CN214899883U CN202120512352.0U CN202120512352U CN214899883U CN 214899883 U CN214899883 U CN 214899883U CN 202120512352 U CN202120512352 U CN 202120512352U CN 214899883 U CN214899883 U CN 214899883U
Authority
CN
China
Prior art keywords
factory building
movable support
steel structure
cable movable
protective sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202120512352.0U
Other languages
Chinese (zh)
Inventor
张天达
唐世奇
白楠
韩凯
王鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Power Transmission And Distribution Engineering Co ltd
State Grid Corp of China SGCC
Original Assignee
Jilin Power Transmission And Distribution Engineering Co ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Power Transmission And Distribution Engineering Co ltd, State Grid Corp of China SGCC filed Critical Jilin Power Transmission And Distribution Engineering Co ltd
Priority to CN202120512352.0U priority Critical patent/CN214899883U/en
Application granted granted Critical
Publication of CN214899883U publication Critical patent/CN214899883U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Installation Of Indoor Wiring (AREA)

Abstract

The utility model relates to a temporary cable movable support applied to a steel structure factory building, which belongs to the technical field of temporary electric wiring installation of the steel structure factory building; the ceramic insulation protective sleeve is hollow and is embedded with a connecting component; the bottom end of the porcelain insulating protective sleeve is provided with a base assembly, the base assembly is detachably connected with the connecting component, and the top end of the porcelain insulating protective sleeve is provided with an adjusting assembly; the base component is made of a ferromagnetic material. The utility model discloses the whole light in weight of device does not harm the former thing surface, installation, demolish, convenient to carry, the one-man operation of being convenient for during the use.

Description

Be applied to interim cable movable support of steel construction factory building
Technical Field
The utility model belongs to the technical field of the interim power consumption wiring installation of steel construction factory building, especially, relate to a but be applied to interim cable movable support of steel construction factory building.
Background
With the rapid development of national power grid construction, steel structure plants are gradually popularized and popularized in the aspect of electric power infrastructure due to the convenience of the steel structure plants in many aspects from the aspects of environmental protection, economy, safety and the like.
In the installation and construction process of a steel structure, how to arrange temporary electricity utilization to be the problem which is difficult to solve by each construction unit at present, the firmness and the attractiveness of wiring are met, and the original structure of the operation environment is not damaged. Therefore, a new device is needed to meet the above needs.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a be applied to steel construction factory building's interim cable movable support to in solving steel construction installation work progress, the technical problem of interim power consumption.
In order to achieve the above object, the utility model discloses a be applied to steel construction factory building's interim cable movable support's concrete technical scheme as follows:
a movable temporary cable support applied to a steel structure factory building comprises a ceramic insulating protective sleeve, wherein the ceramic insulating protective sleeve is hollow and is embedded with a connecting component;
the bottom end of the porcelain insulating protective sleeve is provided with a base assembly, the base assembly is detachably connected with the connecting component, and the top end of the porcelain insulating protective sleeve is provided with an adjusting assembly;
the base component is made of a ferromagnetic material.
Furthermore, the inner wall of the connecting part is provided with an internal thread;
the base component comprises a magnetic base, wherein a screw is arranged in the middle of the magnetic base and matched with the internal thread.
Furthermore, the middle of the magnetic base is provided with a mounting through hole, one side, away from the porcelain insulating protective sleeve, of the mounting through hole is provided with a limiting groove, one end of the screw is abutted to the limiting groove, and the other end of the screw penetrates through the mounting through hole and is in threaded connection with the connecting component.
Further, the bottom of the magnetic base is provided with an anti-skid groove, and anti-skid rubber is arranged in the anti-skid groove.
Furthermore, the adjusting component comprises a fixing part adhered to the top of the insulating knob insulator, an adjusting part is arranged on one side of the fixing part, and a limiting part clamped with the adjusting part is arranged on the other side of the fixing part.
Further, spacing portion includes the U type piece of being connected with the fixed part, and U type piece sets up the fixture block towards one side integrated into one piece of fixed part, keeps certain clearance between fixture block and fixed part, is provided with a plurality of spacing through-holes with fixture block size assorted on the regulating part.
Further, the base component is made of polyamide fiber.
Furthermore, the fixing part is made of rubber, and the adjusting part is made of polyamide fiber.
The utility model discloses a but be applied to interim cable movable support of steel construction factory building has following advantage: the device has light weight (not more than 500 g), does not damage the surface of an original object, is convenient to install, dismantle and carry, and is convenient to operate by one person when in use.
Drawings
Fig. 1 is the utility model discloses a be applied to interim cable movable support's of steel construction factory building front view.
Fig. 2 is the utility model discloses a be applied to movable support's of interim cable of steel construction factory building bottom view.
Fig. 3 is the utility model discloses a be applied to steel construction factory building's interim cable movable support's adjustment assembly's schematic structure.
Fig. 4 is the utility model discloses a but be applied to interim cable movable support structure sketch map of steel construction factory building.
Fig. 5 is the utility model discloses a be applied to steel construction factory building's interim cable movable support's insulating knob insulator's schematic structure.
Fig. 6 is the utility model discloses a be applied to interim cable movable support's of steel construction factory building structural schematic diagram one.
Fig. 7 is the utility model discloses a be applied to interim cable movable support's of steel construction factory building structural schematic diagram two (the screw is not shown).
Fig. 8 is the utility model discloses a be applied to interim cable movable support's of steel construction factory building front view.
Fig. 9 is a sectional view in the direction a-a of fig. 8.
Fig. 10 is the utility model discloses a be applied to movable support's of interim cable of steel construction factory building structure schematic diagram.
The notation in the figure is: 1. a porcelain insulating protective sleeve; 2. a connecting member; 3. a base assembly; 301. a magnetic base; 302. a screw; 303. mounting a through hole; 304. a limiting groove; 305. an anti-slip groove; 4. an adjustment assembly; 401. a fixed part; 402. an adjustment section; 403. a limiting part; 4031. a U-shaped block; 4032. a clamping block; 404. and limiting through holes.
Detailed Description
In order to understand the utility model discloses a purpose, structure and function better, combine the figure below, it is right to combine the utility model relates to a be applied to interim cable movable support of steel construction factory building and do further detailed description.
As shown in fig. 1-10, the temporary cable movable support applied to a steel structure factory building of the present invention comprises a ceramic insulating protective sleeve 1, wherein the ceramic insulating protective sleeve 1 is hollow and embedded with a connecting component 2, and the connecting component 2 is made of high-strength steel, so that the support strength is ensured and the insulating effect is achieved;
the bottom end of the porcelain insulating protective sleeve 1 is provided with the base component 3, the base component 3 is detachably connected with the connecting component 2, and the top end of the porcelain insulating protective sleeve is provided with the adjusting component 4, so that the porcelain insulating protective sleeve can adapt to cables of different sizes and plays a role in strengthening and fastening;
base subassembly 3 adopts strong magnetic material, and the spiral structure of base subassembly 3 upper end adoption and the internal screw of upper end adapting unit 2 fasten mutually, and the installation of being convenient for is dismantled, and the base utilizes magnetic force characteristic and steel structural component to carry out the physics simultaneously and is connected, has guaranteed the stability of equipment.
In the present embodiment, an internal thread is provided on the inner wall of the connecting member 2;
the base component 3 comprises a magnetic base 301, a screw 302 is arranged in the middle of the magnetic base 301, and the screw 302 is matched with the internal thread.
In this embodiment, a mounting through hole 303 is formed in the middle of the magnetic base 301, a limiting groove 304 is formed in one side of the mounting through hole 303, which is far away from the porcelain insulating protective sleeve 1, one end of the screw 302 abuts against the limiting groove 304, and the other end of the screw penetrates through the mounting through hole 303 and is in threaded connection with the connecting component 2.
In this embodiment, the bottom of the magnetic base 301 is provided with an anti-slip groove 305, and an anti-slip rubber is provided in the anti-slip groove 305, so as to increase the friction between the magnetic base 301 and the steel structure, and to achieve stable connection.
In the present embodiment, the adjusting assembly 4 includes a fixing portion 401 adhered to the top of the insulating knob insulator, wherein an adjusting portion 402 is disposed on one side of the fixing portion 401, and a limiting portion 403 engaged with the adjusting portion 402 is disposed on the other side;
in this embodiment, through the physics viscose with fixed part 401 and the firm with porcelain insulating protective cover 1 top, regulation part 402 cooperatees with spacing portion 403, and adjustable fastening size is convenient for adjust corresponding size to different diameter cables, guarantees that the device fastening is firm.
In this embodiment, the limiting portion 403 includes a U-shaped block 4031 connected to the fixing portion 401, a fixture 4032 is integrally formed on one surface of the U-shaped block 4031 facing the fixing portion 401, a certain gap is maintained between the fixture 4032 and the fixing portion 401, so that the adjusting portion 402 can pass through, a plurality of limiting through holes 404 are formed in the adjusting portion 402, the size of each limiting through hole is matched with that of the fixture 4032, the adjusting portion 402 is pressed downward during adjustment so that the adjusting portion can pass through the gap, and after the adjustment is completed, the adjusting portion 402 is close to the limiting portion 403 under the action of the cable, so that the limiting portion 403 is engaged with the limiting through holes 404, and the purpose of binding the cable is achieved.
In the present embodiment, the base member 3 is made of a polyamide fiber material.
In the present embodiment, the fixing portion 401 is made of rubber, and the adjustment portion 402 is made of polyamide fiber.
Porcelain insulating protective cover 1 constitutes insulating knob insulator with adapting unit 2, often selects porcelain material as the insulator among the electric power production process for use, and porcelain material has insulating nature good, characteristics such as stable performance, and as device main part support insulation system, the inside cavity of knob insulator is equipped with the same size interior spiral steel column, guarantees the whole holding capacity of device.
The structure adopts the modularization to assemble, and ann tears conveniently open, and the pleasing to the eye range of application of appearance is wide, has expressed the physics cohesiveness perfection of magnetic force and metal material in the power production process, has both satisfied the pleasing to the eye of interim cable wiring, security and saved original loaded down with trivial details fixed operation flow that punches again, has simple structure, the fast advantage of installation rate, compares with traditional construction method and has promoted the efficiency of construction greatly, has improved construction process quality.
When in use: the base assembly 3 is first fastened to the connecting part 2. Adjusting the adjusting component 4 to a proper margin according to the size of the power cable, and finally adsorbing the device at a proper position on site;
because the inside steel column connecting part 2 inside of insulating lag 1 of porcelain is interior spiral structure, is equipped with protruding bolt on the magnetism base 301 of strong magnetism, and the bolt size accords with steel column internal diameter size, and magnetism base 301 has strong magnetism simultaneously and can adsorb the wiring at steel construction arbitrary position, the interim cable of the work progress of being convenient for.
It is to be understood that the present invention has been described with reference to certain embodiments, and that various changes or equivalents may be substituted for elements thereof by those skilled in the art without departing from the spirit and scope of the invention. In addition, many modifications may be made to adapt a particular situation or material to the teachings of the invention without departing from the essential scope thereof. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of the present application are intended to be covered by the present invention.

Claims (8)

1. A temporary cable movable support applied to a steel structure factory building is characterized by comprising a porcelain insulating protective sleeve (1), wherein the porcelain insulating protective sleeve (1) is hollow and is embedded with a connecting component (2);
the bottom end of the porcelain insulating protective sleeve (1) is provided with a base component (3), the base component (3) is detachably connected with the connecting component (2), and the top end of the porcelain insulating protective sleeve is provided with an adjusting component (4);
the base component (3) is made of a ferromagnetic material.
2. The temporary cable movable support applied to the steel structure factory building according to claim 1, wherein inner threads are arranged on the inner wall of the connecting part (2);
the base component (3) comprises a magnetic base (301), a screw (302) is arranged in the middle of the magnetic base (301), and the screw (302) is matched with the internal thread.
3. The temporary cable movable support applied to the steel structure factory building is characterized in that a mounting through hole (303) is formed in the middle of the magnetic base (301), a limiting groove (304) is formed in one side, away from the porcelain insulating protective sleeve (1), of the mounting through hole (303), one end of the screw (302) abuts against the limiting groove (304), and the other end of the screw penetrates through the mounting through hole (303) to be in threaded connection with the connecting component (2).
4. The temporary cable movable support applied to the steel structure factory building is characterized in that an anti-skid groove (305) is formed in the bottom of the magnetic base (301), and anti-skid rubber is arranged in the anti-skid groove (305).
5. The temporary cable movable support applied to the steel structure factory building is characterized in that the adjusting component (4) comprises a fixing part (401) adhered to the top of the insulating knob insulator, an adjusting part (402) is arranged on one side of the fixing part (401), and a limiting part (403) clamped with the adjusting part (402) is arranged on the other side of the fixing part.
6. The temporary cable movable support applied to the steel structure factory building is characterized in that the limiting portion (403) comprises a U-shaped block (4031) connected with the fixing portion (401), a clamping block (4032) is integrally formed on one surface, facing the fixing portion (401), of the U-shaped block (4031), a certain gap is kept between the clamping block (4032) and the fixing portion (401), and a plurality of limiting through holes (404) matched with the clamping block (4032) in size are formed in the adjusting portion (402).
7. The temporary cable movable support applied to the steel structure factory building is characterized in that the base component (3) is made of polyamide fiber.
8. The temporary cable movable support applied to the steel structure factory building is characterized in that the fixing part (401) is made of rubber, and the adjusting part (402) is made of polyamide fiber.
CN202120512352.0U 2021-03-11 2021-03-11 Be applied to interim cable movable support of steel construction factory building Active CN214899883U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120512352.0U CN214899883U (en) 2021-03-11 2021-03-11 Be applied to interim cable movable support of steel construction factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120512352.0U CN214899883U (en) 2021-03-11 2021-03-11 Be applied to interim cable movable support of steel construction factory building

Publications (1)

Publication Number Publication Date
CN214899883U true CN214899883U (en) 2021-11-26

Family

ID=79036370

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120512352.0U Active CN214899883U (en) 2021-03-11 2021-03-11 Be applied to interim cable movable support of steel construction factory building

Country Status (1)

Country Link
CN (1) CN214899883U (en)

Similar Documents

Publication Publication Date Title
US10845093B2 (en) Support assemblies for solar energy panels
CN205578907U (en) Anchor clamps of fixed cable
CN214899883U (en) Be applied to interim cable movable support of steel construction factory building
CN207314966U (en) A kind of insulator crossarm
CN213301858U (en) Clamp for bending electrical cabinet shell
CN205259532U (en) A combination formula fossil fragments spare for doing wall hanging plate
CN212905603U (en) OPGW (optical fiber composite overhead ground wire) suspension fitting
CN210947375U (en) Assembled furred ceiling structure
CN209805255U (en) Improved generation high stability cable conductor anchor clamps
CN203287596U (en) Profiling resin insulated wire clamp
CN203103848U (en) Wiring device
CN210245281U (en) Conductive rod easy to adjust and install
CN210898241U (en) High-low voltage electrical complete equipment assembling tool of power distribution system
CN216530283U (en) Portable wire clamp for electric power engineering
CN214255483U (en) Repeatedly usable's pencil positioner for weak current engineering
CN214255597U (en) Three-wire voltage cable fixing clamp device
CN219554445U (en) Electric power engineering cable strutting arrangement
CN213937368U (en) Elasticity-adjustable wire connecting device for power transmission line tower
CN214543461U (en) Electric junction box row installation mechanism
CN212113592U (en) Electronic type moulded case circuit breaker's mounting structure
CN213954087U (en) Diameter-variable anti-falling hoop
CN219627293U (en) Electrical cable positioning device
CN218208518U (en) Pole top iron convenient to install
CN220397340U (en) Solar panel base for solar street lamp
CN215452462U (en) Wire clamp for high-voltage transmission line with optimized surface field intensity

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant