board (10).
2. The fixing and connecting mechanism for the building curtain wall engineering as claimed in claim 1, wherein: the size of the connecting plate (6) corresponds to that of the mounting groove (4), and the position of the screw hole (7) corresponds to that of the through hole (5).
3. The fixing and connecting mechanism for the building curtain wall engineering as claimed in claim 1, wherein: reinforcing holes (11) are formed in the positions, corresponding to the middle of the connecting plate (6), of the inner cavity of the transverse steel frame (8), and reinforcing screws (12) are fixedly connected to the inner cavities of the reinforcing holes (11).
4. The fixing and connecting mechanism for the building curtain wall engineering as claimed in claim 1, wherein: the angle steel plate (2) is made of a 2cm steel plate, the angle steel plate (2) is fixedly connected with a wall body through an expansion screw (13), and the other side of the angle steel plate is fixedly connected with the vertical mounting plate (1) through a screw (14).
5. The fixing and connecting mechanism for the building curtain wall engineering as claimed in claim 1, wherein: the curtain wall board (10) is provided with sealing strip (15) with the junction department of joint groove (9), sealing strip (15) are triangle strip of paper used for sealing.
CN202121309991.3U 2021-06-10 2021-06-10 Fixed connection mechanism for building curtain wall engineering Expired - Fee Related CN214941470U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121309991.3U CN214941470U (en) 2021-06-10 2021-06-10 Fixed connection mechanism for building curtain wall engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121309991.3U CN214941470U (en) 2021-06-10 2021-06-10 Fixed connection mechanism for building curtain wall engineering

Publications (1)

Publication Number Publication Date
CN214941470U true CN214941470U (en) 2021-11-30

Family

ID=79053784

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121309991.3U Expired - Fee Related CN214941470U (en) 2021-06-10 2021-06-10 Fixed connection mechanism for building curtain wall engineering

Country Status (1)

Country Link
CN (1) CN214941470U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114396130A (en) * 2021-12-22 2022-04-26 晨达建设集团有限公司 Curtain wall for building engineering design and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114396130A (en) * 2021-12-22 2022-04-26 晨达建设集团有限公司 Curtain wall for building engineering design and construction method

Similar Documents

Publication Publication Date Title
CN214941470U (en) Fixed connection mechanism for building curtain wall engineering
CN103469943B (en) Multi-angle glass curtain wall unit plate and consisting of glass curtain wall system
CN215948602U (en) Quick mounting structure of building curtain
CN217150836U (en) Assembled aluminum plate curtain wall
CN214461549U (en) Energy-saving curtain wall with heat insulation function
CN210507963U (en) Detachable panel unit curtain wall
CN214739069U (en) Indoor display screen installation component of energy-saving building
CN212336440U (en) Splicing type energy-saving curtain wall
CN211817276U (en) Semi-hidden curtain wall structure
CN210737854U (en) Sound insulation curtain wall convenient to install
CN207700471U (en) A kind of connection structure of glass and metal plate curtain wall
CN215406776U (en) Simply-installed building curtain wall
CN112227575A (en) Convenient architectural decoration curtain of dismantling
CN221372612U (en) Environment-friendly curtain wall convenient to install
CN221143209U (en) Curtain wall panel structure provided with film pasting screen
CN220434290U (en) Panel edges and corners protection subassembly that ALC light board wall installation was used
CN212271335U (en) Unit type energy-saving combined curtain wall
CN212802170U (en) Special-shaped splicing system for simple installation of half units
CN213062551U (en) Energy-concerving and environment-protective sound insulation thermal-insulated building curtain
CN215484245U (en) Decoration wall surface dry hanging internal corner joint mounting structure
CN215330758U (en) Spliced curtain wall for building
CN216810450U (en) Curtain wall construction for outdoor architectural decoration
CN219825749U (en) Fireproof metal composite curtain wall plate
CN211172602U (en) Concatenation formula glass curtain wall
CN212772970U (en) Energy-saving assembled building wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211130